WORK PLAN FOR THE PROPOSED CONSTRUCTION OF NUTRITION SITE IN MAGWI PHCC

ID Task Task Name M1 M2


Mode D-1 D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19 D20 D21 D22 D23 D24 D25 D26 D27 D28 D29 D30 D31 D32 D33 D34 D35 D36 D37 D38 D39 D40 D41 D42 D43 D44 D45 D46 D47 D48 D49 D50 D51 D52 D53 D54 D55 D56 D57 D58 D59
1 CONSTRUCTION OF TRANSITIONAL SHELTER AND
A LATRINE

2 MOBILIZATION

3 Material and Labor mobilization to site

4 SUBSTRUCTURE

5 Setting Out, Excavation & Earth Works

6 Concrete strip Foundation

7 Plinth Walls

8 Oversite Concrete

9 Completion of Substructure 6/18

10 BUILDING FRAME

11 Walling

12 RC columns

13 RC beams

14 Completion of Building Frame 6/27

15 DOORS AND WINDOWS

16 Window and Door Fabrication

17 Window and Door Fixing

18 Completion of Windows and Dooor 6/28

19 ROOF STRUCTURE

20 Steel Roof Fabrication

21 ROOF FINISHES

22 Roof Covering

23 WALL FINISHES

24 Wall plaster Rendering (Internal and External)

25 Wall Paint (Internal and External)

26 FLOOR FINISHES

27 Floor Screeding incl. Skirting

28 Completion of Finishes 7/22

29 PROJECT INSPECTION AND HANDOVER 7/26

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: WORK PLAN_CONSTRU
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 6/10/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress