Project HSE Plan
Project HSE Plan
Project HSE Plan
Table of Contents
1. Introduction 3
1.1. Intro and scope of the Project H&S Management Plan 3
1.2. Project description and key dates 3
1.3. Roles and responsibilities 4
2. Local laws, regulations and other compliance requirements 5
3. Operational planning (for multiple sites, detail all site-specific information) 5
3.1. Activity risk assessment planning 5
3.2. Hazard identification and activities risk assessment 5
3.3. Objectives and targets 6
3.4. Work permit system 8
3.5. Management of contractors and sub-contractors 8
4. Health and safety management at project site 8
4.1. Management of hazardous materials 8
4.2. Access and site security 9
4.3. Site Induction and Site Safety Rules 9
4.4. Workplace inspections 10
4.5. Site induction and training 10
4.6. Emergency and evacuation procedures 11
5. Communication and information sharing 11
5.1. Internal communication 11
5.2. External communication 11
5.3. Consultation with the workforce 12
5.4. Accident and incident reporting and investigation 12
5.5. H&S risks during operation 12
6. Audit and monitoring 12
6.1. Project files and records 12
6.2. Audit and monitoring 13
7. Revisions of the Plan 13
8. Table of references to Templates and Guidance documents 14
1. Introduction
UNOPS endeavours, in all its projects and operations, to prevent personal injuries, ill health and
damage to property.
This Project Health and Safety (H&S) Management Plan (hereafter “the Plan”) has been designed to
assist the management of activities and support a risk-based approach to preventing dangerous acts
that could lead to injuries or illnesses or serious incidents in the workplace.
This Plan is a live document that will be reviewed on a regular basis and updated if necessary.
Project Duration
While the Project Manager holds the overall responsibility for Health and Safety management in the
Project, other roles may hold accountability, or need to be consulted and informed of various work
packages (e.g. the Contractor, the Office Director, the Programme Manager, the Project Design
Manager). Table 2 below outlines Roles and responsibilities for Infrastructure projects in the
assurance set-up.
consultation with
the workforce &
visitors
Check that design
changes that
affect H&S are
recognised and A R C R*
assessed during
construction
phase
Ensure that
works
contractors are
procured using
the appropriate
FIDIC based A R I
contract.
(Defines
responsibilities
for H&S /
insurance etc.)
Ensure that
contractor(s)
employ effective
A R C
H&S
management
techniques
Ensure effective
arrangements in
A R I
place for site
security/access
Ensure
arrangements in
place for Site A R I R*
induction and
safety briefings
Ensure that
suitable welfare
facilities and first A R I
aid arrangements
are in place
Ensure that
reporting of
accidents /
incidents
R C I R*
structural failures
are reported in
line with their
relevant OI
Ensure work
permit system is
A R I R*
established and
implemented
Health and Safety legislation and other relevant requirements in Yemen are described in the Yemen
Office legal register using form HSE03. This should also include the relevant requirements of
interested parties that have been identified by the local office using form HSE02. A check for legal
compliance has been performed to ensure that this project is compliant with legal and other
requirements, using form HSE04.
A copy of the legal register is available [in HSSE server]. UNOPS Project Manager will review these
laws and regulations every [12 months] to make sure that there are no changes which may affect
this plan.
A staged approach to project/site hazard identification and risk control is a requirement of this plan.
Hazard identification and subsequent risk assessment will be an ongoing process throughout the life
of the project (up to defects notification period, if part of the contract). The Contractor receives
already during the tender phase a schedule of key risks/hazards identified during design (form HS07,
Schedule of Key Tasks, can be used for this purpose). These tasks should be carefully considered
during the development of detailed Risk Assessments.
UNOPS Project Manager ensures that the risk assessments developed by the Contractor(s) are
aligned with the requirements of form HS05, including as a minimum:
● Contractor(s) has identified all foreseeable hazards within the assessed activity
● Hazards have been prioritized by their magnitude (high, medium or low)
The Contractor has developed Risk Assessments using Form HS05 that were reviewed by the UNOPS
Project Manager and accepted prior to works commencing. The requirement to produce Risk
Assessments applies to activities performed by sub-contractors as well.
The workforce shall be briefed on the contents of appropriate Risk Assessment(s) prior to works
commencing; briefings are formally recorded using form HS06.
The Risk Assessment(s) will be amended as necessary to ensure that the works progress in a safe
manner. The Risk Assessment(s) for this Plan are attached as (Annex 1).
All UNOPS personnel have the authority to stop any activity that has the potential to cause injury or
damage property until such times as the works are managed in a safe manner.
The project will have the following Health and Safety objectives and targets:
The following activities at site will require the Contractor(s) to obtain a signed work permit from
UNOPS Project Engineer before commencing these activities at site:
● Bidders receive key documentation outlining the requirements of UNOPS Health and Safety
Management Systems during the tender phase. The selected contractor shall comply with
all UNOPS H&S requirements for the whole duration of the contract. These requirements
equally apply to any subcontractors hired by the contractor. It is the contractor’s
responsibility to ensure that subcontractors comply and to demonstrate such compliance in
submittals and during verification processes by UNOPS.
● If pre-bid meetings, site visits and/or contract commencement meetings are carried out,
H&S requirements and submittals should be discussed, both for day-to-day work and for
H&S critical stages/activities.
