Republic of the Philippines

DEPARTMENT OF EDUCATION
EDUCATION FACILITIES DIVISION
DepEd Complex, Meralco Avenue, Pasig City

PROGRAM OF WORKS
BILL OF QUANTITIES

PROJECT: Date:
Repair and Rehabilitation of various DepEd Central Office Buildings and Ground Improvement
(Bonifacio Bldg - Lot 3)
OWNER: DEPARTMENT OF EDUCATION
LOCATION: DepED Complex, Meralco Avenue, Pasig City
Approved Budget for Contract: 24,258,103.44
Completion Period:
Minimum Required Manpower:
Project Engineer Electrician Painter Helper
General
Foreman
Carpenter
Laborer
Mason
Plumber
Welder
Direct Cost
ITEM Adjusted Unit Adjusted Total
ITEM DESCRIPTION % of Total UNIT Quantity
NO. Estimated Direct Unit Direct Cost Cost
Cost Cost
(7) (8)
(1) (2) (3) (4) (5) (6) (9)
(6)/(5) (9)/(5)

Page 1 of 4
A. General Requirements
Mobilization / Demobilization /Temporary
a.1 lot 1.00
Facilities
a.2 Project Billboard each 1.00
a.3 Construction Safety and Health CD 120.00
B. Removal Works
Removal of Existing Roofing Sheets,
b.1 sq.m 1,774.16
Gutter, Ridge Roll and Flashing
Removal of Existing Ceiling and Frames @
b.2 sq.m 1,815.29
5th Floor including CRs from GF-5th Flr
b.3 Removal of Existing Trench Drain l.m 98.60
Mini
mum
Required
Equipment:
Power Tools

Removal of Existing Tiles, Fixtures and


b.4 sq.m 1,126.75
Pipes at CRs from GF-5th Flr
Removal of Existing Walls/Dry Walls @
b.5 lot 1.00
CRs
C. Hauling and Clearing Works
Clearing and Hauling of Debris (NonUsable
c.1 lot 1.00
Materials)
Hauling of salvaged material to kasipagan
c.2 area - Usable Materials (Beside DepEd lot 1.00
Complex)
D. Roofing Works
d.1 Long-span Metal Roofing sq.m 1,811.57
E. Earthworks
Earthworks (Structural Excavation,
e.1 Backfilling and Compaction, Clearing and cu.m 7.86
Grubbing)

Page 2 of 4
F. Concreting Works
f.1 Concreting Works (Media Lounge) cu.m 15.21
G. Rebar Works
g.1 Rebar Works (Media Lounge) kgs 1,437.70
H. Form Works
h.1 Form Works (Media Lounge) sq.m 50.94
I. Masonry Works
i.1 Masonry Works (Media Lounge) sq.m 92.66
J. Doors and Windows
j.1 Doors and Windows (Media Lounge) lot 1.00
K. Steel Works
k.1 Truss at Media Lounge lot 1.00
L. Carpentry Works
Carpentry for Ceiling @ 5th Flr & CRs from
l.1 sq.m 1,853.99
GF-5th flr, at Media Lounge
M. Electrical Works
m.1 Conduit, Boxes and Fitting lot 1.00
m.2 Wires and Wiring Devices lot 1.00
m.3 Lighting Fixture / Fixture lot 1.00
N. Plumbing and Sanitary Works
n.1 Drainage Line Works lot 1.00
n.2 Water Line Works lot 1.00
n.3 Sewer Line Works lot 1.00
n.4 Fixtures, Partitions and Accessories lot 1.00
Signed by:

Name and
Signature of

Page 3 of 4
n.5 Rain Water Collector lot 1.00
O. Auxiliary
o.1 Auxiliary at Media Lounge lot 1.00
P. Furniture
p.1 Furniture at Media Lounge lot 1.00
Q. Painting Works
Painting (Exterior Walls, Interior Ceiling &
q.1 Interior Walls of 5th Flr and CRs, at Media sq.m 8,066.88
Lounge)
q.2 Scaffolding set 848.00
R. Tile Works
Tile Works @ Cr's Floors & Walls from
r.1 sq.m 1,165.45
GF5th Flr, at Media Lounge

TOTAL CONSTRUCTION COST % Php


Bidder's
Authorized
Representative

Position

Name of Bidder

Date

Page 4 of 4