(J1) PTW - Electrical Work - Rev04
(J1) PTW - Electrical Work - Rev04
(J1) PTW - Electrical Work - Rev04
Hearing protection/ Pelindung telinga Safety harness/ Pelindung jatuh Arc flashes protective equipment
Alat pelindung dari sinar arc
Other/Lain-lain :
PRECAUTIONS CHECKLIST
Lock-Out and Tag-Out (LOTO) System is implemented (if required). Correct voltage is used for connections.
The area of work has been inspected and found free from Work area is free from flammable liquids or water.
electrical fire hazard. Suitable fire extinguishers are available in the work area.
ELCBs, Grommets and industrial sockets are use in all DPs. Suitable PPE (including high voltage gloves) are provided and
Earthing arrangements are ensured. worn as required.
Suitable safety signs are provided and installed.
I confirm that all the items defined above have been completely examined and found in compliance with HSE requirements, and that the relevant
employees are trained/competent enough for safe execution of the work .
Sub-Contractor’s Electrical Supervisor: Date:
Approved By/ Disetujui oleh Name/ Nama Signature/ Tandatangan Date/ Tanggal
Site Manager / Construction Manager
The Permit is to be signed off 30 minutes prior to the end of the shift at the last valid day of this permit and reported to permit coordinator.
Permit akan ditandatangani 30 menit sebelum berakhirnya shift dan diakhir masa berlaku permit serta laporkan ke Permit Kordinator.
Job Complete/Pekerjaan selesai Job Incomplete/ Pekerjaan belum selesai
I have checked the workplace and declaring that I withdraw all my workforces from the area and it is safe.
Saya telah memeriksa area kerja dan menyatakan bahwa saya telah menarik semua pekerja saya dari dari lokasi kerja dan aman
Permit holder Name and Signature/ Date/
Pemegang Permit dan tandatangan: Tanggal: