PMP Documentation V7-English
PMP Documentation V7-English
PMP Certification
• PMI vs PMP ?
• Requirements for PMP exam
• Guidelines for completing PMP application
• About the PMP exam
PMI vs PMP
PMI : Project Management Institue
– Non profit organisation based in USA
– Certification program
– Local chapters
10/12/2021 10
Summary
10/12/2021 11
Chapter 1 : The
Fundamentals of
project Management
10/12/2021 12
Project Management Fundamentals
A PROJECT :
A PROJECT characteristics :
1. Scope
2. Time
3. Cost
Project Management Fundamentals
Modern approach :
A project has more than three constraints
Project Management Fundamentals
AN OPERATION
« Is ongoing endeavover that produce repetitive outputs, with resources
assigned to do basically the same set of tasks according to the standards
institutionalized in a product life cycle »
Characteristics
Repetitive
Dedicated resources
Business process oriented
Project Management Fundamentals
A PROGRAM
A PORTFOLIO
PROJECT MANAGEMENT
Life Cycle(1/4)
Life Cycle(2/4)
There are many types of project life cycles depending on the industry we work in.
• Predictive : project scope, time and cost are determined in the early phases
then changed are carefully managed.
• Iterative : project scope is determined in the early phases but time and cost
estimate are routinely modified as the team understanding increases.
• Adaptive : the detailed scope is defined and approved before the start of an
iteration (agile method or change-driven life cycle)
• Hybrid: a combination od predictive and adaptive lifecycle. If the scope is
known enough (predictive) if not (adaptive)
Project Management Fundamentals
Life Cycle(4/4)
Project Phase
Project Gate
a project collect, analyses, transforms and distributes lots of data and information, in
various format, to project team members and other stakeholders.
Tailoring
Projects exist and operate in environments that may have an influence on them.
• conditions, not under the control of the project team, that influence the project
• internal or external to the organization
• input to almost all processes
exp:
- Organizational culture, structure and governance
- Geographic distribution of facilities and resources
- Infrastructure
- Information technology software
- Marketplace conditions
- Financial considerations
- Political climate
Environment in which projects operate
• Plans
• Processes
• Policies
• Procedures
• Knowledge bases
It also includes the organization's lessons learned from previous projects and
historical information
Environment in which projects operate
Stakeholders
« An individual, group, or organisation who may affect, be affected by, or
perceive itself to be affected by a decision, activity, or outcome of a project »
Environment in which projects operate
Projectized (project-oriented)
Project
coordination
CEO
Matrix (1/2)
CEO
Matrix (2/2)
1. Balanced : the functional manager and the project Manager have the same
level of influence
2. Strong : The Project Manger has more influence than the functional manager
3. Weak : The functional Manger has more influence than the Project Manager
, in this form of matrix organisation the project manager’s role might be more of
a :
Project Expediter: Staff assistant and communication coordinator,
but connot make decisions.
Project Coordinator: have power to make some decisions.
Environment in which projects operate
Power Balance
The role of Project Manager
The Role of Project Manager
PM definition
• Project Team
• Resource Managers
• Sponsors
• PMOs
• Stakeholders
The Role of Project Manager
PM competences
Leadership skills
involve the ability to guide, motivate and direct a team.
Dealing with people :
study people’s behaviors and motivations
Manager Vs Leader
The Role of Project Manager
Manager vs Leader
The Role of Project Manager
Performing Integration
• Project manager play a key role in working with the sponsor to understand the
strategic objectives and ensure the alignment of the project objectives and results
with those of business areas.
• Project manager is responsible for guiding the team to work together to focus on
what is really essential at the project level : integration of processes, knowledge
and people.
• We assume that the organizations has a formal process to review and analyze
potential projects and select the projects that best align with the strategic goals of
the organization.
• The reasons a project was selected can impact which constraints are more flexible
and will influence how the project manager plans and manages the project.
Project Selection
• Net Present Value (NPV) : PV of the total benefits (income or revenue) minus
the costs over many time periods.
If the NPV is positive, the investment is a good choice
The project with the greatest NPV is typically selected.
Question : An organization has two projects from which to choose
1. Project A will take three years and has an NPV of $45,000.
2. Project B will take six years and has an NPV of $85,000.
Project Selection
• Payback Period : refers to the length of times it takes for the organization to
recover its investment in a project before is starts accumulating profit.
Example : The are two projects from which to choose ?
1. Project A with a payback period of six months.
2. Project B with a payback period of 18 months.
Exercice
Summary
10/12/2021 59
Chapter 2 :
Predictive
project Management
10/12/2021 60
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Integration management
• Develop Project Charter
• Develop Project Management Plan
• Direct and Manage Project Work
• Manage Project Knowledge
• Monitor and Control Project Work
• Perform Integrated Change Control
• Close Project or Phase
62
Integration management
Definition:
63
Integration management
Monitor and Control Project Work Monitoring and controlling process group
64
Develop project Charter
Develop Project Charter process
66
Develop project Charter
The PC may be created by the PM but is issued by the sponsor in the initiating
process group.
the PC is influenced by all the project management knowledge area, this is
why Develop Project Charter is an Integrated process.
67
Project charter
68
Develop project Charter
Business Document
• Business case explains the business need and the analysis used to justify the project
investment:
Which of the possible projects or programs will best support your company’s strategic plan.
69
Develop Project Management Plan
OPAs
Interpersonal and team
skills
- Conflict Management
- Facilitation
- Meeting Management
Meeting
70
Develop project management plan
Management plan:
• = The strategy for managing the project and the processes in each knowledge area: How
will I define, plan, manage and control: scope, schedule, cost, quality,…) the creation of
PMP is an integral part of PM’s job.
• 3 Baselines :
• Scope baseline
• Schedule baseline
• Cost baseline
• Additional components :
• Requirements management plan
• Change management plan.
• Configuration management plan.
• Project lifecycle description.
• Development approach
71
Develop project management plan
72
Direct and Manage project Work
• The process of leading and performing the work defined in the project
management plan and implementing approved changed to achieve
the project's objectives
73
Direct and Manage project Work
Schedule
Budget
Executing project = managing Risk
Quality
... (other knowledge areas)
The project manager should:
Ensure common understanding: make sure everyone has the last version of
communication management plan and knows how to use it
Being of service: Assisting the team in implementing solutions, letting them know
about information that will affect them, facilitating the team discussion to review
options,…
74
Direct and Manage project Work
75
Manage Project Knowledge
OPAs
76
Manage Project Knowledge
Knowledge Management:
Tools and techniques which connect people, face-to-face or virtually, or both so they can work together
to create new knowledge, share this knowledge and integrate other team members knowledge.
• Networking
• Meetings
• Discussion forums (focus group)
• conferences, seminars, workshops
• Training...
Information Management:
Tools and techniques used to create information then connect people to this information in order to
share simple, unambiguous, codified explicit knowledge for this process.
• Method for codifying knowledge
• Lessons learned register
• Library services
• Project Management Information System (PMIS)
• Information gathering...
77
Monitor and control project work
78
Monitor and control Project Work
The change requests are evaluated and approved or rejected in the Perform
integrated change control process.
Monitor & Control project Work is not Monitoring and controlling process group.
