Module5 Print
Module5 Print
Topic: Welcome
Topic: Key Aspects of the Port Redevelopment Project
Topic: Community Health and Safety (ESS4)
Topic: Resource Efficiency and Pollution Prevention and Management (ESS3)
Topic: Labor and Working Conditions (ESS2)
Topic: Additional Issues
Topic: Summary
Read More
This course aims to provide an in-depth introduction to the elements of the World
Bank’s Environmental and Social Framework for Investment Project Financing.
Before taking this course, you are encouraged to read the Environmental and
Social Framework itself and to use it as a reference document as needed, both
while taking the training and in the future.
This course was developed for World Bank staff and therefore some references
may be specific to World Bank staff.
As for all Environmental and Social Standards, the following principles apply:
The level of assessment and impact mitigation design should cover all
relevant issues while being proportionate to the level of risk
The Mitigation Hierarchy should be used in all circumstances
The following principles are particularly relevant to ESS2, ESS3 and ESS4:
Apply national law and/or the Environmental, Health, and Safety Guidelines
or other recognized Good International Industry Practice (GIIP), whichever is
most stringent
Apply the “Polluter Pays” principle
Implement technically and financially feasible measures for efficient
consumption of resources, particularly water, energy, and raw materials
Promote accessibility, safety and climate change considerations in the design
and construction of civil works
Mitigation Hierarchy
Adopting a Mitigation Hierarchy approach means:
Anticipate and avoid risks and impacts to the extent possible
Where avoidance is not possible, minimize or reduce risks and impacts to
acceptable levels
Once risks and impacts have been minimized or reduced, mitigate
Where significant residual impacts remain, compensate for or offset them,
where technically and financially feasible
Learning Objectives
By the end of this module, you will be able to:
Explain the objectives and key requirements of ESS2, Labor and Working
Conditions; ESS3, Resource Efficiency and Pollution Prevention and
Management; and ESS4, Community Health and Safety
Describe how they should be addressed during the preparation and
implementation of an investment project
Recognize several Helpful Approaches, Mindsets, and Behaviors that are key
for successful implementation of the Environmental and Social Framework
Good morning.
Thank you for joining the project team for this port redevelopment project that the
World Bank is considering financing.
As you know, we are currently at the identification stage and have a first draft
Project Concept Note that sets out the proposed scope of the project at this stage.
We appreciate your involving both Cheung and me early in the project, so we can
work efficiently as a team to ensure that the project’s environmental and social
risks are identified and managed effectively.
And the fact that the Borrower has approached the World Bank to discuss the
social and environmental issues at such an early stage also gives us the
opportunity to ensure that these issues are addressed as part of the project
design, rather than as after-thoughts.
This should make managing any risks easier and less expensive and it should
lead to a more sustainable project.
Excellent.
As we go through the relevant elements of the Environmental and Social
Standards, I think you’ll find that a lot of it is quite familiar. The Environmental and
Social Framework retains many elements of the former safeguard policies without
major changes.
And I can assure you that not everything in the Environmental and Social
Framework is new!
In many cases, existing requirements have been better articulated, which should
be helpful.
Of course, there are also some aspects that are new, such as the objectives and
requirements relating to resource efficiency and climate change, and to working
conditions for workers hired under the project.
Let’s start by looking at this map and the aerial photos so we can build a shared
picture.
As you can see, there is an existing port that has been in operation for over 70
years with an annual cargo tonnage of approximately 12 million tons.
The goods come in by road along the coast from the industrial zone, and by train
from the agriculturally rich Leugap River valley over here.
The redevelopment will require removing or upgrading some existing facilities,
and expanding the port.
The Borrower would like to see a tripling of the annual cargo tonnage, they want
to expand the type of goods that can be handled, and they want improved access
for bigger ships and better road access to accommodate a greater volume of
goods.
Then there will be some new warehouses in this area over here, and they also
plan to upgrade that access road from an unpaved one lane road with passing
bays to a full two lane tarmac road, so we can expect a substantial permanent
increase in the volume and speed of traffic, which raises road safety issues.
Project Definition
Are all of those elements going to be part of the project?
Yes, as far as we know, the Borrower is planning to ask the Bank to contribute to
financing everything I’ve mentioned, so they will all be part of the project.
There have been some early discussions about possibly requesting another
multilateral or bilateral donor to co-finance the access road.
