2011 Bridge Michaud
2011 Bridge Michaud
Parsons Brinckerhoff
Abstract With the evolution of computer aided design tools for modeling in 3D
space, significant advancements have been made to traditional methods of
modeling geometry of bridge and tunnel structures. While significant advances
have been made in the building and industrial sectors, the 3D modeling of
transport structures, including bridges and tunnels, has been less progressed. This
has been largely due to the complex road control lines, and geometry variability
which tends to evolve during the design process. As a consequence, the more
recent successful application of 3D CAD methods has relied on new techniques
that allow the 3D model to be generated with more powerful generation tools and
techniques. This paper describes some of the recent developments in these
methods. The benefits of 3D CAD methods have been proven on recent projects
including the Eastlink and Westgate Freeway Upgrade in Melbourne, the CLEM7
in Brisbane and other recent major infrastructures projects around the country.
Construction has also realised the benefits of the 3D CAD methods. Increasingly,
the designer is being requested to provide 3D geometry models to aid with the
setup of survey models and to provide ease of cross checking of construction
against the design models. The method increases the geometric reliability of
designs, a benefit which flows into construction saving time and improving
productivity. This paper includes examples of the construction benefits that have
been realised on the above mentioned major bridge and tunnel projects with the
aid of the new advancements in 3D CAD methods.
Introduction
CAD methods were introduced to the drafting world in the mid 1980’s and were a
major change from the traditional methods of drawing. The traditional methods
relied on two-dimensional (2D) drawing methods using projected planes for
describing elements. The introduction of CAD effectively transferred the tool
used to create structural drawings from the paper space to the machine space, but
was still effectively adopting the same drawing methods. The drawing practice
remained effectively unchanged and was being undertaken by the same people
using their known skills.
Greater change occurred in the civil engineering area, where the computers were
used for the design of road and drainage elements, and the simpler output for
generating drawings were more easily applied to the drafting world. In the civil
engineering world, much greater integration of design and drawing was quickly
established and now these tools are the standard method.
More recently, the use of 3D modeling and the direct application of the model
information to drawings has become more widespread in the bridges and other
civil structures industry. This has been accompanied by a demand from the
construction industry for the provision of model information for construction
purposes where the digital information can be used directly in survey equipment
and in machine controlled applications.
Over the next few years, it is expected the 3D modeling will be business as usual
for the substantial part of our drafting works for bridges and below-ground
structures.
The geometric basis for bridges and other transport structures is the road
alignment. This is generated in the 3D using packages such as MX or InRoads
and provides a 3D surface as the basis of the bridge.
The solid elements of the bridge need to be fitted to this surface. Increasingly
these surfaces involve complex geometry with varying width, curves, super
elevation and it is an exceedingly difficult piece of work to fit solid linear
elements such as beams to these surfaces using traditional drafting techniques.
Bridge and tunnel modeling using 3D CAD methods 205
The availability of 3D modeling tools which can accept the surface from the road
geometry and be used as the basis for determining the bridge geometry has
provided an obvious solution to this difficult and complex work. It has been a
natural progression that practitioners would seek to use the available tools to solve
these problems.
The extended use of 3D modeling to the drafting area has required the
development of applications to extract data directly from the 3D model and
transfer this to the 2D drawing. Various routines and macros have been developed
for different purposes, and this remains an evolving area, but it is now common to
206 Paul Michaud, Nandor Kaity and Robert Alexander
extract setout data and dimensional information from the 3D models directly to
drawings.
The traditional drawing set formed the basis of the information used on site. This
information was entirely contained on the drawings and was visual only. It is now
becoming more common that the deliverable for construction is both the drawing
set and the 3D model, and both are required for construction. The setout
information can be contained within the model and the detailing information can
be contained on the drawings, with dimensions referenced back to control lines
and control points within the model.
The use of the 3D structural model in this process is typically undertaken by the
design drafter as the engineer has less visibility on the product. This requires
recognition as part of the design process and it is essential that a strong
verification process is established to ensure independent checking of the work.
This is the same situation as has developed in the civil engineering area where the
work is typically undertaken by civil designers. In the structural area, the 3D
drafter effectively undertakes a geometric design process, and this has always
been the case.
The use of 3D modeling can handle complex geometry in real space. This
provides certainty of dimensional and set out information when assembling
complex elements fitted to varying road geometry. This model must be
independently verified by another drafter to ensure correctness. Subsequent use of
the model as the base of all information taken for the various elements of the
structure will provide certainty that it is correct.
