Design and Analysis of Approach Embankment Bridges Over Soft Soils
Design and Analysis of Approach Embankment Bridges Over Soft Soils
Design and Analysis of Approach Embankment Bridges Over Soft Soils
Abstract
The growth of urban areas near watersides induces the need of construction over compressible soils. This paper
presents a study on the behavior of approach embankments bridges over clay soils with special focus on its
foundations. In order to achieve results several projects were developed and the results were analyzed and
achieved based on the comparison between software Plaxis 2D modeling and the experimental embankments.
An equal set of base data was considered for all the projects. The underlying data is equal to the embankment
AE1 data, in order to represent the same real problem. The AE1 is one of the three experimental embankment led
to breakage, developed within the frame of the Magnani doctoral work in 2006. Four models were projected
ranging from constructive methods: from the more deformable - conventional embankment with geo-
reinforcement at the base and foundation treated with vertical drains built-in stages - to the more rigid- staked
embankment - passing on the intermediate - embankment over stone-columns and embankment over jacketed
stone-columns.
¶
E-mail: [email protected] 1
Master Student
Carmo Cardoso
The embankments were constructed on the Side edges were also planned to reduce the
scope of the doctoral thesis of Henrique Magnani three-dimensional effects of embankments due to
de Oliveira [2] . The main objective was to study its limited length, to minimize potential disruptions
the behavior of reinforced embankments and displacements in the longitudinal direction to
executed over a very soft clay deposit in a regime sections, and also to prevent the disruption of a
rapid construction and are part of the Via landfill that could influence the conditions of
Expressa Sul project, a road that links the stability given the vicinity.
downtown area to the southern part of the island
The pre-assembled vertical drains were carved
of Santa Catarina.
using the spiking of a keyless chuck with 15 cm
The location of the experimental embankments diameter, with a horizontal spacing between
was determined to obtain the lowest possible drains of in a triangular pattern and length
thickness of hydraulic embankment, to simulate in order to cross the full layer of clay.
the most critical situation, looking for the area of
The AE1 embankment featured a length of m,
maximum possible homogeneity both on
plus the edges, with of cross section and
geotechnical and geometric level, to favor the
slopes with an 1,5:1,0 (H:V) inclination.
understanding of the observed data, and finally,
as close as possible to the construction site to The embankment stopped rising in height when it
ensure greater representation and less distance reached the rupture, which occurred at .
to transport the materials which would be used. The performance is presented in Fig. 3.
The obtained location is presented in Fig.2
2
Carmo Cardoso
As in the case of experimental embankment, it is The clay stratum is modeled with the material
considered that the body of the embankment is model of Soft Soil, which parameters are
executed with the same hydraulic fill sand, with presented in table 3. The groundwork layer is
parameters presented in Table 1, and modeled in modeled with Mohr-Coulomb model and material
the software model Plaxis Hardening Soil with the characteristics presented in table 4.
material.
3
Carmo Cardoso
Table 3 – Characteristic Parameters of Soft Soil - Soft Soil properties due to phased construction. To
model [1]
Parameters Value achieve this the equation of repressions for a
Geotechnical parameters fixed quota of landfill was applied considering the
Bulk weight γ [kN/m3] 13,7 submersion of the layer, by [3], EQ. [A].
OCR 1
-9
Vertical permeability 10 ( ) [A]
-9
Horizontal permeability 10
Constitutive parameters
Having reached a rating of to a
Initial void ratio e0 3,5
Effective Friction angle ∅’ [°] 30 embankment of height .
Dilatancy angle [°] 0
Effective Cohesion c’ [kPa] 5
The secondary settlements calculation based on
Modified compression index λ* 0,1565 the methodology proposed by Martins (2005),
Modified swelling index k* 0,0344 exposed in [2], was applied and reached an
estimation from Eq.[B] a value of .
Table 4 – Characteristic Parameters of Bottom Sand –
Mohr-Coulomb model [1]
Parameters Value ( ) ( ) [B]
Geotechnical parameters
Bulk weight γ 17,5
The conclusion was that it is necessary to build a
Initial void ratio e0 0,5
-4 embankment of height
Vertical permeability 10
Horizontal permeability 10
-4 to compensate the repressions in the
Constitutive parameters completion, .
Effective Friction angle ∅’[°] 33,8
Dilatancy angle [°] 3,8 The overhead is estimated so that the height of
Effective Cohesion c’ 0
the embankment overhead causes a primary
Stiffness Modulus 100 000
discharge equal to or greater than the total
Poisson coefficient, ν' 0,30
discharge previously estimated. It has been
estimated an overload of , using the
Projects
equation of repression by primary densification,
In all projects developed, such as the AE1
EQ. [C], to be removed at the end of the 18
landfill, it was agreed to put a geo-reinforcement
months construction phase.
on the foundation as a backup step.
