Redis
Redis
Redis
Preface Page
The training report includes skills, knowledge and experiences I got during my 24 weeks of training.
The report contains 3 main chapters.
The first chapter contains information about the training establishment such as functions, organization
structure, SWOT analysis, performance, profitability and usefulness of the company. The second
chapter contains information about works carried out in site, designing work, and handling with
equipment, labour handling, site visits and experiences and skills gathered. The third chapter contains
the conclusion of the training program and suggestions to improve training program.
Training program provide the chance for apply my theoretical and practical knowledge which I gained
from my university, and gave a wide knowledge in the areas of management, labour handling, cost
management and working skills. Now I have the perfect idea about how to works as a civil engineer
and what are the responsibilities.
I would like to thank Mr. S. Kodikara inspector of NAITA, for his guidance to improve the training
program and how to complete the daily diary.
Also I would like to thank Dr.K.Baskaran, training coordinator of Department of Civil Engineering
for guiding me to achieve good performance in training.
I would like to thank Mr. Manjula , Human Resource Officer of ICC (PVT) LTD for providing me
placement at the establishment.
I would like to thank Mr. Gamini Wijesinghe, Project Manager and Officer in Charge of
Undergraduate of CMC-B-Project and Mr.Deeptha Liyanage Project Manager and Officer in Charge
of Undergraduate of Havelock city Phase II Project to supervising ,guiding and teaching during the
training programe.
I would like to thank Mr. Samintha Jayakody , Divisional Grand Manager of ICC (PVT) LTD of
helping during the training.
I would like to thank Mr.Nandana, Site Engineer of CMC-B-Project for helping during the training.
I would like to thank Mr.Tharanga, Site Manager of Havelock City Phase II for helping during the
training.
I would like to thank Site Agents, Supervisors and Technicians for helping and supporting me. Also I
would like to thank other staffs and labor who helped me to successfully complete my training.
Table of Contents
Preface Page .............................................................................................................................................. i
CHAPTER 1 ............................................................................................................................................. 1
CHAPTER 2 ............................................................................................................................................. 8
Training Experiences................................................................................................................................ 8
........................................................................................................................................................ 14
2.4.2Admixtures ............................................................................................................................. 17
CHAPTER 3 ........................................................................................................................................... 53
CONCLUSION ...................................................................................................................................... 53
Annex 1 .................................................................................................................................................. 55
List of figures
Figure 1 ICC Logo ................................................................................................................................... 1
Figure 2 saftey helmet ............................................................................................................................ 13
Figure 3 cylinders to protect fire ............................................................................................................ 13
Figure 4 saftey notice board ................................................................................................................... 14
Figure 5 saftey notice board ................................................................................................................... 14
Figure 6 slump test apparatus ................................................................................................................. 16
Figure 7 Waker ....................................................................................................................................... 18
Figure 8 Timber box ............................................................................................................................... 19
Figure 9 parking bay construction work ................................................................................................ 20
Figure 10 sand cone test apparatus ......................................................................................................... 21
Figure 11 Getting subgrade sample ........................................................................................................ 22
Figure 12 Kerb type A ............................................................................................................................ 22
Figure 13 Kerb type C ............................................................................................................................ 22
Figure 14 Chicken meshs ....................................................................................................................... 28
Figure 15 Water proofing at Block C ..................................................................................................... 32
Figure 16 intial ponding ......................................................................................................................... 33
Figure 17 preperation for water proofing ............................................................................................... 33
Figure 18 Initial ponding in passage way............................................................................................... 33
Figure 19 Reinforcement work at floor 22 ............................................................................................. 34
Figure 20 Prepared Reinforced bar ........................................................................................................ 34
Figure 21 Machine for r/f preperation work........................................................................................... 37
Figure 22 Our site R/F work shop ......................................................................................................... 38
Figure 23 Typical door frame arrangement ............................................................................................ 44
List of tables
1.1.1 Introduction
International Construction Consortium private limited is one of the leading construction contractors in
Sri Lanka, which serves and develops our country in construction industry. ICC was established on
23rd May 1980. ICC Pvt. Ltd is a group company of FINCO GROUP . ICC is having multi sector
capability.
