Module3 Print
Module3 Print
Topic: Welcome
Topic: Scope of Application
Topic: The Borrower’s Responsibilities
Topic: Environmental and Social Assessment Process
Topic: Other Environmental and Social Assessment Requirements
Topic: Environmental and Social Risk Management
Topic: Summary
Read More
This course aims to provide an in-depth introduction to the elements of the World
Bank’s Environmental and Social Framework for Investment Project Financing.
Before taking this course, you are encouraged to read the Environmental and
Social Framework itself and to use it as a reference document as needed, both
while taking the training and in the future.
This course was developed for World Bank staff and therefore some references
may be specific to World Bank staff.
Objectives of ESS1
The objectives of ESS1 are to:
Identify, evaluate and manage the environmental and social risks and impacts
Follow the Mitigation Hierarchy approach
Adopt differentiated measures so that adverse impacts do not fall
disproportionately on the disadvantaged or vulnerable, and they are not
disadvantaged in sharing development benefits and opportunities
Utilize national environmental and social institutions, systems, laws,
regulations and procedures
Recognize and enhance Borrower capacity
Learning Objectives
By the end of this module, you will be able to:
Describe the Borrower’s responsibilities for assessing, managing and
monitoring environmental and social risks and impacts
Explain the Mitigation Hierarchy approach
Explain how to apply ESS1 to Associated Facilities, and Technical Assistance
supported through investment lending
Describe several environmental and social assessment tools and explain when
they should be used
Explain the meaning and importance of integrated environmental and social
risk assessment and management
What is a project?
Activities for which the World Bank financing is sought by a Borrower, and as
defined in the legal agreement between the Borrower and the World Bank.
Identify
Identify the parties involved in design and operation of the Associated Facility and
their respective roles.
Explain
Explain to what extent and for what reasons the Borrower lacks or has limited
control or influence over the design and /or operation of the Associated Facility.
Describe
Describe and evaluate the risks, if any, which this lack or limitation of the
Borrower’s control or influence over the Associated Facility presents to the project,
the environment or project-affected people.
The Borrower is required to demonstrate the reasons and extent to which it
cannot exercise control or influence over the Associated Facilities.
Example
For example, if the Technical Assistance is:
Supporting the preparation of a feasibility study for construction of new
infrastructure which will require land acquisition, the study (including cost
estimates and timeframes for implementation) should incorporate the relevant
requirements of ESS5 (Land Acquisition, Restrictions on Land Use and
Involuntary Resettlement)
Advising on the preparation of a forest policy management, the analysis and
recommendations should incorporate the principles of habitat protection and
sustainable forest management of ESS6 (Biodiversity Conservation and
Sustainable Management of Living Natural Resources)
Discovery Question
The World Bank and a Regional Development Bank are
co-financing the construction of a new gas-fired thermal power plant. The project
location is immediately adjacent to an existing coal-fired power plant which the
Ministry of Energy is in the process of upgrading with more modern technology to
reduce SO2 and particulate emissions. Just before the new power plant becomes
operational, the Ministry of Energy constructs a dedicated gas pipeline to connect
the new plant to an existing gas field which serves several regions of the country.
At the same time, an existing transmission line which previously evacuated power
from the coal-fired plant is upgraded to enable it to serve both the coal and the
new gas plant.
Five years after the new plant begins operations, the government uses a public-
private partnership to build an extension which increases its capacity by thirty
percent. At that time, the Government expands the gas field to help meet the
increased consumption of the expanded power plant as well as growing demand
from the domestic and industrial sectors nationwide.
Discovery Question
In the scenario, which of the following would be an Associated Facility to a World
Bank-financed project, as defined in ESS1?
Correct Choice
Gas field
X Gas pipeline
Objectives
Here are the objectives of the environmental and social assessment process.
The Borrower:
Conducts an environmental and social assessment to:
o Identify and evaluate potential environmental and social risks and project
impacts
o Design measures to mitigate and manage these risks and impacts
Consults with the World Bank to help identify potential issues and to define the
process to be used and the tools to be prepared
The environmental and social assessment process documents how the Mitigation
Hierarchy was followed in project design and preparation, including:
Describing and analyzing alternative locations, technologies or approaches
that were considered
Indicating why alternatives were or were not adopted or recommended
Where residual adverse risks or impacts are anticipated, the environmental and
social assessment:
Describes the nature and significance of the residual risks and impacts
Identifies risks and impacts considered to be significant
The assessment covers the entire life cycle of the project and may continue into
the implementation phase.
