Ground Grid Design REVISADO
Ground Grid Design REVISADO
Ground Grid Design REVISADO
MAYAGÜEZ CAMPUS
ENGINEERING DEPARTMENT
Group:
Edgar Vega Feliciano
José Sánchez Rivera
Fernando Lozano Inca
Table of Contents
Tables…………………………………………………………………………………….……2
Material Prices……………………………………………………………………………..…..5
Information Provided………………………………………………………………………..…6
A) Design Rectangular grid without ground rod……………….……………………….…7
B) Design Rectangular grid with ground rods…………………………………………….13
C) Design L-shaped grid with ground rods………………………………………….……..16
References……………………………………………………………….……………………..20
2
Tables
3
Table 2: Typical Values of Df.
4
List Material Prices
Materials Price
5
Information Provided
6
A) Design Rectangular grid without ground rod
The first step of the design was to acquire the conductor information, converting the 211.6 kcmil
Using the resulting mm2, the diameter of the 4/0 AWG conductor is found using equation [2]:
d=
√ 4
π
× A mm 2 [2]
d=
√ 4
π
×107.22=11.684 mm
The next step is to determine the touch and step criteria, which starts with the reflection factor
‘k’ and the surface layer derating factor ‘Cs’, using equation [3] and [4] respectively.
ρ−ρs
K= [3]
ρ+ ρs
285−3000
K= =−0.8265
285+ 3000
C s=1−
0.09 1−
( ρρ )s [4]
2 hs +0.09
C s=1−
0.09 1−(
285
3000 )
=0.7230
2 × 0.102+ 0.09
With the crushed-rock resistivity of 3000 Ω-m and the derating factor the step voltage and touch
voltage is calculated for a person of 50kg, respectively. It is important to note that the voltages
7
0.116
E step50=( 1000+ 6 C s ρ s ) [5]
√ts
0.116
E step50=( 1000+ 6 ×0.7230 ×3000 ) =2298.98V
√0.5
0.116
Etouch 50=( 1000+1.5 C s ρs ) [6]
√t s
0.116
Etouch 50=( 1000+1.5 ×0.7230 ×3000 ) =697.78 V
√ 0.5
Etouch Estep
697.75 V 2298.86 V
Table 4: Design Requirements
The next step is to choose the conductor spacing ‘D’, which was set to 3.8 m between each conductor.
Consequently, the length of the conductor ‘Lc’ is set by equation [7]:
LC = ( LD +1)× L +( LD +1) × L
x
y
y
x [7]
LC = ( 120
3.6
+1 )× 80+ (
3.6 )
80
+1 ×120=5,533.33 m
LT =LC + LR
[8]
The resulting grounding mesh is shown below in figure 1.
8
Figure 1: Rectangular grid without ground rod with D = 3.6
Furthermore, the determination of the grid resistance and the ground current is required in order to
determine the ground potential rise ‘GPR’, and are acquired using equation [8] and [9] respectively.
R g=ρ
[ 1
+
1
LT √ 20 A (
1+
1
1+ h √ 20 / A )] [9]
R g=285
[ 1
+
1
5,533.33 √ 20 ×9600
1+ ( 1
1+0.5 √ 20/9600
=1.3378 Ω)]
I G=D f × Sf × 3× I o [10]
Finally using equation [10] the ground potential rise, the first design test is achieved.
GPR=I G × RG [11]
GPR=5171.04 × 1.3378=6918 V
9
Since the GPR is greater than the touch voltage this means more steps are required to ensure the grid
satisfies the requirements of voltages. The criteria used for determining if the grid is safe is the mesh
voltage ‘Em’ and the ‘Es’ which is the step voltage of the grid. The factors that affect these voltages are
geometric factor composed of factors ‘na’,’nb’,’nc’,’nd’, geometrical spacing factor ‘km’, irregularity
factor ‘Ki’, the corrective weighting factor emphasizing the grid depth ’kh’, and corrective weighting that
adjusts effects of inner conductors on the corner ’kii’, which are calculated from equation [12] through
[20].
