Technical Data For Towers
Technical Data For Towers
TRANSMISSION LINE
SL No Description Page No
1 Introduction 1
2 Overall Procedure 1
3 Safety procedure 1
4 Statutory Requirement 2
5 Inspection 2
7 Protective system 16
8 Dispatching Procedure 17
9 Switching Procedures 17
10 Handing Over 17
11 Energization 18
12 De-Energization 18
14 Acceptance criteria 18
15 Documentation 18
ABBREVIATIONS
AC Alternating Current
AM Asset Management
CEA Central electricity authority
CLR insulator Composite Long Rod Insulator
CBIP Central Board of Irrigation and Power
CERC Central Electricity Regulatory Commission
CTUIL Central Transmission Utility of India Limited
DC Direct Current
D/C Double Circuit
FS type Fully submerged type foundation
Foundation
GS Ground Switch
IS Indian standard
ICAO International Civil aviation organization
MOEF Ministry of Environment and Forest
M/C Multi circuit
NTAMC National Transmission Asset Management System
OPGW Optical Fiber Ground wire
PTCC Power and tele-communication coordination committee
ROW Right of way
RTAMC Regional Transmission Asset Management System
S/C Single circuit
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
1.0 INTRODUCTION
This document includes overall procedure, safety rules, Statutory Requirements,
dispatching procedure, switching sequences, inspection, testing & measurement,
observations, acceptance criteria and documentation of test results for pre-
commissioning procedures for transmission lines.
Different type of electrical clearances are tabulated as per CEA document (Measures
relating to Safety and Electric Supply Regulations, 2010), CBIP manual for
Transmission line in 2014, Forest conservation Act, 1980 & forest conservation
Rules, 2003 & POWERGRID latest technical specifications for transmission lines.
Different values indicated in this document is for reference purpose only; however,
if there is any difference between the values indicated in this document & the
values in the technical specifications/drawings; the values of technical
specifications/drawings will prevail.
The detailed inspection and handing over documents are required to be checked for
the entire length of transmission line before energization. Geo-tagged digital
Photographs of all tower locations using high-resolution digital camera need to be
handed over to taking over team and preserved as part of taking over record.
2.0 OVERALL PROCEDURE
First, it is to be ascertained that the transmission line to be energized is ready for
operation and has been properly handed over (released) in writing. This will include
all safety aspects, Electrical inspector clearance, PTCC clearance, statutory
clearance, regulation/ system operator requirement and final inspection, if any.
Instructions for the work and supervision are given by the test leader (Line in
charge). However, regular operators will execute all switching and operational
activities.
Line charging instructions received from Engineering department & CTUIL should be
clearly understood by the Line in charge and doubts, if any, are to be got clarified
prior to the energization of the line.
Once, the line is handed over for charging, no work shall be permitted without a
valid work permit.
Engineering department & CTUIL recommendations, system operator/ regulation
requirements are to be followed before putting the system into continuous
operation.
3.0 SAFETY PROCEDURES
Energization implies an abrupt and serious change of the working conditions in the
line.
In order to avoid serious accidents, thorough information must be imparted to all
personnel involved in the construction of transmission line. In-charge of the
1|Page
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
Transmission line must ensure that due publicity has been made to the public in all
the villages/ areas along the line route cautioning them against climbing the towers
etc. and that the line is proposed to be charged on notified date. It is also to be
confirmed that all the agencies involved in construction activities shall not carry out
any job on the said line without a valid work permit.
It shall be ensured that before charging all men, material, Tools & plants and any
temporary earthing on any part of the entire length of line are removed.
It must be ensured that any power supply/ low voltage charging used as “anti-theft
measure” must be disconnected and isolated to avoid accidental connection.
All equipment tests and pre-commissioning tests must have been completed,
reconnected (in case cables were isolated for testing purpose) and documented as
per prescribed format.
The system must be formally declared ready for Energization and handed over for
operation in writing.
4.0 STATUTORY REQUIREMENT
4.1 The concerned authorities shall be informed before commissioning the line and
their approval shall be obtained in accordance with latest Central Electricity
Authority (Measures relating to Safety and Electric Supply) Regulations.
4.2 Before charging of the line, PTCC approval from concerned authority shall be
obtained.
