Numerical Relay
Numerical Relay
V.H.Manohar
On Deputation from DAE, India
Electromechanical Static
Analogue Digital
Numerical
- Digital
- Numerical
1
8/19/2021
Comparison of Protective Relay Technologies..contd. Comparison of Protective Relay Technologies..contd. Comparison of Protective Relay Technologies..contd.
2
8/19/2021
Comparison of Protective Relay Technologies..contd. Numerical Relay-Hardware Architecture Numerical Relay-Hardware Architecture
It consists of
Sl. Subject Electro- Static/ Numerical • One or more Digital Signal Processors (DSPs),
No. mechanical Electronic
• Memory,
• Digital and analogue input/output (I/O),
13. Digital Not possible Not available Available
communication port • A power supply.
14. Commissioning No No Yes Where multiple processors are used, one of them is a general controller of
support from relay the I/O, Human Machine Interface (HMI) and any associated logic while the
others are dedicated to the protection relay algorithms.
The internal communications bus links the hardware and therefore is a critical
component in the design. It must work at high speed, use low voltages, yet be
immune to conducted and radiated interference from the electrically noisy
substation environment. Excellent shielding of the relevant areas is therefore
required.
3
8/19/2021
Additional Features of Numerical Relays Additional Features of Numerical Relays Inspection and Testing of Numerical Relays at Factory
Measured Values Display CB Control/State Indication /Condition Monitoring Routine Tests
Sequence quantities (positive, negative, zero) Disturbance Recorder (Oscillograph)
Power, reactive power and power factor -High Voltage Test (2000 Volts for 1 minute)
Time Synchronization from External Clock
Energy (kWh, kVArh) -Measurement of Insulation resistance.
Max. demand in a period ( kW, kVAr; average and peak values) Programmable Logic
-Verification of wiring as per approved schematics.
Harmonic quantities Provision of Setting Groups
-Calibration/Functional checks.
Frequency ISSUES THAT ARISE DUE TO INTRODUCTION OF NUMERICAL RELAYS
Temperatures/RTD status
-Pick up and Drop off Voltage and Timing Checks
Software version control
Motor start information (start time, total no. of -Electrical Control, Interlock and sequential Operation Tests
Relay data management
Starts/re-accelerations, total running time
Testing and commissioning
Distance to fault
Site commissioning is usually restricted to
-running the in-built software self-check,
VT/CT Supervision
-verifying that currents and voltages measured by the relay are correct,
-The VT failure algorithm can be accomplished by detecting residual voltage without
-checking the protection functions.
the presence of zero or negative phase sequence current.
-CT supervision is carried out more easily. The general principle is the calculation of a
Any problems revealed by such tests require specialist equipment to resolve so it is simpler to
level of negative sequence current that is inconsistent with the calculated value of
replace a faulty relay and send it for repair.
negative sequence voltage.
Inspection and Testing of Numerical Relays at Factory Inspection and Testing of Numerical Relays at Factory Special Tests on Numerical Relays
Type Tests
Type test report for the following tests Special Tests on Numerical Relays Block diagram of real-time digital relay test system
1. Burn in test for100 hrs.
2. Dielectric Withstand Tests (IEC 60255-5) Functional Testing by Real Time Simulation of power system at independent testing
3. High Voltage Impulse Test (IEC 60255-5) laboratory using Real Time Digital Simulator (RTDS)
4. DC Supply Interruption (IEC 60255-11)
5. AC Ripple on DC supply (IEC 60255-11) The Purpose of this test is to measure the operating times and dynamic accuracy or
6. AC Voltage Dips and Short Interruptions (IEC 61000-4-11)
sensitivity of the relay by simulating the various faults in the power system. These tests
7. High Frequency Disturbance (IEC 60255-22-1)
are indented to verify the correct operation of internal algorithm (logic) i.e. starting,
phase selection, tripping, indications, output contacts and resetting time and to check
8. Fast Transient Disturbance (IEC 60255-22-4)
the stability against external faults, inrush current and sympathetic inrush current (these
9. Electrostatic Discharge (IEC 60255-22-2)
are for transformer protection numerical relay For example MiCOM P645).
10. Surge Immunity (IEC 61000-4-5)
11. Radio Frequency Electromagnetic Field Compatibility Test (IEC 60255-22-2)
12. Atmospheric Environment Tests
- Temperature (IEC 60255-6) and Humidity (IEC 60068-2-3)
13. Mechanical Stress Tests
- Vibration (IEC 60255-21-1)
- Shock (IEC 60255-21-2)
4
8/19/2021
Special Tests on Numerical Relays Testing of Protection Scheme at Site Testing of Protection Scheme at Site
Preliminary Checks Commissioning checks of Scheme
Real Time Digital Simulator (RTDS) of Power System
• Check nameplate details of every associated equipment according to • Each wire shall be traced by continuity tests and it should be made sure that the
specification. wiring is as per relevant drawings. All interconnections between panels /
equipment shall be similarly checked.
• Check for physical damage.
• Measurement of insulation resistance of all wires and relays
• Check tightness of all bolts, clamps and connecting terminals.
• HV test
• Check cleanliness
• Configuration and Settings of relays, other alarm, tripping devices and
• Check earthing interlocks as per scheme.
• Check panel heaters. • Functional checking of all control circuits – e.g. closing, tripping, control,
interlock, supervision, and alarm circuits including proper functioning of the
• Check Bill of Materials in each panel component equipment.
Testing of Protection Scheme at Site PERIODIC MAINTENANCE TESTS PERIODIC MAINTENANCE TESTS
Commissioning checks of Relays
• Periodic testing is necessary to ensure that a protection scheme Protection System Maintenance Program (PSMP)
• Check internal wiring.
continues to provide satisfactory performance for many years after An ongoing program by which Protection System components are kept in working order
installation. and proper operation of malfunctioning components is restored. A maintenance program
can include:
• Insulation resistance measurement of all terminals to body. • The self-checking facilities of numerical relays assist in minimizing • Verification — A means of determining that the component is functioning correctly.
• Insulation resistance measurement of AC to DC terminals failures due to faulty relays. • Monitoring — Observation of the routine in-service operation of the component.
• Defects in secondary wiring and incorrect connections are virtually • Testing — Application of signals to a component to observe functional performance or
• Check operating characteristics by secondary injection. eliminated if proper commissioning after scheme installation/ output behavior, or to diagnose problems.
alteration is carried out. The possibility of incorrect settings is • Physical Inspection — To detect visible signs of component failure, reduced
• Check pickup of DC coils during scheme commissioning checks. performance and degradation.
minimized by regular reviews of relay settings.
• Calibration — Adjustment of the operating threshold or measurement accuracy of a
• Check operation of electrical/mechanical targets. • Network fault levels change over time, and hence setting measuring element to meet the intended performance requirement.
• Configuration and Relay settings. calculations may need to be revised. • Upkeep — Routine activities necessary to assure that the component remains in
• Switching and testing errors are minimized by adequate training of good working order and implementation of any manufacturer’s hardware and
• Each C.T. and V.T. connection with particular reference to their polarities for software service advisories which are relevant to the application of the device.
personnel, use of proven software, and well-designed systematic
directional relays. • Restoration — The actions to restore proper operation of malfunctioning components.
working procedures.
• Functional tests of all Numerical Relays by Simulation using simulation kit. • It is desirable to carry out maintenance on protection equipment at
times when the associated power apparatus is out of service.
Sample Commissioning Procedure
5
8/19/2021