Shelter-Manual-50 x150 x23
Shelter-Manual-50 x150 x23
Shelter-Manual-50 x150 x23
ASSEMBLY MANUAL
(W50H23DP SERIES)
Model # 5015023
W15.25mxL45.75m xH7.015m
1
5015023DP Parts List
4 Shoulder Tube 28
5 Standing Leg 32
6 Purlin 195
7C Ratchet 40
10L Lower Door Track at Left for Front and Back Door 2
10R Lower Door Track at Right for Front and Back Door 2
11L Upper Door Track at Left for Front and Back Door 2
11R Upper Door Track at Right for Front and Back Door 2
12 Door Crossbeam 4
12A Boom 2
26 Mechanical Wheel 2
Attachment Bag 1
18 Clip 80
24B 10x60 bolt for door beam and Vertical support tube 8
28 Rope 1
29 Tools 2
3
32 10X30mm Bolt 24
35 Roof Cover 3
4
Sketch Frame Figure 1 (W15.25xL45.75xH7.015)m
5
SPECIFICATION
Width: 15.25m Height: 7.015m Length: 45.75m
Door Size: W5.49m x H4.88m
IMPORTANT-----READ MANUAL FIRST
Improper site preparation, Assembly and Maintenance may invalidate warranty and cause
unnecessary and costly mistake. If you have any questions contact your local dealer.
For User Friendly assembly we have identified each individual component with the part code as
indicated in the parts list. Please refer to the part code numbers and drawing to ensure problem free
assembly.
It’s necessary to tighten the roof fabric enough to avoid “hammocks” on the roof and also re-tighten
once or twice again after a few months of use. This is important when assembly in cold weather
(autumn and winter) because the fabric is stiff then and when we got the sun and warm weather
afterwards it will make the fabric “slack” again and need to be re-tighten before next winter.
It’s the owners responsibility to take of snow immediately if not slide off by itself.
READ ALL INSTRUCTIONS BEFORE ASSEMBLY
1. Keep work area clean. Cluttered areas invite injuries. Do not set up near snow drifts, in slippery
places, in high winds, or wet location.
2. Keep children away. All children should be kept away from the work area.
3. Don’t over reach. Keep proper footing and balance at all times.
4. Do not assemble in under the influence of alcohol or drugs. Read warning labels on prescriptions
to determine if your judgment or reflexes are impaired while taking drugs. If there is any doubt,
do not assemble.
5. Be aware of possible windy conditions; fasten the bases in concrete if these conditions are likely
to occur. Remove the cover during hurricane.
6. Be careful with power and heat sources. Do not keep heat sources near the tarpaulin. Do not
expose to open flame.
7. Be aware of personal safety during assembly and use. Be careful not to pinch fingers with clips
and tubes when assembling: when using makes sure there is adequate ventilation for exhaust and
other dangerous fumes.
6
EQUIPEMNT AND TOOLS FOR INSTALIATION
1. Measuring tape
2. Crane
3. String for alignment
4. Step ladder
5. Welder
6. Sledge hammer
7. Wrench
8. Scissors
INSTALLATION PROCESS
A—BASE PLATES INSTALLATION
Please refer to the diagram (Base Plate Figure 2) to place the base plates.
7
B—MAIN FRAME INSTALLATION
1.(Part No. 1A*1+No.2A*2+No.3A*2+No.4A*2 + No.5*2)As Figure 3 shown, to find one piece
of top bent tube for front and end wall (No.1A), two pieces of upper roof curving tube for front
and end wall (No. 2A), two pieces of lower roof curving tube for front and end wall (No.3A), two
pieces of shoulder tube for front and end wall (No. 4A) and two piece of standing leg (No.5).
Connect them by using bolt 12*40mm (No. 23), which makes the first group of end arch frame.
8
Middle Arch Frame Figure 4
3.As Figure 5 shown,after installing these two groups of arch frame, please connect the purlin
(No.6) between these two groups of arch frame using bolt 10*90mm (No. 24). There are 13
pieces of purlin (No. 6) between each two groups. By turns, after install other groups of arch
frame and purlin, the assembly of the main frame is finished.
Figure 5
9
4.Connect the steel wire at side (No.17 )with purlin (No.6) by using iron triangle(No.18A) and bolt
10*90(No.24) . Assemble steel wire between two arches (No.19) and longitudinal steel wire one
the top of each arch (No.19A) by using clip(No.18)(see Figure 5).
Do not tighten down the nuts completely until frame is fully assembled and set in place. the
arches, the front and back panel should be assembled well on the ground before erected into
the base flanges.
Figure 8
2. Spread the door cover (No. 34) on the ground, and insert the vertical support tube (No. 25)
into the horizontal fabric pouch of the door cover.
11
3. Wrap the steel wire on the mechanical wheel (No.26 ). Then put it through the double
pulley to the single pulley. The other end of steel wire through the double pulley directly.
4. Then let the installed steel wire go down through the hole on the vertical support tube
(No.25) separately from top to bottom. Tie a knot in the bottom of vertical support tube, so
it cannot pass back .
5. Erecting the whole door cover and fix it well on the frame by using rope.
6. Thus, the door can be open and close by operating the winch wheel.
Figure 9
1. Spread the roof cover (No. 35) and lay parallel to one side of the frame.
2. Insert the tension tube (No. 22) into one side of roof cover only and cut some pockets which
correspond to the position of ratchet. Then place the plastic plug (No. 27) on each end of
tubes.
3. Attach the ropes and throw over the frame. Then pull the roof cover EVENLY, CAREFULLY AND
SLOWLY.
4. Do not forget to insert PVC tube ( No. 31) into the front and back ends of roof cover, and fix
them by using small ratchet ( No.33). Finally knit them using rope. ( If the whole roof cover is
made up by several pieces of small cover, please also insert PVC tube to two sides of each
small cover and combine them by rope.)
12
Figure 10 (5015023DP have 3 pcs of roof cover)
(A) (B)
14
(C) (D)
(E) (F)
NOTE: DO NOT LEAVE THE ROOF COVER UNATTACHED UNDER ANY
CIRCUMSTANCES until the final assembly and tightening has been completed.
The process is quite easy. But some tightening adjustments will be necessary to
produce a flat, tension ed roof cover. Please adjust the roof cover every month.
Please Note:
Please use the tape wrapped around the gap between the steel
skeleton after installing.
15