Progress Measurement Sheet (VKZ)
Progress Measurement Sheet (VKZ)
Progress Measurement Sheet (VKZ)
1 PRELIMINARY AND
SUPERVISORY SERVICES 1,101,661.90 KES
GRADING AND
13 WEEDKILLER 2,000,700.00 KES
APPLICATION
water supply
PIPEWORK - MANHOLES
CLASS K AND PIPEWORK 554,400.00 KES
ANCILLARIES
12,940,050.00
sewer
BILL ITEM NO. DESCRIPTION BILLED AMOUNT PROGRESS UNIT
(KES)
PIPEWORK - MANHOLES
CLASS K AND PIPEWORK 5,832,800.00 KES
ANCILLARIES
PIPEWORK - SUPPORTS
CLASS L AND PROTECTION,
ANCILLARIES TO LAYING 1,200,000.00 KES
AND EXCAVATION
33,658,740.80
Boundary wall
P PRELIMINARY AND
SUPERVISORY SERVICES 843,105.00 KES
GRADED CRUSHED
13 STONE SUBBASE AND 2,550,000.00 KES
BASE
17 CONCRETE WORKS 7,218,000.00 KES
21,047,900.00
show houses
29,618,709.80 KES
% PROGRESS
BILL WEIGHT PHYSICAL % PROGRESS WEIGHTED % AS
PROGRESS ON BILL ITEM PROGRESS SCHEDULED
IN THE POW
% PROGRESS
BILL WEIGHT PHYSICAL % PROGRESS WEIGHTED % AS
PROGRESS ON BILL ITEM PROGRESS SCHEDULED
IN THE POW
% PROGRESS
BILL WEIGHT PHYSICAL % PROGRESS WEIGHTED % AS
PROGRESS ON BILL ITEM PROGRESS SCHEDULED
IN THE POW
1 100
Days behind
Daily Cost=Contract schedule=SV/daily
Contract Period Amount/Contract Period cost
498 158,988.75 -150
534 24,232.30 -147
523 64,357.06 -506
556 54,443.69 -322
60 350,798.33 -6
168 0
% certified to date Commencement Date Completion Date Current Day Lapsed days
69.83% 8/29/2023 1/8/2025 11/1/2024 430
72.49% 8/29/2023 2/13/2025 11/1/2024 430
3.16% 8/29/2023 2/2/2025 11/1/2024 430
42.12% 8/29/2023 3/7/2025 11/1/2024 430
76.00% 8/29/2023 2/13/2024 11/1/2024 430
89.69% 3/1/2024 4/30/2024 11/1/2024 245
Bill No Expected total value of work done
WEIGHTED %
PROGRESS ON POW
5.01 12,533,760.00
1.39%
1.04%
5.02 1,671,168.00
47.84% 5.03 19,697,752.37
0.00%
5.04 2,785,280.00
0.00%
36,687,960.37
2.53%
52.80%
66.67%
WEIGHTED %
PROGRESS ON POW
30.66%
60.36%
3.76%
0.86%
95.63%
WEIGHTED %
PROGRESS ON POW
7.78%
1.13%
70.19%
17.33%
3.57%
100.00%
WEIGHTED %
PROGRESS ON POW
3%
7% sc
0% exc
0% Blinding
3% rc
13.09% fw
backfilling
reinforcement
foundation walling
superstructure walling
keying
polythene damp proofing
WEIGHTED % coping
PROGRESS ON POW
5%
3% shs
24%
12%
1%
12%
34%
8%
100.00%
WEIGHTED %
PROGRESS ON POW
100.00
22,335,761.87
17,594,682.76
39,930,444.63 0.42
1,437,660.00
126,000.00
19,697,752.37
784,000.00
22,045,412.37
2/13/2025 9/10/202
680
value
8160000
34272000
22,510,629.41 88%
25,622,122.00