Module4 Print
Module4 Print
Topic: Welcome
Topic: Scope of Application and Requirements
Topic: Stakeholder Engagement
Topic: Stakeholder Engagement During Project Preparation
Topic: Stakeholder Engagement During Project Implementation
Topic: Grievance Mechanisms
Topic: Stakeholder Engagement in Other Standards
Topic: Summary
Read More
This course was developed for World Bank staff and therefore some
references may be specific to World Bank staff.
Learning Objectives
By the end of this module, you will be able to:
Describe why Borrowers should engage with stakeholders
Define the two types of stakeholders
Discuss in detail what is required from the Borrower at each stage of
the project regarding stakeholder engagement and information
disclosure
Describe the key elements of a Stakeholder Engagement Plan
Detail the requirements for a grievance mechanism
Describe specific requirements for stakeholder engagement and
information disclosure found in other Environmental and Social
Standards
Objectives of ESS10
ESS10 and its objectives are aimed at establishing a systematic, open and
transparent engagement between the Borrower and project stakeholders
throughout the life of the project.
Definition of Stakeholders
Who are stakeholders?
Project-affected parties: Those who are, or are likely to be, affected by
the project
Other interested parties: Those who may have an interest in the project
and who could, for example:
o Influence the opinions of affected parties either positively or
negatively
o Affect the implementation process or the sustainability of the
project’s outcomes
Stakeholders
The stakeholders of a project will vary depending on the details of the
project.
Project-affected Parties
Project-affected Parties refers to both intended beneficiaries of the project
and those likely to be affected by the project because of actual impacts or
potential risks to their physical environment, health, security, well-being or
livelihoods. These stakeholders may include individuals, groups, or local
communities.
Examples:
Provide advice on methodologies, appropriate timing and
documentation processes
Monitor the implementation of stakeholder engagement
o Monitoring could include participating in the consultation activities
in person or through a third party
Forms of Engagement
Forms of engagement include:
Public meetings
Community meetings
Individual interactions
Focus group discussions
Standing committee meetings
Questionnaires/Household surveys
Participatory processes, for example, seasonal mapping, community
mapping, community transects, participatory rural appraisal
Engagement techniques applied may vary from project to project.
Meaningful Consultations
Meaningful consultation is essential and it is a two-way process that:
Provides stakeholders with opportunities to express their views on
project risks, impacts and mitigation measures and allows the Borrower
to consider and respond to them
Begins early in the project planning process and continues on an
ongoing basis, particularly when new risks or impacts arise
Encourages stakeholder feedback to inform project design and help
identify and mitigate risks and impacts and considers and responds to
such feedback
Is based on the prior disclosure and dissemination of relevant, objective,
meaningful and accessible information
Supports active and inclusive engagement with project-affected parties
Is free of external interferences
Is documented and disclosed by the Borrower
Overview
The Grievance Mechanism:
Allows stakeholders to register grievances, concerns, suggestions,
inquiries, and complaints
Supports submission of grievances at multiple locations and through
multiple mechanisms
Is accessible to all stakeholders regardless of their social, cultural, or
economic standing
Where feasible and suitable, may use existing formal and informal
grievance mechanisms, supplemented as needed
Should be proportionate to the nature of the project and the potential
risks and impacts of the project
Accessibility
The grievance mechanism should be readily accessible to all project-
affected parties, at no cost and without retribution. For example:
An inaccessible grievance mechanism would be in a location that is not
reachable for particular groups of stakeholders, such as women or
people who live in remote areas
An accessible grievance mechanism would enable anonymous
complaints to reduce the risk of retribution
Key Elements
The grievance mechanism should:
Include a log for registering and tracking grievances and actions taken.
Discovery Question
The grievance mechanism established as part of the Stakeholder
Engagement Plan may be utilized under the Land Acquisition, Restrictions
on Land Use and Involuntary Resettlement (ESS5) and Indigenous
Peoples/Sub-Saharan African Historically Underserved Traditional Local
Communities (ESS7).
Correct Choice
X True
False
Discovery Question
Which of the following are acceptable options if resolution of grievances
has not been achieved or affected parties are not satisfied with the
proposed resolution?
Correct Choice
Information Dissemination
Dissemination of information on the grievance process:
Project-affected parties should be informed by the Borrower about the
grievance process as part of stakeholder engagement.
A record of responses to grievances should be disclosed.
Procedures, such as response times, appeals processes, and so on,
should be publicly advertised.
Information on the procedure, governing structure and decision makers
should be available.
Discovery Question
According to ESS10, a new grievance mechanism should be setup
specifically for the project and to avoid issues that are often associated
with pre-existing systems, such as discrimination, gender imbalance, elite
capture, and/or lack of confidence in local officials.
Correct Choice
True
X False
Recap
Here is a quick recap of the main points covered in this module.
Stakeholders
Borrower
Information Disclosure
Grievance Mechanism
Stakeholders
There are two types of stakeholders, project-affected parties and other
interested parties
Stakeholder engagement can increase stakeholder understanding and
build support for and ownership of projects
Stakeholder engagement is critical to improve project design and
successful project implementation
Effective and inclusive engagement makes it possible for communities
to provide input into project design and mitigation measures
Borrower
The Borrower undertakes stakeholder identification and analysis
The Borrower should assess identified stakeholders and determine their
levels of influence and interests in a project
Stakeholder identification and analysis helps determine the level and
type of communication and engagement that is appropriate for a project
Information Disclosure
Disclosing project information is essential to help stakeholders
understand the potential opportunities of a project and the risks and
impacts of a project
The Borrower should disclose and publicize information in a way that
will reach all relevant groups and individuals
Meaningful consultation is a two-way process that provides
stakeholders with opportunities to express their views on project risks,
impacts, and mitigation measures, and allows the Borrower to consider,
and respond to them
Grievance Mechanism
The Grievance Mechanism allows stakeholders to register grievances,
concerns, suggestions, inquiries, and complaints
The Grievance Mechanism is accessible to all stakeholders regardless
of their social, cultural, or economic standing
The Grievance Mechanism addresses concerns and handles
grievances promptly and effectively and in a transparent and culturally
appropriate manner
Project-affected parties should be informed by the Borrower about the
grievance process as part of stakeholder engagement