Company Logo:
Telephone: 00 94 11 4400600
Email: [email protected]
Website: www.icc-construct.com
1. Project Development Division (To handle Development Projects either on its own
or in Joint Venture with both Local and Foreign Collaborators on turnkey basis or
otherwise)
2. An infrastructure Development division
3. A Building Construction division (To handle high-rise buildings, Shop and Office
Complexes and other commercial buildings, factories, warehouses, housing
complexes, etc)
4. A Water supply & Sanitation Division
5. A Road Construction Division
6. A Pilling Division
7. A Housing Development division
ICC carried out projects all over Srilanka. Also ICC was carried out projects in Doha, Qatar and
Republic of Maldives.
ICC has 3 fully owned subsidiaries, ICC Housing (pvt) ltd, Durra Building Systems and Nivasie
Developers (pvt) ltd.
1.4 Awards
The company is an ISO 9002:2000 certified companies and is backed by three Banking
consortiums ensuring adequate banking facilities to undertake major construction projects.
The country hosted the International Federation of Asian and West pacific Contractors
Association and ICC was the only Sri Lankan Company to win a gold award for civil
engineering for their road construction project in 2007.
Another award company won the Award for Construction Excellence for their construction of
SLIIT Building at Malambe in 2007, given by the Institute for Construction Training and
Development, Sri Lanka. (ICTAD)
Won the ICTAD award for Construction Excellence for their construction Of Iceland
Residencies in last year.
ICC has also won the following awards presented by the National Chamber of Commerce of
Sri Lanka
First Runner-Up award for „Best Realized Growth‟ in 2004.
Winner of Best Construction and Engineering Company presented in 2006.
Second Runner Up for the best company under large category presented in 2006.
CHAIRMAN
VICE CHAIRMAN
CEO
GENERAL
MANAGER
CONSTRUCTI
ON
PROJECT
SITES
ELECTRICAL
DIVISION
1.6.1 strengths
Company has long history which created legacy and trust among stakeholders.
Company certified with the ISO 9001: 2008 standard
Company has adequate working capital and banking facilities which help the company to
undertake major projects.
It has global market presence & international projects.
Since ICC has its own supplier basis for building material supply, company can able to get
quality and cheaper materials.
Company has good organization structure which easy for decision making and control.
High employee safety, safety officers are recruited in each site and employees are guided to use
safety procedures and equipment.
Good labour resource & salary.
1.6.2 Weaknesses
Lack of engineers and technical staff at sites.
Higher cost of construction materials.
Lack of skilled workers.
Company is over reliance on single industry, if construction industry affected company‟s
going concern is questionable.
Low supply of high grade steel, this one issue affected by construction companies in Sri
Lanka.
High labour and material wastage.
Mainely target projects in Colombo
Language problems at site.
Lack of machineary equipments.
1.6.3 Opportunities
As the Government of Sri Lanka, nowadays encourage and focus on the development projects mostly,
the involvement to the construction industry has rapidly grown up. Therefore, the chances and
opportunities are growing for every bodies connected to this field. I think, this will become a blessed
1.6.4 Threats
Delay of project.
Economic factors & unemployment
Safety of staff & workers & site .
Competition from other construction firms is a threat for the company.
Bad weather may cause delay.
Rules & regulations
Legal problems
Labour resource- lack of salary for labours when compared with other companies.
Maintenance of labour camps.
Increase the number of staff will reduce the material & labour wastage.
Pay more attention on trainees ( field visites , site lectures , sharing experience ).
Contract No : MCUDP/CMC/W/12(B)
Vat : 12%
Consultant - He is the Engineer who designs, estimates, prepare tender documents and all the drawings
of the job according to the requirement of Client./ after the job is executed, it is the responsibility of
the consultant to follow the work whether it is according to his design.
Contractor - The work designed by the consultant to be given group of person or organization known
as Contractor.. It‟s contactor‟s responsibility to carry out the work according to the B.O.Q. and given
drawings and also finish the job in specified time period.
Project manager is the person who has to communicate with head office and site manager.
Advising the client at outset of the project on financing and land acquisition, preparing the brief
and appointment of consultant and contractors.
Planning, controlling and directing for the client.
Responsible for all section of the administration, technical and other parts.
2. Site manger – Site Managers should maintain construction documents such as weather reports,
concrete pouring charts, drawings etc. he should update daily work approval sheets, information of
labor, machinery, tools and progress of the previous day work.
