Course Objectives:
Course Pre-requisites:
Course
Topic Course name Semester
code
Building construction and
Stages of Construction 3
construction materials
Course Outcomes:
Duration
COn Description Cognitive Level
(Hours)
Identify principles involved in construction
CO1 15 Understanding
management and procedures for land acquisition
Apply the project management tools and schedule
CO2 14 Applying
the network model.
Describe contract management and construction
CO3 15 Understanding
equipment
Series Test 2
CO - PO Mapping:
Course
PO1 PO2 PO3 PO4 PO5 PO6 PO7
Outcomes
CO1 3
CO2 3
CO3 3
CO4 3
Course Outline:
Module Duration
Description Cognitive Level
outcomes (Hours)
Identify principles involved in construction management and procedures
CO1
for land acquisition
Identify the principles of management and list the
M1.01 3 Remembering
various types of organization
Contents:
Construction Management-Principles of Management
Organization-objectives, principles of organization, types of organization:
government/public and private construction industry, Role of various personnel in
construction organization.
Agencies associated with construction work- owner, promoter, builder, designer,
architects.
Role of consultant for various activities: Preparation of Detailed Project Report (DPR),
monitoring of progress and quality, settlement of disputes.
Principles governing site layout. Factors affecting site layout. Preparation of site layout.
Land acquisition procedures and providing compensation
CO2 Describe the project management tools and schedule the network model
Use bar charts to show the activities in a
M2.01 3 Applying
construction work
Identify the terms related with network for the
M2.02 3 Understanding
given construction project
Schedule network for the given construction
M2.03 4 Applying
project
M2.04 Describe material management. 4 Understanding
Series Test - I 1
Contents:
Identifying broad activities in construction work & allotting timeperiod to it, Methods of
Scheduling, Development of bar charts, Merits & limitations of bar chart.
Elements of Network: Event, activity, dummy activities, Precautions in drawing Network,
Numbering the events.
CPM networks, activity time estimate, start and finish time of activity, project duration.
Floats: Types of Floats-Free, independent and total floats, critical activities and critical
path. Outline PERT networks
Purpose of crashing a network, Normal Time and Cost, Crash Time and Cost, Cost slope,
Optimization of cost and duration.
Introduction to BIM- Management Software
Material Management- Ordering cost, inventory carrying cost, Economic Order Quantity
Store management, various records related to store management, inventory control by
ABC,VED technique, Introduction to material procurement through portals (e.g.,
www.inampro.nic.in)
Contents:
Define tender and tender procedure -EMD, Security Deposit, Procedure for e-tender
Types of Construction contracts
Contract documents, specifications, general and special conditions
Contract Management, procedures involved in arbitration and settlement (Introduction
only)
Identify different modern equipment used in construction projects. -bull dozer, angle dozer,
excavator, power shovel, forklift, tower crane, back hoe, back hoe loader, gantry crane, slip
form paver, grader, TBM etc. State the specific use of various construction equipment.
Identify the factors related to selection of equipment.
CO4 Describe safety measures at construction projects
Series Test - II 1
Contents:
Construction safety: Basic principles of safety - Major causes of accidents at project site -
Effects of accidents - Safety practices at construction site - Excavation, Working at Heights,
Fire, Underwater, Marshlands etc.- Precautions in handling hazardous materials -
Occupational hazard - Role of supervisor/ Engineer in ensuring safety at construction site -
Labour Laws and Acts pertaining to Civil construction activities (Introduction)