5.0 INSPECTION
Before the line is scheduled to be handed over for the pre-commissioning/
Energization, the same shall be inspected by representatives of POWERGRID and
Construction Agency. Such inspection shall include:
i) Right of way/ way leave/ electrical clearance
ii) Jumper drops
iii) Foundation and Revetments/ Protection Work
iv) Tower and Tower accessories
v) Earthing
vi) Hardware fittings
vii) Insulators
viii) Conductors and Earth wire/OPGW
ix) Accessories for conductor and Earth wires/OPGW
x) Aviation Warning Signals (Lights/globules/painting)
xi) Bird Diverter (if applicable)
2|Page
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
3|Page
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
5.1.2.2 Clearance of earth wire/OPGW with Top conductor at mid span to Top conductor
Availability of required vertical clearances (as per design & POWERGRID
Specification) between conductor and earth wire/OPGW shall be ensured through
random checking. Minimum clearances between conductor and earth wire/OPGW
at mid-span shall be as indicated below:
Voltage 66 132 220 +/- 320 40 +/- 500 765 +/- 800 1200
(kV) HVDC 0 HVDC HVDC
Minimum 3 6.1 8.5 8.5 9 9 9 12(pole) 18
mid span 6.1(DMR)
clearance
(in meter)
4|Page
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
Where an overhead direct current (DC) line crosses another overhead line, clearances shall
be as under: -
Minimum clearances in meters between AC and DC lines crossing each other
SI. System Voltage 100 200 300 kV 400 kV 500 kV 600 800
No (AC/DC) kV DC kV DC DC DC DC kV kV
. DC DC
1 Low and Medium 3.05 4.71 5.32 6.04 6.79 7.54 9.04
AC
2 11-66 kV AC 3.05 4.71 5.32 6.04 6.79 7.54 9.04
3 110-132 kV AC 3.05 4.71 5.32 6.04 6.79 7.54 9.04
4 220 kV AC 4.58 4.71 5.32 6.04 6.79 7.54 9.04
5 200 kV DC 4.71 4.71 5.32 6.04 6.79 7.54 9.04
6 300 kV AC 5.32 5.32 5.32 6.04 6.79 7.54 9.04
7 400 kV AC 5.49 5.49 5.49 6.04 6.79 7.54 9.04
8 400 kV DC 6.04 6.04 6.04 6.04 6.79 7.54 9.04
9 500 kV DC 6.79 6.79 6.79 6.79 6.79 7.54 9.04
10 600 kV DC 7.54 7.54 7.54 7.54 7.54 7.54 9.04
11 765 kV AC 7.94 7.94 7.94 7.94 7.94 7.94 9.04
12 800 kV DC 9.04 9.04 9.04 9.04 9.04 9.04 9.04
13 1200 kV AC 10.44 10.44 10.44 10.44 10.44 10.44 10.44
5|Page
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
Provided that no guarding are required when line of voltage exceeding 33 kV crosses
over another line of 250 V and above voltage or a road or a tram subject to the
condition that adequate clearances are provided between the lowest conductor of the
line of voltage exceeding 33 kV and the top most conductor of the overhead line
crossing underneath the line of voltage exceeding 33 kV and the clearances as stipulated
in regulation 58 from the topmost surface of the road maintained
5.1.2.4 Electrical clearance from railway tracks shall be as stipulated under Sec-III, Vol-II of
Technical Specification of POWERGRID.
(i) Vertical clearance for OHE (other than high rise OHE):
Sl. No. Transmission line voltage level Minimum clearances from Rail Level
New Power Line crossing or crossing
planned for alteration
1 Above 66 kV & up to 132 kV 15.56 m
2 Above 132 kV & up to 220 kV 16.46 m
3 Above 220 kV & up to 400 kV 18.26 m
4 Above 400 kV & up to 500 kV 19.16 m
5 Above 500 kV & up to 800 kV 21.86 m
(ii) Vertical clearance for high-rise OHE*:
Sl. Transmission line voltage level Minimum clearances from Rail Level
No. New Power Line crossing or crossing
planned for alteration
1 Above 66 kV & up to 132 kV 17.56 m
2 Above 132 kV & up to 220 kV 18.46 m
3 Above 220 kV & up to 400 kV 20.26 m
4 Above 400 kV & up to 500 kV 21.16 m
5 Above 500 kV & up to 800 kV 23.86 m
(iii) Clearance between highest traction conductor & lowest crossing conductor
Sl. Transmission line voltage level Minimum clearances from Rail Level
No. New Power Line crossing or crossing
planned for alteration
1 Above 66 kV & up to 132 kV 3.05
2 Above 132 kV & up to 220 kV 4.58
3 Above 220 kV & up to 400 kV 5.49
4 Above 400 kV & up to 500 kV 7.94
5 Above 500 kV & up to 800 kV 7.94
*Applicable only for electrification of routes where double stack container having
maximum height of 6809 mm is plying
6|Page
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
(1) An overhead line shall not cross over an existing building as far as possible and no
building shall be constructed under an existing overhead line.
