Remedies For Breach of Contract
Remedies For Breach of Contract
Remedies For Breach of Contract
1. DAMAGES
CHAIN OF CAUSATION
In an action for damages, the plaintiff must establish that the defendant’s
breach occasioned the loss incurred by him, or the injury he suffered. The
requirement of causation may be either factual or legal causation. Factual
causation requires the application of the ‘but for’ test that is, but for the
breach of contract, the plaintiff would not have suffered the loss. Legal
causation on the other hand requires the breach to be the direct cause of the
plaintiff’s loss. Thus, where there are other intervening actions or events
between the time of breach and the time of loss so much that the
defendant’s breach cannot be regarded as the cause of the loss suffered, an
action for damages may fail. Such intervening actions which may break the
chain of causation may be that of the plaintiff or a third party. The action or
omission of the plaintiff may break the chain of causation where it was so
unreasonable that the defendant ought to be relieved of all liabilities. The
action of a third party may break the chain of causation where the plaintiff
had a duty to prevent the action. Where the intervening act was however
reasonably foreseeable by the defendant, he may remain liable for damages
to the plaintiff.
In BEOCO LTD. v. ALFA LAWAL CO. LTD. [1994] 4 ALL ER 464, the first
defendant installed a heat exchanger at an oil refinery. After installation, a
crack was discovered which resulted in a leak. The second defendant was
employed to repair the crack but the repair was only partially successful.
Despite this, the plaintiff put the equipment back into use and two months
later, it exploded causing extensive damage. The first defendant was found
guilty of breach of warranty, while the second defendant was found guilty of
breach of the contract to repair the cracks. The Court however held that the
cause of the explosion resulting in the extensive damage was the
recklessness of the plaintiff to carry out proper tests before putting the
machinery to use. Thus, the plaintiff cannot recover damages in respect of
the loss of profit suffered as a result of the extensive damage from the
explosion because it was not directly caused by the breach of contract. In
STANSBIE v. TROMAN [1948] 2 KB 48, a contractor contracted to decorate a
house leaves the front door opened and the house was burgled. The
contractor was held to remain liable for damages to the owner for failure to
take reasonable care.
The rule of remoteness broadly requires the plaintiff to establish that the
damage alleged was of a kind which was reasonably foreseeable by the
defendant. It aims to set a limit on the extent of the loss or injury for which
the defendant may be held liable. This was given detailed consideration in
KOUFOS v. CZARNIKOW LTD. [1969] 1 AC 350, where the respondents
chartered the appellant’s ship to take a consignment of the respondent’s
sugar from Constanza to Basrah. The ship arrived Basrah nine days later
than it ought to have arrived due to some deviations made by the appellant
in breach of the contract. The respondent had intended to sell the sugar
promptly on arrival at Basrah but the appellant was unaware although aware
that there was a sugar market in Basrah. Shortly before the respondent
could sell the consignment, the price of sugar fell resulting in a loss to the
respondent. The respondent then brought an action in damages to recover
the difference in price. The appellant admitted liability to pay damages for
the delay period of nine days but argued that the fall in market value should
not be taken into account in assessing the damages. The Court held that the
loss due to the fall in market price was not too remote to be recoverable as
damages. Although the appellant was not told that the sugar was to be sold
immediately on arrival at Basrah, he knew there was a market for sugar at
Basrah. As such, he should have reasonably contemplated that it was likely
that the sugar would be sold in the market at market price on arrival, and he
should ordinarily have known that market prices are prone to fluctuation.
After the determination of the nature and extent of damages, the Court is
usually faced with quantifying the damages in monetary terms. The
principles applicable to the assessment or quantum of damages for breach of
contract were explained in IJEBU-ODE LG v. ADEDEJI BALOGUN & CO. [1991]
1 NWLR (PT. 166)136, where the Court stated that assessment of damages
for breach is calculated based on the loss sustained by the innocent party,
which loss was either in contemplation of the parties at the time of the
contract, or is an unavoidable consequence of the breach. In this case, the
appellant council awarded a contract to the respondent company for the
construction of a market. The contract was wrongly terminated and the
respondent brought an action for damages. It was established that the
respondent would have realized profits of 20% or more from the contract
sum. The Court held that 20% of the contract sum was the loss sustained as
a consequence of the breach and this must have been in the contemplation
of the parties at the time of the contract. Thus, 20% of the contract sum was
the amount of damages the respondent was entitled to as this is the amount
that would put him in the position he would have been if there had been no
breach of the contract.
MITIGATION OF DAMAGES