Method Statement For Testing and Commissioning OF Lighting Control System
Method Statement For Testing and Commissioning OF Lighting Control System
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All
previous cover pages are hereby superseded and are to be destroyed.
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.0 PROCEDURE
8.0 ATTACHMENTS
PROJECT NAME
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Lighting Control System Testing and
Commissioning Page 3 of 12
1.0 PURPOSE
The purpose of generating this method statement is to define the procedure step by step to implement the
correct practices for Lighting Control System Testing and commisioning through the guidelines contained
herein so as to ensure that the job execution complies with specification and serves the intended function to
satisfactory level where applicable in the building of the project.
2.0 SCOPE
This document details the Lighting Control system Testing and commissioning for
Implementation proposed to Petrolleum instiute research Centre as follow:
3.0 REFERENCE
4.0 DEFINITIONS:
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are
specified at relevant steps in the procedure:
- Project Manager.
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- Stor Keeper
- Project Manager is the overall responsible for the project in terms of work execution, safety, planning &
quality. The Project Manager will maintain the planning progress and coordination of works with the
main contractor.
- The work progress shall be carried out as per planned program and all the
equipment’s required to execute the works shall be available and in good
condition as per project planned.
- Specific attention is paid to all safety measures and quality control in
coordination with Safety Engineer and QA/QC Engineer and in line with PSP and
PQP.
- The monitoring of executions of works at site and should be as per the approved
shop drawings and project specifications.
- Ensure WIRs and MIRs are being raised for activities in timely manner and
inspected by the Consultant.
- Check and insure that all activities / work done / completed prior to offer for
consultant inspection.
- He will follow and carried out all the relevant tests as per project specifications.
- Obtain the required clearance prior to Consultant’s inspections.
- Should acquire any necessary civil works clearances and coordination.
- Coordinate with site construction team.
- One who will assist the Consultant Engineer / Inspector during inspection.
- The carrying-out of work and the proper distribution of all the available
resources in coordination with the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning
with the Site Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the
PROJECT NAME
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Lighting Control System Testing and
Commissioning Page 6 of 12
concerned Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the
same to the Site Engineer immediately.
- The implementation of all safety measures in accordance with the HSE plan and
that the whole work force is aware of its proper implementation.
- The implementation of safety measures is adequate to maintain a safe working
environment on the work activity.
- Inspection of all the site activities and training personnel in accident prevention
and its proper reporting to the Construction Manager and the Project Manager.
- The site is maintained in a clean and tidy manner.
- Ensure only trained persons shall operate the power tools.
- Ensure all concerned personals shall use PPE and all other items as required.
- Ensure adequate lighting is provided in the working area at night time.
- Ensure high risk elevated areas are provided are barricade, tape, safety nets
and provided with ladders.
- Ensure service area/inspection area openings are provided with barricade, tape,
and safety nets.
- Ensure safe access to site work at all times.
- Responsible for overall Store operations in making sure to store the material
delivery to the site and keep it in suitable area that will keep the material in safe
from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with
QA/QC and concerned Engineer.
- The carrying-out of work and the proper distribution of all the available resources in coordination
with the sub-contractor Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
- Complying with the sub-contractor basic design practices, particularly those related to safety and
engineering
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
6.0 EQUIPMENTS
7.0 PROCEDURE
- Prior to commissioning carry out a pre – commissioning check as per the check
list given below, to ensure that adequate quality is maintained.
- Testing and commissioning will be done as per specifications for testing and
commissioning of the system:
8.0 ATTACHMENTS
- Quality Control Procedure
- Inspection and Testing Plan
- Check List – Pre-Commissioning
- Check List – T & C Report
- Risk Assessment