0% found this document useful (0 votes)
13 views17 pages

LMA8X05 - Learning Unit 3

Uploaded by

raymotsena
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views17 pages

LMA8X05 - Learning Unit 3

Uploaded by

raymotsena
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17

8/10/22

LMA8X05 – PROJECT MANAGEMENT

15 August 2022

Scheduling

Schedule is the conversion of a project action plan into an


operating timetable

Basis for monitoring a project

One of the major project management tools

Work changes daily, so a detailed plan is essential

Background Not all project activities need to be scheduled at the same level of
detail

Most of the scheduling is at the WBS level, not the work package
level

Only the most critical work packages may be shown on the


schedule

Most of the scheduling is based on network drawings

1
8/10/22

Network Scheduling Advantages

• Consistent framework

• Shows interdependences

• Shows when resources are needed

• Ensures proper communication

• Determines expected completion date

• Identifies critical activities

Network Scheduling Advantages

• Shows which of the activities can be delayed

• Determines start dates

• Shows which task must be coordinated

• Shows which task can be run parallel

• Relieves some conflict

• Allows probabilistic estimates

Activity: A specific task or set of tasks that are required by


the project, use up resources, and take time to complete

Event: The result of completing one or more activities

Network: The combination of all activities and events that


define a project

Terminology
Path: A series of connected activities

Critical: An activity, event, or path which, if delayed, will


delay the completion of the project

Critical Path: The path through the project where, if any


activity is delayed, the project is delayed

2
8/10/22

Terminology
Sequential Activities: One activity must be completed before the
next one can begin

Parallel Activities: The activities can take place at the same time

Immediate Predecessor: That activity that must be completed just


before a particular activity can begin

AON and AOA Format

Constructing the Network


• Begin with START activity
• Add activities without precedences as nodes
• There will always be one
• May be more
• Add activities that have those activities as precedences
• Continue

3
8/10/22

Sample of Network Construction

10

10

Sample of Network Construction

11

11

Developed by Henry L. Gantt

Gantt (Bar) Shows planned and actual


progress
Charts

Easy-to-read method to know


the current status

12

12

4
8/10/22

Advantages

• Easily understood
• Provide a picture of the
Advantages current state of a project
and
Disadvantage
Disadvantage

• Difficult to follow complex


projects
13

13

Microsoft Project Gantt Chart

14

14

Microsoft Project AON Network

15

15

5
8/10/22

An Important Aside on Estimating Activity Times


• It is vital to good project management to be meticulously honest in estimating the time required to
complete each of the various tasks included in the project

• No false deadlines

• Evaluate alternative ways of completing work.

16

16

Solving the Network

17

17

The AON Network from the previous table

18

18

6
8/10/22

Calculating Activity Times


TE =
(a + 4m + b )
6
æ (b - a ) ö
2

s2 =ç ÷
è 6 ø
s = s2

19

19

Critical Path and Time

20

20

Calculating Early and Late Start and Finish Dates

21

21

7
8/10/22

Calculating Early and Late Start and Finish Dates


•Forward Pass

22

22

Calculating Early and Late Start and Finish Dates


•Backward Pass

23

23

Critical Path and Time

24

24

8
8/10/22

Slack

25

25

Slack Values

26

26

First develop a good network diagram

Add the duration estimates for all activities on each


Calculating path through the network diagram

the Critical
Path The longest path is the critical path

If one or more of the activities on the critical path


takes longer than planned, the whole project
schedule will slip unless the project manager takes
corrective action

27

27

9
8/10/22

Example of Determining the Critical Path


• Consider the following project network diagram. Assume all times are in days.

C=2 4 E=1
A=2 B=5
start 1 2 3 6 finish

D=7 5 F=2

1. How many paths are on this network diagram?


2. How long is each path?
3. Which is the critical path?
4. What is the shortest amount of time needed to complete this project?

28

28

Example of Determining the Critical Path

29

29

Exercise
• Given the information on the student data set for this problem, create the project schedule network.
Then, using the Two-pass method, calculate and show the early and late starts and slack for each
activity and the critical path.
Activity Days Immediate Predecessor
A 5
B 2 A
C 4 A
D 7 A
E 3 B
F 6 B,C
G 8 E,F

30

30

10
8/10/22

Resource Allocation

31

Allocating resources (human,


technical, etc) to projects
What is
Use in both individual and
Resource multiple, simultaneous projects
Allocation?
Relates to scheduling and
costs

32

32

Critical Time and


Faster an
activity is
completed,
Path
costs are
interrelated more is the
cost

Method— Thus many

Crashing Change the


schedule and
you change
activities can
be speeded
up by
a Project the budget spending
more money

33

33

11
8/10/22

To speed up, or expedite, a project

Of course, the resources to do this


must be available
What is
Crunching a project changes the
Crashing / schedule for all activities
Crunching?
This will have an impact on schedules
for all the subcontractors

Crunching a project often introduces


unanticipated problems
34

34

Crashing – Example

35

35

Crashing – Example

Activity B on the
critical path is
the least
expensive
choice

36

36

12
8/10/22

Crashing – Example

After 2 rounds,
both critical
paths are 23
days.

37

37

Crashing – Example

Continuing to
crash activities
until it is not
worthwhile

38

38

Crashing – Example

Continuing to
crash activities
until it is not
worthwhile

39

39

13
8/10/22

Fast-tracking is another way


to expedite a project
• Mostly used for construction projects
• Can be used in other projects

Refers to overlapping design


Fast- and build phases
Tracking
Increases number of change
orders

Increase is not that large

40

40

CPM/PERT ignore resource


utilization and availability

The With external resources, this may


Resource not be a problem

Allocation It is, however, a concern with


Problem internal resources

Schedules need to be evaluated in


terms of both time and resources

41

41

Time limited: A project must be finished


by a certain time

Time Use Resource limited: A project must be


finished without exceeding some specific
and level of resource usage

Resource Overdetermined: when time, cost, and


Use scope are fixed

System-constrained: A project requires a


fixed amount of time and resources

42

42

14
8/10/22

Resource Loading
• Resource loading describes the amount of resources an existing schedule requires

• Gives an understanding of the demands a project will make of a firm’s resources

43

43

Resource Usage Calendar

44

44

Less hands-on May be able to use


management is just-in-time inventory Improves morale
required

Resource Fewer personnel


When an activity has
slack, we can move
May also be possible
to alter the sequence

Levelling
problems that activity to shift of activities to
its resource usage levelize resources

Large projects with


Small projects can Software can multiple resources
levelize resources
be levelized by hand for larger projects are complex to
levelize

45

45

15
8/10/22

Standards to Measure Schedule Effectiveness


1. Schedule slippage

2. Resource utilization

3. In-process inventory

46

46

(1) Schedule Slippage

• The time past a project’s due date

• Slippage may cause penalties

• Different projects will have different penalties

• Expediting one project can cause others to slip

• Taking on a new project can cause existing projects to slip

47

47

(2) Resource Utilization

• The percentage of a resource that is actually used

• Excess resource utilization and uncoordinated multiproject


scheduling can be expensive

• We want a schedule that smoothes out the dips and peaks of


resource utilization

48

48

16
8/10/22

(3) In-Process Inventory

• This is the amount of work waiting to be processed because there


is a shortage of some resource

• Similar to WIP in manufacturing

• Holding cost is incurred

49

49

50

50

Due 29 August 2022

Using the WBS of assignment 3, complete the following activities:


• Create a Gantt chart using Microsoft Projects
• Determine the critical path
• Determine the duration of the project
• Perform a resource allocation for each activity
• Calculate the overall cost of the project
• Create a budget for the project

51

51

17

You might also like