ID Task Task Name Duration % Complete Start Finish Predecessors Half 2, 2023 Half 1, 2024
Mode J S N J M M J
1 TSF Stage 2 111 days 74% Mon 23/10/23 Mon 25/03/24
2 Contract Award 0 days 100% Mon 23/10/23 Mon 23/10/23 23/10
3 Sign Of contract 20 days 100% Mon 23/10/23 Fri 17/11/23 2
4 Start of activities 0 days 100% Fri 27/10/23 Fri 27/10/23 27/10
5 FINISH BY ROX 101 days 100% Fri 27/10/23 Fri 15/03/24 4
6 TSF Stage 2 Construction 107 days 65% Fri 27/10/23 Mon 25/03/24
7 Bush Clearing & Tree Removal 9 days 100% Fri 27/10/23 Wed 08/11/23 4
8 Removal of Topsoil 7 days 100% Thu 09/11/23 Fri 17/11/23 7
9 Levelling Valleys 14 days 100% Mon 20/11/23 Thu 07/12/23 8
10 Waste dump preparation 7 days 100% Fri 27/10/23 Mon 06/11/23 4
11 Borrow Pit Preparation 7 days 100% Fri 27/10/23 Mon 06/11/23 4
12 Diversion Channel (tsf) 10 days 100% Tue 07/11/23 Mon 20/11/23 11
13 EAST WALL 20 days 93% Mon 13/11/23 Fri 08/12/23
14 Cut & Fill 16 days 100% Mon 13/11/23 Mon 04/12/23
15 Filling of Emergency Spillway 7 days 100% Fri 24/11/23 Mon 04/12/23 14FF
16 Batter preparation 2 days 100% Tue 05/12/23 Wed 06/12/23 14
17 Safety Bund 2 days 0% Thu 07/12/23 Fri 08/12/23 16
18 Completion 0 days 0% Fri 08/12/23 Fri 08/12/23 08/12
19 South-East Basin 28 days 99% Wed 15/11/23 Fri 22/12/23
20 Cut & Fill 28 days 100% Wed 15/11/23 Fri 22/12/23 14SS+2 days
21 Completion 0 days 0% Fri 22/12/23 Fri 22/12/23 22/12
22 North Wall 32 days 93% Tue 05/12/23 Wed 17/01/24
23 Cut & Fill 25 days 100% Tue 05/12/23 Mon 08/01/24 14
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: TSF Stage 2 - Seguela - Pro
Date: Sat 02/03/24 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 1
ID Task Task Name Duration % Complete Start Finish Predecessors Half 2, 2023 Half 1, 2024
Mode J S N J M M J
24 Batter preparation 5 days 95% Tue 09/01/24 Mon 15/01/24 23
25 Safety Bund 2 days 0% Tue 16/01/24 Wed 17/01/24 24
26 Completion 0 days 0% Wed 17/01/24 Wed 17/01/24 17/01
27 West Wall 46 days 77% Mon 25/12/23 Mon 26/02/24
28 Relocation Of TDRT 7 days 100% Mon 25/12/23 Tue 02/01/24 20
29 Cut & Fill 28 days 82% Wed 03/01/24 Fri 09/02/24 28
30 Batter preparation 7 days 75% Mon 12/02/24 Tue 20/02/24 29
31 Safety Bund 4 days 0% Wed 21/02/24 Mon 26/02/24 30
32 Completion 0 days 0% Mon 26/02/24 Mon 26/02/24 26/02
33 Decant Tower 1&2 36 days 60% Mon 27/11/23 Mon 15/01/24
34 Precast 20 days 100% Mon 27/11/23 Fri 22/12/23
35 Installation 10 days 30% Tue 02/01/24 Mon 15/01/24 20FS+6 days
36 Rockfill 10 days 10% Tue 02/01/24 Mon 15/01/24 35SS
37 Lining Prep Works 57 days 34% Fri 05/01/24 Mon 25/03/24
38 AnChor Trench 46 days 30% Thu 11/01/24 Thu 14/03/24 40FF
39 Final Wearing Course Basin 50 days 50% Fri 05/01/24 Thu 14/03/24 40FF
40 Lining Installation 46 days 25% Thu 11/01/24 Thu 14/03/24
41 Final Wearing Course Crest 7 days 0% Fri 15/03/24 Mon 25/03/24 40
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: TSF Stage 2 - Seguela - Pro
Date: Sat 02/03/24 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 2