It makes it easier that our requirements for environmental and social assessment
would be proportionate to the relatively low risk of this type of activity.
That is, unless there are specific issues, for example, if they are going to be used
to store hazardous materials.
Discovery Question
If a project includes existing facilities or activities:
Correct Choice
It must meet all the relevant requirements of the Environmental
and Social Standards before the project is approved by the
World Bank
As part of the Environmental and Social Commitment Plan, the
Borrower is required to indicate which of the Environmental and
Social Standards are relevant
As part of the environmental and social assessment process,
the Borrower must demonstrate that the facilities or activities
are fully consistent with the World Bank Group’s Environmental,
Health, and Social Guidelines
X As part of the Environmental and Social Commitment Plan, the
Borrower is required to adopt and implement measures
satisfactory to the Bank so that the facilities or activities will
And if there is runoff into the bay it could have serious environmental
consequences, including killing many fish or making them unfit for consumption.
Also, I understand there will be some dredging to enable the port to handle larger
ships, and there is a lot of heavy industry upstream.
If the environmental and social assessment indicates there are heavy metals or
other toxins in the sediments,
there will be the issue of how the sediments can be contained during dredging
and where it can be disposed of afterwards.
There is also the issue of handling and disposal of any hazardous materials such
as asbestos or lead in the construction debris.
Of course. One thing I noticed right away from the map and aerial photos is that it
looks like the main port access road goes right through these coastal communities.
The aerial photos show a lot of homes and other buildings along the road, and
people have to cross the road to get to their fishing boats which are moored on
the other side.
I think we should advise the Borrower to carry out a road safety assessment as
part of the environmental and social impact assessment, so the results can be
used as an input for the design of the project. On our site visit, we will need to
take a good look at the site of the proposed new port entrance, since operations
at this location could generate a lot of noise and dust and exhaust emissions from
trucks moving through or idling in the area for long periods.
This would have implications for health in the nearby residential areas and
possible disturbances from nighttime illumination. The Borrower should apply the
World Bank Group’s Environmental, Health, and Safety Guidelines for Ports,
Harbors, and Terminals or the local regulations, whichever is more stringent. This
comparison between the Environmental, Health, and Safety Guidelines, and the
local regulations should be part of the environmental and social assessment.
Aisha and I will be able to help you review the results and provide guidance to the
Borrower.
Ecosystem Services
Ecosystem services are generally divided into four types:
Provisioning services, such as the production of food and water
Regulating services, such as the control of climate and disease
Supporting services, such as nutrient cycles and crop pollination
Cultural services, such as spiritual and recreational benefits
ESS4 relates specifically to provisioning and regulating services.
Emergency Events
ESS4 Paragraphs 19 - 23:
An emergency event is an unanticipated incident, arising from either natural or
man-made hazards (such as fire, explosions, leaks or spills). It may occur for a
variety of reasons, from extreme weather to failure to implement preventative
procedures.
For projects having the potential to generate emergency events, the Borrowers
will put in place measures designed to address the event in a coordinated manner
in order to avoid injury to the extent possible and to minimize, mitigate and
compensate any impacts that occur.
The Borrower will conduct a risk hazard assessment as part of the environmental
and social assessment of the project, and prepare an Emergency Response Plan
in coordination with the relevant local authorities and the affected communities
and/or workers. The Emergency Response Plan will be proportionate to the
nature and scale of the hazard and will include (as appropriate):
Engineering controls (such as containment and automatic shut-off systems)
Secure access to emergency equipment on-site and nearby
We should flag now that an Emergency Response Plan will likely need to be a
component of the Environmental and Social Commitment Plan and remind our
counterparts that Environmental, Health, and Safety Guidelines for Ports, Harbors,
and Terminals provide a lot of guidance on good international practice for these
aspects.
So ESS4 is the Standard that addresses the requirements for dealing with
hazardous materials?
Actually, three of the Standards are relevant here.
Knowledge Check
Drag Item Drop Target
ESS2 Protecting workers’ health and
safety
ESS4 Protecting community health and
safety
ESS3 Managing chemicals and hazardous
materials
ESS3 Objectives
I guess this leads us to ESS3.
Aside from hazardous materials, is there anything else we should discuss in
relation to our pollution Standard?
Actually, ESS3 covers all types of pollution prevention and management,
and also efficient use of resources such as water, energy and raw materials.
