Detailed Unit Price Analysis For Construction Works
Detailed Unit Price Analysis For Construction Works
Detailed Unit Price Analysis For Construction Works
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. EQUIPMENT
Bored Pile Machine,1500mm di-crwlr type,300 hp hr 1.00 1.00 1.00 9,477.75 9,477.75
Loader,Wheel Type, Komatsu,1.80 cu.m/123 hp hr 0.50 1.00 0.50 2,550.00 1,275.00
Dump Truck, All Models, 11.5 cu.m. capacity, 290 HP hr 1.00 1.00 1.00 1,750.32 1,750.32
Ancillary Equipment (20% of above) 2,500.61
TOTAL A 15,003.68
B. LABOR
Foreman hr 1 1 1 206.69 206.69
Laborer hr 2 1 2 94.62 189.24
TOTAL B 395.93
TOTAL A + B 15,399.61
TOTAL D -
E. ESTIMATED DIRECT COST P/l.m 15,399.61
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. EQUIPMENT
Crane, Crawler Standard Boom,91-100 mt. tons/290 hr 1.00 1.00 1.00 5,360.00 5,360.00
hp
TOTAL A 6,432.00
B. LABOR
Foreman hr 1 1 1 206.69 206.69
Skilled Labor hr 16 1 16 141.87 2,269.90
Laborer hr 16 1 16 94.62 1,513.87
TOTAL B 3,990.46
TOTAL A + B 10,422.46
PM6 Reinforcing Steel bar, Grade 60 (Cut and Bend including Splicing) kg 654.18 80.93 52,941.94
TOTAL D 55,589.03
E. ESTIMATED DIRECT COST P/l.m 60,800.26
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. EQUIPMENT
TOTAL A 11,614.74
B. LABOR
Foreman hr 1 1 1 206.69 206.69
Skilled Labor hr 2 1 2 141.87 283.74
Laborer hr 4 1 4 94.62 378.47
TOTAL B 868.90
TOTAL A + B 12,483.64
TOTAL D 2,861.27
E. ESTIMATED DIRECT COST P/l.m 9,103.09
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 0.5 0.5 206.69 103.35
L19 Laborer hr 1 1 1 94.62 94.62
TOTAL A 197.96
B. EQUIPMENT
TOTAL B 19.80
TOTAL A + B 217.76
TOTAL D 105.00
E. ESTIMATED DIRECT COST P/set 322.76
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. EQUIPMENT
E325 Water Pump, 100mm suction dia. hr 1.00 1.00 1.00 271.58 271.58
E326 Concrete Vibrator, Flexible Shaft Type 2" Head Dia. hr 4.00 1.00 4.00 93.08 372.32
TOTAL A 772.68
B. LABOR
L13 Foreman hr 1 1 1 206.69 206.69
L19 Skilled Labor hr 2 1 2 141.87 283.74
L20 Laborer hr 4 1 4 94.62 378.47
TOTAL B 868.90
TOTAL A + B 1,641.58
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 4 1 4 141.87 567.48
L19 Laborer hr 8 1 8 94.62 756.93
TOTAL A 1,531.10
B. EQUIPMENT
Crawler Crane, All Models, 36-40
E014 hr 1 1 1 1,940.04 1,940.04
MT, 190HP
Vibro Hammer, DPD600T
E029 Hydraulic Pile Driver, 60 ton hr 1 1 1 2,165.46 2,165.46
capacity, 201HP
E065 Generator Set, 250 kW hr 1 1 1 847.38 847.38
Welding Machine, Gas/ Diesel
E069 hr 1 1 1 549.78 549.78
Driven, 70HP
E086 Cutting Outfit hr 1 1 1 46.36 46.36
Minor Tools, (10% of Labor) 153.11
TOTAL B 5,702.12
TOTAL A + B 7,233.23
TOTAL D 4,327.48
E. ESTIMATED DIRECT COST P/sqm 4,448.03
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L05 Asst. Foreman/Leadman hr 1 1 1 188.55 188.55
L17 Skilled Laborer hr 2 1 2 141.87 283.74
L19 Laborer hr 4 1 4 94.62 378.47
TOTAL A 850.75
B. EQUIPMENT
Backhoe, R180LC-9S, 0.76
E025 hr 1 1 1 4,603.26 4,603.26
m3/1.05 yd3 capacity, 126HP
Dump Truck, All Models, 9.0 cu.m.