● Suppliers should comply with UNOPS minimum HSE requirements
Occupational diseases may occur as a result of exposure to hazardous substances in the form of
inhaled particulates, ingested materials or skin contact with substances. Such possibilities have been
identified in the Risk Assessment(s) and appropriate controls put in place. The main types of
hazardous materials that have been identified are:
Table 4 - Hazardous materials
Risk Responsible
Hazardous material Control method
rating person
Provide proper PPE
Provide training on safe handling
Paint products 9 of chemicals and their related Contractor
hazards Store paint products in
an adequate
Place
Provide proper PPE
Provide training on safe handling
Cleaning and polishing 9 of chemicals and their related Contractor
chemicals hazards Store cleaning chemicals
in an
adequate place
Hazardous materials/chemicals used at the site shall have Material Safety Data Sheets (MSDS). The
MSDS are obtained from the manufacturer/supplier of the materials and should be requested with
each purchase of products.
Material Safety Data Sheets will be included in the Toolbox talks and risk assessment briefings. This
information will be made available to any employee or sub-contractor or visitor who may interact
with the materials/chemical substances on site.
UNOPS Project Manager will ensure that the Contractor(s) have put in place all measures to
establish the site according to UNOPS guidance (GHS12).
It is the Project Manager responsibility to ensure that all site security requirements identified in the
Risk Assessment for this activity are fully implemented.
4.3. Site Induction and Site Safety Rules
Site inductions will be carried out by the contractor. Arrangements for site inductions for this project
shall be:
● Any new worker coming to the work site will be briefed on the site safety rules including the
site logistics plan, hazards, evacuation procedures, emergency and first aid procedures, and
the duties and responsibilities of all persons on site.
● A Site Induction briefing and Site Safety Rules has been developed in Arabic and in English
● All attendees of the Site Induction briefing will be recorded and included in UNOPS Site
Induction Register (form HSE07).
● Visitors will be given a brief site induction (based on an either oral or written Visitor’s
induction) and will be accompanied at all times during their visit to the site.
● UNOPS personnel at Site should ensure that workers carrying out safety critical tasks have
the necessary induction, qualifications and/or on the job training/licensing for the tasks they
carry out.
Inspections of the project site should be carried out weekly. Contractor(s) will undertake weekly
inspections of the whole work site, and specifically of:
- equipment
- small equipment (form HS15)
- scaffolds (form HS14)
- lifting devices (form HS16)
- electrical cables
- fire extinguishers
- first aid kits
Records of the inspections should be kept using form HSE05 and/or other dedicated forms, or the
Contractor(s) forms where approved by UNOPS:
UNOPS personnel at site will be responsible to for the assurance of these inspections. UNOPS site
team are responsible for ensuring that the inspection findings and recommendations are closed out
in a timely manner.
Induction, training and awareness activities have been planned and consideration given to ensuring
that personnel doing H&S critical activities are covered.
[Add or remove training as necessary]
Table 5 - Training
Planned training Nominated staff Frequency
Excavation Annually
The HSE training matrix (form HSE18) can be used to keep detailed records of site inductions,
toolbox talks and training.
[Include additional details on training as relevant]
4.6. Emergency and evacuation procedures
Emergency and evacuation procedures will be tested through appropriate drills that will be held
every month and, where possible, may involve relevant interested parties [UNOPS, Contractor’s
Personnel, and specify others].
- emergency contact numbers available on notice and information boards over the project
work areas and site offices
- H&S weekly meetings and daily toolbox talk. They may be dedicated to H&S or H&S may be
one part of the agenda. Additional H&S meetings will be organised when needed. Meeting
minutes will be distributed to UNOPS, Contractor’s team and sub-contractors.
- Weekly inspections (form HSE05); including Health and Safety items will be performed
jointly by UNOPS team and the Contractor(s) team; the report will be prepared by UNOPS
H&S Manager/Coordinator and shared with the Contractor(s) for necessary actions.
- Site H&S quarterly report (form HSE12); the quarterly report is a summary of the site weekly
inspection report findings and corrective action. It is prepared by UNOPS site H&S
Manager/Coordinator to be shared with the Contractor(s) and with UNOPS Senior
Management in the country as well as with UNOPS HQ.
- Toolbox talks
- Information and guidance signage will be present at site in both Arabic and English
languages.
- The Site Notice Board will be used to convey daily updates and information.
5.2. External communication
Queries on health and safety management from local communities, journalists, business community,
neighbours, local representatives, and any other external parties will be handled according to the
UNOPS Yemen HSSE practices.
Arrangements for consulting and coordinating with the workers at site will be as follows:
All significant accidents or incidents and high potential near misses shall be reported to UNOPS HQ
using form HSE09.
They should be thoroughly investigated and action taken to prevent recurrence. For Class 1
incidents, the outcomes of the review shall be reported to UNOPS HQ using form HSE10. Lessons
learned should be captured using HSE11.
UNOPS and Contractor’s personnel have an obligation to report all incidents and near misses to the
UNOPS Project Manager/H&S coordinator, and will receive proper induction in this sense. Significant
incidents and near misses should be recorded in Table 6:
To prevent/reduce risks at the use and maintenance phase or during the facility/structure operation,
UNOPS will provide the project end user with an operation and maintenance manual, which explains
how to operate and maintain the asset in a safe manner.
UNOPS health and safety management electronic files will form the archived component of the
records for this project, in line with the UNOPS Record Retention Policy and to facilitate internal and
external audit and review. As a minimum they will consist of:
The UNOPS H&S system shall be formally documented to allow for control and accountability.
Table 7 - Revisions
Revision date Name and title Description of main changes
Fahmi Alaswar
0 Document Creation
HSSE Officer
8.
Table 8 - References
TOPICS TEMPLATES GUIDANCE
Site induction and training HSE08 Visitor induction register See catalogue of Toolbox talks