(2) Where an overhead line of voltage, exceeding 650 V passes above or adjacent to
any building or part of a building, it shall have on the basis of maximum sag a
vertical clearance above the highest part of the building immediately under such
line, of not less than clearance mentioned as per below table for respective voltage
level
(3) The horizontal clearance between the nearest conductor and any part of such
building shall, on the basis of maximum deflection due to wind pressure, be not
less than clearance mentioned as per below table for respective voltage level
Note: Clearance are calculated as per norms specified in clause no 61 of CEA safety
regulation 2010
(4) For High Voltage Direct Current (HVDC) systems, vertical clearance and horizontal
clearance, on the basis of maximum deflection due to wind pressure, from
buildings shall be maintained as below:
7|Page
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
Explanation: - For the purpose of this regulation the expression “building” shall be
deemed to include any structure, whether permanent or temporary.
5.1.2.6 Minimum Clearance in air above ground and across road surface of Highways or roads
for lowest conductor of an AC overhead lines, including service lines of nominal
system voltage
As per sub regulation (1) of regulation (58) of CEA draft safety regulation 2021
*Higher clearance predominantly induction effects and time varying electric field (ICNIRP
limit:10 kV/m for occupational exposure) at voltage exceeding 400 kV
8|Page
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
5.1.2.7 Minimum Clearance in air above ground and across road surface of Highways or roads
for lowest conductor of an DC overhead lines,
As per sub regulation (1) of regulation (58) of CEA draft safety regulation 2021
Clearance between
Nominal system Clearance above conductor & road surface
Voltage (in kV) ground across high way (in meter)
Highway clearance required 4.75 meter higher than ground clearances (considering the
vehicle height 4.75 meter as mentioned in the Indian road congress documents, 1983)
5.1.2.8 Power line/cable crossing with waterway:
Minimum Clearance of Power Conductor over the Highest Flood Level in case of
navigable/non navigable rivers (As per clause no 4.5.1 of CBIP manual on
Transmission line, 2014)
a) AC system
AC Voltage Level in kV Minimum Clearance above H.F.L (mm)
(Nominal voltage)
Navigable River Non-navigable river
66 19000 3650
110 19000 4300
132 19220 4300
220 20100 5100
400 21900 6400
765 25550 9400
1200 29900 11000
b) DC system
9|Page
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
10 | P a g e
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
records.
5.3.2 Special Towers
In addition to the above checks for towers, ladders and platforms provided in
special towers shall be properly tightened and no foreign material shall be left out
on such platforms.
5.3.3 Earthing of Towers
Ensure that proper earthing (Pipe type earthing in one of tower leg/ Counterpoise
Earthing) of tower has been done and earthing strip is neither damaged nor broken
and is properly fixed to the stub.
Ensure that Additional earthing is provided on every 7 to 8 kms distance at tension
tower for direct earthing of both shield wires (Earth wire/ OPGW).
Ensure that Additional Rod type earthing is provided in one of foundation pit
(Diagonally opposite to pipe type earthing) of all the transmission line towers in
normal soil (i.e., Dry, Wet cultivated, Wet, PS, FS & Black cotton soil) in addition to
pipe type earthing.
In case of counter poise earthing, it is to be ensured that earth wire is sufficiently
buried in the ground to avoid digging out during cultivation. The length of
counterpoise shall be as per technical specification. The same shall be laid uniformly
and stacking/ coiling of counter poise wire is not allowed.
Before charging of the line, ensure that tower footing Impedance at each tower is
below 10 ohms. If tower footing impedance of any tower (before stringing) has
been recorded higher than 10 ohms, additional counterpoise type earthing/
Chemical earthing shall be provided to bring the tower footing impedance value
below 10 ohms.
Earthing of special towers shall be verified as per approved drawings applicable for
special towers/ special foundation.
5.3.4 Tower accessories
All danger plates, number plates, circuit plates and phase plates shall be in position
as per the specification and properly tightened.
All phase plates shall be fixed in correct phase sequence. Special care may be taken
at transposition towers for indicating the correct phase sequence.
It shall be ensured that the anti-climbing device (ACD) is provided at the suitable
height of tower. In case of barbed wire type ACD, barbed wire shall be tightly fixed.
It shall be ensured that the step bolts (for normal towers) are provided up to the
peak of the tower. Any missing step bolts shall be replaced.
Fixing of bird-guards shall be ensured at all towers to prevent birds perching on
suspension insulator strings.
11 | P a g e
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
12 | P a g e
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
5.7.6 Others
It shall be ensured that all temporary/ local earthing, guys, T & P (Tools and Plants),
foreign material, Pilot rope used in OPGW stringing and other loose material, which
were used during stringing/ tower erection, have been removed.
If, there is any change in the ground profile before commissioning of line from the
approved profile, the extra earth/ obstruction/ temporary sheds/ any other
construction shall be removed.
