Project Management Individul Report
Project Management Individul Report
The project’s activities were identified as the first step of creating the
network diagram. Government documents, international procedures, SOPs,
expert opinion, and others could be used as sources. The table below is a
comprehensive list of project’s activities as agreed by key stakeholders.
F Build K Construct
Underdrains, Bridge B
Storm Substructure
Sewers, and
Miscellaneou
s Drainage
Structures
L Construct
Bridge B
Superstructure
The WBS provides scope clarity that helps in constructing project’s network
diagram. The network diagram connects the entire project’s activities and
captures their sequence and dependencies. The figure below illustrates the
project network diagram as agreed by key stakeholders.
Figure 2: Project Activity Network Diagram
Figure 2 is a roadmap that streamlines project activates from start till end.
Each activity has an estimated completion duration identified by
stakeholders. The duration is used to identify the project's critical path which
is the longest sequence of dependent activities and the shortest possible
project completion time.
The figure below illustrates the critical path method used for calculating the
project’s critical path.
In Figure 3, the path of the critical activities is marked by red arrows. Any
delay in the critical path causes delay in the project completion date.
The forward pass method is used to calculate the earliest start (ES) and
earliest finish (EF) of each activity. EF=ES+D equation is used forward
throughout the network. In this method, the ES of each activity is equivalent
to the EF of its immediate predecessor. Then, the critical path is determined
as the longest EF of the final activity. Therefore, the shortest possible time to
complete the project is 77 weeks.
For further detailed analysis, the backward pass method is used to calculate
late start (LS) and late finish (LF) for each activity. LS=LF-D is the equation to
determine LS for each activity. In this method, the LF of an activity is
equivalent to the smallest LS of immediate successor. As a result, the total
float (TF) can be calculated via TF= LS-ES or TF= LF-EF. The activities with
zero TF are considered within the critical path. Activity with positive TF can
be adjusted without impacting the overall project duration.
The figure below is an influence (power) vs impact (interest) grid for visual
illustration.
Figure 4: Influence (power) vs Impact (interest) Grid
In general, the grid is divided into four sections, each section is managed
with different strategies as outlined in the table below.
By default, all projects have associated risks. These risks, if not managed
effectively, could hinder project success and cause harm to associated
stakeholders. Project risk management is a process where all the project
risks are identified, assessed, and prioritized to proactively minimize
potential adverse negative effects for smooth project delivery. It ensures
that all stakeholders are well aware of the potential risks and their respective
impacts, therefore, developing a contingency plan.
The table below captures all potential project’s risks with detailed analysis
and mitigation strategy.
Lesson Learnt
The team has successfully developed a comprehensive activity list, WBS,
task dependencies, and completion estimate. They Identified relative
stakeholders, discussed risks from end user view, and used approved
standards and specifications.
However, the team did not capture project risks, calculate project critical
path, assess stakeholders, cost calculation, develop communication plan.