Technology Meets Constructability
Technology Meets Constructability
“But It Worked in the Model!” series continues to address the balance between
technology and constructability, with a focus on load paths.
Technology Meets
Constructability:
Part II
BY DAVID RUBY, SE, PE
Force Distribution Via Load Path details. This is when the designer confirms that a load path does
In a structural steel building, lateral forces are not directly distrib- exist within the structural concept.
uted by the concrete-filled metal deck slab (diaphragm) to the LFRS A concrete-filled metal deck diaphragm uses continuous col-
but rather are distributed via the collector beams and drag struts that lectors or struts as collection elements for the distribution of
support the diaphragm. However, due to the nature of analysis soft- the lateral forces originating in other portions of the structure
ware, these forces remain in the diaphragm and are not shown or re- to the LFRS.
ported as floor beam axial forces in the typical computer output. ASCE 7-10: Minimum Design Loads for Buildings and Other
The distribution of the lateral forces requires the existence of a Structures clearly defines diaphragm design provisions for mod-
load path from the diaphragm to the LFRS. To determine the mag- erate- to high-seismic areas (SDC B-F) and the importance of
nitude of these forces, the structural engineer may choose to revise identifying structural irregularities that may trigger an increase in
the model’s diaphragm constraints or take a hands-on approach. This the design forces. Diaphragm requirements for a structure whose
approach includes reviewing the results, verifying the continuity of LFRS is governed by wind are noted in ASCE 7-10 Chapter 26.
the load path, establishing the magnitude of the collector forces, pre- A simple diaphragm is defined as “a building in which both wind-
paring joint balance calculations, defining the metal deck diaphragm ward and leeward wind loads are transmitted by roof and verti-
attachment requirements and including the beam axial forces and cally spanning wall assemblies, through continuous floor and roof
connection capacity requirements in the design documents. diaphragms, to the main wind force-resisting system (MWFRS).”
ASCE 7-10 defines a diaphragm as “a roof, floor or other
Up-Front Planning membrane or bracing system acting to transfer lateral forces to
A designer’s rush to develop the analysis model may be short- the vertical MWFRS. For analysis under wind loads, diaphragms
changing the development of the structural concept by minimizing constructed of un-topped steel decks, concrete-filled steel deck
or skipping the schematic and preliminary stages in initial project and concrete slab, each having a span-to-depth ratio of two or less,
planning. At the schematic stage, the designer conceptualizes the shall be permitted to be idealized as rigid.”
fundamental design options, including the interaction (load path) SDI DDM003 states: “Some authorities define diaphragms as
of the subsystems. In the preliminary stage, the designer proves in the list that shows direct comparisons.”
the feasibility of the interacting subsystems and establishes basic Diaphragm Stiffness SDI G’ (kip/in.)
dimensions. Details of this interaction become part of the final Flexible 14.3 to 6.67
Semi-flexible 100 to 14.3
design/analysis stage where the focus is to refine the preliminary Semi-rigid 1,000 to 100
stage decisions by specifying all elements and related connection Rigid over 1,000
SEPTEMBER 2018
The stiffness of a concrete-filled metal deck diaphragm is a func- direction. The only mechanism delivering the lateral forces to the
tion of the metal deck gage, span and number of side-lap fasteners. braced bays is the beams on Column Line 1. There is no framing
For a typical concrete-filled floor slab with a 2-in. 20-gage metal on Column Line 1.8 to distribute the lateral forces from the dia-
deck spanning 6 ft, 3 in. with side-lap fasteners at 15 in., the dia- phragm to braced frames. “No load path” is the concern.
phragm stiffness G’ = 2,558 kips/in. (according to the Vulcraft 2008 The lack of framing on Column Line 1.8 leads one to question
Steel Roof and Floor Deck Catalog) > 1,000 kips/in.; therefore, a typical the adequacy of the original design concept as there are no specific
concrete-filled metal deck floor slab may be considered rigid. details, notes or specifications that address the strength, stiffness
and connection of the diaphragm to the LFRS. Typical metal deck
A Diaphragm Working Overtime attachments are shown without any details relating to the distribu-
A revisit of Example 1 from the previous article in this series tion of the diaphragm’s lateral forces directly to the braced frames
finds that the collectors necessary to transfer the lateral forces to on Column Line 1.8.
the LFRS on Column Line 1.8 do not exist (see Example 1, previ- It is no doubt that this concept “worked in the model” and the
ous page). The LFRS consists of vertically braced bays of varying rigid diaphragm may distribute some portion of the lateral loading
levels of stiffness (shown in blue). The braced bays are located at to the stand alone braced bays. But will that distribution echo the
the elevator and stair shafts, with the majority off the building grid. original analysis and subsequent final design?