Site security
3.Engineering staff
This group consists of engineers, assistant engineers, technical officers and training engineering staff.
The site engineer divides work among those persons. They have to check the all works with
technically which are under going their section. Material requisitions are approved and checked the
material consumption. They should ensure that the work is carried out according to the details in
construction drawings and specifications and prepare reinforcement schedules of the project. Attend
the daily site meeting and discuss about the problems uncounted.
He is the person who is responsible for every administrative work in the site. He is instructed by the
site manager. He always contact with the administrative section at head office. Every purchasing
material is arranged by him. In addition, he is responsible for preparing of sub contractors bills and
other bills and as follows
Security services should be carefully checked on daily basis and report promptly all
shortcomings to project manager.
Keep well assistance with storekeepers to find out requirement to store daily.
All the copies of attendance sheet and any other documents pertaining to employees form be
carefully packed and dispatched to need office at the end of every month. Every personal
accident looks after the purpose of employee and he should take action.
5.Consultant –
Consultant is agent of client who carried out the work for him and he has to design and prepare the
details of the project to the satisfaction of the client. He has to administer the work units its
completion. In this task, a consultant has to administer the work until its completion. In this task, a
consultant has to give details and certification wherever necessary. he has to supervise the work
Normaly site meetings are carried out by project manager.The meetings carried out were
Work process meeting ( once a week at site office – in evening times 6.00pm)
Site work process meeting by site agent (in case of nessary ,for site supervisors)
Saftey meeting ( at site on Tuesdays & Fridays morning by safety officer ,following project
manager(PM) or divisional grand manager(DGM) address to the staff & labours, site managers
also talk for some minutes to inform the work for the week to labours)
Site meeting (at site meeting room , by PM or DGM , about the work process with staff)
Sub contractors meeting(at site meeting room , by PM or DGM, with sub contractors)
When we involve in a construction work, always we have to check the dimension and quality of the
work and progress of work. For this work, we have to refer many documents at site. Such as
Shop drawings
Bills of quantities
Accident reports
Method statement, so on
There are lot of accidents can happen in any construction work. Safety procedures can manage to stop
these accidents and maintain a safty site environment to reduce the chances for accidents.
Occupational Health and Safety Management Systems are accordance with the OHSAS 18001:2007
requirements. There are lot of boards displayed at site & office to show how to prevent the accidents
and the procedure of work with safety.
Quality management system of ICC Readymix concrete plant bears the DNV ISO 9001 YEAR 2008
certification. The plant comprise a fully computerized batching plant of 50m3 per hour capacity.
Readymix concrete is covered by BS 1926.
Volume batching – measuring volume of materials ( only for small concrete volumes)
Way batching – measuring mass of materials .
Basic components of concrete : Cement , fine aggregates , Coarse aggregates ,Water , Air , Admixtures
Handling of aggregate : We have to prevent segregation and control of moisture of the material . This
can be minimized by proper storing.
Process of mixer :
Ready mix concrete can obtain better quality concrete by using automated equipment. Truck mixtures
are required to transport.
Concrete slump test - cone filled by 3 layers of concrete . each layer should be tamped atleast
25 times with tamp rod of 16mm diameter &600mm length .After cone removed and alloed for
slumping . Slump measured by steel rule. Different types of possible slumps are normal slump
, shear slump , collapse slump . For a given type and maximum size of aggregate, the higher the
water content the higher the slump. This test is very useful to know the workability of concrete.
Procedure – placed the mould in horizontal surface . placed mix concrete in the mould using scoop in
layers. Each layer was about 50mm . each layer was compacted by compacting bar. After
casting the cubes,stored them in a place of free vibration and prevent conditions of
moisture loss. (casted for 24 hours) . Remove the cubes from the mould and marked that
for indentification and immediately palced under water in a curing tank until such time
that compressive strength testing is done.
In CMC-B-Project we did concreting for bus bays, parking bays & some earth structures. Also we used
precast concrete structures as strom line pipes, kerbs , manholes , catch pits ,etc.
In Havelock city phase II project we did concreting for car park , man holes and balance structural
works. We went to ICC Readymix plant as a field visit.