5.8 AVIATION WARNING OBSTRUCTION SIGNALS (LIGHTS/ GLOBULES/ PAINTING)
It shall be ensured that following measures have been taken in the line/ Towers
falling within obstruction zone of civil aviation and defense establishments as per IS-
5613(latest revision), ICAO Guidelines and POWERGRID specification.
5.8.1 Day markers
5.8.1.1 Structure marking: The structure portion excluding cross arms above 45-meter
height shall be painted in alternate bands of international orange and white color as
per IS-5613(latest revision) & ICAO Guidelines.
5.8.1.2 Line markers may be provided as per the technical specification.
5.8.2 Night markers
It shall be ensured that proper aviation lights at the peak level/ at specified heights
of towers have been provided along with Solar panels/ Battery banks/ Control
cubicles and other accessories as per specification. The functioning of lights with
simulation shall be checked/ verified.
5.9 BIRD DIVERTERS
Bird diverters shall be placed in identified stretches as per conditions stipulated by
forest authority to avoid the chance of collision of birds with transmission line.
6.0 TESTING AND MEASUREMENT
6.1 Tower footing Impedance Measurement
Tower footing impedance measurement is to be carried out using tower footing
impedance tester. The value of impedance should be below 10 ohms. If impedance
value is higher than 10 ohms, additional counterpoise type earthing/ chemical
earthing shall be provided to bring the tower footing impedance value below 10
ohms. These measurements may preferably be carried out during dry climate.
Tower footing impedance need to be measured for all tower location and the values
need to be recorded for future reference and document will be handed over to
RHQ-AM. RHQ-AM will carry out impedance measurement at 5% locations on
sample basis. Corrective action will be taken if impedance values are higher than 10
ohms.
6.2 Before commissioning of the lines following tests may be carried out:
14 | P a g e
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
If the test results are satisfactory, it confirms that marking of the phases are in
order.
6.2.2 Insulation Resistance Test of Line
This test may be carried out using 5 kV or 10 kV Insulation Tester preferably power
driven to ascertain the insulation condition of the line. If, 5 kV Insulation Tester is
used for insulation resistance measurement, it shall be ensured that the induced
voltage (CVT reading) is less than the instrument withstanding capacity to avoid the
possibility of damage of instrument.
15 | P a g e
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
trip test, that the protections are actually functionally enabled. This verification
serves to prevent that energization takes place of a line where a protection has
been disabled for test or other reason.
8.0 DISPATCH PROCEDURES
All operational activities (switching etc.) must be coordinated and communicated
with the system dispatcher i.e. NTAMC/ RTAMC/ RLDC/ NLDC. In this respect, the
general procedures already established by POWERGRID, Regulator and System
Operator will be followed.
9.0 SWITCHING PROCEDURES
For each activity, the instructions to the operators and the communications to the
dispatchers will be made in writing or by confirmed telephone messages. The
switching procedures first to be properly documented step by step and understood
by everybody involved in the switching operation prior to the energization. Any
clarification required in the procedures must be resolved. The format established by
the utility for switching orders and operational data logging shall be followed. Each
and every activity must be listed and described, so that complete information is
available for detailed investigation, if required in future.
10.0 HANDING OVER
The transmission line shall be inspected prior to Energization and a formal handing
over document to be jointly signed by the representative of SUPPLIER (if available),
ERECTION AGENCY and POWERGRID. However, all contractual taking over has to be
resolved separately as per the terms and conditions of the contract. Handing over
shall be limited to the completion of Erection and ready for Energization.
The relevant format No AM/COMM/LINE/1a & AM/COMM/LINE/1b which are in
part-B of document for handing over is also a part of documentation
Any outstanding points or remaining activities are to be listed and signed jointly by
the representatives of POWERGRID and ERECTION agency as per the Format No:
AM/COMM/LINE/2 of part-B of this document. These documents are also to be
retained at line office with a copy to regional office. The remaining activities
outstanding points are classified in the following category.
Details of the SECTIONS:
A. List of outstanding activities remaining in any part of the line
B. A list of temporary arrangements introduced.
C. Check list of records properly documented, completed and signed as per Format
No: AM/COMM/LINE/1 of part-B of this document
D. Original tracing of Profile, Route Alignment, Tower Design, Structural Drawings,
Bill of Materials, Shop Drawings, stringing charts (initial and final as applicable)
etc. of all towers/ line submitted to POWERGRID.
After resolving the above-mentioned outstanding activities or with only minor
remaining points which do not influence on charging of line, handing over of the
17 | P a g e
POWER GRID CORPORATION OF INDIA LTD.
CORPORATE ASSET MANAGEMENT
DOCUMENT NO: D-2-01-70-01-03-Part A
DOCUMENT NAME: PRE-COMMISSIONING PROCEDURES FOR TRANSMISSION LINES
18 | P a g e