Labour Schedule Arc 425 Addendum

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Project Title: AFRICAN FARMERS HOUSE Contractor: HINADI LIMITED

Date: 13TH OCTOBER 2003 LABOUR SCHEDULE Prepared By: O.Ajayi


2004 2005 2006 2007 2008
S/NO TEAM J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A REMARK
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

1 SITE MANAGEMENT 6 6 6 6 6 6 6 6 10 10 10 10 14 14 18 18 18 20 20 20 20 20 20 20 24 24 24 24 24 24 24 24 24 24 24 24 28 28 28 28 28 28 28 28 28 28 28 28 22 22 16 16 12 12 8 8
2 CARPENTERS 8 8 1 1 1 1 1 1 1 1 4 4 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 2 2 2 2 2 2 2 2
3 UNSKILLED LABOUR 16 16 16 2 2 2 2 2 6 6 8 8 8 8 8 8 8 8 10 10 10 10 10 10 10 12 12 12 12 12 12 12 12 12 12 12 12 12 12 14 14 14 14 16 8 8 8 8 4 4 4 4 4 4 4 4
4 BLOCK LAYERS 6 26 26 2 2 2 2 2 2 2 5 5 5 5 5 5 5 5 9 9 9 9 9 9 9 9 9 9 9 9 9 9 12 12 12 12 16 7 7 7 7 4 4 2 2 2 2
5 ELECTRICIANS 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 3 3 3 3 3 3 3 3 3 23 23 23 33 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 23 23
6 PLUMBERS 4 4 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 8 8 8 8 8 8 8 8 8
7 COMPRESSOR DRIVERS 3 3
8 CONCRETE CUTTERS 3 3
9 STEEL FIXERS 2 2 4 4 12 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 4
10 BOREHOLE TEAM 5 5
11 PILING TEAM 18 18 27 27 27 27
12 BACKACTER DRIVERS 4 4 4 4
13 CRANE OPERATORS 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
14 CONCRETE PUMP 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
15 STRUCTURAL STEEL ERECTORS 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
16 PRECAST CONCRETE 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
17 AIR CONDITIONING 28 28 28 28 28 28 28 28 36 36 40 40 48 48 48 48 48 48 40 28 28 20
18 ALUMINIUM ROOFING 4 4
19 ASPHALT 3 3 3 3
20 CURTAIN WALLING 8 8 8 8 8 8 8 8 8 8 8 8 8
21 STONEWORK 3 3 3 3 3 3 3 3 3
22 SPRINKLER 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16
23 LIFT INSTALLATION 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64
24 MARBLE 18 18 18 18 18 18 18 18 18 18
25 SUSPENDED CEILING 21 21 21 21 21 21 21 21 21 21 21
26 TILERS 6 6 6 6 6 6 6 6
27 RAISED ACCESS FLOOR 6 6 6 6 6 6 6 6 6
28 DEMOUNTABLE PARTITION 6 6 6 6 6 6
29 MOSAIC 9 9 9 9
30 GRANITE 6 6 6 6 6
31 PAINTERS 3 3 3 3
32 JOINERS 4 4 4
33 SEWAGE TREATMENT 8 8 8 8 8

MONTHLY TOTAL 42 70 60 34 34 38 38 38 46 23 34 36 48 42 47 54 65 70 72 72 72 72 72 72 76 102 102 102 112 122 122 136 151 147 147 147 167 167 231 244 262 266 283 289 286 275 275 281 276 277 245 226 212 95 25 12

300
270
240
210
180
150
120
90
60
30
0

FIGURE: 2.4 LABOUR SCHEDULE