Fig. 5. Bridge deck plan, as documented, referencing 3D road model for setout information. No
horizontal, vertical setout information shown.
208 Paul Michaud, Nandor Kaity and Robert Alexander
Typically, the model is used to control the geometry, and hence there are
particular identified control lines within the model that are verified to be correct.
These “verified string lines” (the ES lines on Figure 4) are issued for construction
and used by the constructors and other end users. The 2D drawings provide the
required detailed dimensional information of structural elements and are
referenced from the control lines for construction purposes. In Figure 4, the 300
dimension to the edge of the deck is dimensioned from the verified string line
(ES). The adoption of the 3D model as a deliverable avoids the need to transfer
complex set out information to structural drawings, (e.g. varying deck levels) and
removes the risk of errors and omissions. The result is a simpler and better
product. Refer Figure 5.
The use of the CADPro application enables the direct calculation of all bearing
levels and taper plate dimensions for girder bridges directly from the 3D structural
model. By fixing minimum deck thickness, girder depth, bearing design
information and entering 3D road design, CADPro optimises deck thickness and
calculates the remaining variable bearing geometry. This information is then
transferred directly to the drawings. There is a greater certainty that this
information is correct, and there is no reliance on a series of complex geometrical
sections by the design drafter that must also go through an equally complex
checking process by another drafter. Refer Figure 6.
The 3D structural models exist in real 3D coordinate space and are tied to the
design road geometry. Hence the inclusion of geological profiles within the
overall 3D project model allows the design team to identify the relationship
between structure and ground information at any location. Pile toe levels can be
extracted from the model, and geological profile for design on below-ground
structures can be obtained at any section. This is the closest the design team will
get to modeling the below ground environment in which the structures are
positioned. Refer Figure 7.
Fig. 7. Geological and bridge 3D models, showing relationship between structure and geological
profile.
Another useful application is the ability to obtain the design deck thickness over
the girders from the 3D models. The deck thickness can be obtained as the
difference between the road surface and the top of girders and plotted as a contour
of deck thickness. This enables designers to validate the design assumptions and
provides certainty that the finished surfaces can be achieved.
Fig. 8. The issued bridge 3D model verification PDF, showing other 3D models as “References”
and all bridge structural elements “Levels” (below), bridge only and level/reference control box
(above).
Complex geometrical areas can be modeled in 3D, and then the data transferred to
analysis models such the finite element analysis software Strand7. In this case,
the designer is able to model the true geometry of the element. This application is
the normal case for design of tunnel linings (refer Figure 9) and is also used for
structural modeling of beam elements.
The interfaced models are also used for safety-in-design reviews where the
constructors, operators and maintainers get an accurate view of the final product
and can provide input into the design to ensure constructability and operational
requirements are optimised. This tool was used extensively on the Airport Link
project in Brisbane for all the underground structures.
212 Paul Michaud, Nandor Kaity and Robert Alexander
Similarly, to services interfaces, the 3D structural models are interfaced with the
road geometry to provide true 3D topographical models of the finished road. This
integrated road and structure model, with associated road furniture, has been used
on a recent project to check sight distances and verify the road design.
The use of 3D modeling has allowed much greater integration of design with
construction (and also operations and maintenance). Many of the benefits
described for the designers, are equally applicable to the construction, particularly
where designers and constructors are working together to optimise design.
The best outcomes will be achieved where designers and constructors are working
together, and the 3D modeling tool allows these teams to virtually build the
finished product at the design stage. This optimises the design, ensures certainty
for the construction site, and significantly reduces the potential for site difficulties
to arise.
The 3D staging models can also be linked to program activities and hence the
development of 4D modeling that illustrates the construction with time. This is a
useful construction planning tool, particularly for severely time constrained
operations such as railway track possessions. This area of activity is referred to as
Bridge and tunnel modeling using 3D CAD methods 213
“virtual design and construction” and is an emerging area. There are limited
examples where this has been applied on a comprehensive basis.
The provision of a 3D model for construction purposes with verified set out
information greatly assists the survey teams. The same models assist shop
detailers and reinforcement schedulers. The use of the base 3D models by all
parties in the design-delivery supply chain removes the risk of errors. The concept
of a single model as the basis is sometimes referred to as “the single point-source
of truth”. This is a significant advantage in construction.
Much work is being done in the area of integrated models and linking to time and
cost. There are numerous examples of 3D modeling for communication and
consultation purposes. This is a large area and beyond the scope of this paper, but
relevant to note that the structural modeling usefulness does not stop at the
structures door.