[ ( ) ( )] [C]
Conventional Embankment
The conventional embankment project is built in
The assessment was to use the same system of
stages and foresees the placement of vertical
drains that were used in embankment AE1.
drains and overhead in order to speed up primary
Mattress sizing draining made according to
repressions and anticipate secondary
Cadergren methodology (1967) exposed in [2],
repressions.
follows with this spacing of drains and with
In the pre-sizing phase, through analytical thick layer of draining able to set seven horizontal
in 1985, by Rowe and Sodermenn exposed in [2], [5] ,Fig.6. The obtained permeabilities are in the
developed to evaluate the tensile forces following table.
mobilized in strengthening from the value of Table 5 – Permeabilities of Soft Clay
Parameters Value
predictable deformation, , in function of a
Vertical permeability
dimensionless parameter Ω, which relates from a
Horizontal permeability
abacus. Horizontal permeability in the smear
zone
Plane strain horizontal permeability
Through the analysis we projected a strain
for a geo reinforcement presenting a Plain strain horizontal permeability in
the smear zone
tensile stiffness modulus in direction, to 5%
deformation (J5% ), de approximately
[4], we may concluded that the maximum traction
which can be mobilized in the reinforcement is in
an order of magnitude of , much lower than
the .
purely radial drainage, , due to the effect By this means and after running the model in
of vertical drains. It wasn’t considered the effect Plaxis 2D software, it was possible to get the
1
of smear and changes of the values of the offsets at the top of the embankment which is
coefficients of permeability due to phased presented in graphic form in Figure 6, where it is
construction in order to simplify and to visible a near blistering when the overload
compensate the non-consideration of vertical is removed. It was found that the geo-
drainage component. reinforcement has a maximum axial effort
5
Carmo Cardoso
Fig. 7 shows that the construction in stages Table 6 – Characteristic parameters of the materials of
the Stone-Column - Mohr-Coulomb model
produced settlements smaller than estimated
Parameters Value
analytically and that more time is needed to Geotechnical parameters
stabilize due to the densification of clayey Soil unit weight above phreatic level γh
18
[kN/m3]
stratum. Soil unit weight below phreatic level γsat
20
[kN/m3]
-4
Jacketed Stone-Columns Embankment Vertical permeability 1,16x10
-4
Horizontal permeability 1,16x10
The Jacketed Stone-Columns Embankment has
Constitutive parameters
as an advantage regarding conventional Initial void ratio, e0 0,5
embankments: shorter construction time and Effective Friction angle, ∅’[°] 38
added control over the repressions, causing an Dilatancy angle, [°] 12
Effective Cohesion, c’ [kPa] 5
increase in resistance of the clay due to the 3
Stiffness Modulus E’[kN/m2] 25x10
drainage reached and the increased strength of
index n’ 0,30
the foundation.
In the modeling process the unit cell concept was
It was agreed that the columns would measure
used with equivalent diameter ,
length, to be built-in the layer, diameter
using the option of symmetry, Axisymmetry
, forming a square weave of side, in
model.
order to ensure the absence of differential
settlements at the top of the embankment. The
criteria applied was the one proposed by [6]
which presents the EQ. [D].
[D]
6
Carmo Cardoso
7
Carmo Cardoso
stone was not introduced since this appraisal was The most expensive solution is the proposed
not viable per meter of longitudinal embankment. Embankment on Jacketed Stone-Columns, with a
cost of 5.690,00 € per meter longitudinal
After obtaining the costs for each submitted
embankment, showing no advantage for the
proposal it is reasonable to conclude that the
solution of the Landfill staked. The proposed
more flexible solution - Conventional
Embankment staked is the most rigid and more
Embankment - is in fact the more cost efficient,
reliably.
with a cost of 3.061,00 € per meter of longitudinal
embankment. However it is also the solution that In several projects the incline of slopes did not
requires more time - 18 months - for the change, 1:2 (vertical: horizontal) for being one
stabilization of compressible stratum. initial condition. However, it is more likely that
more rigid solutions may be executed with
The time factor should be analyzed in sets with
steeper slopes, which would translate into less
other factors such as the time of construction of
earth volume that in the end would reflect
other infrastructure or other interventions that the
significantly on the final cost.
area will suffer. The waiting time between stages
of construction could be used, in its entirety, for
the construction of other infrastructure.
Fig. 11 – Section type of each solution: A - Conventional Embankment; B - Embankment over Jacketed Stone-Columns;
C - Embankment over piles.
8
Carmo Cardoso
The economic analysis was performed with the [6] Filz, G. (2012). Column-Supported
Embankments: Settlement And Load
intention of compare the cost of each solution Transfer. Geotechinical Engineering
and was used the mean value of the Portuguese State Of The Art And Practice - Keynote
market. However, the values contains prices of Lectures From Geocongrees, (p. 54).