DPR of The Mahi Site

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 12

Project Information

Client Mahi Terry


Place Amravati
Vendor / Sub-Contractors - Manpower
Mechanical 3
Fitter 1
Welder 1
Rigger 1
Helper
Electrical
Refractory
Insulation
Equipments Owner
5.5 TPH SF Boiler Forbes Marshall
1

1
2

1
2
3

1
2
Weather 3/5/2023
Temperature 26 Degree
centegrate

26 Degree
Real feel centegrate
Humidity 91% Rain
Dew point 24 Deg Cent
Visibility 11KM

Pressure 1,005mBar

Visitors Representing Time

NOTES
DAILY PROGRESS REPORT

Resources -Personal
Welding machine-3,Grinding M/c-1,Spaners set-2 set,Distribution bord-1, 63 Ampere,

Tommorow Planning 03/06/2023


Instruments air piping Taping for View glass and AFR for SSK Fire fighting
Limit switch in Pneumatic cylinder of ICBD
Tommorow Planing 05/06/2023
Material segregation work for IBR inspection.
Feed water suction piping work
Tommorow Planing 06/06/2023
Inspection of Boiler and accessories with IBR authourity
Installation of accessories on the boiler
Equipment installation Checklist checked and signed by customer
Today planing 07/06/2023
Installation of accessories on the boiler
Fabrication of Blowdown piping
Today planing 08/06/2023
Fabrication of MPA Blowdown piping
FWP suction pipe line 4mtr completed from Pump
Today planing 9/6/2023
Boiler gauge glass drain pipe line with funnel
Today planing 10/06/2023
Fabrication of Gauge glass Open drain pipe line&FWT Over flow& Drain pipe
Firefighting pipe line in Boiler House
Today Planning 12/06/2023
Grate ash screw cooling water pipe line
Safety valve steam exhaust pipe line installation completed
Today Planing 13/06/2023
Cooling water pipe line grate ash screw
Gauge glass drain pipe line
Today Planing 14/06/2023
FWT and Gauge glass drain pipe Towards Blowdown pit
Today Planning 15/6/2023

completion of Boiler Blowdown pipe&Drain overflow FWT pipe up to pit Battery limit 15/6/2023
Today Planning 16/06/2023
Black color bend of Boiler installation
Painting of supports
PS of Bagfilter
Attending of Punch point,Access steps provided from tube cleaning platform to Mobrey
platform.
Tommorow Planning 17/6/23
Fittings installation for Cooling water pipe line,Instruments air ball valve,PU tubing for
SSK RALV,Firefighting PAV Tubing,
Today Planning 19/6/2023
BBCS INSTALLED
Today Planing 28/6/2023
connection of BBCS to Flash vessel and drain pipe connection from flash vesel 17/7/2023
Installation of electrical control pane. 17/7/2023

17/7/2023
Painting of structure.
MPA blowdown pipe from boiler to blowdown pit. 15/7/2023
FWT accessories FWP Suction and drain pipe completion 17/7/2023
Chemical dosing equipment installation and piping 17/7/2023
Installed Equipments
MDC 13/04/23
APH 13/04/23
FD fan 14/04/2023
ID fan 14/04/23
DSG 14/04/23
Boiler 14/04/23
Chimney 14/04/23
Column&Hopper of Bagfilter 16/04/2023
Bagfilter With welding 19/04/2023
SSK,SSK Y-Chute and SSK RALV with Structure platform 20/04/23
Furnace Ash Door 20/04/23
Sealing plate of Boiler 21/04/23
RALV APH,MDC and Bagfilter 21/04/2023
Furnace View Glass of Boiler 21/04/2023
Bagfilter Controll panel 21/04/23
Grate ash screw 10/04/2023
Metering screw 12/05/2023
Fuel storagr hopper 15/05/2023
Fuel Bucket Elevator 18/05/2023
fuel Crusher 20/05/23
fuel screw conveyor 21/05/23
Boiler Accessories & Instruments installation 10/06/2023
Safety valve exhaust pipe line installation 12/06/2023
boiler blowdown pipe boiler to Pit completed 14/06/2023
boiler Gauge glass drain pipe with funnel up to pit completed 15/06/2024
Feed water tank over flow and drain pipe From tube cleaning structure to pit 15/06/2023
Instrument air pipe internal boiler house completed 10/06/2023
Fire fighting pipe internal boiler house completed 09/06/2023
BBCS Installed 19/6/2023
Installation column&Structure of FWT 08/07/2023
Installation of FWT 10/07/2023
MPA blowdown pipe from boiler to blowdown pit. 15/7/2023
Hinderance / Delays/Breakdowns/Other Reasons
Due to Bad wheather and Rain,work was stopped before 2 hours(20/04/23)(05:00PM to
07:00PM)

Due to Bad wheather and Rain,work was stopped before 2 hours (05PM to 07:00PM)
(26/04/23)
Due to Disturbance of Power and bad wheather work is disturb
Due bad wheather work was hamper(29/04/23) 12:30PM and 3:30PM
Due to bad wheather work is start late (03/May/23)
Due to unavailability of FWT structure and control panel room,both work still pending ,
From day first.(13th Aprill 2023)
Blowdown pipe line and drain pipe line work is hampered due to Civil work in boiler house
from (10th June 2023)
Material Received / Required at site
Bagfilter, MDC,FD Fan,ID Fan,Cooling fan
Electrical,Control Panel (ICP cum MCC)
Boiler &Accessories received
Chimney, Received
Pipe and fittings Material Received on
Ladder in pit of FHS (Mahi Terry) 14/04/23
Controll Room for Electrical panel 14/04/23
FWT structure installaed
Flour for Feed water pump area 14/04/23
Flour requirements for Power pack and Platform structure of SSK 14/04/23
Requirements Fuel Handling System on the site 14/04/23
Water for Boiler Hydrotest (Mahi Terry) 14/7/2023
17/7/2023
By: Deepchand
Status Hours
08:30Hrs

Completed
Completed

Completed
WIP

Completed
WIP
Completed

Completed
WIP

WIP Dumped Raw material in Boiler House

WIP Dumped Raw material in Boiler House

WIP Dumped Raw material in Boiler House


WIP

WIP
Completed

WIP
WIP

WIP Dumped raw material removed

Completed

Completed

Completed

Completed

Completed

Completed
Status
WIP
flour WIP
Waiting of
Manpower
Completed
WIP
WIP

Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Hours lost
2

40Minuts
2 Hours
2 Hours Rain

5 Days
Supplier
FMPL 14/04/23, Received
FMPL 14/04/23 Received
FMPL 14/04/23 Received
Before,14/04/23
26/05/2023

1/6/2023 Civil work start


8th July2023
25/04/23 Completed
8/5/2023 Completed
8/5/2023 Received

You might also like