ESS3 Objectives
To promote the sustainable use of resources, including energy, water, and raw
materials
To avoid or minimize adverse impacts on human health and the environment
by avoiding or minimizing pollution from project activities
To avoid or minimize project-related emissions of short- and long-lived climate
pollutants
To avoid or minimize generation of hazardous and non-hazardous waste
To minimize and manage the risks and impacts associated with pesticide use
I visited the port last year and it seemed to me that the area may already be fairly
polluted.
For example, there are a lot of areas where the soil looks contaminated with oil.
Since the port has been in operation for a long time already, it’s possible that
there is historical pollution at the site.
This will have to be considered during the scoping process for the environmental
and social assessment,
because if historical pollution exists that could affect communities, workers or the
environment, then the Borrower would need to undertake a health and safety risk
assessment and carry out some site remediation if necessary.
Doesn’t ESS3 also say something about greenhouse gases?
Yes, that’s right.
We start by making an assessment as to whether the project could involve
significant greenhouse gas emissions.
If so, the Borrower is responsible for estimating gross greenhouse gas emissions
related to the project, but we may provide assistance if they need it.
And finally, on the resource efficiency side, the environmental and social
assessment should look for opportunities to conserve water and energy as much
as is technically and financially feasible, particularly during the construction and
operational phases.
Discovery Question
From each of the following pairs, select the statement that reflects the
requirements of ESS3.
Correct Choice
When the project is a potentially significant user of energy, the
Borrower will demonstrate that all available energy-reducing
technologies and measures have been incorporated in the
project design.
X When the project is a potentially significant user of energy, in
addition to applying the resource efficiency requirements of
ESS3, the Borrower will adopt measures specified in the
Environmental, Health, and Safety Guidelines to optimize
energy usage, to the extent technically and financially feasible.
ESS3
Resource efficiency
The Borrower will implement technically and financially feasible measures for
improving efficient
consumption of energy, water and raw materials, as well as other resources. Such
measures will integrate the principles of cleaner production into product design
and production processes to conserve raw materials, energy and water, as well
as other resources. Where benchmarking data are available, the Borrower will
make a comparison to establish the relative level of efficiency.
A. Energy use
The efficient use of energy is an important way in which the Borrower can
contribute to sustainable development. When the project is a potentially significant
user of energy, in addition to applying the resource efficiency requirements of this
Environmental and Social Standard, the Borrower will adopt measures specified
in the Environmental, Health, and Safety Guidelines to optimize energy usage, to
the extent technically and financially feasible.
Discovery Question
Select the statement that reflects the requirements of ESS3.
Correct Choice
X For projects with a high water demand that have potentially
significant adverse impacts on communities, other users or the
environment, the requirements of ESS3 include:
Development and monitoring of a detailed water balance
Identifying opportunities for improvement in water use efficiency
Benchmarking to available industry standards of water use
efficiency
For projects with a high water demand that have potentially
significant adverse impacts on communities, other users or the
environment, the requirements of ESS3 include:
ESS3
B. Water use
When the project is a potentially significant user of water or will have potentially
significant impacts on water quality, in addition to applying the resource efficiency
requirements of this Environmental and Social Standard, the Borrower will adopt
measures, to the extent technically and financially feasible, that avoid or minimize
water usage so that the project’s water use does not have significant adverse
impacts on communities, other users and the environment. These measures
include, but are not limited to, the use of additional technically feasible water
conservation measures within the Borrower’s operations, the use of alternative
water supplies, water consumption offsets to maintain total demand for water
resources within the available supply, and evaluation of alternative project
locations.
Projects With High Water Demand
For projects with a high water demand that have potentially significant adverse
impacts on communities, other users or the environment, the following will apply:
A detailed water balance will be developed, maintained, monitored and
reported periodically
Objectives of ESS2
OK, I guess we’ve saved our new Standard on Labor and Working Conditions for
last.
I have to say, ESS2 is the one I know the least about.
It’s fairly new to me too, so I will probably need to consult with some of my
colleagues on how to apply it in the context of this project.
ESS2 Objectives
To promote safety and health at work
To promote the fair treatment, non-discrimination and equal opportunity of
project workers
To protect project workers, including vulnerable workers such as women,
persons with disabilities, children (of working age, in accordance with this
Environmental and Social Standard) and migrant workers, contracted workers,
community workers and primary supply workers, as appropriate
To prevent the use of all forms of forced labor and child labor
To support the principles of freedom of association and collective bargaining of
project workers in a manner consistent with national law
To provide project workers with accessible means to raise workplace concerns
The part of ESS2 that will probably be most familiar to you is occupational health
and safety.
