NC 50166 PL 000 15 24 001 0

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

STORAGE CALCULATION FOR CCTV SYSTEM

DOCUMENT CLASS - 2

Rev. Date Status Status Description Prepared Checked Approved

0 07/05/2024 IFT Issued For Tender ABG LYJ DTS

B 21/03/2024 IFA Issued For Approval ABG LYJ DTS

A 16/02/2024 ICR Issued For Company Review ABG LYJ DTS


THIS DOCUMENT IS THE PROPERTY OF ADNOC GAS (AG), AND CONTAINS INFORMATION WHICH IS PROPRIETARY.THIS INFORMATION TO BE HELD IN CONFIDENCE.NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT
IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ADNOC GAS (AG).

1 / 10 Uncontrolled When Printed


ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

SUMMARY OF DOCUMENT REVISIONS


Rev. Date Section
Revision Description
No. Revised Revised
A 16/02/24 First Issue Issued for Company Review
B 21/03/24 Pg No. 9 & 10 Issued for Approval
0 07/05/24 Nil Issued for Tender

2 / 10 Uncontrolled When Printed


ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

TABLE OF CONTENTS

1. PROJECT DESCRIPTION .................................................................................................... 4


1.1 Introduction ......................................................................................................................... 4
1.2 Project Scope ...................................................................................................................... 4
2. PURPOSE ............................................................................................................................ 4
3. DEFINITIONS & ABBREVIATIONS...................................................................................... 5
3.1 Definitions ........................................................................................................................... 5
3.2 Abbreviations ...................................................................................................................... 5
4. ORDER OF PRECEDENCE.................................................................................................. 6
5. REFERENCE DOCUMENTS ................................................................................................ 7
5.1 Project Document................................................................................................................ 7
6. UNIT OF MEASUREMENT ................................................................................................... 7
7. STORAGE CALCULATION .................................................................................................. 9

3 / 10 Uncontrolled When Printed


ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

1. PROJECT DESCRIPTION
1.1 Introduction
ADNOC Gas (AG), hereafter referred as COMPANY plays a strategic role in ADNOC and the UAE
hydrocarbon value chain by contributing significantly for the development of UAE.

COMPANY operates various assets: gas processing facilities and manages integrated Sales Gas
Pipeline Network to supply sustainable gas at each consumer with agreed battery limit pressure and
flow rate through various sales gas pipelines of total length of approximately 3,000 km spread down
from western to eastern part of the UAE. The pipeline network delivers sales gases to ADNOC, EWEC,
DEL, EGA/EMAL, and various other industrial consumers in Abu Dhabi and Northern Emirates.

The main and critical existing facilities and/or manifolds of ADNOC Gas sales gas pipeline networks
are as following:

• Habshan Compressor Facility


• Maqta Manifold Facility
• KM-42 Station
• Taweelah Gas Compressor Plant (TGCP)
• Thammama-C Manifold

1.2 Project Scope


As part of the enhancement of pipeline network, COMPANY intends to build new pipelines to supply
gas from RLPP (Ruwais LNG Pre-conditioning Plant at Habshan 5) to Ruwais LNG Plant (RLNG)
utilizing the ESTIDAMA sales gas compressors at HGCP (hereafter referred as PROJECT / Package-
8).

As part of the project, a new suction pipeline of 48”/52” (TBC based on hydraulics) shall be installed
from Ruwais LNG Pre-conditioning Plant at Habshan 5 to HGCP and a new discharge pipeline of
52”/56” (TBC based on hydraulics) shall be installed from HGCP to RLNG at Ruwais.

For implementation of the mentioned scope COMPANY has engaged ENGINEER to perform DEFINE
STAGE (FEED) for the PROJECT including preparation of PROJECT DEFINITION REPORT(S) and
EPC Enquiry Package(s).

2. PURPOSE
The purpose of this document is to define the Storage Calculation for CCTV System for the ‘Sales Gas
Pipeline Network Enhancement Project – Package 8 - DEFINE Stage’.

4 / 10 Uncontrolled When Printed


ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

3. DEFINITIONS & ABBREVIATIONS


3.1 Definitions

COMPANY ADNOC Gas (AG)

Sales Gas Pipeline Network Enhancement Project – Package 8-


PROJECT
DEFINE Stage

The party who shall carry out the FEED / DEFINE stage activities in
ENGINEER
conjunction with SOS and SOR requirements.

3rd Party Specialist carrying out specific studies – if any.

