CE142 LEC11 Project Planning and Scheduling
CE142 LEC11 Project Planning and Scheduling
CE142 LEC11 Project Planning and Scheduling
Construction
Project Planning and Scheduling
Introduction
KINDS OF PLANNING
12
Planning a Project
13
Planning a Project
18
Planning a Project
19
Planning a Project
20
Programming Techniques
22
Steps in the Planning Process
A B C D E F G
Mobilization A A
Gantt Chart
◼ The bar or Gantt Chart is a widely used simple project scheduling
technique.
◼ Advantages include:
Direct correlation with time.
Straight forward relationship with projects involving a limited
number of tasks.
Straight forward integration of subtasks having separate scheduling
charts.
Time schedule is flexible and is expanded to show tasks of shorter
nature.
Progress against the plan is easily reflected.
◼ Disadvantage includes:
That it does not convey the complex interrelationships that may
occur between tasks.
Gantt Chart
Planning and Scheduling
Milestone Chart
◼ A Milestone chart is similar to a Gantt Chart with the
emphasis placed on task completion.
PERT Chart
PRECEEDING SUCCESSOR
A B ACTIVITY C
ES LS D EF LF D ES LS
EVENT
Planning and Scheduling
CPM Example
Critical Path Method
ACTIVITY ACTIVITY PREDECESSOR
DURATION
NO.
Earliest Start Times Established
1 Mobilization 1 day
2 Layout and Staking 1 day 1
3 Excavate Footing 4 days 2
4 Fabricate Footing rebar 2 days 1
5 Fabricate Column Rebar 3 days 4
6 Install Footing Rebars 1 day 3,4
7 Install Column Rebars 4 days 6,5
8 Concreting of Footing 1 day 7
9 Fabricate Column Forms 5 days 2
10 Install Column Forms 2 days 9,8
11 Concreting of Column 2 days 10
Critical Path Method
NETWORK DIAGRAM
INST
COL
FORM
FAB
FORM
9 10
COL
CONC
COL
INST INST
CONC
EXC FTNG COL
MOB FTNG
L&S FTNG REB REB
1 2 4 5 7 8 11
FAB
FTNG
REB
3 6
FAB
COL.
REB
CPM Calculations
The calculations of the critical path and
the project duration is relatively simple,
requiring only addition and subtraction.
Forward Pass
The first step in the calculations is to perform a
forward pass. In this step, the early start and early
finish of each activity are calculated. The early start
(ES) is the earliest time as activity may start. The
early finish (EF) is the earliest point at which an
activity can be completed.
EF = ES + D
CPM Calculations
Backward Pass
The second stage is to move backward through the
network and determine the late finish and late start
times of each activity. The late finish (LF) for the
activity in the network is assumed to be equal to the
early finish calculated in the forward pass. If there
are multiple closing activities, the greatest early
finish is used. All other nodes are calculated using:
LF = Minimum LS of all following activities
Then the late start (LS) can be calculated as:
LS = LF - D
CPM Calculations
CPM Float
Critical activities cannot be delayed or else the
duration of the project will be longer. Activities with
equal ES and EF or zero float are considered critical
activities and belongs to the critical path.
FREE FLOAT:
Free float is the minimum early start
of all the following activities less the early
finish
FF = ESMIN – (ES + DURATION)
DATA SHEET:
B A 3
C B 4
D A,B 2
E C 3
F D 1
BUILDING CONSTRUCTION METHODOLOGY
( BY PERT/CPM DIAGRAM)
PROJECT: ONE(1) STOREY ONE (1) CLASSROOM SCHOOL BUILDING
DURATION: 30 CALENDAR DAYS
PROCUREMENT/DELIVERY OF CONSTRUCTION MATERIALS C
26 26 28
ELECTRICAL/SANITARY ROUGH-IN H
INST. ELECT/
14 23 25 MECH/SANITARY
FIXTURES
CARPENTRY WORKS U
P 1
23 25 29 30
EARTH
2
MOVE- MOVE
WORKS MASONRY
IN CONCRETE PAINTING OUT
WORKS ROOF FRAMING ROOFING FINISHES T
A B E WORKS G K M O S V
0 0 2 2 4 4 5 9 9 3 12 12 5 17 17 4 21 21 4 25 25 3 28 28 30 30
2 2 2
WAIT WAIT
WAIT WAIT WAIT
D F L 2 N Q R
2 3 4 7 2 12 15 17 19 2 21 24 4 25 28
WAIT
SOIL 1 BACKFILL INST. OF PURLINS INST. GUTTER & INST. FAB. MATLS &
POISONING FLUSHING HARDWARE
I J
9 18 3 12 21
DAMPROOFING/SLAB ON FILL
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
CALENDAR DAYS
LEGEND:
NETWORK - A B
ES LS EF LF
ACTIVITY -
EVENT - A
ES LS
DUMMY -
CRITICAL PATH -
Example Problem
Duration Immediate
Activities
(Days) Predecessors Cost