Transportation of concrete : the concrete is came from ICC readymix plant for the CMC-B-Project. So
the transportation is a important factor for delivered the concrete in correct time. Here the concrete
transported by truck mixtures which having rotating drums. So segregation can be avoided.
Segregation is the process of separation of concrete into mortar and aggregate .By proper rotation it
can be avoided . Infact the transportation should be done with minimum delay to avoid hardening.
Before laying of ABC surface should be cleaned to make sure surface is free of dust.
After compacting the minimum thickness of ABC layer is 75mm and the maximum thickness
should not exceed 200 mm.
In order to minimize segregation, the material should be kept wet during transport and
spreading.
Mix should be thoroughly mixed in order to get uniform mix of ABC.
Segregated coarse and fine coarse
Figure 7 Waker
Placing concrete –
concrete is transfer from trucks by bob cat vehicle . The concrete should be placed in its final position
rapidly so that it is not too stiff to work. All the instruments must washed before taking concrete.
We used this concrete mixer to produce concrete for kerb beds where small volume is required. For
preparation of concrete using volume batch it is important to maintain volume ratio of
Cement:Aggregate:Sand . In order to measure the volume, a wood box is prepared, where the volume
of the timber box is equal to the volume of 50 Kg cement. So volume of Aggregate, Sand can be
measured. It is always likely to produce concrete that can maintaining it‟s slump within 150mm.
Quarry dust used as sand the ratios of Cement:Aggregate:Sand for different grades of concrete.
All the informations are given in the plan for leveling such as finish level at road edge , cross fall ,
chainage ,width ,offset from C/L to P/B edge & finish level.
We marked the levels which gained by leveling instrument on steel bar by shallow tape . Connect the
all bars by using a twin .Then we ensure that the height of subgrade should be 400mm from twin level.
if it not there we did the excavation for the requied height .Then we asked for the RFI from the RDA
surveyor to check the levels . After got permission we compacted the subgarde by roller around 15-20
passings.
Here all areas cannot be rolled by roller because of existing manholes , catch pits ,pipe lines &
concrete slabs. So we used plate rammer & waker to compact these areas.
After we compacted the subgrade again check the levels and 400mm height. Then we requested to the
lab for the field density test to obtain the degree of compaction.
After it asked to check RDA surveyor for the levels of kerbs and required permission for concreting
the parking bay . Then we did concreting. We layered 200mm thickness of class C concrete . After it
we did proper curing for some days & clean the area too.
Field density test carried out for subgrade soil and ABC layer. By conducting field density test
compaction of the layer can be determined. Sand cone method was used in our lab for this test.
We have obtained field density more than 100% this may be due to grading difference between
gradation of ABC in the lab and field, mixing may not be well in the field, segregation may exist,
moisture may be different in the field and size of the roller is different, where in lab compaction is
given by hammers it is differ from compaction given by roller.
When doing field density some soil areas were removed and replaced with ABC. It is a problem of soil
and due to that compaction cannot be done for that soil.
Kerbs we used :
Design level
20mm sand
100mm ABC
Subgrade level
Procedure
We had first construct the centre line kerbs according to design level . After got approval from RDA &
consultant we start to compact the subgrade soil by waker & plate rammer . the height of subgrabe soil
layer from design level is 180 mm. after we did the field density test for obatain the compaction
percentage . then got the approval for filling ABC . Then we filled the 100mm of ABC layer and
moisture it and compacted. Again we did the field density test and got approval from consultant.
I had observed the ABC trial test and knew how they did it. The tested area was cleaned and 75mm
holes were made by the help of baker machine and the trial ABC was filled the area. Then the area was
compacted by the roller and the number of rolling was counted. Field density test was carried out after
18th & 28th passing of roller. The test was done randomly selected points in the area. The results was
for 18th passing is 100.7% , 94.4% & for 28th passing 103.3% ,96.8%.
Here the main problem is we cannot keep the straight line for excavation because of existing features
such as concrete slabs , strom water pipes , man holes , and other cables. So we have to decide the path
of excavation always to reduce the bending of pipe line often. After it we measured the off set lengths
from 7m line from centre line for the drawing purpose.
Pressure test was carried out to check for the leakages . . If the initial pressure is 9 Bars, every 1 hour
the test is carried out. If the initial pressure is 6 Bars every 24 hours pressure drop is measured.