We need to work with the Port Authority to make sure there are suitable plans for
occupational health and safety during construction, including things like the
provision of personal protection equipment, and accident, and incident reporting
procedures.
They should also have a system for monitoring and reporting on the
implementation of their occupational health and safety plan, including reporting
any fatalities or serious injuries to the World Bank.
Discovery Question
What is normally the minimum age at which a person can be employed or
engaged in connection with a World Bank-financed project?
Correct Choice
12 years
X 14 years
16 years
18 years
hazardous or interfere with the child’s education or be harmful to the child’s health
or physical, mental, spiritual, moral or social development
Discovery Question
ESS2 calls for workers to be informed or notified of which of the following?
Correct Choice
X Their rights related to hours of work, wages, overtime,
compensation, and benefits
X Conditions under which deductions will be made from wages
Their rights under national labor and employment law as well as
those arising from the requirements of ESS2 and from United
Nations/International Labor Organization Standards
Training opportunities to the extent that these may contribute
directly to opportunities for salary increase or promotion
Terms of Employment
Project workers will be provided with information and documentation that is clear
and understandable regarding their terms and conditions of employment. The
information and documentation will set out their rights under national labor and
employment law (which will include any applicable collective agreements),
including their rights related to hours of work, wages, overtime, compensation,
and benefits, as well as those arising from the requirements of this Environmental
and Social Standard. This information and documentation will be provided at the
beginning of the working relationship and when any material changes to the terms
or conditions of employment occur.
Project workers will be paid on a regular basis as required by national law and
labor management procedures. Deductions from payment of wages will only be
made as allowed by national law or the labor management procedures, and
project workers will be informed of the conditions under which such deductions
will be made. Project workers will be provided with adequate periods of rest per
week, annual holiday, and sick, maternity and family leave, as required by
national law and labor management procedures.
Where required by national law or the labor management procedures, project
workers will receive written notice of termination of employment and details of
severance payments in a timely manner. All wages that have been earned, social
security benefits, pension contributions and any other entitlements will be paid on
or before termination of the working relationship, either directly to the project
workers or where appropriate, for the benefit of the project workers. Where
payments are made for the benefit of project workers, project workers will be
provided with evidence of such payments.
Right to Organize
In countries where national law recognizes workers’ rights to form and to join
workers’ organizations of their choosing and to bargain collectively without
interference, the project will be implemented in accordance with national law. In
such circumstances, the role of legally established workers’ organizations and
legitimate workers’ representatives will be respected, and they will be provided
with information needed for meaningful negotiation in a timely manner. Where
national law restricts workers’ organizations, the project will not restrict project
workers from developing alternative mechanisms to express their grievances and
protect their rights regarding working conditions and terms of employment. The
Borrower should not seek to influence or control these alternative mechanisms.
The Borrower will not discriminate or retaliate against project workers who
participate, or seek to participate, in such workers’ organizations and collective
bargaining or alternative mechanisms.
SUMMARY
ESS2 Requirements
The Borrower prepares and implements written labor management procedures
applicable to the project. This:
o Documents a clear agreement between the World Bank and the
Borrower and
o Provides the basis for the World Bank’s monitoring and due diligence
during project implementation
Types of Workers
The second thing to know is that ESS2 has different requirements that apply to
different types of workers.
You mean, like men and women? Or skilled and unskilled workers?
No, I mean direct workers employed by the Borrower specifically to work on the
project, subcontractors, community workers, people employed by the Borrower’s
primary suppliers, and civil servants who contribute to project implementation but
are not employed under the project.
And the Standard applies not only to full-time workers, but also to part-time,
temporary, seasonal and migrant workers.
Primary Suppliers
Primary suppliers are those suppliers who, on an ongoing basis, directly provide
goods or materials essential for the core functions of the project.
For primary supply workers, the Borrower will identify potential risks of child labor,
forced labor and serious safety issues which may arise in relation to primary
suppliers. Where there is a significant risk of child labor or forced labor related to
primary supply workers, the Borrower will require the primary supplier to identify
those risks, consistent with the Environmental and Social Standards requirements
relating to child or forced labor. If child labor or forced labor cases are identified,
the Borrower will require the primary supplier to take appropriate steps to remedy
them. Where there is a significant risk of serious safety issues related to primary
supply workers, the Borrower will require the relevant primary supplier to
introduce procedures and mitigation measures to address such safety issues.
