Qu 23089 Mipco
Qu 23089 Mipco
Qu 23089 Mipco
To: Messrs
MIPCO
Procurement & Contracts Department
Abu Dhabi – U.A.E
INDEX
------------------------------
PAGE
1. Scope of Work........................................................................................... 3
1.1 Exclusions............................................................................................. 3
2. Economical Proposal................................................................................3
3. Terms and Conditions..............................................................................4
3.1 Notes:(General).................................................................................... 4
3.2 Completion:.......................................................................................... 4
3.3 Payment:.............................................................................................. 4
3.4 Validity:................................................................................................. 4
2
TELFORD INTERNATIONAL LTD
1. Scope of Work
New ECS Shock dosing system nozzle inspection, cleaning & repair
MS and RA will be provided by the inspection party prior to start the job.
Diving team with diving supervisor, Along with Equipment's Test certificates & Divers
Health certificates.
Surface supplied mobile diving unit with CCTV unit, video camera, light, control panel &
diving related equipment’s.
Provide the Inspection report & video.
Provide permit acceptor.
Chemical dosing under water line replacement by diving team including CPVC pipe
material/support material like U clamps.
Technical specification:
Medium: Sodium Hypochlorite (NaOCl) concentration – 12%
Pipe Material specification:
Material: CPVC
CPVC Pipe and Fittings: GF
1.1 Exclusions
Our offer does not include any work other than, specified in Scope of work.
Pipe support material considered are U clamps, bolts, gaskets and neoprene
sheet. In case of any structural material required shall be quoted separately after
underwater inspection.
Any major repair required (will be brought into the notice of concerned TTEO&M
Engineer for further proceedings as variation
Crane/Forklift to be arranged by client
Scaffolding
2. Economical Proposal
Sl no Scope Unit Unit rate Total Cost
(AED) (AED)
Chemical dosing line nozzle under water
1 2 Days 10,305.00 20,610.00
inspection & cleaning by diving team
Chemical dosing under water line
replacement by diving team including CPVC Lump
2 29,880.00 29,880.00
pipe material/support material sump
3
TELFORD INTERNATIONAL LTD
3.2 Completion:
As per above scope of work
3.3 Payment:
As per MIPCO standard payment terms
3.4 Validity:
Our Offer is valid for 60 days from date the of order submission.