HAZOP
HAZOP
HAZOP
Search for:
Piping Design & Layout
Piping Stress Analysis
o Piping Stress Basics
o Caesar II
o Start-Prof
Piping Interface
o Mechanical
o Process
o Instrumentation
o Pipeline
o Civil
Piping Materials
Piping Design Softwares
o PDMS
o E3D
o SP3D
Jobs
Table of Contents
What is HAZOP?
HAZOP Mechanism
Advantages of HAZOP
Key Documents required for HAZOP
HAZOP Team Composition
HAZOP Timings
Application of HAZOP Analysis
What is HAZOP?
The full form of HAZOP is a Hazard and Operability Study. This is a comprehensive
multi-disciplinary team exercise to critical review (Study) the piping design (Layout/
Routing/Placement of branches/inline instrumentation items/equipment, etc.) with respect
to Hazardous and Operational considerations and requirements.
The HAZOP technique was initially developed to analyze chemical process systems but has later
been extended to other types of systems and also to complex operations and to software systems.
No or not
Other than
More
Early
Less
Late
As well as
Before
Part of
After
Reverse (of intent)
Others can be crafted as needed
HAZOP Mechanism
HAZOP is now a mandatory activity. It is a qualitative, experience intensive exercise as of now.
It is in the form of deviation analysis. After the process design, the steady-state specifications of
each stream in the flowsheet are known.
The HAZOP team exhaustively asks itself questions as to what will happen if this specification
deviated on the positive or negative side of the expected steady-state value. It debates the
possible causes and consequences of each such eventuality. Anything which appears to them as
likely to lead to hazardous situations is debated further and possible means of avoiding the same
or raising alarm if it happens so that remedial action can be taken etc. are recommended. This
may lead to the recommendation of additional instrumentation on lines and equipment, Hi-Lo
alarms and trips, etc. may be required to be provided.
The idea of HAZOP is to foresee a hazardous situation and take measures and abundant
precaution to avoid them and increase process safety.
Hazop is a structured analysis, conducted after the design review, to ensure the design is suitable
for all the intended operating conditions and complies with the HSE requirements. This process
is also to ensure that the fundamentals of the design are thoroughly explained, understood, and
examined.
1. Definition Phase
2. Preparation Phase
3. Examination and
4. Documentation and follow-up phase.
Important characteristics of all four HAZOP phases are provided in the image below.
HAZOP Phases
The examination phase is the most important HAZOP phase among the four phases. A typical
flowchart of HAZOP Examination phase is provided below:
HAZOP Examination phase flow-chart
Advantages of HAZOP
The benefit of the HAZOP is that early identification and assessment of the critical hazards
provide essential input to project development decisions. This leads to a safer and more cost-
effective design with a minimum cost of change penalty. Other benefits of HAZOP are
Chairman (independent)
Lead engineers from Process, Instrumentation & Control (both from Design team and
Client/ End-user)
Operations engineer (from Client/ End-user)
Lead engineers from Mechanical/Piping, Pipeline, HSE, and Electrical as required. (Both
from Design team and Client/ End-user)
The following image shows a typical team composition for HAZOP Analysis.
Typical HAZOP Team
HAZOP Timings
The HAZOP study should preferably be carried out as early in the design phase as possible to
have an influence on the design. On the other hand; to carry out a HAZOP we need a rather
complete design. As a compromise, the HAZOP is usually carried out as a final check when the
detailed design has been completed.
A HAZOP study may also be conducted on an existing facility to identify modifications that
should be implemented to reduce risk and operability problems.
Typically HAZOP in EPC design companies is performed 3 to 4 weeks after the Design review
meeting, once the design review points are incorporated in the key documents.
Chemical,
Petro-chemical
Pharmaceutical
Refinery
Food
Oil and gas
Nuclear
Fertilizer
Power plants