The party which has a subcontract with ENGINEER to provide


SUBCONTRACTOR services or carries out all or part of the Design, as specified by
ENGINEER

The party(s) which manufactures and/or supplies piping, equipment


VENDOR
and services to perform the duties specified

SHALL The use of the word “Shall” indicates a mandatory requirement

The use of the word “Should” indicates a strong recommendation to


SHOULD
comply with the requirements of this document

3.2 Abbreviations

Abbreviation Full Name

ADNOC Abu Dhabi National Oil Company


AG ADNOC GAS
BVS Block Valve Station
CCTV Closed Circuit Television
CRS Consumer Receipt station

DGS Design general Specification

EPC Engineering Procurement and Construction


FEED Front End Engineering Design
FOC Fiber Optic Cable

FOPP Fiber Optic Patch Panel

HGCP Habshan Gas Compressor Plant


IEC International Electrotechnical Commission
IEEE Institute of Electrical and Electronics Engineers

5 / 10 Uncontrolled When Printed


ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

Abbreviation Full Name


IP Ingress Protection / Internet Protocol
ISO International Telecommunication Union
Km Kilometers
MPLS-TP Multiprotocol Label Switching – Transport Profie
OEM Original Equipment Manufacturer
PTZ Pan Tilt Zoom
SDH Synchronous Digital Hierarchy
SEC Security
TIA Telecommunications Industry Association
UPS Uninterrupted Power Supply

UTP Unsheilded Twisted Pair

4. ORDER OF PRECEDENCE
In the event of any apparent conflict, the order of precedence for document shall be followed in
descending order of precedence:

1. UAE Statutory requirements and/or Regulations


2. Project Specifications, Datasheets and Drawings.
3. COMPANY Specifications.
4. ADNOC Standards
5. International Standards and Industrial Codes.

6 / 10 Uncontrolled When Printed


ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

5. REFERENCE DOCUMENTS
5.1 Project Document

S. No. Document Number Document Description

1 DWG-50166-PL-000-15-24-009 Block Diagram for CCTV System for EPC Package 8

2 PP-50166-PL-000-15-24-002 Design Philosophy for Security CCTV System

3 DOD-50166-PL-000-15-24-004 Datasheet for Security CCTV System

6. UNIT OF MEASUREMENT

Table 6-1: Units of Measurement


Quantity Unit Symbols

Length Metre m

Area 2
Square metre m
3
Cubic metre m
Volume
Litre l
3
Normal cubic metre Nm

Standard Cubic Feet scf

Time Second s

Minute min

Hour h

Day d

Degree Celsius °C
Temperature
Kelvin K

bar (gauge) bar (g)


Pressure
bar (absolute) bar (a)
Amount of
Mole mole
Substance
3
Density kilogram per cubic meter kg/m

Energy British Thermal Unit BTU

7 / 10 Uncontrolled When Printed


ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

Quantity Unit Symbols

Energy, Work and


Heat
Joule J
Quantity

Watt W
Power, heat flow
KiloWatt kW

Current Ampere A

Frequency Hertz, cycles per second Hz

Voltage Volts V

Nominal Pipe
Inches in
diameter

Millimetre mm
Pipe Wall Thickness
Pipe Schedule Sch

Gas volume Million Standard Cubic Feet MMSCF

Million Standard Cubic Feet Day MMSCFD


Gas volumetric flow
3
rate Cubic meter per hour m /h

parts per million by weight ppm wt


Concentration
parts per million by volume ppm (v)
Standard conditions
Standard conditions for gas measured in cubic meter (& cubic feet) shall be at 15°C
temperature and 1.01325 bar (a) pressure.

8 / 10 Uncontrolled When Printed


ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

7. STORAGE CALCULATION (PACKAGE 8)

EPC Package 8

Stations Resolution Compr Record FPS No. of No. of Total Total Total
-ession ing Days Came- Storage Storage Storag-
type ras (station e
wise) includi
ng 50%
spare

RLPP 1920x1080 H.265 Motion 25 30 2 2.2 TB

953-BVS-01 1920x1080 H.265 Motion 25 30 4 4.5 TB

954-BVS-01 1920x1080 H.265 Motion 25 30 4 4.5 TB

954-BVS-02 1920x1080 H.265 Motion 25 30 4 4.5 TB


34 TB 51 TB

954-BVS-03 1920x1080 H.265 Motion 25 30 4 4.5 TB

954-BVS-04 1920x1080 H.265 Motion 25 30 4 4.5 TB

954-BVS-05 1920x1080 H.265 Motion 25 30 4 4.5 TB

RLNG CRS 1920x1080 H.265 Motion 25 30 4 4.5 TB

Note:

The quantity of cameras indicated are preliminary and shall be further validated and finalized based on the
coverage study during Detail Engineering phase.

9 / 10 Uncontrolled When Printed


ADNOC Classification: Internal

SALES GAS PIPELINE NETWORK ENHANCEMENT


PROJECT FEED SERVICES
PACKAGE-8

STORAGE CALCULATION FOR CCTV SYSTEM


COMPANY Project No.
COMPANY DOC. No. NC-50166-PL-000-15-24-001 Rev. 0
50166

7.1 Storage in total for all the stations (EPC Package 2-7 and 8)

Stations Resolution Compr Record FPS No. of No. of Total Total


-ession ing Days Cameras Storage Storage
type including
50% spare

All Stations
in EPC 1920x1080 H.265 Motion 25 30 183 316 TB 474 TB
Package#2-7

All Stations
in EPC 1920x1080 H.265 Motion 25 30 30 34 TB 51 TB
Package 8

Total Storage required 350 TB 525 TB

Note:

The storage calculation indictaed are preliminary and shall be further validated by EPC Contractor during
Detail Engineering phase.

10 / 10 Uncontrolled When Printed