2 × LC
n a= [12]
Lp
2 ×5,533.33
n a= =27.6667
400
n b=
√ Lp
4 ×√ A
nb=1 square [13]
n b=
√ 400
4 × √ 9600
=1.0103
[ ]
0.7 × A
Lx × L y Lx × Ly
n c= , nc =1 square∧rectangular
A
[14]
n c=1
n D =1 [15]
n=na ×n b × nc × nd [16]
10
[( ( D+ 2× h )2 K ii
) ( )]
2
1 D h 8
Km= ln + − + × ln
2π 16 ×h × d 8 × D × d 4 × d K h π ( 2× n−1 )
[17]
[( ) ( )]
2
1 3.6
2
( 3.6+ 2× 0.5 ) 0.5 0.7498 8
Km= ln + − + × ln =0.5366
2π 16 ×0.5 ×0.01168 8 × 3.6 ×0.01168 4 ×0.01168 1.2247 π ( 2× 27.9505−1 )
K i=0.644+0.148 × n [18]
K i=0.644+0.148 × 27.9505=4.7807
K h= 1+
√ h
, h =1 m
ho o
[19]
√
K h= 1+
0.5
1
=1.2247
1
K ii = , K ii =1 when rods present
2 [20]
( 2× n ) n
1
K ii = 2
=0.7498
( 2× 27.9505 ) 27.9505
Finally, the mesh voltage is calculated using equation [20], which requires all the previous calculations.
This is going to be the determinant value that decides if the grid can be used.
ρ× I G × K m × K i
Em = [21]
LC + L R
285 × 5,171.04 ×0.5366 × 4.7807
Em = =683.203V
5,533.33+0
For calculating the step voltage, first is needed to acquire the spacing factor for step voltage ‘Ks’.
11
Ks=
[
1 1
+
1 1
+ ( 1−0.5 n−2 )
π 2 × h D+h D ] [22]
Ks=
1
[ 1
+
1
+
1
π 2 × 0.5 3.6+0.5 3.6
( 1−0.527.9505−2) =0.4844 ]
]
As a result, the step voltage is obtained from equation [22].
ρ× I G × K s × K i
E s=
0.75 × LC +0.85 × LR
[23]
285× 5,171.04 × 0.4844 × 4.7807
E s= =822.31 V
0.75 ×5,533.33+0.85 × 0
Therefore, the mesh voltage and step voltage satisfy the requirements presented in table 4.
In the final analysis we found that the biggest spacing, that reduced the cost of the grid and make
the grid safe, was found when a spacing between the conductors is 3.6 meters, resulting in a
12
Figure 2: Matlab Program for part A
The tool used to fasten the process was a program in matlab that used a guide, shown in figure 2.
In this figure it is shown all the vales and parameter used and also the outputs.
13
For this part of the project the developed matlab program was used to iterate and find the
minimum total cost. The mesh voltage and step voltage obtained from part A still apply.
From the table below is seen the options that are suitable for the design. It is important to note
that it was only taken into account the cost of the conductor and rods. Therefore, the most
economic option is with a spacing of 5 meters but it was decided that the 3.8 meters spacing was
Conductor Spacing
Max Rods Number of Rods Em (V) Es (V) Total Cost
(m)
3.8 841 38 697.44 539.54 $ 59,682.60
4 651 110 697.5 505.08 $ 59,286.10
4.5 520 256 697.2 436.09 $ 58,247.90
5 425 364 697.53 384.97 $ 57,122.40
Table 6: Conductor spacing suitable for the design of the grid.
14
To determine the total length of conductors and rods it was first determined that the spacing is
3.8 meters with 38 rods.
LR =nr × Lr [24]
LR =38 ×2.438=92.6440 m
LC = ( 120
3.8
+1 )× 80+ (
3.8 )
80
+1 × 120=5,252.63 m
LT =5,252.63+92.6440=5,345.28 m
R g=285
[ 1
+
1
5,345.28 √ 20 ×9600
1+ (1
1+0.5 √ 20/9600 )]
=1.3397 Ω
GPR=5,171.04 × 1.3397=6927.37 V
Lastly, ‘Em’ and ‘Es’ are computed from equations [11] through [22]:
2 ×5,533.33
n a= =52.5263
400
n b=
√ 400
4 × √ 9600
=0.7144
K ii =1
K h= 1+
√ 0.5
1
=1.2247
15
[( ) ( )]
2
1 3.8
2
( 3.8+2 × 0.5 ) 0.5 1 8
Km= ln + − + × ln =0.4121
2π 16 ×0.5 ×0.01168 8 × 3.8× 0.01168 4 ×0.01168 1.2247 π ( 2× 37.5227−1 )
K i=0.644+0.148 ×37.5227=6.1974
285× 5,171.04 ×0.4121 × 6.1974
Em = =697.377 V
[
5252.63+ 1.55+1.22
(√ 2.438
2
120 + 80
2 )] 92.6440
Ks=
1
[
1
+
1
+
1
π 2 × 0.5 3.8+0.5 3.8
( 1−0.537.5227−2 ) =0.4761 ]
285× 5,171.04 × 0.2374 ×6.1974
E s= =1082.17 V
0.75× 5252.63+0.85 × 92.6440
16
Figure 4: Matlab Program for part B.
