Week 10 Assignment
Week 10 Assignment
1. A project consist of 5 activities. The expected time of the project in weeks is ___.
a. 12
b. 15
c. 16
d. 18
Ans: B
Solution:
Path Duration
1-2-4-5 (A-B-E) 12
1-2-3-4-5 (A-C-D-E) 15
2. Activity A to K are required to complete a project. The time estimate and the immediate
predecessor of these activities are given below. If the project is to be completed in minimum
possible time, the latest finish time for an activity G is __ hours.
a. 5
b. 10
c. 8
d. 9
Ans: B
Solution: The LFT of activity G = 10 hours.
3. Activities A, B, C and D form the critical path for a project with PERT network. The means
and variances of the activites duration for each activities is given below. The probability that
the project will be completed within 40 days is ___ (round off to two decimal places)
Activity A B C D
Mean 6 11 8 15
Variance 4 9 4 9
a. 0.25
b. 0.5
c. 0.65
d. 0.85
Ans: B
Solution: Since 𝑇𝑠 = 40 days, 𝑇𝐸 = 6 + 11 + 8 + 15 = 40
Therefore, it’s the mean of the normal distribution. So, probability is 0.5
4. The number of hours required for each activity is shown alongside the nodes. The slack on the
activity L is ___ hours.
a. 1
b. 2
c. 3
d. 4
Ans: B
Solution:
Time long path A-B-C-F-I-J-K = 42 hours
Time along path A-B-C-E-H-L = 31 hours
Time along path A-B-C-D-G-H-L = 40 hours.
Therefore, slack for L is 42-40 =2 hours
5. The arc length of a directed graph of a project are shown in the figure. The shortest path
length from node 1 to node 6 is ___.
a. 7
b. 9
c. 12
d. 14
Ans: A
Solution: The shortest path will be 7.
6. Processing time and due dates for six jobs waiting to be processed at work center are given
below. The average tardiness using shortest processing time rule is ___.
a. 4.26
b. 5.65
c. 6.33
d. 8.46
Ans: C
Solution: By SPT rule, total tardiness is 38. Therefore Average tardiness is
𝑇𝑜𝑡𝑎𝑙 𝑇𝑎𝑟𝑑𝑖𝑛𝑒𝑠𝑠 38
= = 6.33 𝑑𝑎𝑦𝑠
𝑁𝑜. 𝑜𝑓 𝑗𝑜𝑏𝑠 6
7. The total float (in days) for the project network given below is __
a. 0 and 4
b. 1 and 4
c. 2 and 3
d. 3 and 1
Ans: B
Solution: Total float for activity e = 7-2-4 = 1 and for f = 12-4-4 = 4
8. Consider the given project network, where number along various activities represent the
normal time. The free float on activity 4-6 and the project duration are:
a. 2, 13
b. 0, 13
c. -2, 13
d. 2, 12
Ans: A
Solution: The critical path is 1-2-5-6-7
𝑇𝑒 = 3 + 2 + 3 + 5 = 1 3
Free float (4-6) path is = 8-4-2 = 2
9. For a particular project, eight activities are to be carried out. Their relationship with other
activities and expected duration are given below.