LMA8X05 - Learning Unit 3
LMA8X05 - Learning Unit 3
15 August 2022
Scheduling
Background Not all project activities need to be scheduled at the same level of
detail
Most of the scheduling is at the WBS level, not the work package
level
1
8/10/22
• Consistent framework
• Shows interdependences
Terminology
Path: A series of connected activities
2
8/10/22
Terminology
Sequential Activities: One activity must be completed before the
next one can begin
Parallel Activities: The activities can take place at the same time
3
8/10/22
10
10
11
11
12
12
4
8/10/22
Advantages
• Easily understood
• Provide a picture of the
Advantages current state of a project
and
Disadvantage
Disadvantage
13
14
14
15
15
5
8/10/22
• No false deadlines
16
16
17
17
18
18
6
8/10/22
s2 =ç ÷
è 6 ø
s = s2
19
19
20
20
21
21
7
8/10/22
22
22
23
23
24
24
8
8/10/22
Slack
25
25
Slack Values
26
26
the Critical
Path The longest path is the critical path
27
27
9
8/10/22
C=2 4 E=1
A=2 B=5
start 1 2 3 6 finish
D=7 5 F=2
28
28
29
29
Exercise
• Given the information on the student data set for this problem, create the project schedule network.
Then, using the Two-pass method, calculate and show the early and late starts and slack for each
activity and the critical path.
Activity Days Immediate Predecessor
A 5
B 2 A
C 4 A
D 7 A
E 3 B
F 6 B,C
G 8 E,F
30
30
10
8/10/22
Resource Allocation
31
32
32
33
33
11
8/10/22
34
Crashing – Example
35
35
Crashing – Example
Activity B on the
critical path is
the least
expensive
choice
36
36
12
8/10/22
Crashing – Example
After 2 rounds,
both critical
paths are 23
days.
37
37
Crashing – Example
Continuing to
crash activities
until it is not
worthwhile
38
38
Crashing – Example
Continuing to
crash activities
until it is not
worthwhile
39
39
13
8/10/22
40
40
41
41
42
42
14
8/10/22
Resource Loading
• Resource loading describes the amount of resources an existing schedule requires
43
43
44
44
Levelling
problems that activity to shift of activities to
its resource usage levelize resources
45
45
15
8/10/22
2. Resource utilization
3. In-process inventory
46
46
47
47
48
48
16
8/10/22
49
49
50
50
51
51
17