All new pipelines which will convey filtered water should be disinfected with Chlorine and a
satisfactory bacteriological analysis of the water certified.
The amount of content of Chlorine solution applied should be provided a dosage of not less than 50 mg
per litre, introduced into the lines. After a contact period of 24 hours, the chlorine residual at the end of
the pipelines should not be less than 25 mg per litre.
1m3 volume of pipelines require 150g Bleaching powder. Accordingly Bleaching powder requirement
can be calculated, and 10% can be added for wastages.
Cover to reinforcement
2.8.1 Plastering
Plastering is the process of covering rough walls and uneven surfaces. After completing brick work
plaster is applied to give better uniform smooth surface for walls. Normally plastering is done after the
roof was covered.
Fire resistance
To provide a true, even smooth and finished surface to the work and improve the appearance.
There are several type of plasters
Lime plasters
Cement plasters
Lime-Cement plasters
Cleaned the related area which we hope to start plastering without timber parts & nails.
Chipped extra concrete surfaces & loose concrete particles.
Removed oil or paint surfaces
The walls should be well washed, cleaned, and kept wet for at least one hour before the plaster
is applied.
Placed chicken mesh to edges of connecting of brick wall and concrete wall.
Method of Application
We need to place the mortar level gauges before plastering a wall. For this purpose we used center
plumb bob to establish the level gauges on wall surface.
Centre plumb bob hang over to 300mm off line near the bottom corners of the walls, then the
measuring tape is kept perpendicular to the plumb string and paste the bottom level gauges according
to the mentioned plaster thickness. A tile piece is embedded top of the each gauge to identifie them.
By using bottom gauges other gauges are placed with the help of stretched string. The top level gauges
are fixed using a plumb bob.
Centre plumb bob - This is used to fix gauges by taking distance from the off line.
Level bar - Level Bar is used to make surface vertical. It is used to checked plaster whether it is
finished. Correctly to spot gauge to spot gauge. should be long enough to cover between two
gauges. And also it shold be straight.
Sponge piece - Sponge piece are used to make final plaster using this make a smooth surface.
Trowel(float) – This is the most important tool to apply plater . It used to spread the mortar on
requird surface.
Hawk – It is used to temporarly hold plaster.
Placing Gauges
Plumb bob
Gauge
Chicken Mesh
sSs
Stuctural
Block work
concrete
Chicken Mesh
In the site, Chicken mesh required where the block walls contact with structural concrete or stud
columns.
The expansion rate of concrete and block wall are different. So there will be chance for cracks.
Chicken mesh used to prevent such cracks.
The mesh is nailed to the joining place of the blocks and concrete and plaster is made.
Defects in Plastering
Cracks - Plastered surface may be developing cracks, which may thin hairline cracks. , or wide
open cracks. If cracks are not easily noticeable, they are not considered as defects. The
development of thin hair cracks is known as “crazing” and it may be due to the following
reasons.
o Excessive thickness of plasters causing excessive shrinkage.
o Finished surface being very smooth; generally rough finished surfaces cracks less than
smooth finished surfaces.
o Expansion or shrinkage of the plaster itself during drying.
o Movement in the backing due to expansion or shrinkage of backing materials.
Introduction
A Building is constructed for the purpose of providing its occupants and contents, protection
from the elements such as rain, wind and heat. The subject of water proofing relate mainly to
rain water which is shielded by the roof , floors and the walls. The objective of any water
proofing application is to inhabit the penetration of water into the substrate , may it also be a
slab, wall or a floor of a building.
Concrete surfaces- Over head tanks , toilet areas , Terrace slabs, Basement slabs, under ground
water sumps
Block walls – Toilet areas, Over haed tanks
Joints – Expansion joints , construction joints
Weak concrete – Honeycombs, cracks
Water proofing or water resistant describes objectives relatively unaffected by water or resting the
ingrees of water under specified conditions.
Materials : Roof seal –P , Bituprime as primer coat , Master flow 96 , Synroof HB –Arcylic joint
Method of application
Initial ponding – Water was filled into the grouted area (masterflow 96 grout ) & observerd after 24
hours. The water leakage was checked & if there was any leking it was repaired by using construction
grout.
wal
l
Fille
t
Floor
Method of application
Here we did Reinforcement arrangements for car parking, Man holes. And also we did some small
reinforcement works for some floors.