Types of Impacts
The environmental and social assessment process should consider, identify and
evaluate all potential risks and impacts associated with the project, including:
Direct, Indirect and Cumulative Risks and Impacts
Local, Offsite and Transboundary Risks and Impacts
Residual Risks and Impacts
but predictable activities that are enabled by the project and that may occur later
or at a different location. Cumulative impacts can result from individually minor but
collectively significant activities taking place over a period of time.
Six “run of the river” hydropower projects along a single river channel, each
diverting water for a relatively small percentage of the total length of the river, but
collectively resulting in loss of a large percentage of riverine ecosystem.
The collective impacts of dozens of small scale poultry farms in an area, all of
which are sources of manure entering the same river.
Impact remaining following application of avoidance, minimization and mitigation
measures
Traffic noise remaining after all feasible traffic noise reduction options have been
implemented.
The Borrower will also address risks and impacts associated with any primary
suppliers of the project, as set out in ESS2 and ESS6.
Primary Suppliers
Primary suppliers are those suppliers who, on an ongoing basis, provide directly
to the project goods or materials essential for the core functions of the project.
Assessing environmental and social risks and impacts continues throughout the
life-cycle of the project, through monitoring of indicators, such as:
Emissions into air and water
Populations of indicator species
Road accidents
Screening
Most countries have laws requiring that environmental assessments be carried
out for certain types of projects, usually based on factors relating to the nature,
scale and location of the proposed activities. Often these laws include
differentiated assessment requirements based on a screening and classification
process similar to that described in the World Bank’s Environmental and Social
Policy (Paragraph 20), although the categories and criteria may be different from
those used by the World Bank. A comparison of the national system for project
risk screening with the assessment requirements associated with different risk
categories is one of the aspects the World Bank will assess when considering
whether to agree that the Borrower will apply part or all of its own framework to
implement a World Bank-supported project to meet the requirements of the ESF.
The World Bank also assesses the capacity of the Borrower or Financial
Intermediaries to screen subprojects against the relevant laws or World Bank
criteria in the case of projects involving multiple subprojects that are identified,
prepared and implemented during the course of the project.
Environmental Assessments
Most national laws refer to environmental assessment rather than environmental
and social assessment, but also usually call for addressing social risks and
impacts arising from changes in the physical or biological environment.
Scoping
Refers to identifying potential environmental and social risks and impacts on
which the environmental and social assessment should focus, the methods to be
used and the level of effort needed to fully understand the risks and impacts and
the options for mitigating them. The results of the scoping process should inform
the preparation of the Terms of Reference for the environmental and social
assessment, including any studies on specific aspects such as a social conflict
analysis, a cultural heritage assessment, and a biodiversity management plan.
Assessment
This step includes: (i) Detailed identification and evaluation of potential risks and
impacts, based on collection and analysis of specific data, and (ii) Identification
and recommendation of appropriate and feasible measures to reduce and
manage the risks and impacts and identification of likely residual (unavoidable
and non-mitigatable) risks and impacts.
Monitoring
Monitoring project implementation may also be regarded as part of adaptive
management, as information from monitoring should be used to improve project
approaches or implementation as needed.
Scoping helps the Borrower determine, in consultation with the World Bank, which
tools to use, depending on baseline information available and the nature and
significance of the project’s potential risks and impacts. For example:
A full and comprehensive Environmental and Social Impact Assessment (see
outline in ESS1, Annex 1) for large, complex projects with multiple significant
risks that are not fully understood or may be difficult to manage
A limited or targeted assessment, or only an environmental and social
management plan, when potential project risks and impacts are easily
identified, and appropriate and reliable mitigation measures are well known
When a project consists of a program or a series of subprojects, and the risks and
impacts cannot be determined until the program or subproject details have been
identified during project implementation, the Borrower can prepare an
Environmental and Social Management Framework that sets out the principles,
rules, guidelines and procedures for assessing their environmental and social
risks and impacts as part of the process of preparation and approval of the
subprojects.