E042 hr 2 1 2 1,448.40 2,896.80
capacity, 290 HP
Payloader, HL730-7A, 1.80 cu.m. /
E003 hr 1 1 1 2,516.34 2,516.34
2.40 yd3 capacity, 125HP
TOTAL B 10,058.94
TOTAL A + B 10,909.69
TOTAL D 450.00
E. ESTIMATED DIRECT COST P/sqm 886.39
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 4 1 4 141.87 567.48
L19 Laborer hr 8 1 8 94.62 756.93
TOTAL A 1,531.10
B. EQUIPMENT
E073 Bar Cutter, 25 mm, Single Phase hr 1 0.5 1 224.15 112.07
E076 Bar Bender, 25 mm, Single Phase hr 1 0.5 1 358.53 179.27
Cargo/ Service Truck, All Models,
E047 hr 1 0.15 0 1,236.24 185.44
9-10 MT capacity, 270HP
TOTAL B 629.88
TOTAL A + B 2,160.99
TOTAL D 53.37
E. ESTIMATED DIRECT COST P/kg 65.37
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 4 1 4 141.87 567.48
L19 Laborer hr 8 1 8 94.62 756.93
TOTAL A 1,531.10
B. EQUIPMENT
E073 Bar Cutter, 25 mm, Single Phase hr 1 0.5 1 224.15 112.07
E076 Bar Bender, 25 mm, Single Phase hr 1 0.5 1 358.53 179.27
Cargo/ Service Truck, All Models,
E047 hr 1 0.15 0 1,236.24 185.44
9-10 MT capacity, 270HP
TOTAL B 629.88
TOTAL A + B 2,160.99
TOTAL D 58.37
E. ESTIMATED DIRECT COST P/kg 70.37
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 1 1 1 141.87 141.87
L19 Laborer hr 1 1 1 94.62 94.62
TOTAL A 443.18
B. EQUIPMENT
TOTAL B 44.32
TOTAL A + B 487.50
TOTAL D 285.60
E. ESTIMATED DIRECT COST P/sqm 383.10
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 0.5 0.5 206.69 103.35
L17 Skilled Laborer hr 1 1 1 141.87 141.87
L19 Laborer hr 1 1 1 94.62 94.62
TOTAL A 339.83
B. EQUIPMENT
TOTAL B 33.98
TOTAL A + B 373.82
TOTAL D 367.50
E. ESTIMATED DIRECT COST P/sqm 442.26
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 2 1 2 141.87 283.74
L19 Laborer hr 6 1 6 94.62 567.70
TOTAL A 1,058.13
B. EQUIPMENT
Concrete Vibrator, Flexible Shaft
E071 hr 2 1 2 93.08 186.15
Type 2" Head Dia.
E061 Pumpcrete, Trailer Mounted hr 1 0.3 0 5,072.46 1,521.74
TOTAL B 1,813.70
TOTAL A + B 2,871.83
READY MIX CONCRETE 4000PSI (28Mpa) @ 14 DAYS cum 1.05 7,850.00 8,242.50
TOTAL D 9,314.03
E. ESTIMATED DIRECT COST P/cum 10,126.65
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 2 1 2 141.87 283.74
L19 Laborer hr 6 1 6 94.62 567.70
TOTAL A 1,058.13
B. EQUIPMENT
Concrete Vibrator, Flexible Shaft
E071 hr 2 1 2 93.08 186.15
Type 2" Head Dia.
E061 Pumpcrete, Trailer Mounted hr 1 0.3 0 5,072.46 1,521.74
TOTAL B 1,813.70
TOTAL A + B 2,871.83
READY MIX CONCRETE 4000PSI (28Mpa) @ 14 DAYS cum 1.05 7,850.00 8,242.50
TOTAL D 9,396.45
E. ESTIMATED DIRECT COST P/cum 10,209.08
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 2 1 2 141.87 283.74
L19 Laborer hr 6 1 6 94.62 567.70
TOTAL A 1,058.13
B. EQUIPMENT
Concrete Vibrator, Flexible Shaft
E071 hr 2 1 2 93.08 186.15
Type 2" Head Dia.
