Work Schedule of The Phutung Substation (November To December 2023)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Kathmandu Valley Transmission Capacity Reinforcement Project

Phutung Substation

11/10/2023

11/11/2023

11/12/2023

11/13/2023

11/14/2023

11/15/2023

11/16/2023

11/17/2023

11/18/2023

11/19/2023

11/20/2023

11/21/2023

11/22/2023

11/23/2023

11/24/2023

11/25/2023

11/26/2023

11/27/2023

11/28/2023

11/29/2023

11/30/2023

12/10/2023

12/11/2023

12/12/2023

12/13/2023

12/14/2023

12/15/2023

12/16/2023

12/17/2023

12/18/2023

12/19/2023

12/20/2023

12/21/2023

12/22/2023

12/23/2023

12/24/2023

12/25/2023

12/26/2023

12/27/2023

12/28/2023

12/29/2023

12/30/2023

12/31/2023
11/2/2023

11/3/2023

11/4/2023

11/5/2023

11/6/2023

11/7/2023

11/8/2023

11/9/2023

12/1/2023

12/2/2023

12/3/2023

12/4/2023

12/5/2023

12/6/2023

12/7/2023

12/8/2023

12/9/2023
Duration
S.N Description of work Start Date End Date Remarks
(Days)

A Working days to complete the Scheduled work. 11/2/2023 12/31/2023 60

Rebar work of the staircase (inner & outer) up to


1
6.5m level.
11/2/2023 11/4/2023 3 x x x
2 Formworks work of the staircase. 11/1/2023 11/5/2023 5 x x x x
Rebar work of the remaining portion and including
3 scaffolding work of the 6.5m level (lintel beam of the
TRF-1 & 2)
11/3/2023 11/7/2023 5 x x x x x
Concrete work of the remaining portion of the 6.5m
4 level beam and staircase (inner & outer) up to 6.5m 11/8/2023 11/8/2023 1 x
level.
Formworks work of the 8.5m level beam.(ACDC room
5
and control & relay room)
11/2/2023 11/10/2023 9 x x x x x x x x x
Rebar work of the column and firewall up to 8.5m
6
level beam.( TRF-1&2 and GIS hall)
11/7/2023 11/10/2023 4 x x x x
7 Dipawali & Chhath festival leave 11/11/2023 11/21/2023 11 x x x x x x x x x x x
Remaining formworks work of the 8.5m level beam
8
and slab.(ACDC room and control & relay room)
11/22/2023 11/28/2023 7 x x x x x x x
Formwork work of the column and firewall including
9
GIS hall column up to 8.5m level.
11/25/2023 12/1/2023 7 x x x x x x x
Concreting work of the column and firewall including
10
GIS hall column up to 8.5m level.
12/2/2023 12/3/2023 2 x x
Rebar work and including electrical conduit placing
11 work of the 8.5m level beam and slab.(ACDC room 11/29/2023 12/5/2023 7 x x x x x x x
and control & relay room)
Verification work of the formwork, rebar work and
12
electrical conduit placing work.
12/6/2023 12/6/2023 1 x
Concrete work of the 8.5m level beam and slab.(ACDC
13
room and control & relay room)
12/7/2023 12/7/2023 1 x
14 Curing of the 1st floor slab/2nd floor level. 12/8/2023 12/9/2023 2 x x
Rebar work of the column of the 2nd floor and corbel
15 of the GIS hall column for EOT crane including TRF-1 12/10/2023 12/16/2023 7 x x x x x x x
&2 (firewall & column)
Formwork work of the column of the 2nd floor and
16 corbel of the GIS hall column for EOT crane including 12/12/2023 12/16/2023 5 x x x x x
TRF-1 &2 (firewall & column)
Verification work and concrete work of the column of
17 the 2nd floor and corbel of the GIS hall column for 12/17/2023 12/20/2023 4 x x x x
EOT crane including TRF-1 &2 (firewall & column)
Finishing work of the TRF-1 & 2 and GIS foundation
18 (rail track placing and Ms-plate and including 12/19/2023 12/25/2023 7 x x x x x x x
concreting work.)

Rebar and formwork of the 10.5m level beam. And


19
including verification work.
12/21/2023 12/30/2023 10 x x x x x x x x x x
12 Concrete work of the 10.5m level beam o fthe CRB. 12/30/2023 12/31/2023 2 x x