SP 05
SP 05
SP 05
APPROVAL LOG
DATE SIGNATURE
DISTRIBUTION
COPY NO. OWNER/LOCATION
1 Safety Procedure Manual
UNCONTROLLED COPY
KANKAKEE POLYMER PLANT SAFETY PROCEDURE
REVISION LOG
DATE DESCRIPTION OF CHANGE
3/10/92 Original Issue
10/7/93 Revision - General Review
2/24/95 Revision - Put into ISO format
8/3/95 Revision - General Review
9/10/96 Revision - Included welding shield requirements in Section 3.11 d.
04/03/98 Revision- Added welding U/V Guidelines
6/29/99 Revision – Annual Review (clarified specific barrier tape usage)
3/1/00 Revision- Annual Review and revised plant job titles and responsibilities per
plant re-organization
3/10/00 Revision- added requirements necessary for Hot Work performed in
Confined Spaces [Section 3.11(i)]
9/07/00 Revision- Added “Records Generated’ Section
4/20/01 Revision - Annual Review - No updates req’d
5/9/01 Revision - Updated responsibilities due to plant reorganization. EHS
Coordinator will be the primary contact for the safety approval on permit.
7/9/02 Revision – Annual Review (including permit process and interviews), No
updates Required.
2/17/03 Revision – Added conditions when a Hot Work Permit must be voided
3/21/03 Revision – Annual Review Updated the isolation requirements for non-
hazardous material piping. Revised the approval process to allow the
Operation Coordinator to be the primary permit authorizer.
6/15/04 Revision – Annual Hot Work Permit Procedure Review – No Changes
Req’d
UNCONTROLLED COPY
KANKAKEE POLYMER PLANT SAFETY PROCEDURE
REVISION LOG
DATE DESCRIPTION OF CHANGE
9/16/05 Revision – Annual Hot Work Permit procedure Review –
2/24/06 Revision— Misc. changes to procedure and permit, changed Operation
Coordinator to Permit Writer. Added additional information to scope
about electrical enclosures, concrete/asphalt cutting and monomer
unloading. Revised atmosphere check under permit Writer
responsibilities.
UNCONTROLLED COPY
KANKAKEE POLYMER PLANT SAFETY PROCEDURE
1.0 PURPOSE
To prevent fires, explosions, or the generation of toxic materials during hot work.
2.0 SCOPE
This standard covers all hot work activities in the process building, monomer tank
farm, and all plant sumps, trenches, and catch basins where flammable or
combustible materials may be present. Hot Work for the purpose of this standard is
defined as any open flame, welding arc, mechanical or electrical device that is
capable of igniting a flammable environment. Any electrical equipment used in the
plant will be deemed capable of igniting a flammable environment unless it has been
approved by a national testing laboratory (Underwriters Laboratory, Factory Mutual,
etc.) for use in a hazardous environment.
A Hot Work Permit is required in all areas within the plant (excluding the
maintenance shop and contractor’s parking lot and as described by this procedure)
where welding, brazing, metal cutting or grinding, or any other similar activity is done
with intense heat or open flames. In addition, any electrical equipment (excluding
explosion-proof rated equipment) used in classified areas will need a Hot Work
Permit as defined by this standard.
A Hot Work Permit is required for opening electrical enclosures in classified areas
with the exception of those enclosures which are intrinsically safe.
All concrete cutting will require a hot work permit due to the possibility of cutting re-
enforcement metal embedded in the concrete.
During periods of monomer unloading no Hot Work Permit will be issued in the
unloading or storage areas.
A copy of the Hot Work Permit is attached to the controlled copy of this procedure in
the Safety Procedure Manual.
3.3 Procedure guidelines for hot work performed in the Contractor’s parking lot
UNCONTROLLED COPY
KANKAKEE POLYMER PLANT SAFETY PROCEDURE
4.0 STANDARD
4.1 No hot work will be performed in the plant without following all of the
requirements of this section. The following approvals will be required prior
to beginning the hot work:
Maintenance/
Contractors: Maintenance Technician performing the work will sign
the Hot Work Permit. If a contractor performs the hot
work, the contractor is responsible for providing this
signature approval.
UNCONTROLLED COPY
KANKAKEE POLYMER PLANT SAFETY PROCEDURE
need arises.
4.3 The need for a Hot Work Permit will be identified on the Safe Work Permit
form. The Permit Writer will originate the Hot Work Permit and perform all
atmospheric monitoring required prior to performing the hot work.
Readings will be taken at enough locations to be representative of the
entire work area. The Plant’s Hot Work Permit form will be used for all hot
work done at the Kankakee Polymer Plant. The Hot work Permit will be
completely filled out, any items not applicable will be marked N/A.
4.5 The Permit Writer is responsible for recording the expiration time at the end
of the Hot Work or when the Hot Work Permit expires (due to the shift
schedule or a predetermined expiration). Prior to this permit expiration, a
thorough inspection of the work area must be made to ensure it is left in a
safe condition.
4.6 One Hot Work Permit will be issued to cover all activities associated with
one task involving hot work.
Note: The Job Description Board is used to list all Hot Work
Permits that are currently active. Operation Technicians
working in the Control Room are expected to review this
board prior to the beginning of their work shift and
periodically throughout the shift. It will be immediately
updated as Hot Work Permit are initiated and completed.
After the Hot Work Permit is complete and the permit sign-
off in place, both the White and Hard Copies will be
forwarded to the EHS Department for storage.
Hard Copy: Posted at the job-site until the hot work is complete.
4.8 Before beginning any hot work, all involved individuals shall:
4.8.1 Determine that a valid Hot Work Permit has been posted at the job-
site.
4.8.2 Review and comply with the permit safeguards and protective
equipment requirements.