Such procedures and mitigation measures will be reviewed periodically to
ascertain their effectiveness. The labor management procedures will set out roles
and responsibilities for monitoring primary suppliers. The ability of the Borrower to
address these risks will depend upon the Borrower’s level of control or influence
over its primary suppliers. Where remedy is not possible, the Borrower will, within
a reasonable period, shift the project’s primary suppliers to suppliers that can
demonstrate that they are meeting the relevant requirements of this
Environmental and Social Standard.
Discovery Question
Does ESS2 apply to government civil servants who are working in connection with
a project?
Correct Choice
Yes, they are treated as direct workers
No ESS2 requirements apply to them
X All ESS2 requirements apply to them if there has been a legal
transfer of their employment to the project
X If not legally transferred, only the provisions on child and forced
labor and Occupational Health and Safety apply to them
ESS2 Paragraph 8
Where government civil servants are working in connection with the project,
whether full-time or part-time, they will remain subject to the terms and conditions
of their existing public sector employment agreement or arrangement, unless
there has been an effective legal transfer of their employment or engagement to
the project. ESS2 will not apply to such government civil servants, except for the
provisions of paragraphs 17 to 20 (Protecting the Work Force) and paragraphs 24
to 30 (Occupational Health and Safety).
If the environmental and social assessment concludes there are significant risks,
the Borrower needs to require the relevant suppliers to introduce procedures and
measures to address them and to review the situation periodically to ascertain
that they are effective.
In the case of child and forced labor, the Borrower has to monitor the primary
suppliers, and if any cases are identified, require the suppliers to take steps to
remedy them.
The Borrower’s specific responsibilities for all of this are set out in the labor
management procedure.
One last thing: you remember I mentioned labor influx earlier, as a potential issue
for community health and safety.
Well, bringing a large labor force to a worksite is also an issue for workers’ health
and safety and general working conditions, particularly if there will be a labor
camp for the workers.
The labor management procedures should set out criteria for their living
conditions, and this needs to be incorporated into any contracts which will involve
the use of contracted workers.
Pesticide Management
Where it has been determined that pesticides are needed to address significant
economic or health impacts of pests or vector-borne diseases, they should be
selected, formulated, packaged, handled, stored, disposed of and applied
according to relevant international Standards (e.g., the Food and Agricultural
Organization’s International Code of Conduct on Pesticide Management) and the
World Bank Group Environmental, Health, and Safety Guidelines. Key elements
of good pesticide management include:
Avoid pesticide products containing active ingredients that are restricted under
national laws or international conventions, except for purposes defined as
acceptable under the relevant laws or conventions
Avoid formulated pesticide products that fall within criteria of carcinogenicity,
mutagenicity or reproductive toxicity as set forth by relevant international
agencies
Avoid use of any other pesticide products that are internationally recognized to
pose other potentially serious risks to human health or the environment if the
country lacks restrictions on their distribution and use or if they are likely to be
used by, or accessible to, farmers or others without the training, equipment
Recap
Here is a quick recap of the main points covered in this module.
ESS2
ESS 3
ESS4
Helpful Approaches, Mindsets, and Behaviors
ESS2
Promote safety and health at work
Promote the fair treatment, non-discrimination and equal opportunity of project
workers
Protect project workers, including vulnerable workers, children (of working age)
and migrant workers, contracted workers, community workers and primary
supply workers, as appropriate
Prevent the use of all forms of forced labor and child labor
Support the principles of freedom of association and collective bargaining of
project workers
Provide project workers with accessible means to raise workplace concerns
ESS 3
Promote the sustainable use of resources, including energy, water and raw
materials
Avoid or minimize adverse impacts on human health and the environment by
avoiding or minimizing pollution from project activities
Avoid or minimize project-related emissions of short and long-lived climate
pollutants
Avoid or minimize the generation of hazardous and non-hazardous waste
Minimize and manage the risks and impacts associated with pesticide use
ESS4
Anticipate and avoid adverse impacts on the health and safety of project-
affected communities
Promote quality and safety, and considerations relating to climate change, in
the design and construction of infrastructure, including dams
Avoid or minimize community exposure to project-related traffic and road
safety risks, diseases and hazardous materials
Have in place effective measures to address emergency events