79
Monitor and control Project Work
Change requests:
Result of comparing planned results to actual results.
Changes may include: Corrective actions, Preventive actions, and defect repair.
80
Monitor and control Project Work
Preventive action:
A documented direction to perform an activity that can reduce the probability of negative
consequences associated with project risks.
Defect repair:
The formally documented identification of a defect in a project component with a
recommendation to either repair the defect or completely replace the component.
81
Perform Integrated change control
82
Close Project or phase
INPUT Tools & Techniques OUTPUT
Agreement
Procurement documentation
OPAs 83
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Scope management
• Overview
• Plan Scope Management
• Collect requirements.
• Define scope.
• Create WBS (Work breakdown structure)
• Validate Scope
• Control scope
85
Scope management
Scope management processes:
86
Plan Scope Management
87
Plan Scope Management
EEF Meeting
OPAs
88
Collect Requirements
Collect Requirements process
89
Collect Requirements
91
Define scope
Define Scope = Define what is and what is not included in the project and its
deliverable.
Determine
requirements 1
Project scope 5
statement
2
Go-Back: Determine
Determine
Adjust requirements budget & Schedule
Scope
4
Balance
requirements
against the budget & Schedule 3
and other constraint
92
Define scope
93
Define scope
Project Scope Statement:
94
Create WBS
EEF
OPAs
95
Create WBS
WBS: Work Breakdown Structure
WBS breaks the project into smaller and more manageable pieces.
WBS shows a complete hierarchy of the project.
The first level of the WBS is completed before the project is broken down further.
Each level of the WBS is a smaller piece of the level above.
WBS includes only deliverables that are really needed.
WBS is created with inputs from the team and stakeholders.
Creating WBS allows the team to walk through the project in their minds and improvs the project plan.
WBS helps people better understand the project and makes it feel more achievable.
96
Create WBS
WBS Dictionary
Scope baseline:
97
Validate Scope
98
Validate Scope
Project documents
Project documents - Requirement documentation
- Requirement documentation - Requirement Traceability Matrix
- Requirement Traceability Matrix - Lessons learned register
- Quality Report
- Lessons learned register
Verified delivrables
99
Validate Scope
Inputs
Work must be completed and checked each time before you meet with the customer:
Validated deliverable from the CONTROL QUALITY process.
Take the approved scope with you
Requirements traceability matrix
The requirements documentation
Outputs
Accepted deliverables
Change requests
Work performance information
Project documents updates
100
Validate Scope
The two processes are very similar: both involve checking for the correctness of work.
Perform Quality Control: The quality control department checks to see if the quality
requirements specified for the deliverables are met and makes sure the work is correct
Validate Scope: the customer checks and hopefully accepts the deliverables.
101
Validate Scope
Complete deliverables
(Direct & manage project Execution)
QC inspection
(Validate deliverables)
Validate Scope
(Meet customer) Changes are requested
(Ask customer for a description of the change)
102
Control Scope
103
Control Scope
104
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Schedule management
• Plan Schedule Management
• Define Activities
• Sequence Activities
• Estimate Activity Durations
• Develop Schedule
• Control Schedule
106
Schedule management
107
Plan Schedule Management
108
Plan Schedule Management
109
Define Activities
110
Define Activities
111
Sequence Activities
112
Sequence Activities
Network diagram
Start End
113
Sequence Activities
Activity A Activity B
114
Sequence Activities
Activity B Activity B
115
Sequence Activities
Activity duration
ES EF
Activity name
Float
LS LF
116
Sequence Activities
Types of dependencies
117
Sequence Activities
Leads and lags
118
Estimate Activity Durations
119
Estimates Activity duration
OPAs
120
Estimate Activity Durations
One-point Estimate : in this technique, the estimator submits one estimate per
activity. This type of techniques is used for projects that do not require a
detailed, highly probable schedule .
121
Estimate Activity Durations
Parametric Estimating :
- Used algorithm to calculate cost or duration based on historical data and project
parameters.
- It Uses a statistical relationship between historical data and other variables to
calculate an estimate for activity parameters, such as cost, budget and duration
- This technique can produce higher levels of accuracy depending on the
sophistication and underlying data built into the model
122
Estimate Activity Durations
Three point Estimate (PERT) : With this technique ,estimators give an optimistic (O),
pessimistic(P), and most likely (M) estimates for each activity, this ultimately provides a risk-based
expected duration estimate by taking average or a weighted average of the three estimates.
𝑃 + 4𝑀 + 𝑂
(Beta distribution)
6
Expected Activity Duration (EAD) :
𝑃+𝑀+𝑂
(Triangular distribution)
3
𝑃−𝑂
Beta Activity Standard Deviation (SD or σ) : 6
𝑃−𝑂
Activity Variance (V) : [ ]²
6
⇒ 𝑉 = (𝑆𝐷)²
123
Develop Schedule
124
Develop Schedule
OPAs
125
Develop Schedule
Resource leveling
Resource smoothing
126
Develop Schedule
Critical Path :The sequence of schedule activities that determines the duration
of the project , It is the longest path through the project .
Near-critical path : the path wich is close in duration to critical path.
Float (Slack) :Total Float ,Free Float ,Project Float
127
Develop Schedule
Total Float : the amount of time an activity can be delayed without delaying the
project end date or an intermediary milestone.
Free Float : the amount of time an activity can be delayed without delaying the
early start date of successors
Project Float :the amount of time a project can be delayed without delaying the
externally imposed project completion date required by costumer or management.
128
Develop Schedule
Data analysis:
129
Develop Schedule
Schedule compression
Fast tracking :This techinque involves doing critical path activities in parallel
that were originally planned in series.
130
Control Schedule
131
Control Schedule
132
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Cost Management
134
Cost Management
135
Plan Cost Management
136
Plan Cost Management
137
Plan Cost Management
Meeting
EEF
OPAs
138
Estimate Costs
139
Estimate Costs
OPAs
PMIS
Decision Making
- Voting
140
Estimate Costs
Estimating techniques
One-point estimate
Analogous estimating
Parametric estimating
Three-point estimates
141
Estimate Costs
Estimating techniques
142
Estimate Costs
Range of estimating
Definitive Estimate: Later during the project, the estimate will become
more refined (+/-10%)
143
Determine Budget
144
Determine Budget
Determine Budget
145
Determine Budget
Business documents
- Business cases
- Benefit management plan
Agreement
EEF
OPAs
146
Control Costs
148
Control Costs
149
Control Costs
150
Control Costs
151
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Quality Management
Program
153
Quality Management
Definition:
Quality management:
includes creating and following policies and procedures to ensure
that a project meets the defined needs it was intended to meet from
the customer’s perspective.
This can also mean the same thing as completing the project with no
deviations from the project requirements.
154
Quality Management
155
Quality Management
156
Quality Management
Notes about Quality:
• Gold Plating: Giving the customer extras (extra functionality, higher quality
components, extra scope,…)
Advanced quality thinking does not recommend this practice and neither does
PMI.
• Prevention over Inspection: «Quality must be planned in, not inspected in »
Is it better to inspect work to find problems or to prevent them in the first place?
• Marginal Analysis: Looking for the point where the benefits or revenue to be
received from improving quality equals the incremental cost to achieve that
quality
157
Quality Management
Notes about Quality:
• Just in Time (JIT): Receiving goods only as they are needed in the production
process, thereby reducing inventory costs.
