HFY4 5171 02 HSE PD 0004 - 0 Work Permit Management Procedure CodeA
HFY4 5171 02 HSE PD 0004 - 0 Work Permit Management Procedure CodeA
HFY4 5171 02 HSE PD 0004 - 0 Work Permit Management Procedure CodeA
PHASE FOUR
SOURCE WATER WELLS TIE-INS
(Y2021-Y2022)
DETAIL DESIGN DOC.NO.: HFY4-5171-02-HSE-PD-0004 REV.: 0 PAGE 1 OF 17
HFY-CON/F&C1114-1137/02
SOURCE WATER WELLS TIE-INS
(Y2021-Y2022)
0 ISSUED FOR CONSTRUCTION 23.12.2022 Brijesh K Pal Huang Lidan Wang Kai Zhao Houxi
1
WORK PERMIT
MANAGEMENT PROCEDURE
REVISION HISTORY
2
WORK PERMIT
MANAGEMENT PROCEDURE
Contents
1.0 PURPOSE ................................................................................................................ 4
5.0 INSTRUCTION.......................................................................................................... 6
3
WORK PERMIT
MANAGEMENT PROCEDURE
1.0 PURPOSE
This procedure is established for ensuring the effective control of the hazard
construction activity, risk controlling and reducing, accident prevention, personnel health
and safety protection, and safe production. PCH HSE PTW should be implemented at
work site and XYNM PTW procedure should conform to PCH PTW procedures.
2.0 SCOPE
This procedure is applied to all of the construction area of the Provision of SOURCE
WATER WELLS TIE-IN IN Y2021.
3.0 DEFINITIONS
Unless the context otherwise requires, the following terms and expressions in this shall
have the following meaning. Use of capital lettering in the text will denote the use of a
defined term. Defined terms, which are not contained in item 3.0, shall be deemed
contained as per this procedure.
3.1 Definition of Terms and Abbreviations
The following terms are standard throughout this to define a condition or course of
action.
COMPANY PetroChina International Iraq FZE Iraq Branch
CONTRACTOR Jiangsu Xinyang New Material CO., Ltd
Vendor Manufacture/Suppliers of Goods/Equipment
THE SITE The XYNM construction site areas
THE SUB-CONTRACTOR Any party entering into a contract with XYNM to provide
equipment, goods, services and/or manpower.
AUTHORIZED PERSON A person who has permission to carry out the task is either
from external authorizing bodies or internally by either
XYNM or Sub-contractor management.
Shall Indicate a mandatory requirement
Should Indicate a strong recommendation to comply with the
requirement
PCH PetroChina International Iraq FZE Iraq Branch
PO Purchase Order
PMC Project Management Consultant
PPM Project Procurement Manager
CM Project Construction Manager
4
WORK PERMIT
MANAGEMENT PROCEDURE
4.0 RESPONSIBILITIES
4.1 The Operation Personnel
XYNM personals to comply with All PCH safety procedures and requirements
Familiar with the potential risk and emergency event during the operation
Wear work suit and use PPE correctly.
Start work until getting the PTW
Stop any work when face the risk
Comply with XYNM Safety operation manual and construction plan to work.
4.2 Job person in charge
Prepare formulate safety measures and emergency plan for the organization
Take charge of emergency relief supplies.
Apply for confined space work permit.
Start safety training and emergency drills for employees.
Control the “start/stop” order for construction.
Organize rescue in the event of an emergency.
Make sure the safety when staff in and out of the limited space
4.3 Construction manager and site supervisor
5
WORK PERMIT
MANAGEMENT PROCEDURE
Control the whole process of work and responsible for the approval of dangerous
work permit
Take charge of work rules and inspections in daily work
Control the materials list of storage
Supervisor to ensure all the safety requirements are in place before work start and
during the work
4.4 HSE officer
HSE officer should take charge of the TBT and JHA before start the work, also who is
the regional coordinator for all related matters with work permit system. The range of
work covers get work permit, site supervision and inspections. And record the daily work.