For the L-shaped, two rectangles of the same size were used in order to create the geometric
form of an L. The horizontal length was chose to be 100m and the vertical length 48m.
Again, a software was used in order to speed up the process of optimizing the total cost. For
the design this time it was used the most economic option.
Conductor Spacing
Max Rods Number of Rods Em (V) Es (V) Total Cost
(m)
4.5 530 45 697.53 830.93 $ 51,711.00
5 434 153 697.26 763.48 $ 50,585.60
5.5 363 237 697.3 710.14 $ 49,518.50
6 309 304 697.38 666.73 $ 48,528.80
Table 7: Conductor spacing suitable for the design of the grid.
17
Figure 5: L-shape grid with nr=304 and D = 6.
LC =2 ×
[( 100
6 )
+ 1 × 48+(48
6 ) ]
+1 × 100 −48=3,448 m
R g=285
[ 1
+
1
4189.15 √20 × 9600
1+ ( 1
1+ 0.5 √20 /9600
=1.35436Ω )]
GPR=5,171.04 × 1.35436=7,003.46 V
18
2 ×3,448
n a= =13.9032
496
n b=
√ 496
4 × √ 9600
=1.1250
[ ]
0.7 ×9600
100 × 148 100× 148
n c= =1.2172
9600
n=13.9032× 1.1250× 1.2172× 1=19.0378
K ii =1
√
K h= 1+
0.5
1
=1.2247
[( ) ( )]
2
1
2
6 ( 6+ 2× 0.5 ) 0.5 1 8
Km= ln + − + × ln =0.6284
2π 16 ×0.5 ×0.01168 8 × 6 ×0.01168 4 ×0.01168 1.2247 π 2× 19.0378−1 )
(
K i=0.644+0.148 ×19.0378=3.4616
285 ×5,171.04 × 0.6284 × 3.4616
Em = =697.377 V
[
3,448+ 1.55+1.22
2.438
√ 1002+ 1482 (
741.152
)]
Ks=
1
[ 1
+
1 1
+ ( 1−0.519.0378−2 ) =0.4203
π 2 × 0.5 6+ 0.5 6 ]
285× 5,171.04 × 0.4203× 3.4616
E s= =666.773 V
0.75× 3,448+0.85 ×741.152
19
Figure 4: Matlab Program for part C.
Result Discussion
The project analyzes the parameters of the design of a ground grid for a transmission
substation, based on the Std.80 IEE. The software used for to optimize the design of the grid was
20
Matlab, for the evaluation and comparison of the voltages and costs of materials. Three types of
topographies were designed, a rectangular with no rods, which resulted in a minimum cost of
$61,530.7; a second design of a rectangular grid with ground rods resulted in a minimum cost of
$57,122.40; and finally the L-shaped grid with ground rods that had the minimum cost of
$48,528.80. With this result we can conclude that the best design, based on economics, is the L-
References:
[1]. “4/0 Soft Drawn, Stranded, Bare Copper Wire.” Wire and Cable Your Way,
www.wireandcableyourway.com/4-0-soft-drawn-stranded-bare-copper-wire.html
21
[2]. “Copper Coated Ground Rods, 3/4 IN x 8 FT.” What Are the Benefits of a Retrofit? |
Graybar Lighting, www.graybar.com/store/en/gb/copper-coated-ground-rods-3-4-in-x-8-ft-
25405875#{Material Finish:Copper}&{Rod Size (Inches):3/4 in.}&{Length:8 ft.}.
[3]. IEEE Standard Substation committee,“ Std. IEEE 80 Guide for Safety in AC Substation
Grounding”, IEEE Institute of Electrical and Electronics Engineers, 2013.
22