158
Plan Quality management
159
Plan Quality Management
This technique helps make sure the project is not spending too much to
assure quality.
COQ involves looking at what the costs of conformance and non-
conformance to quality will be on the project and creating an appropriate
balance.
161
Plan Quality management
• Benchmarking:
Looking at past projects to get ideas for improvement on the current project
and to provide a basis to use in measuring quality performance.
162
162
Plan Quality management
• Flowcharting:
163
Plan Quality management
Outputs
164
164
Plan Quality management
Outputs
165
165
Manage quality
166
Manage Quality
INPUT Tools & Techniques OUTPUT
Data Analysis
Data Gathering
Decision Making
Data Representation
Design for X
Problem Solving
Quality improvement Methods
se
168
168
Manage quality
These tools and techniques are used as part of the Manage quality process
Manage quality reviews the quality management plan and uses the
measurements taken in the quality control process
Quality Audits:
Checks if you are complying with company policies, standards, and procedures
Determine whether the policies, standards, and procedures being used are
efficient
se and effective
Usually done by QA department, but could be done also by the PM
169
169
Manage quality
Process Analysis:
170
170
Manage quality
171
171
Manage quality
172
Control Quality
INPUT Tools & Techniques OUTPUT
173
Control quality
Definition
174
174
Control quality
Terms to learn:
3 or 6 Sigma :
175
175
Control quality
Terms to learn:
X-Sigma :
176
Control quality
1- Data Gathering
2- Data Analysis
3- Inspection
4- Testing / product evaluations
5- Data representation
6- Meeting
177
Control quality
Control Chart
Spécification limit:
Out of control:
Rule of Seven:
Mean (Average)
178
178
Control quality
179
179
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Project Resource Management
181
Project Resource Management
Resource Management processes :
182
Plan Resource management
183
Plan Resource management
Notes
• Other project may be competing for the same resources May impact
project costs , Schedules , risks , quality ….
184
Plan Resource Management
Meeting
EEF
OPAs
185
Plan Resource management
Expert Judgment
Data representation
• Hierarchical charts : WBS ; OBS ; RBS
• Assignment Matrix : RACI Chart
• Text oriented formats
Organizational theory
Meeting
186
Plan Resource management
Outputs
187
Estimate Activity Resources
• The process of estimating team resources and the type and quantities of materials ,
equipment and supplies necessary to perform project work
• This process is performed periodically throughout the project as needed
• This process was in Time management
• This process is closely coordinated with other processes such as Estimate Costs
process
188
Estimate Activity Resource
PMIS
EEF
Meeting
OPAs
189
Acquire Resources
• The process of obtaining team resources and the type and quantities of materials ,
equipment and supplies necessary to perform project work
• This process is performed periodically throughout the project as needed
190
Acquire Resources
191
Acquire Resources
Negotiating:
Resources may be acquired through negotiation.
Resource can also be acquired from outside the organization from
external vendors, suppliers, contractors…
Virtual team:
Teams that don’t meet face to face. In the big projects, you can
reach out to the whole world to find the best team members
Hallo Effect:
Something to be aware of when dealing with team members.
Exple: you are a great programmer, therfore, we will make you a PM, and expect
you to be great at that as well
192
Develop Team
• The process of improving competencies, team member interactions and the overall
team environment to enhance project performance
193
Develop Team
194
Develop Team
High performance can be achieved by :
• Forming
• Storming
• Norming
• Performing
• Adjourning
195
Manage Team
196
Manage Team
OPAs
197
Manage Team
198
Manage Team
The PM will likely need to use many leadership styles through the life of a project.
The term ‘’Situational leadership’’ refers to a manager using different leadership
styles, based on the people and project work they are dealing with.
Terms related to leadership:
• Directing
• Facilitating • Bureaucratic
• Coaching • Charismatic
• Supporting • Democratic or Participative
• Autocratic • Laissez-faire
• Consultative • Analytical:
• Consultative-Autocratic • Driver
• Consensus • Influencing
• Delegating
199
Manage Team
Conflict Management:
• Conflict is inevitable, because of :
200
Manage Team
Conflict Management:
• Conflict can be beneficial:
201
Manage Team
Conflict Management:
Through openness
By identifying the cause
By people involved and their immediate managers (not by physical
separation or upper management) intervention (last choice)
One exception: Breaking laws, policies, ethics (instances of professional & social
Responsibility), the PM must go over the head of the person in conflict
202
Manage Team
Conflict Management:
203
Manage Team
204
Control Resources
205
Control Resource
OPAs
206
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Communication Management
208
Communication Management
209
Communication Management
210
Plan Communication Management
Meeting
211
Plan communications management
Other stakeholders
212
Plan communications management
• Communications types
• Communications Models
• Communications Technology
• Communications Channels
213
Plan communications management
Communications types
214
Plan communications management
Communications models
Message
Encode Decode
215
Plan communications management
Communications models
• Effective communication
• Effective listening
216
Plan communications management
217
Plan communications management
Communications Channels
N(N-1)/2 , Where N equals the number of people
218
Plan communications management
• Needs
• Reasons
• Between
• Methods
• Responsible
• When
• How often
219
Manage communications
220
Manage Communications
OPAs Meeting
221
Manage communications
Manage communications
• It goes beyond the distribution of information and seeks to ensure that the
information being communicated to project stakeholders has been appropriately
generated as well as received and understood.
• Techniques for effective communications management include
Sender-receiver models
Choice of media
Writing style
Meeting management techniques : Conflicts
Presentation techniques
Facilitation techniques
Listening techniques
222
Monitor communications
223
Monitor Communications
OPAs
224
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Risk Management
226
Risk Management
Risk management:
• Includes risk management planning , the identification , qualitative and quantitative
analysis of risks , risk response planning and monitoring and controlling the risk reponses.
• It saves time and money on a poject
• The project manager works to increase the probability and impact of opportunities on
the project.
• The project manager works to decrease the probability and impact of threats to the
project
• Risks are identified and managed starting in initiating and are continually kept up-to-
date or added to while the project is underway
227
Risk Management
Uncertainty
• A lack of knowledge about an event that reduces confidence in conclusions
drawn from the data.
se
228
228
Risk Management
Risk factors
• The probability that will occur (What) .
• The range of possible outcomes
• Expected timing in the project life cycle
• The anticipated frequency of risk events from that source (how often)
se
229
229
Plan Risk Management
EEF
OPAs
230
Plan Risk Management
Plan risk management
231
Plan Risk Management
232
Plan Risk Management
Companies and PMO should have standard lists of risk categories that all projects
can use to help identify risks.