With the exception of the columns on Column Line 1 and two
north-south braced bays, the braced bay columns do not have any No Load Path!
collectors or other members attached. A revisit of Example 2 from the most recent article, although
It is common to assume that the floor slab will provide a rea- similar, has a very different issue.
sonably stiff diaphragm in the analysis of multistory buildings, As previously stated, the concrete-filled metal deck slab provides
providing stability, picking up the gravity loads and distributing a rigid diaphragm in the analysis of multistory buildings. Tradition-
the lateral loads to the braced bays. However, in this structure the ally, the concrete diaphragm provides stability, picks up the gravity
diaphragm will be working overtime. The floor plan is void of any loads and distributes the lateral forces to the LFRS. However, in this
east-west collectors and has limited collectors in the north-south structure the diaphragm will again be working overtime.
SEPTEMBER 2018
The model provided a blue and green result, which subsequently ii. The concrete-filled metal deck in a structural steel
appeared on the design documents. But what was lacking? building must satisfy all applicable strength and
• Stiffness equalization of moment frames and braced frames serviceability requirements while providing stability
• Review of the braced frame lateral force for imbalance and lateral stability bracing of the structural
• Review of the load path for lateral force distribution steel elements.
• Verification of the collector beams’ existence and capacity to d. In concrete structures, the slab, acting as a diaphragm,
distribute the lateral load between the braced frames and mo- transfers the lateral shear forces directly to shear walls
ment frames (LFRS). In systems that contain beams or ribs, the elements
• Verification of the collector beam connection capacity below the concrete slab stiffen the diaphragm even further.
• Awareness that no load path existed between Column Line 6 e. In steel structures, the concrete-filled metal deck transfers
moment frames and Column Line 5 braced frames the lateral forces to the LFRS by way of collector beams
A potential load path issue exists. or drag struts (load path).
In both examples, let us remember: “It worked in the model!” f. Approval of shop drawings, often performed by junior
The examples used in this and preceding articles were taken staff, should include the review of essential elements of
from as-built structures and/or structural drawings of structures the structure’s LFRS. This is best performed with direct
issued for pricing purposes. Our review of the structure was based oversight by senior staff.
on the sizes and loading shown on the design documents. It is pos- g. Final design details must reflect the model’s
sible that many of these concerns were corrected during the build- boundary conditions.
ing process, but the original design documents did not properly h. Designs require review by an experienced
represent the complete scope of work to be priced and executed by structural engineer.
the fabricator and/or the erector. i. Computer programs provide information and are
not decision makers.
What Lessons Have We Learned? j. The computer is only a tool, nothing more.
1. Structural software has become the primary source for structural 2. Remember, claiming “But it worked in the model!” means very
design and analysis for structural engineers. However, without little and certainly does not guarantee success.
an understanding of the fundamental concepts of structure,
the results may be your worst nightmare. Structural engineers Designing structures is an art that incorporates earned as well
require an understanding of structures and their behavior to as learned knowledge: knowledge gained from experience, knowl-
prevent devastating errors that are often overlooked during the edge gained from mentors and knowledge gained from successes.
analysis and design process. But perhaps most of all, it incorporates the knowledge gained from
a. A well-defined load path is essential. our failures. Henry Petroski, in his book To Engineer is Human,
b. Structural steel and concrete are different materials and states, “Thus the colossal disasters that do occur are ultimately
their structural analysis should reflect this. failures of design, but the lessons learned from those disasters can
c. The concrete slab and the concrete-filled metal deck serve do more to advance engineering knowledge than all the successful
different functions in their respective models. machines and structures in the world.”
i. According to ACI 318, Section 12.3, concrete diaphragms Failures provide perspective for moving forward and they pro-
must have sufficient thickness so that all applicable mote the quest for answers and alternate solutions. Collaboration
strength and serviceability requirements are satisfied. between designers and contractors can satisfy that quest through
SEPTEMBER 2018