4.9 Anyone performing hot work (requiring a permit) must have a fully executed
Safe Work Permit prior to beginning the work. This includes all contractors,
inspectors, supervisors, operations personnel, and maintenance personnel.
4.10 No Hot Work Permit will be valid for more than one shift. If the work is to
occur over more than one shift, then a new permit must be issued at the
start of the new shift.
4.11 The Hot Work Permit becomes void under the following conditions:
If the fire/emergency alarm sounds
At a given time specified on the Hot Work Permit
At the end of the shift on which it is issued
If the work does not commence within two hours or if work ceases for
over one hour
UNCONTROLLED COPY
KANKAKEE POLYMER PLANT SAFETY PROCEDURE
a. Preparing the hot work area and equipment for work. This
preparation may include steaming lines, inspections of pump
seals and flanges (etc.), and ensuring that all affected vessels
and lines have been blinded and cleared.
e. Check the work area after the hot work has been completed to
insure that everything has been left in a safe condition.
4.12.2 The Permit Writer has the following responsibilities after Operations
has prepared the work area:
a. Verifying that the equipment and area are properly prepared for
hot work.
f. Upon completion of the testing, fill out the Hot Work Permit and
communicate the requirements to all personnel involved in the
hot work.
a. Verifying that the equipment and area are properly prepared for hot
work.
f. Notifying the Permit Writer of the need for a Hot Work Permit.
g. Providing the safeguards noted on the Hot Work Permit such as fire
watch, fire extinguisher, sealed sewers, etc.
4.13 Before the Hot Work Permit is issued, the area must be prepared as follows
(Responsibility for performing these tasks is with the individual performing
the hot work unless noted otherwise):
e. A Fire Watch must be assigned to the job when there are open flames,
welding, or cutting involved. The Permit Writer will determine if a Fire
Watch is needed for all other Hot Work on a case-by-case basis. The
Fire Watch (if necessary) must be provided with a 20 pound dry
chemical ABC fire extinguisher as a minimum. Note that the Permit
Writer does have the ability to specify an alternative type of unit should it
be appropriate for the work (for example a portable Halon unit may be
appropriate for an electrical closet).
ii. The Fire Watch will not leave the immediate area when the hot
work is in progress. The Fire Watch can play an active part in the
UNCONTROLLED COPY
KANKAKEE POLYMER PLANT SAFETY PROCEDURE
work, but must stop all other activities when the ignition source is
actually initiated.
iii. The Fire Watch must be able to summons outside assistance at all
times during the hot work. This can be accomplished by the use of
plant radios, air horns, or voice/hand signals. They will be expected
to immediately summons outside assistance should a fire occur.
They will be expected to immediately notify the Operations
Supervisor should a fire occur which they have extinguished.
i. Hot Work in a confined space will require, not only a Hot Work Permit; it
will also require a Safe Work Permit and Confined Space Entry Permit.
The following special requirements apply to all welding, cutting and
grinding in permit required confined spaces:
UNCONTROLLED COPY
KANKAKEE POLYMER PLANT SAFETY PROCEDURE
4.14 The work area must be maintained in a safe condition. The following
conditions must be adhered to:
4.15 The following activities must be done at the end of the hot work project:
a. The individual performing the hot work must make a final check of the
area to ensure that everything has been left in a safe condition.
b. The Fire Watch must remain in the area for at least thirty minutes
(unless otherwise specified on the Hot Work Permit) after the completion
of the work when welding, brazing, or other similar activity involving an
open flame or intense heat has been performed. Certain situations may
require longer attendance, so the 30 minutes should be viewed as a
minimum.
c. The Permit Writer will inspect the hot work area before returning the
area back to service.
pulled through conduits, but can not be sealed in the conduit at the
completion of the work). In such instances, either of two actions may be
taken:
A new Hot Work would be issued to continued the work during the next
shift, or
The opening where wiring is exposed must be sealed with materials
necessary to prevent flammable gas to penetrate the electrical system
(i.e. duct tape, plastic, and if necessary oakum to seal the opening)
d. The Permit Writer must immediately sign-off the permit identifying the
time the work was completed. This sign-off will be completed prior to the
equipment being put back into service.
4.16 A Lock-out/Tag-out and Isolation Form must be prepared for all hot work
that requires isolation and/or blinding. This list must include the type,
location, service, and number of blinds installed for the hot work. The
minimum blinding requirements are as follows:
UNCONTROLLED COPY
KANKAKEE POLYMER PLANT SAFETY PROCEDURE
4.16.2 Only Utility water, boiler feed water, deionized water, fire water,
steam condensate, potable water, steam, air, and finish product
lines may be isolated using a double block and bleed valve. The
Bleed valve must be located between the double block and verified
to be open. The bleeder must also be locked in the open position.
4.16.3 Where installed, blinds shall be located at the flange closest to the
vessel or the section of piping where the hot work will be performed.
A variance from the EHS Department must be obtained if the blind is
to be located elsewhere, or if no flanges exist.
4.17 The EHS Manager (or their designee) will perform an annual review of the
Hot Work Permit Procedure, including a sampling of permit forms and a
field observation of a permit in progress. Input will be solicited from permit
writers and affected individuals as necessary to ensure that the process is
effective and functional. Any required corrections or improvements will be
added to the procedure and appropriate training provided.
UNCONTROLLED COPY
APPENDIX I
Manual
Metal Arc - 100-200 33 133 230
TIG Argon 50 3 13 23
150 10 40 65
300 17 76 131
Plasma Arc
Welding Plant Air 100-275 18 76 131
Plasma Arc
Cutting
(dry) Plant Air 400-1000 26 104 180
Plasma Arc
Cutting (w/
water
injection) Nitrogen 300 36 143 246
750 18 76 131
UNCONTROLLED COPY