• External : market shifts , Regulatory , government
• Internal : Time , cost or scope changes , inexperience , poor planning
• Technical : Changes in technology
• Unforeseeable
233
Plan Risk Management
234
234
Plan Risk Management
235
235
Identify Risks
• Checklist analysis
• Diagramming techniques : Ishikawa diagrams
237
Identify Risks
238
Perform Qualitative Risk Analysis
239
Perform Qualitative Risk Analysis
Update Project
Expert judgment Document
Project Management Plan Data Gathering
- Risk Management Plan - Risk Rigister
- Interviews - Risk Report
- Stakeholder Register
Project Document Interperonal and team skills - Issue log
- Risk Rigister - Facilitation
- Assumption log
- Stakeholder Register
Data Analysis
- Risk data quality assessement
- Risk Probability and impact assessement
EEF - Assessement and other parameters
OPA
Risk Categorization
Data representation
- Probability and impact Matrix
- Hierarchical charts
Meeting
240
Perform Qualitative Risk Analysis
241
Perform Qualitative Risk Analysis
242
Perform Qualitative Risk Analysis
243
Perform Qualitative Risk Analysis
To remember
• Watchlist (non-critical or non-top risks)
• Trends : qualitative analysis may be redone in planning or while the project
work is being done because the project manager should know if risk is
increasing , decreasing or staying the same
244
Perform Quantitative Risk Analysis
Perform Quantitative risk analysis
It involves a numerical analysis of the probability and impact of the risks moved to
this process
• .Determine which risk event warrant a response
• Determine overall project risk
• Determine the quantified probability of completing the project objectives
• Determine cost and schedule reserves
• Identify risks requiring the most attention
• Is more research needed to understand the risk before a quantitative assessment
can be done?
• Create realistic targets
245
Perform Quantitative Risk Analysis
EEF
OPA
246
Perform Quantitative Risk Analysis
247
Perform Quantitative Risk Analysis
248
Perform Quantitative Risk Analysis
249
Perform Quantitative Risk Analysis
250
Perform Quantitative Risk Analysis
251
Plan Risk responses
Plan risk responses
252
Plan Risk Responses
253
Plan Risk responses
Tricky points
• Can you eliminate all risks on a project ?
• Do something to make sure the opportunities happen
• Decrease the probability and/or impact of threats or increase the probability
and/or impact of opportunities
For the remaining residual threats that cannot be eliminated
• Do something if the risk happens (Contingency plans)
• Do something if contingency plans are not effective (Fallback plans)
254
Plan Risk responses
255
Plan Risk responses
256
Plan Risk responses
257
Implement Risk Responses
258
Implement Risk Responses
OPA
259
Monitor Risks
Control risks
260
Monitor Risk
261
Monitor Risks
Control risks
Other work that will be part of the monitor and control risks process includes
• Workarounds
• Risk assessments
• Risk audits
• Reserve analysis
• Status meeting : Risk should be a major topic at status meeting to keep focus on
risks
• Closing of risks that are no longer applicable
262
Monitor Risks
WPI
Change request
Project management plan updates
Project document updates
Organizational process assets updates
263
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Procurement Management
265
265
Procurement Management
• The project manager needs to plan for the time procurements take
• The four sequential procurement management process are
266
Plan Procurement Management
INPUT Tools & Techniques OUTPUT
OPA
267
Plan Procurement Management
268
Plan Procurement Management
Make-or-buy analysis
The cost invlolved in managing the procurement should be considered as part
of the decision , in addition to the direct costs of the product or service
Example
• to lease : daily lease cost is 120$
• To buy : Investment 1000$ + Daily cost is 20$
How long it will take for the lease cost to be the same as the purchase cost ?
269
Plan Procurement Management
270
Plan Procurement Management
Contract types
There are just three main categories of contract types
• Fixed price (FP)
• Time and material (T&M)
• Cost reimbursable (CR)
271
Plan Procurement Management
272
Plan Procurement Management
273
Plan Procurement Management
Contract types: Fixed price (FP)
3) Fixed price Award fee (FPAF)
• Award amount based on performance
• The total possible amount is determined in advance
• Example : there is a maximum of X$ fee available
• The award paid is judged subjectively
274
274
Plan Procurement Management
Contract types: Fixed price (FP)
4) Fixed price Economic price Adjustment (FPEPA)
5) Purchase order PO
• Fixed price contract
275
275
Plan Procurement Management
Contract types: Time and material
• The buyer pays on a per-hour or per item-basis
• it has elements of a fixed price contract ( Price per hour ) and a CR
contract (In the material costs)
• We should add « not to exceed » clause in the contract
276
276
Plan Procurement Management
Contract types: Cost reimbursable (CR)
Cost Reimbursable
• Is used when the exact scope of work is uncertain Costs cannot be
estimated accurately enough to use FP
• The buyer has the most cost risk because the total costs are unknown
• Example : Research and development
1) Cost contract
• There is no profit (non-profit organizations)
2) Cost plus fee (CPF) or cost plus percentage of cost (CPPC)
• The buyer must pay all costs plus a percentage of costs as fee
• Sellers are not motivated to control costs
277
Plan Procurement Management
Contract types: Cost reimbursable (CR)
3) Cost plus fixed fee CPFF
• Plus negotiated fee that is fixed before the work begins
4) Cost plus incentive fee
• Plus a fee that will be adjusted according to performance
• We estimate the total cost
• The seller gets a percentage of the saving if the actual costs are less than the
target costs
• The seller shares the cost overrun with the buyer (80% the buyer and 20%
the seller )
• Exercise
se
278
278
Plan Procurement Management
• The buyer pays all costs and a base fee plus an award amount based on
performance
279
Plan Procurement Management
Contract types
280
Plan Procurement Management
281
281
Plan Procurement Management
• RFP request for proposal : it request a detailed proposal on how the work
will be accomplished , who will dot it , price , company experience
• Invitations for bid (IFB , or request for bid , RFB) IFBs usually request a
total price to do all the work
• Request for quotation (RFQ) requet a price quote per item , meter or other
unit of measure
282
282
Plan Procurement Management
283
283
Conduct Procurement
Conduct procurement
It invloves
• getting the procurement documents created in the plan procurements
process to the sellers
• answering the seller’s questions
• Reviewing the responses to select a seller
284
284
Conduct Procurement
INPUT Tools & Techniques OUTPUT
287
Control Procurement
Conflict
The procurement manager is the only one with authority to change the contract
If the project manager want to initiate a change to the procurement state
of work , it cannot be changed without the procurement manager’s
approval
Termination
Contract can be terminated before the work is complete
Termination for cause : the seller breaches the contract
for convenience : The buyer no longer want the work to be done
288
Predictive Project
ProgramManagement
Integration management
Scope management
Schedule management
Cost management
Quality management
Resource management
Communication management
Risk management
Procurement management
Stakeholder management
Social and professional responsibilities
Stakeholder management
Stakeholder management
290
Stakeholder management
291
Stakeholder management
Stakeholders management Done during
Identify all of them Initiating
Determine their requirements Initiating
Identify Stakeholders
293
Identify stakeholder
294
Identify Stakeholder
295
295
Identify Stakeholder
Stakeholder register
The Stakeholder register should be consulted and updated regularly
• Identification information : Name , organizational position…
• Assessment information : Major requirements , main expectations…
• Stakeholder classification : Internal/External ,
Supporter/Neutral/Resistor
296
296
Plan Stakeholder engagement
297
Plan Stakeholder engagement
Stakeholder register
Enterprise environmental factors
Organizational process Assets
298
298
Plan Stakeholder engagement
C : Current D : Desired
299
299
Manage Stakeholder engagement
300
Manage Stakeholder Engagement
301
Monitor Stakeholder engagement
302
Monitor Stakeholder Engagement
INPUT Tools & Techniques OUTPUT
Work performance
Project Management Plan Data analysis
- Stakeholder engagement plan - Alternatives analysis Information
- Communication Management plan - Route cause Analysis Change Request
- Resource Management plan - Stakeholder Analysis
Meeting 303
Summary
10/12/2021 304
Chapter 3 :
Agile
project Management
10/12/2021 305
Agile project Management
10/12/2021 307
Section 1 :
Agile Introduction &
Overview
10/12/2021 308
Agile Introduction & Overview
Objectives
10/12/2021 309
Agile Introduction & Overview
Definition of Agile
10/12/2021 310
Agile Introduction & Overview
What is Agile
Agile is a famliy of project devlopment processes
Agile emphasis:
• Face-to-face communication;
• Business and developer collaboration
• Working software as the primary
demonstration of progress
• Emphasis of effective engennering technicques
• Ferquent demonstartions of progress and early
return of investment
• Adaptation to business change ; and
• Retrospectives and continuous improvement
10/12/2021 311
Agile Introduction & Overview
10/12/2021 312
Agile Introduction & Overview
Agile Manifesto Principles
Source: www.agilemanifesto.org
10/12/2021 313
Agile Introduction & Overview
Agile Core Principles and practices
Continuous
Accpetance of all
Involvement of the
requirements
customer
Sustainble peace of
Retrospectives
velocity
10/12/2021 315
Agile Introduction & Overview
Benefits of Agile
As Agile has rapidely become one of the more popular and effective techniques to
manage projcts , it is imporant to understand the benefits to its adopters
10/12/2021 316
Agile Introduction & Overview
Quiz
Quest 1 : what does the Agile manifesto principle « Build projects around motivated
Individuals » mean?