Yes. This is an example of applying the proportionality principle. For these types
of projects ESS1 sets different requirements for how the Borrower carries out the
environmental and social assessment and prepares and implements the
subprojects depending on their risks:
For High Risk subprojects, it is in accordance with the Environmental and
Social Standards
For Substantial, Moderate or Low Risk subprojects, it is in accordance with
national law and any requirements of the Environmental and Social Standards
that the World Bank deems relevant to particular subprojects
For subprojects that are identified during the scoping process as being likely to
have minimal or no adverse environmental or social risks, no further
environmental and social assessment is required
It is important to note that these provisions do not apply to subprojects in
Financial Intermediary projects, which are addressed separately in ESS9.
Independent specialists
The Borrower should ensure that the persons carrying out the environmental and
social assessment have the necessary technical expertise, competency and
experience to evaluate the project’s risks and impacts and determine how the
relevant requirements of the Environmental and Social Standards will be met.
The use of independent specialists to carry out environmental and social
assessments is intended to ensure objectivity and avoid real or perceived conflict
of interest. The independent specialist should generally not be involved in other
aspects of preparation, design and implementation of the project. However, in
certain circumstances where an expert has been involved in some aspects of the
project (such as feasibility studies), he/she may be engaged by the Borrower for
the environmental and social assessment if the Borrower can demonstrate to the
satisfaction of the World Bank that there is no conflict of interest and that doing so
would benefit the assessment.
Information Disclosure
Under ESS10:
The Borrower is expected to engage with, and provide sufficient information to,
stakeholders:
o Throughout the life-cycle of the project
o Starting as early as possible in project identification and preparation
The Borrower discloses information from the environmental and social
assessment process in a timely and accessible manner
Under ESS1:
The Borrower provides to the World Bank and publicly discloses
documentation relating to the environmental and social risks and impacts of
High Risk and Substantial Risk projects, prior to project appraisal
The documentation:
Addresses key risks and impacts of the project
Mitigation Hierarchy
The Borrower is responsible for developing mitigation measures, in line with the
Mitigation Hierarchy.
The steps of the Mitigation Hierarchy are:
Anticipate and Avoid
Minimize or Reduce
Mitigate
Compensate For or Offset Significant Residual Risks
Minimize or Reduce
Examples of measures to reduce or minimize risks include use of low-emission
and “benign by design” technologies, and lowering the height of a proposed dam
to reduce the number of people needing resettlement.
Mitigate
Examples of mitigation measures include providing alternative access to
important cultural or natural resource assets, installing underpasses or green
bridges across busy roadways, and physical rehabilitation or ecological
restoration of construction sites.
The ESCP
Provides a full and accurate summary of material measures and actions
required to avoid, minimize, reduce or otherwise mitigate the potential
environmental and social risks and impacts of the project, including:
o Measures to revise policies or strategies or to build capacity within the
institutions involved in implementing the project
o Actions required by national laws and regulations that are also relevant
to satisfying the requirements of the Environmental and Social
Standards
o Actions that the Borrower may have taken prior to approval of the project
by the World Bank
Sets out the institutional arrangements (including personnel, budget and
timelines for implementation)
Includes all the relevant measures and agreed actions where:
o Use of the Borrower framework has been agreed
o A “Common Approach” is used for a project co-financed by the World
Bank and financing partners.
Managing Contractors
Contractors can have a major impact on communities and the environment
depending on how they operate their business and manage their staff. Therefore,
managing contractors is an essential element of environmental and social risk
management.
The Borrower is ultimately responsible for ensuring that the project is
implemented in a manner consistent with the Environmental and Social Standards.
Contractors retained by or acting on behalf of the Borrower or its implementing
agency are considered to be under the direct control of the Borrower.
Knowledge Check
How many Environmental Standards and Social Standards are there?
Correct Choice
Recap
Here is a quick recap of the main points covered in this module.
ESS1
The Borrower’s Responsibilities
Methods and Tools
The ESA Process
Impact
Stages
ESS1
Applies to all activities, including Technical Assistance, supported through
Investment Project Financing, and to Associated Facilities
Requires engaging with stakeholders and disclosing information throughout
the project life-cycle
Impact
The ESA process should consider, identify and evaluate all potential risks and
impacts associated with the project, including:
Direct, Indirect and Cumulative Risks and Impacts
Residual Risks and Impacts
Stages
The main stages of the environmental and social assessment process to be
carried out by the Borrower are:
Screening
Scoping
Assessment
Risk Management Planning
Monitoring