Mahadevanna Hit
Mahadevanna Hit
For foundation :
1x31.60x0.60x0.60 = 11.37 Cum
1x31.60x0.45x0.45 = 6.39
17.76 M3
@ Rs.1795.16/M3 Rs.31882=00
14 Cutting and clearing the jangle and small fire wood tree for
agriculture and levelling area etc., complete
1x120x65=7800m2
@ Rs. 2.50/- Rs. 19,500=00
15 Earth work excavation for levelling and lowering the
agriculture land (other than foundation work) and removing
the excavated earth to distance not exceeding 150m and
lift upto 1.50mt and spreading levelling etc., complete
wherever necessary.
1x150x90x0.35=4725m3
@ Rs.24.41-m3 Rs.1,15,375=00
16. Miscellaneous and stuff cutting works L/s Rs. 65,125=00
Total Amount Rs.2,00,000=00
Part – A Barn and Bulk Shed Repairs work Rs.3,00,000=00
Part – B Agriculture land levelling Rs.2,00,000=00
Total : Rs.5,00,000=00
Reports :
An estimate amounting for Rs.5,00,000=00 (Rupees Five lakhs
fifty thousand only) is prepared for above work with available
provisions are adopting the current S.R. of 2024-25 of Mysore
circle.
For foundation :
1x31.60x0.60x0.60 = 11.37 Cum
1x31.60x0.45x0.45 = 6.39
17.76 M3
@ Rs.1795.16/M3 Rs.31882=00
14 Cutting and clearing the jangle and small fire wood tree for
agriculture and levelling area etc., complete
1x60x40=2400m2
@ Rs. 2.50/- Rs. 6,000=00
15 Earth work excavation for levelling and lowering the
agriculture land (other than foundation work) and removing
the excavated earth to distance not exceeding 150m and
lift upto 1.50mt and spreading levelling etc., complete
wherever necessary.
1x60x40x0.35=840m3
@ Rs.35.05-m3 Rs. 29,442=00
16. Miscellaneous and stuff cutting works L/s Rs. 64,558=00
Total Amount Rs. 1,00,000=00