10/12/2021 317
Agile Introduction & Overview
Response
Quiz
Quest 1 : what does the Agile manifesto principle « Build projects around motivated
Individuals » mean?
10/12/2021 318
Agile Introduction & Overview
Quiz
Quest 2 : Which of the following is not seen as a benefit of Agile ?
10/12/2021 319
Agile Introduction & Overview
Response
Quiz
Quest 2 : Which of the following is not seen as a benefit of Agile ?
10/12/2021 320
Agile Introduction & Overview
Quiz
Quest 3 : why doesn’t Agile recommand Big Design up-front ?
o Designing up front wastes time that can be better spent on other activities
10/12/2021 321
Agile Introduction & Overview
Quiz
Response
Quest 3 : why doesn’t Agile recommand Big Design up-front ?
o Designing up front wastes time that can be better spent on other activities
10/12/2021 322
Agile Introduction & Overview
Quiz
Quest 4 : why is continous integration seen as valuable ?
o Integration is hard and often delayed just before the final build ; if code is
continuously compiled and checked. Conflicts can be identified when they are easy to
manage
o It is part of the techniqye called kaizen that emphassizes continuous improvement
o It ensures that srcum of scrum projects can deliver a potentially implementable
o By using a continuous integration approch , a project can oflload many core
development processes to an automated server.
10/12/2021 323
Agile Introduction & Overview
Quiz
Response
Quest 4 : why is continous integration seen as valuable ?
o Integration is hard and often delayed just before the final build ; if code is
continuously compiled and checked. Conflicts can be identified when they are easy to
manage
o It is part of the techniqye called kaizen that emphassizes continuous improvement
o It ensures that srcum of scrum projects can deliver a potentially implementable
o By using a continuous integration approch , a project can oflload many core
development processes to an automated server.
10/12/2021 324
Agile Introduction & Overview
Quiz
Quest 5 : which of the following Agile Manifesto values is incorrect ?
10/12/2021 325
Agile Introduction & Overview
Quiz
Response
10/12/2021 326
Agile Introduction & Overview
Summary
10/12/2021 327
Agile project Management
10/12/2021 328
Section 2 :
Agile Frameworks
&
Methods
10/12/2021 329
Agile Frameworks & Methods
Objective
10/12/2021 330
Agile Frameworks & Methods
Extreme
Scrum programming Lean Kanban
10/12/2021 331
Agile Frameworks & Methods
Scrum
Scrum is one of the leading Agile techniques developed in the 1990 by ken
shwaber and jeff sutherland
10/12/2021 332
Agile Frameworks & Methods
Advantages of Agile/Scrum
Many studies and surveys have outlined the advantages of Agile development.
10/12/2021 333
Agile Frameworks & Methods
Agile Methods Deliver Value Faster
This chart illustrates how Agile methods deliver value faster than expensive, traditional methods.
10/12/2021 334
Agile Frameworks & Methods
Scrum Values
10/12/2021 335
Agile Frameworks & Methods
Scrum Values
The Scrum roles are an important feature of Scrum.Scrum defines three roles:
10/12/2021 336
Agile Frameworks & Methods
Scrum Events and Artifacts
Sprint Planning
Sprint Planning helps decide the tasks that the team has committed to achieve the Sprintgoal.
The team should make an informed commitment about what will deliver. A typical Sprint
Planning Meeting takes anywhere between one and two hours per week of Sprint.
Agile Frameworks & Methods
The Daily Scrum is a meeting of the team, by the team, and for the team.
Agile Frameworks & Methods
Sprint Review
Backlog item refers to any work done by the team that adds value to the customer.
Agile Frameworks & Methods
Scrum Events and Artifacts
Product Backlog
Product Backlog items may be feature requests, bug fixes, technical tasks, and so on.
Agile Frameworks & Methods
Scrum Events and Artifacts
Definition of Done
XP Practices
XP Teams
Here are the role descriptions for different types of XP Team members:
Agile Frameworks & Methods
Crystal is a family of methodologies invented by Alastair Cockburn. Following are the seven
properties of Crystal Project:
Agile Frameworks & Methods
DSDM Techniques
Iterative Development
Time-Boxing
MoSCoW Prioritization
MUST
SHOULD
COULD
WON’T
Facilitated Workshops
Modeling
Agile Frameworks & Methods
Waste constitutes over 90% of a process. We must constantly look for it and for ways to eliminate it.
Agile Frameworks & Methods
kanban
DevOps
DevOps
Other Agile Frameworks
DevOps enables faster delivery of value created by Agile into operations. This is a system with
efficient DevOps:
Agile Frameworks & Methods
There must be close co-ordination between several roles in an Agile team and an IT team.
Agile Frameworks & Methods
Quiz
Quiz
Other Agile Frameworks
Response
Quiz
o Continous integration
o Ubiquitous language
10/12/2021 364
Agile Frameworks & Methods
Quiz
Response
o Continous integration
o Ubiquitous language
10/12/2021 365
Agile Frameworks & Methods
Key Takeaways
There are many techniques and methodologies to choose from under the Agile umbrella.
The Waterfall method is logical, however, it’s expensive to change.
Crystal is strong on communication, Dynamic Systems Development Method (DSDM), or Atern, is
good at timeboxing and prioritization, and XP has good guidance on engineering practices.
Agile and Scrum techniques have to be complementary to DevOps processes to ensure that the
value developed can be deployed quickly and seamlessly.
Agile and Scrum should also link to IT Service Management because products are ultimately tied to
business services that are supported by IT Operations.