And also we attended a lecture on how to do reinforcement in site by our project manager. He
explained about the work process at the site work shop.
BRC Mesh
Here we used 10mm ,12mm , 16mm ,20mm bars for these small reinforcement works.
10 - Bar size
5 - Type of bar
B1 – Location
We discuss about the design work of Reinforcement bars with our desogn engineer. They used codes
BS 8666:2005 – Reinforcement shape codes & BS 8110: Part1 1985 Part three for the reinforcement
design work.
Submission of material application and obtaining the approval for the brand R/F bar
Estimating & ordering the required quantity of R/f bar.
Stacking the R/F bars in orderly manners.
Preparation of bar bending schedules and obtaining approval from the consultants.
Requesting required quanity of bars from the store.
Cutting & bending bars as per the bar bending schedule
Fixing bars in accordance with relavent drawings & specifications
Obtaining approval for fixed bars.
Wrong diameter.
Wrong shape.
Wrong arrangement.
Things to considered
Bar bending schedules should be prepared in accordance with the drawings and specifications
and get it approved by the consultants.
Bars should be cut and bent according to the bar bending schedule.
The R/F bars should be fixed/ tied in accordance with the drawing.
The specified covering to the steel bars should be maintained.
Check the diameter of the bars , number of bars , spacing between bars , lap lengths , anchor
lengths & covering.
Check the proper arrangement.
Tying of bars - The bars crossing one another were tied together at every intersection. Binding
wires were used for this purpose. They were twisted tightly to make the steelwork rigid. It
prevents the displacement of r/f during the time of concreting as well as vibrating.
In our site we did Tapered treaded R/F bar couplers. The advantages are
Cost effective
Easy and simple method
Tightening can be checked with Torque wrench
2.8.4 Tilling
Tiles are the most popular floor finishing material. Floors and wallss laid with ceramic tiles are
becoming very popular these days. Different types of ceramic tiles from cheap glazed tiles to very
expensive fully vitrified tiles and porcelain tiles are available in the market. They can be laid on thick
cement mortar bed or laid on thin bed by using modem adhesives. As flooring can be an expensive
item, much care should be taken in its selection and construction.
Apply mortar upto fixed gauges levels. Level the surface using straight edge.
According to the plan the living room , store room & kitchen room beds are same level (spirit levelled)
In bathrooms & terrae the floor bed had slopes towards gullies.
1075 1065
1080
Gully
The floor bed need to be proper curing & after some days need to check for hollowness.
Steps of Tilling
The wall tilling was finished first and then the floor tiles should start.
All tiles should be fixed according to drawing.
Tile grove lines must be straight.
900
It is use to fix tiles . C800 is a dry premix, water proof , cement based thin bed for fixing tiles.
Application method :
Clean the grout joints as free from dirt , debris & tile spacers .
Mixed the grout and pack joints full with grout .
Remove excess grout.
After grout was set clean the tile faces.
At corners put masking tape both side from up to down. Grout the edges & after 2-3 hours
using sand paper and smooth the edges to get 900.
All above grouts were unsanded grouts. Mixing ratio 10kg bag : 3.75 l water .
Type – Hardwood
wall
Timber planks were sanded with 36,60 & 100 sand paper.
Then it finished with 3 coats of HD Water Borne coatings (kept a day for drying between each
coat)
After final coat we allowed 2 days for drying and curing.
Then we used the floor for light use & after one week is ready for normal usage.
First we marked the door frame opening size in wall according to design.
For that purpose we used steel tape , marking code & plumb bob . there are sample aluminum
door frames . we can used them to mark door size when they available. Important thing to did
is checked the lines are vertically perfect (used plumb bob & spirit level )
After mark lines on walls , if it was need to cut the wall we grinded that area for get required
size and width. ( if we need to grind below 20mm we grind that on one side & if it more than
20mm we grind both sides )
Then the door frames are fixed to wall using hold fastners . we used 5/8” brass wood screws for
fixed hold fastners on door frame . concrete nail was used to fix hold fastners on wall.
Always used the plumb pob and spirit level to check the door frame was fixed horizontally &
vertically accurate. We used aluminum box bars (2”×2”) and wood box bars to hold the door frame
vertically until mounting foam was applied. Also used wood begs for that purpose .
