Method Statement For Roofing Aluminum Cladding Installation
Method Statement For Roofing Aluminum Cladding Installation
Rev. 1
Name: Si Tou Heng Name: Liu Kun Fong Name: Eric Chow Name: Gavin Wong
Post: Senior Project Coordinator Post: Safety Officer Post: Senior Project Post: Deputy Project Director
Manager
CONTENTS
1. Objective
2. Scope of Works
3. Logistic
4. Method
5. Materials/Resources
6. Safety
7. Environmental
8. Safety
9. Permits and License
10. Employee and Third-Party Briefings
11. Emergency Contact List
APPENDICES
Appendix B – ITP
1|Page
Method Statement For Waterproofing Application Revision No:1
1. Objective
This method statement indicates the supply and installation of roofing structural steel framing,
waterproofing and aluminum cladding, under the scope of works 264-00296-40 and 264-
00297-40 - Londoner Grand L8 & L4 Pool Deck Refresh by Circle Engineering Company Ltd.
2. Scope of Works
Londoner Grand L8 pool suite roofing area
2|Page
Method Statement For Waterproofing Application Revision No:1
3|Page
Method Statement For Waterproofing Application Revision No:1
3. Logistic
4|Page
Method Statement For Waterproofing Application Revision No:1
4. Method
1.1. Preparation
Verify on site dimensions including wall-to-wall dimensions and levels, and check
against approved shop drawings to see if the area provided are within acceptable
tolerance.
Working area to be fenced with fencing with stickers as required.
Check and verify the numbering tags on the packing of delivered items to ensure
that the items are delivered to the correct location for installation.
The site needs to be supervised by the relevant person in charge.
5|Page
Method Statement For Waterproofing Application Revision No:1
Roofing Detail
6|Page
Method Statement For Waterproofing Application Revision No:1
Polishing of the old waterproofing membrane with angle grinders and safety
equipment (PPE).
Invitation of Owner Representative and Consultant for inspection for the roofing
surface to receive the new waterproofing membrane once the polishing work
completed.
Setting -out for steel plate then drilling holes for the anchor bolts.
Waterproofing applied at the bottom of steel plate areas. Step 1:
7|Page
Method Statement For Waterproofing Application Revision No:1
Priming: Prepare a 1:1 by volume Nitoproof 725 / clean water mixture. Apply primer
and allow to wet/ soak in to the substrate and dry to a tacky state before coating.
Step 2: Waterproofing Application: Nitoproof 725 should be applied in one coat by
roller or brush or by airless spray at a wet film of 0.8mm.
Waterproofing Curing (24H).
Installation of steel plate with anchor bolts.
Pull-out testing by the third party.
Connection of the steel frame by welding method.
Weld testing by the third party.
Brushing zinc rich epoxy coating to welding locations of steel frame.
Sika 214 grouting for the gap between of the steel plate and RC roofing surface.
Waterproofing applied for the whole area of RC roofing surface, Step 1: Priming:
Prepare a 1:1 by volume Nitoproof 725 / clean water mixture. Apply primer and
allow to wet/ soak in to the substrate and dry to a tacky state before coating. Step 2:
Waterproofing Application: Nitoproof 725 should be applied in one coat by roller or
brush or by airless spray at a wet film of 0.8mm.
Waterproofing Curing (24H). It is a critical step in the waterproofing process,
ensuring that the applied waterproofing membrane adheres properly and achieves
its intended performance.
Installation of #316 S.S. gutter with bird net.
Installation of alum. panel & Half Circular copping, implant weather sealant.
5. Equipment
Aluminium Scaffolding
8|Page
Method Statement For Waterproofing Application Revision No:1
Stirring machine
Impact Drill
9|Page
Method Statement For Waterproofing Application Revision No:1
1. Safety
Place health and safety as our number one priority over all other business considerations.
7.1 Emergency Arrangements
In the event of accident/serious accident
Report site supervisor to PM/SPM and the relevant parties immediately
Relevant works would be ceased for investigation work.
First aider would present to provide preliminary treatment of the injured.
Direct the injured to the hospital immediately of necessary.
10 | P a g e
Method Statement For Waterproofing Application Revision No:1
Gloves
11 | P a g e
Method Statement For Waterproofing Application Revision No:1
12 | P a g e
Method Statement For Waterproofing Application Revision No:1
Plastic water storage containers shall be used to storage waste water temporarily,
and shall be sealed up properly. It shall be disposed at designated waste water
disposal point assigned by the main contractor. The containers shall not be left
13 | P a g e
Method Statement For Waterproofing Application Revision No:1
open from time to time, and shall not be kept inside the hoarding for a long time
except during the cement mixing and plastering process.
Wooden cover with canvas to cover up the opening
14 | P a g e
Method Statement For Waterproofing Application Revision No:1
15 | P a g e
Method Statement For Waterproofing Application Revision No:1
Appendix B: ITP
16 | P a g e
Method Statement For Waterproofing Application Revision No:1
17 | P a g e