Agile project Management
10/12/2021 367
Section 3 :
Agile
Communication
10/12/2021 368
Agile Communication
Objectives
10/12/2021 370
Agile Communication
Information Radiators
o Task boards
10/12/2021 371
Agile Communication
Information Radiators
10/12/2021 372
Agile Communication
Task board
10/12/2021 374
Agile Communication
10/12/2021 375
Agile Communication
Osmotic Communication
10/12/2021 376
Agile project Management
10/12/2021 377
Section 4 :
Agile Planning,
Monitoring and
Adopting
10/12/2021 378
Agile Planning, Monitoring and Adopting
Agile Estimating, Planning, Monitoring, and Control
After completing this lesson, you will be able to:
Express estimates in story points or ideal time and explain the pros
and cons.
Estimation techniques.
Make progress visible using Burn Down Charts and other forms.
10/12/2021 381
Agile Planning, Monitoring and Adopting
Aligning Agile projects to portfolios and programs
10/12/2021 382
Agile Planning, Monitoring and Adopting
User Stories
User Stories describe anything of value that the team can produce for the customer.
User Stories : 3 C
10/12/2021 384
Agile Planning, Monitoring and Adopting
10/12/2021 385
Agile Planning, Monitoring and Adopting
Story Card
Agile Planning, Monitoring and Adopting
10/12/2021 388
Agile Planning, Monitoring and Adopting
Theme
Epics
10/12/2021 389
Agile Planning, Monitoring and Adopting
Timeboxing
10/12/2021 390
Agile Planning, Monitoring and Adopting
Advantage of Timeboxing
10/12/2021 391
Agile Planning, Monitoring and Adopting
Roadmap/Release Planning
Output
Agileof ReleasePlanning,
Estimating, Planning
Monitoring, and Control
Iteration plan
Only those user stories , that have been selected for the iteration.
Each ietration follows The same consistent pattern
10/12/2021 394
Agile Planning, Monitoring and Adopting
Iteration plan
10/12/2021 395
Agile Planning, Monitoring and Adopting
10/12/2021 396
Agile Planning, Monitoring and Adopting
Iteration
10/12/2021 397
Agile Planning, Monitoring and Adopting
Iteration plan vs release Plan
10/12/2021 398
Agile Planning, Monitoring and Adopting
Tracking Releases
Tracking Sprints
10/12/2021 401
Agile Planning, Monitoring and Adopting
Staying in Control
10/12/2021 403
Agile Planning, Monitoring and Adopting
Work in progress
10/12/2021 404
Agile Planning, Monitoring and Adopting
Kanban Boards
10/12/2021 406
Agile Planning, Monitoring and Adopting
Key Takeaways
The starting point of planning is the definition of user stories. Good user stories follow the
INVEST model and 3 C’s.
Prioritize stories based on Return On Investment (ROI) and Risk.
Get an understanding of the Team’s Velocity.
Use this information to plan at various levels for Roadmap, Release, and Sprint.
Express estimates as Ideal Time or Story Points.
Planning Poker and Affinity are simple, fun approaches to estimation.
Use Burn Down Charts and other indicators to track projects and stay in control.
Agile project Management
10/12/2021 408
Section 5 :
Agile Estimation
10/12/2021 409
Agile Estimation
Objectives
10/12/2021 410
Agile Estimation
Measure of size
10/12/2021 411
Agile Estimation
Estimation
Splitting Stories
Stories need to be split if they are too large, won’t fit into the Sprint, or for more reliable estimation.
Agile Estimation
Prioritization Models
AffinityAgile
Estimation
Estimating, Planning, Monitoring, and Control
Useful when you want quick, reliable estimates for a large number of stories at a time
Agile Estimation
From Product to Sprint Backlog
Agile Estimation
Tracking Work in a Sprint
Agile Estimation
Velocity Calculation
Agile Estimation
Defining Key Metrics in Agile
Agile Estimation
Planning Releases
Agile Estimation
Artifacts
Agile Estimation
Wideband delphi
10/12/2021 430
Agile Estimation
Wideband delphi - process
10/12/2021 431
Agile Estimation
Affinity estimation
10/12/2021 432
Chapter 4 :
PMBOK 7 Edition
10/12/2021 433
Section 1 : The
standard of project
Management
10/12/2021 434
Part 1 : Introduction
10/12/2021 435
Key Terms & concepts
Outcome
As end result or consequence of process or project.
Outcomes can include output and artifacts, but
Have a broader intent by focusing on the benefit
and value that the project was undertaken to
deliver
Portfolio
Projects, programs, subportfolios, and operations
managed as a group to achieve strategic
objectives
Key Terms & concepts
Product
An artifact that is produced, is quantifiable, and
can be either an end item in itself or a
component item.
Program
A group of related projects, subprograms, and
program activities managed in a coordinated
way to obtain benefits not available from
managing them individually.
Project
A temporary endeavor undertaken to create a
unique product, service, or result.
Key Terms & concepts
Project Management
Project Manager
Project Team
value
440
Creating value
• Creating new service , product or result that meets the needs of customers or end users;
• Enanling the chnages needed to facilitate organizational transition to its desired future
State
10/12/2021 441
Value Delivery components
10/12/2021 442
Value Delivery components
10/12/2021 443
Information Flow
10/12/2021 444
Organizational Governance Systems
• A Governance framework can include elements of oversight , control, value assessment
Integration among components , and decision making capabilities.
• Governance systems provid an integrated structure for evaluating changes , issues ,risks
Associated with environnement and any component in the value delivery system. This
Includes portfolio objectives , program benefits and delivrables produced by projects.
• Project Governance include defining the authority to apporve change and make
a business decisions related to the project . Project Governance is aligned with program
and organizational governance
10/12/2021 445
Functions associated with projects
Provide oversight and coordination
Apply Expertise
10/12/2021 446
Functions associated with projects
Provide oversight and coordination
Apply Expertise
10/12/2021 447
Part 3 :Project
Management
principles
448
Project Management principles
10/12/2021 449
Project Management principles
1. Be Deligent , Respectful and carring steward
2. Create a collaborative project team environnement
3. Effectively engage with stakeholders
4. Focus on value
5. Recognize , evaluate and respond to the system interactions
6. Demonstrate leadership behavior
7. Tailor based on the context
8. Build Quality into process and delivrables
9. Navigate complexity
10. Optimize Risk Responses
11. Embrace Adaptability and resiliency
12. Enable change to achieve the envisioned future state
10/12/2021 450
Be Deligent , Respectful and carring steward
10/12/2021 451
Be Deligent , Respectful and carring steward
Stewardship encompasses responsabilities within external or internal to the organization
Within organization :
Operating in alignement with organization its objectifs and strategy , vision , mission
and sustainment of its long term value;
10/12/2021 452
Be Deligent , Respectful and carring steward
Stewardship outside to the organization includes such as resposnabilities
External organization :
Organization’s relationship within external stakeholders such as its partner and channels ;
Impact of the organization or project on the market , social community and regions in
wich it operates ;
Environemental sustainbility and or the organization’s uses materials and nature ressources
10/12/2021 453
Be Deligent , Respectful and carring steward
Integrity
• Stewards behave honestly and ethically in all engagements and communications
• Stewards hold themselves to the highest standards and reflect the values ,
principles and behavios expected of those in their organization.
• Stewards to challenge team members and other steakholders to consider their
words and actions , to be empathetic , self-reflective and open to feedback.
Care
• Care related to the business affair of the organization.
• Care of the environnement
• Sustainable use of nature ressources
• Care include creating a transparent working environnement
• Open communication channels
• Opportunities of stakeholders to raise concerns withount fairness and penalities.
10/12/2021 454
Be Deligent , Respectful and carring steward
Trustworthiness
• Stewards represent themselves , their roles , their project team and their
authority both inside and outside the organization.
• Trustworthiness entails individual identifying conflicts between their personal
interests and those of their organization.
• Conflicts can undermine trust and confidence.
• Stewards protect projects from breaches of trust.
Compliance
• Stewards comply with laws , rules, regulations and requirements that are
properly authorized within or outside of their organization
• Stewards seek appropriate counsel and direction
10/12/2021 455
Project Management principles
1. Be Deligent , Respectful and carring steward
2. Create a collaborative project team environnement
3. Effectively engage with stakeholders
4. Focus on value
5. Recognize , evaluate and respond to the system interactions
6. Demonstrate leadership behavior
7. Tailor based on the context
8. Build Quality into process and delivrables
9. Navigate complexity
10. Optimize Risk Responses
11. Embrace Adaptability and resiliency
12. Enable change to achieve the envisioned future state
10/12/2021 456
Create a collaborative project team environnement
10/12/2021 457
Create a collaborative project team environnement
Team Agreements
Team agreements represent a set of behavioral parameters and working norms
established by the project team and upheled through individual and project Team
commitement. The Team agreements are created in the first of project and continue
to evolve over time in order to work succesfuly
Organizational Structure
Organizational structure are any arrangement of or relation between the elements of
project work and organizational process.
Example of organization structures that can improve collaboration
o Definition of roles and responsabilities
o Allocation of employees and vendores into project teams
o Formal committees tasked with specefic objectif
o Standing meetings that regulary review a given topics
10/12/2021 458
Create a collaborative project team environnement
Processes
Project Teams define processes that enable completion of tasks and work
assignments. For example , project teams may agree to a decomposition process
using a workbreadown structure (wbs) , Backlog or task borad
Clarity on roles and responsabilities can improve team cultures. This incluses
Autority : The condition of having the right , within a given context , to make
relevant decisions , establish or improve procedures , apply project ressources ,
expends fucnds or give approovals. Authority is conferred from one entity to
another ,whether done explicity or implicity.
10/12/2021 459
Project Management principles
1. Be Deligent , Respectful and carring steward
2. Create a collaborative project team environnement
3. Effectively engage with stakeholders
4. Focus on value
5. Recognize , evaluate and respond to the system interactions
6. Demonstrate leadership behavior
7. Tailor based on the context
8. Build Quality into process and delivrables
9. Navigate complexity
10. Optimize Risk Responses
11. Embrace Adaptability and resiliency
12. Enable change to achieve the envisioned future state
10/12/2021 460
Effectively engage with stakeholders
10/12/2021 461
Effectively engage with stakeholders
Stakeholders can affect many aspects of a project , including but not limited to :
• Scope/Requirement , by revealing the need to add , adjust , or remove elements of the scope
and/or project requirements;
• Schedule, by offering ideas to accelerate delivery or by slowing down or stop delivery of key
project activities.
• Cost , by helping to reduce or eliminate planned expenditures or by adding steps,
requirement , or restrictions that increase cost or require addtional resources;
• Project team, by restricting or enabling access to people with skills , knowledge , and experience
needed to deliver the intended outcomes , and promote a learning culture;
• Plans, by provinding information for plans or by advocating for changes to agreed activities
and works;
• Outcome, by enabling or blocking work required for the desired outcomes;
• Cultures, by establishing or influencing – or even defining –the level and character
of engagement of the project team and broader organization;
• Benefits realization , by generating and identifying long term goals so that the project delivers
the inteded identified value.
• Risk ; by defining the risk thresholds of the project , as well as participating in subsequent risk
management activities;
• Quality, by identifying and requiring quality requirements ;
• Success , by defining success factors and participating in the evaluation of success.
10/12/2021 462
Project Management principles
1. Be Deligent , Respectful and carring steward
2. Create a collaborative project team environnement
3. Effectively engage with stakeholders
4. Focus on value
5. Recognize , evaluate and respond to the system interactions
6. Demonstrate leadership behavior
7. Tailor based on the context
8. Build Quality into process and delivrables
9. Navigate complexity
10. Optimize Risk Responses
11. Embrace Adaptability and resiliency
12. Enable change to achieve the envisioned future state
10/12/2021 463
Focus on value
10/12/2021 464
Focus on value
• Value including outcomes from the perspective of the customer or the end user
• Value is the ultimate success indicator and driver of projects
• Value focus on the outcome of delivrables .
• Value of project may be expressed as a financial contribution to the sponsoring or
receiving organization
Business need
• Business provides rationale of the project explaining why the project is undertaking
• Is originates business requirements which reflected in the project charter
• It provides business goals and objectives
• It help to increase the potentiel value from the project outcome/
Project Justification
• Project justification is connected to business need , it is explain why the business
need is worth the investissement and why at this time.
Business Strategy
• Business Strategy is the reason for the project and all needs are related to the
strategy to achieve the value.
10/12/2021 465
Project Management principles
1. Be Deligent , Respectful and carring steward
2. Create a collaborative project team environnement
3. Effectively engage with stakeholders
4. Focus on value
5. Recognize , evaluate and respond to the system interactions
6. Demonstrate leadership behavior
7. Tailor based on the context
8. Build Quality into process and delivrables
9. Navigate complexity
10. Optimize Risk Responses
11. Embrace Adaptability and resiliency
12. Enable change to achieve the envisioned future state
10/12/2021 466
Recognize , evaluate and respond to the system interactions
10/12/2021 467
Recognize , evaluate and respond to the system interactions
10/12/2021 468
Recognize , evaluate and respond to the system interactions
Recognizing , evaluatinf , and responding to system interactions can lead to the
Following positiives outcomes :
10/12/2021 469
Project Management principles
1. Be Deligent , Respectful and carring steward
2. Create a collaborative project team environnement
3. Effectively engage with stakeholders
4. Focus on value
5. Recognize , evaluate and respond to the system interactions
6. Demonstrate leadership behavior
7. Tailor based on the context
8. Build Quality into process and delivrables
9. Navigate complexity
10. Optimize Risk Responses
11. Embrace Adaptability and resiliency
12. Enable change to achieve the envisioned future state
10/12/2021 470
Demonstrate leadership behavior
10/12/2021 471
Demonstrate leadership behavior
• Focusing a project team around agreed goals ,
• Articulating a motivating vision for the project outcomes,
• Seeking resources and support for the projet
• Generating consensus on the best way forward,
• Overcoming obstacles to projects progress,
• Negotiating and resolving confilcot within the project team and between the project team
• And other stakeholders,
• Adapting communication style and messaging so that they are relevant to the audience,
• Coaching and mentoring fellow project team members
• Appreciating and rewarding positive behaviors and contributions
• Providing opportunities for skill growth and developpement
• Facilitating collabirative decision making
• Employing effective conversation and listening
• Empowering project team members and delegating responsibilities to them
• Building a cohesive project team that take responsabilities
• Showing empathy for project team and stakeholders perspectives
• Having self awerness about of one’s own bias and behavior
• Managing and adapting to change during the project life cycle.