Quality officer checked that door frame arrangement was correct or not . After approving 1K PUR
mounting foam was applied to the gap between door frame and wall reval. When the mounting foam
expand aluminium and wood box bars prevent the bending of door frame . Door frames was sealed by
masking tape to protect from damages.
After one day or more excess mounting foam was cut and consultant checked the door frame
arrangement and give approval to fix door sashes. Three hings were used to fix a door sash After fixed
it , door locks and handles were fixed. Here we used double key cylinders to main doors & thumb turn
cylinders to other doors. We had to checked that door can be closed smoothly or not.
Leveling instrument was used to check levels. The walls filled with 100mm and 200mm thick cement
blocks inside the building blocks and with clay bricks in external cladding wall. The blocks should be
laid to a regular bond , usually half bond where possible.
Corners may be bonded by cutting standard blocks. For the supporting of block wall stiffner column
shall be introduced besides timber door openings ,edge of cantilever filler walls and at some corners of
walls.
If the length of filler wall exceeds 5m, one intermediate stiffner column shall be introduced. Tie beams
at lintel level also be introduced along fillr walls.
Here we used 1:5 cement sand mortar for block masonry work construction.
The slab surface should be clean to free from dust , mud ,grout & oil.
According to drawings suitable offlines marked on the floor. Openings & stiffner column
locations also marked .
After got approval ,formwork for concrete ledges can started.
Reinforcement of the stiffner column as per drawings.
After concreted first course of bloc wall was laid
After the concreting was finished remaining block wall continued upwards.
We have to checked vertically alignment of block work. Also need to observe shrinkage cracks on
mortar bed.
Trowel -This is used for spreading mortar, forcing joints and cutting bricks
Plumb bob- This is used for plumbing and maintaining the vertically
Straight edge- Straight edge is the timber plant which is used for checking alignment of faces
of bricks
Cord- This is used for levelling
Sprit Level- This is used for levelling
Square - This is used for setting out right angles and marking bricks for cutting.
Chisel-Chisel is used for cutting the bricks.
Meter rule or measuring tape- This is used to measure the distance to, place to place.
This system consists in four phases such as substrate preparation , leveling compound , architectural
texture base and Compos Silicon W55 finishing coats. The total area of external surface should be
(above level 03 ) 31,337m2.
External paint materials – Cement and Acrylic based leveling compound (NARA)
Tools used : Electric compressors , Airless spray gun , Manual sanders , Infrared moisture meter ,
Moisture machine , Steel float handles , Roller brush , Line marker boat
Method of application
1.Preperation of surface –
Applied SKK primer along the grove by art brush and allowed for drying 4-6hours)
Applied 2nd coat of SK Compo Silicon W55 white colour along the groove line with over
coating intervals of 2 hours.
Applied two coats of SK Compo Silicon W55 overall with approved colour by manual roller
and allowed for drying(2 hours)
Remove all masking
SK Compo Silicon W55 is rain water imperbiable ,can reflect the chloride ion in salty environment &
it repelled the carbon dioxide present in the air. It is a superb sodium chloride resistance.
Period
Materials : SKK CT Under base coats , SKK Eleganstone texture , SKK Cerami top SI clear top coats,
Tools used : Electric compressors , Airless spray gun , Infrared moisture meter , Mixing machine ,
Scaffolding fittings
Scaffolding Frame - This is the main item of scaffolding. It is made by hollow steel sections of
circular shape. Scaffolding is available in various sizes.
Cross Bracings - This is used for fixing of two scaffolding frames in a same level. It is consist
of two steel circular bars how they are coupled together where their centers, by a pin. Each one
can be rotate around the pin.
Joint pin - This is used for fixing of two scaffolding frames where in two adjacent layers,
Arm Lock - This is helped to lock two frames in adjacent layers.
Cat walk panel - This is the flat form where on the scaffolding frames.
G.I. pipes - Scaffolding can also be erected by using G.I. pipes only. But it‟s very difficult and
they can used to support the scaffoldings.
Clamps - There are in two types. Fix and Adjustable clamps (If there has to couple two G.I.
pipes or scaffolding with a G.I. pipe, how produce a right angle to one another this type can be
used). Free and Adjustable clamps(This type can be used to couple two G.I. pipes or
scaffolding frame with a G.I. pipe, how produce any angle).
