Testing and Maintenance of Substation
Testing and Maintenance of Substation
MUNISH MISHRA
Addl. General Manager (OS-Electrical), NTPC Ltd.
CONDITION MONITORING /
w & e internatioNal (Energy section)
MAINTAINING TOOLS
S. Tool/Test Application Frequency
No.
1 Thermography Complete Monthly
switchyard
2 Hot line washing Switchyard Before onset of
bus bar and foggy season
equipments or quarterly for
except Surge coastal areas.
arresters and
Transformer
EHV bushings
3 PID String insulators SOS
4 Leakage current Surge arresters Monthly
monitoring
5 Dissolved Gas Current After 10 years of Learnings
analysis Transformers service or SOS
• Internal galvanizing was deteriorating gradually, giving
6 Corona Complete Under suspended metal traces in oil and on insulation, resulting
Discharge switchyard consideration as in internal PD. Decision for No internal galvanizing to
new technology be done in CT’s.
adoption
• Practices have been revised since.
7 Walk Down Complete Daily
• CT MB’s should have been away from the CT’s.
Check List switchyard
Failure of Disc Insulator at 400 kV
CASE STUDY- CTs Switchyard
• Failures occurred within few months of charging. • Disc insulators commissioned S/Y started failing.
400 kV Bus tripped due to insulator string failure of
• After the first failure.Electrical Test Results did not
R-phase of Bus on Bus bar protection.
show any abnormality for other CT’s.
• Initially Vendor suggested to wash these.
• DGA of oil samples suggest elevated fault gases i.e.
Hydrogen, in some CT’s. Hence it was decided to • However a detailed study revealed that in spite of a
remove such CT’s from service and observe gas trend more polluted environment for Stage - 1 & 2, such
in others. problem never existed.
• In spite of this, a second incident occurred in July ’11. • No traces of tracking due to pollution.
• This CT showed normal levels of gases in the earlier • At the time of failure: Weather: Sunny
testing. No over voltage.
• The earlier removed CT’s were investigated at OEM • Insulation test and capacitance measurement carried
works. out on same lot insulators.
• Decision was taken to remove all such CT’s from • Thermo vision scanning carried out. Difference in
service till root cause is established . temperature found along the string.
HEALTHY INSULATOR
1 264 GΩ 3 38.3 183 GΩ 2.93 38.3
2 214 GΩ 2.74 36.4 236 GΩ 2.42 36.2
3 224 GΩ 2.51 36.1 264 GΩ 2.18 35.9
4 36 GΩ 29.63 194.3 10.9 GΩ 29.7 193.9
5 650 MΩ 53.95 195.1 404 MΩ 55.45 175.7
Learnings
• Deviation in IR and capacitance indicate varied voltage variation along the string.
• Detailed failure analysis done at Vendors premises. They agreed to replace the entire defective lot free of cost due to
the reason that there was some Quality issue in the complete lot.
• PID of insulator strings and thermo vision scanning can provide early signs of failure.