• Facilitating a fail fast learn quickly mindset by acknwoledge mistakes
• Role modeling of desired behaviors
10/12/2021 472
Project Management principles
1. Be Deligent , Respectful and carring steward
2. Create a collaborative project team environnement
3. Effectively engage with stakeholders
4. Focus on value
5. Recognize , evaluate and respond to the system interactions
6. Demonstrate leadership behavior
7. Tailor based on the context
8. Build Quality into process and delivrables
9. Navigate complexity
10. Optimize Risk Responses
11. Embrace Adaptability and resiliency
12. Enable change to achieve the envisioned future state
10/12/2021 473
Tailor based on the context
10/12/2021 474
Tailor based on the context
A Tailored project approach can prodcue direct and indirect benifits to organizations such a:
• Deeper commitment from project team members because the took part in defining the approch
• Customer oriented focus as the needs of the customer and other stakeholders are an imprtant
• More efficient use of project resources , as project teams are conscious of the weight of project
processes
10/12/2021 475
Tailor based on the context
10/12/2021 476
Project Management principles
1. Be Deligent , Respectful and carring steward
2. Create a collaborative project team environnement
3. Effectively engage with stakeholders
4. Focus on value
5. Recognize , evaluate and respond to the system interactions
6. Demonstrate leadership behavior
7. Tailor based on the context
8. Build Quality into process and delivrables
9. Navigate complexity
10. Optimize Risk Responses
11. Embrace Adaptability and resiliency
12. Enable change to achieve the envisioned future state
10/12/2021 477
Build Quality into process and delivrables
10/12/2021 478
Build Quality into process and delivrables
Quality may have several diffrent dimension , including but not limited to the following :
• Performance : Does the delivrable function as the project team and stakeholders inteded
• Conformity . Is the delivrable fit for use . And does meet the specifications?
• Reliability . Does the delivrable produce consistent metrcis each time it is performed or produced
• Resilience .is the delivrable able to cope with unforseen failure and quickly recover?
• Satisfaction. Does the delivrable elicit positive feed back from end users ? This includes usability
• And users experience ?
• Uniformity. Does the delivrable show parity with other delivrable
10/12/2021 479
Build Quality into process and delivrables
The intention is to minimise the waste of resources and maximize the probabilty of
Attaining the desired outcome. The result in :
10/12/2021 481
Navigate complexity
10/12/2021 482
Navigate complexity
10/12/2021 484
Optimize Risk Responses
10/12/2021 485
Optimize Risk Responses
10/12/2021 487
Embrace Adaptability and resiliency
Embrace Adaptability and resiliency
10/12/2021 490
Enable change to achieve the envisioned future state
Section 2 : Project
Performance
Domaines
10/12/2021 492
Project Performance Domaines
10/12/2021 493
Project Performance Domaines
1. Stakeholders Performance Domains
10/12/2021 494
Stakeholders Performance Domain
Stakeholder. An individual, group, or organization who may affect, be affected by, or perceive
itself to be affected by a decision, activity, or outcome of a project.
10/12/2021 500
Team Performance Domain
Project Manager (PM). The person assigned by the performing organization to lead the team
that is responsible for achieving the project objectives.
Project Management Team. The members of the project team who are directly involved in
project management activities. On some smaller projects, the project management team may
include virtually all of the project team members.
Team Performance Domain
Centralized
Predictive
Management and
Management
leadership
Project Manager
Distributed
Agile or lean
Management and
Management
leadership
Scrum Master or servant leader
Team Member
Team Performance Domain
Servant leader
Guidance Growth
Team Performance Domain
Celebrating
Success
Positive
Support Courage
discourse
Team Performance Domain
Open Shared
Respect
communication understanding
Shared
ownership Trust Collaboration
Emotional Intelligence
Team Performance Domain
Conflict Management
Team Performance Domain
Conflict Management
Team Performance Domain
Checking the result
Project Performance Domaines
1. Stakeholders Performance Domains
10/12/2021 511
Development approach and life cycle Performance Domain
Development approach and life cycle Performance Domain
Project Life Cycle. The series of phases that a project passes through from its
initiation to its closure.
Development approach and life cycle Performance Domain
Single delivery
Multiple deliveries
Periodic deliveries
Development approach and life cycle Performance Domain
Development Approach
Development approach and life cycle Performance Domain
Development Approach
Development approach and life cycle Performance Domain
Product, service and result
Degree of Requirement
Scope stability
innovation Certainty
Delivery
Ease of change
options
Risk Safety
Regulations
Requirements
Development approach and life cycle Performance Domain
Life cycle and phase definitions
Development approach and life cycle Performance Domain
Life cycle and phase definitions
Development approach and life cycle Performance Domain
Life cycle and phase definitions
Development approach and life cycle Performance Domain
Aligning of delivery cadence
Development approach and life cycle Performance Domain
Aligning of delivery cadence
Development approach and life cycle Performance Domain
Development approach and life cycle Performance Domain
Checking the result
Project Performance Domaines
1. Stakeholders Performance Domains
10/12/2021 525
Planning Performance Domain
Planning Performance Domain
Crashing. A technique used to shorten the schedule duration for the least
incremental cost by adding
resources.
Planning variables
Legal or
Market
regulatory
conditions
restrictions
Planning Performance Domain
Schedule
Planning Performance Domain
Schedule
Planning Performance Domain
Budget
Planning Performance Domain
Checking the result
Project Performance Domaines
1. Stakeholders Performance Domains
10/12/2021 533
Project work performance Domain
Project work performance Domain
Project work keep the project team focused and project activities running smoothly :
• Managing the flow of existing work , new work and changes to work;
• Keeping the project team focused
• Establishing efficient project systems and processes;
• Communicating with stakeholders
• Managing material , equipment , supplied and logistics;
• Working with contracting professionals and vendors to plan and manage
procurements and contracts
• Monitoring changes that can affect the project ; and
• Enabling project learning and knowledge transfer.
Project work performance Domain
Project
Managing the Managing
communication
project Team physical
and
Focus resources
engagement
10/12/2021 539
Delivery performance Domain
Delivery performance Domain
Deliver of Project
value Delivrables
Quality Suboptimal
outcomes
Delivery performance Domain
Checking the result
Project Performance Domaines
1. Stakeholders Performance Domains
10/12/2021 544
Measurement performance Domain
Measurement performance Domain
Measurement performance Domain
What to measure
Measurement performance Domain
Measurement performance Domain
Measurement performance Domain
10/12/2021 551
Uncertainty performance Domain
Uncertainty performance Domain
Uncertainty performance Domain
10/12/2021 555
Tailoring
What to Tailor
Methods and
Tools
artifacts
Tailoring
What to Tailor
Methods and
Tools
artifacts
Tailoring
Tailoring
Tailoring the performance domain
10/12/2021 560
Section 4 :
Models , Methods
and Artifacts
10/12/2021 561
Models , Methods and approch
Models , Methods and approch
Thank you for your assistance
Are there any others Questions ?
10/12/2021 564