Jack base - Help to maintain the level of the scaffolding sets, when scaffolding has to be
erected on uneven surface.
Stands - A vertical tube member support on a base plate which rest upon a sole plates.
Transom - Horizontal tubes supported by ledgers and supporting scaffold boards.
All standards are correctly aligned and properly supported at their base.
No undue deflection in ledgers putlogs or transoms.
No member of a structure has been removed.
All braces and ties are effective in stabilizing the structure.
All couplers are properly tightened.
All boards are sound and properly supported.
All guardrails and toe boards are in place.
All ladders are sound and properly supported secured.
During my training I have learned about 5-S practices, which is a methodology which make work
place arrangement efficiently and effectively.
5S
Seiri –Sort
Seiton – Streamline
Seiso- Shine
Seiketsu- Standardize
Shitsuke – Sustain
Sort - Eliminate all unnecessary tools, parts, and instructions. Go through all tools, materials,
and so forth in the plant and work area. Keep only essential items and eliminate what is not
required, prioritizing things as per requirements and keeping them in easily-accessible places.
Everything else is stored or discarded.
Streamline - There should be a place for everything and everything should be in its place. The
place for each item should be clearly labeled or demarcated. Items should be arranged in a
manner that promotes efficient work flow, with equipment used most often being the most
easily accessible. Workers should not have to bend repetitively to access materials. Each tool,
part, supply, or piece of equipment should be kept close to where it will be used – in other
words, straightening the flow path. Seiton is one of the features that distinguishes 5S from
"standardized cleanup". This phase can also be referred to as Simplifying.
Shine - Keep the workplace tidy and organized. At the end of each shift, clean the work area
and be sure everything is restored to its place. This makes it easy to know what goes where and
ensures that everything is where it belongs. A key point is that maintaining cleanliness should
be part of the daily work – not an occasional activity initiated when things get too messy.
Standardize - Work practices should be consistent and standardized. All work stations for a
particular job should be identical. All employees doing the same job should be able to work in
any station with the same tools that are in the same location in every station. Everyone should
know exactly what his or her responsibilities are for adhering to the first 3 S's.
Sustain - Maintain and review standards. Once the previous 4 S's have been established, they
become the new way to operate. Maintain focus on this new way and do not allow a gradual
decline back to the old ways. While thinking about the new way, also be thinking about yet
better ways. When an issue arises such as a suggested improvement, a new way of working, a
new tool or a new output requirement, review the first 4 S's and make changes as appropriate.
I was able to identify the ways of industry developing talent and attitude and what are the
responsibilities that should be recognize as a professional engineer in the future. Industrial training not
only gives us the practical knowledge, it gives the management tactics greatly needed by a civil
engineer. . Now I have enough confidence, this will definitely help me in my career. I have learnt
duties of Engineer and responsibility. . I was able to gain a wide knowledge and great experience
about construction work from sites. And also I could understand the real situation in the industrial
organizations and their related environment.
Most of the time, my time was spent at construction sites. When look back into the past, I was really
fortunate enough to cover substantial area of construction field in this tiny period of time. As I could
stay in for about two different sites, I could experience different procedures and methodologies
undertaken by different contractors and work with different personalities. That gave us a kind of life
experience as well. Further, it was a fine experience for me to visit site to ready mix plant where I had
never been before. Those memories leave me with unforgettable experience I gained in the time of my
training session.
Thus we do not get the chance to practice in the field by working under responsibility and gain some
experience on labor handling, material handling, work management and managing documents of the
site etc. Still, we were allowed to manage all the documents at the site given by the contractor to
consultant party and hence could gain knowledge on the document management at the site for some
extent. But, it would be more preferable if there were any tasks appointed on us that would allow us to
work under pressure at the site. That problem will be helped if every trainee had been given exposure
to work under both consultant and contractor parties. Then one can understand the different
responsibilities and tasks performed by each party. It is true that by splitting twenty four weeks for two
sessions will not afford a considerable time period to grab many things from one party. Then, it is
better if training period could extend for even two months period long, if possible.
Finally, I would say except these lesser number of faults, the advantages existing are high. I consider I
could attain maximum possible out of this short period and the knowledge I gained will help me in
future in my career as a Civil Engineer in the field.