SPM 04-1
SPM 04-1
Management
Lecture 07
Project Evaluation
[email protected]
SPM: Topics
• The Business case for a Project
• Project Portfolios
• Project Evaluation
• Programme Management
• Benefits Management
[email protected]
SPM – Business Case
• Objective is to provide a rationale for the project by showing that the
benefits of the project outcomes will exceed the costs of
development, implementation and operation
• Need to account for business risks
[email protected]
SPM – Business Case - Contents
1. Introduction/ background
• Description of the problem to be solved or the opportunity to be tapped in
2. The proposed project
• Describes the scope of the project briefly
3. The market
• In case of new product or service, estimates the demand and likely
competition
4. Organizational and operational infrastructure
• How the organization could impact or potentially would change or need to
change
[email protected]
SPM – Business Case - Contents
5. The Benefits
• Financial benefits, profits, savings. Operational efficiencies.
6. Outline Implementation Plan
• Execution plan
7. Costs
• Cost of execution, schedule of payments, unexpected costs
8. The financial case
• Evaluate the cost and benefits
9. Risks
• Risks associated with estimates
[email protected]
SPM – Project Portfolio Management
Portfolio project management provides an overview of all the projects
that an organization is undertaking or is considering
3 key parts
1. Portfolio Definition
2. Portfolio Management
3. Portfolio Optimization
[email protected]
SPM – Project Portfolio Management
1. Project portfolio definition
• Create a central record of all projects within an organization
• Must decide whether to have ALL projects in the repository or, say, only ICT
projects
• Note difference between new product development (NPD) projects and
renewal projects e.g. for process improvement
[email protected]
SPM – Project Portfolio Management
2. Project portfolio management
• Actual costing and performance of projects can be recorded and assessed
[email protected]
SPM – Project Portfolio Management
The concerns of project portfolio management include:
• Assessing the risk involved with projects
• Deciding how to share resources between projects
• Challenge of what projects to include
[email protected]
SPM – Cost Evaluation
• Technical Evaluation
• Cost-Benefit Analysis
• Financial Forecasting
[email protected]
SPM – Cost Benefit Analysis (CBA)
This relates to an individual project. You need to:
• Identify all the costs which could be:
• Development costs
• Set-up
• Operational costs
• Identify the value of benefits
• Check benefits are greater than costs
[email protected]
SPM – CBA – Net Profit
Year Cash-flow
• ‘Year 0’ represents all the
costs before system is 0 -100,000
operation
1 10,000
4 20,000
• Net profit value of all the
cash-flows for the lifetime of 5 100,000
the application
Net profit 50,000
[email protected]
SPM – CBA – Net Profit
[email protected]
SPM – CBA – Payback Period
This is the time it takes to start generating a surplus of income over
outgoings.
Year Cash-flow Accumulated(recover)
0 -100,000 -100,000
1 10,000 -90,000
2 10,000 -80,000
3 10,000 -70,000
4 20,000 -50,000
5 100,000 50,000
[email protected]
SPM – CBA – Payback Period
• The payback period would be about 4.5 years. This can be calculated
as the last year in which the accumulated cash flow was negative +
(absolute accumulated cash flow at the end of that year / cash-flow
for the next year) e.g. year 4 + (50,000/100,000). This assumes that
the flow of cash is constant throughout the year in question e.g.
£100,000/12 or £8,333 a month in year 5
[email protected]
SPM – CBA – Return on Investment (ROI)
A way of comparing the net profitability to the investment required
[email protected]
SPM – CBA –NPV – Discount Factor
Discount factor = 1/(1+r)t
r is the interest rate (e.g. 10% is 0.10)
t is the number of years
In the case of 10% rate and one year
Discount factor = 1/(1+0.10) = 0.9091
In the case of 10% rate and two years
Discount factor = 1/(1.10 x 1.10) =0.8294
[email protected]
SPM – CBA –NPV – Applying Discount Factor
Year Cash-flow Discount factor Discounted cash flow
NPV 618
[email protected]
SPM – CBA –Internal Rate of Return (IRR)
• Internal rate of return (IRR) is the discount rate that would produce
an NPV of 0 for the project
• Can be used to compare different investment opportunities ( bank,
gold, mutual fund etc)
• There is a Microsoft Excel function which can be used to calculate
[email protected]
SPM – Risk Evaluation
• Project A might appear to give a better return than B but could be
riskier
• Could draw up draw a project risk matrix for each project to assess
risks – see next overhead
• For riskier projects could use higher discount rates
[email protected]
SPM – Risk Evaluation
[email protected]
SPM – Decision Trees
[email protected]
SPM – Programme Management
• D. C. Ferns defi ned a programme as
‘a group of projects that are managed in a coordinated way to gain benefits
that would not be possible were the projects to be managed independently’.
[email protected]
SPM – Programme Management
1. Strategic
Several projects together implement a single strategy. For example,
merging two organizations will involve many different activities e.g. physical
re-organization of offices, redesigning the corporate image, merging ICT
systems etc. Each of these activities could be project within an overarching
programme.
2. Business cycle programmes
A portfolio of project that are to take place within a certain time frame e.g.
the next financial year
3. Infrastructure programmes
In an organization there may be many different ICT-based applications which
share the same hardware/software infrastructure
[email protected]
SPM – Programme Management
4. Research and development programmes
In a very innovative environment where new products are being
developed, a range of products could be developed some of which are
very speculative and high-risk but potentially very profitable and some
will have a lower risk but will return a lower profit. Getting the right
balance would be key to the organization’s long term success
5. Innovative partnerships
“pre-competitive co-operation” to develop new technologies that could
be exploited by a whole range of companies
[email protected]
SPM – Programme Manager vs Project
Manager
Programme manager Project manager
• Many simultaneous projects • One project at a time
[email protected]
SPM – Benefits Management
To carry this out, you must:
• Define expected benefits
• Analyse balance between costs and benefits
• Plan how benefits will be achieved
• Allocate responsibilities for their achievement
• Monitor achievement of benefits
[email protected]
SPM – Benefits Management
These might include:
• Mandatory requirement
• Improved quality of service
• Increased productivity
• More motivated workforce
• Internal management benefits
better decision-making
[email protected]
SPM – Benefits Management
• Risk Reduction
• Economies
• Cost Cutting
• Revenue Enhancement
• Strategic fit (according to plan)
• Benefits can be:
• Quantified & Valued
• Quantified but not valued e.g. a decrease in customer complaints by x%
• Identified but not easily Quantified
[email protected]
Reference
• Software Project Management 5th Edition by Mike Cotterell, Bob
Hughes, Rajib Mall
• Project Evaluation and Programme Management - Chapter 2