Contact with site operation monitor and operation personal, ensure all relevant
employees familiar with the potential risk of work.
Resolve all kinds of problems for current work permit system during work process.
Supervision and implementation of all aspects of the work permit system
Based on the duty, to improve the work process.
Review implementation of work permit system.
Make sure safety measures have been carried on site by inspection.
Control the emergency materials preparation
Train and check safety knowledge of employees.
5.0 INSTRUCTION
PTW system is the basis of site work, XYNW will follow the requirement of COMPANY’s
PTW system.
5.1 Management scope
The following work should apply work permit during the Project:
Hot work, like welding work, in the area of the oil field.
Temporary electricity work, like change the cable, in the area of the oil field
Large scale material transport to the work site.
Intersection activity, like pipe crossing between pipelines
Confined space activity, like work in valve pit
Electricity activity
Excavation activity
Dewatering and sustaining of the foundation pit
Radiation activit
6
WORK PERMIT
MANAGEMENT PROCEDURE
Work at height (over 1.82 meters or 6 feet is required to wear full body harness and
complete working platform and life line.)
Medium-sized and above crane operation
Motor vehicle in and out of the fire proof and the explosion proof area
Tie-in activity
Removing and overhaul of the Current using equipment unit
Special requirement by COMPANY
5.2 Transaction Procedure
5.2.1 Interior work permit
Get the application of interior work permit, should attach the following information:
Application form
Content (covers date, job description and so on)
Plan
Schematic Diagram of the Working Area
JHA
Site technical and safety disclosure and practicable safety precaution testify
This application should submit by engineering department, and HSE officer should
review the data described above.
5.2.2 Interior Application Review.
The application should be reviewed by HSE department firstly and then send to
Engineering department. HSE department reviewed the safety elements for the work,
and make relative safety plan.
Engineering department takes charge of checking the work content, scope, materials
and work surroundings.
At least one day before the work start, HSE officer and Engineering department
personnel and the superintendent should review the work site, which cover:
Safety of tools and materials involved
Operator certification
PPE
Disclosure (Training and communication) performance
Prevention measures
Fire – extinguisher and other emergency facility situation
7
WORK PERMIT
MANAGEMENT PROCEDURE
External work permit means that work permit overcome the power of examination and
approval. The following two activities should apply work permit based on special
application procedure:
The activities conducted in the running facility area of the COMPANY, or
The activities outside of the running area but may influence the safety of the current
running facilities or operators.
5.2.8.1 The process of applying, extension and close
Still applying as per work permit application management procedure, but should also
take additional actions as following:
The Engineering department personnel fills the work permit application (not the
HSE officer) and prepare related materials
The project team applies to the COMPANY or relevant department.
Any activity at site, XYNM must send the PTW for review and sign by PMC also for
issuing if the owner of the area is F&C Dept.
When do activities with high risk level. Any activity at site, XYNM must send the
PTW for review and sign by PMC also for issuing if the owner of the area is F&C
Dept. if the onwer of the area is not F&C, PTW to be send to the concern Dept. for
issuing, but still need PMC sign for technical part and HSE. PCH PTW shall be
review and approve the require document by the concern PMC construction team,
before start the work.
5.3 The Work Permit Management and Filling
The work permit approval department should establish the documentation system to
manage the work permit issuing, closing, and original copy as well. The hard copy will
be destroyed uniformly at end of the year.
9
WORK PERMIT
MANAGEMENT PROCEDURE
7.0 REFERENCE
3.11.1 Permit to Work Guidance- PCH HALFAYA
10
WORK PERMIT
MANAGEMENT PROCEDURE
11
WORK PERMIT
MANAGEMENT PROCEDURE
12
WORK PERMIT
MANAGEMENT PROCEDURE
13
WORK PERMIT
MANAGEMENT PROCEDURE
14
WORK PERMIT
MANAGEMENT PROCEDURE
15
WORK PERMIT
MANAGEMENT PROCEDURE
16
WORK PERMIT
MANAGEMENT PROCEDURE
17