E061 Pumpcrete, Trailer Mounted hr 1 0.3 0 5,072.46 1,521.74
TOTAL B 1,813.70
TOTAL A + B 2,871.83
READY MIX CONCRETE 4000PSI (28Mpa) @ 14 DAYS cum 1.05 7,850.00 8,242.50
TOTAL D 9,891.00
E. ESTIMATED DIRECT COST P/cum 10,663.00
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 1 1 1 141.87 141.87
L19 Laborer hr 3 1 3 94.62 283.85
TOTAL A 632.41
B. EQUIPMENT
Concrete Vibrator, Flexible Shaft
E071 hr 2 1 2 93.08 186.15
Type 2" Head Dia.
E061 Pumpcrete, Trailer Mounted hr 1 0.3 0.3 5,072.46 1,521.74
TOTAL B 1,771.13
TOTAL A + B 2,403.54
READY MIX CONCRETE 5000PSI (35Mpa) @ 28 DAYS cum 1.05 7,850.00 8,242.50
TOTAL D 9,643.73
E. ESTIMATED DIRECT COST P/cum 10,451.37
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 1 1 1 141.87 141.87
L19 Laborer hr 3 1 3 94.62 283.85
TOTAL A 632.41
B. EQUIPMENT
Concrete Vibrator, Flexible Shaft
E071 hr 2 1 2 93.08 186.15
Type 2" Head Dia.
E061 Pumpcrete, Trailer Mounted hr 1 0.3 0.3 5,072.46 1,521.74
TOTAL B 1,771.13
TOTAL A + B 2,403.54
READY MIX CONCRETE 5000PSI (35Mpa) @ 28 DAYS cum 1.05 7,850.00 8,242.50
TOTAL D 10,303.13
E. ESTIMATED DIRECT COST P/cum 11,110.77
Hours
Ref. No. Price Component Unit Qty Total EH Hourly Rate Total (Pesos)
Used
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 2 1 2 141.87 283.74
L19 Laborer hr 6 1 6 94.62 567.70
TOTAL A 1,058.13
B. EQUIPMENT
Concrete Vibrator, Flexible Shaft
E071 hr 2 1 2 93.08 186.15
Type 2" Head Dia.
E061 Pumpcrete, Trailer Mounted hr 1 0.3 0 5,072.46 1,521.74
TOTAL B 1,813.70
TOTAL A + B 2,871.83
READY MIX CONCRETE 5000PSI (35Mpa) @ 28 DAYS cum 1.05 7,850.00 8,242.50
TOTAL D 9,066.75
E. ESTIMATED DIRECT COST P/cum 9,838.75
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 2 1 2 141.87 283.74
L19 Laborer hr 6 1 6 94.62 567.70
TOTAL A 1,058.13
B. EQUIPMENT
Concrete Vibrator, Flexible Shaft
E071 hr 2 1 2 93.08 186.15
Type 2" Head Dia.
E061 Pumpcrete, Trailer Mounted hr 1 0.3 0 5,072.46 1,521.74
TOTAL B 1,813.70
TOTAL A + B 2,871.83
READY MIX CONCRETE 3000PSI (21 Mpa) @ 28 DAYS cum 1.05 7,000.00 7,350.00
TOTAL D 8,268.75
E. ESTIMATED DIRECT COST P/cum 8,952.52
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 2 1 2 141.87 283.74
L19 Laborer hr 6 1 6 94.62 567.70
TOTAL A 1,058.13
B. EQUIPMENT
Concrete Vibrator, Flexible Shaft
E071 hr 2 1 2 93.08 186.15
Type 2" Head Dia.
E061 Pumpcrete, Trailer Mounted hr 1 0.3 0 5,072.46 1,521.74
TOTAL B 1,813.70
TOTAL A + B 2,871.83
READY MIX CONCRETE 3000PSI (21 Mpa) @ 28 DAYS cum 1.05 7,000.00 7,350.00
TOTAL D 8,305.50
E. ESTIMATED DIRECT COST P/cum 9,202.95
A. LABOR
L03 Construction Foreman hr 1 1 1 206.69 206.69
L17 Skilled Laborer hr 2 1 2 141.87 283.74
L19 Laborer hr 6 1 6 94.62 567.70
TOTAL A 1,058.13
B. EQUIPMENT
Concrete Vibrator, Flexible Shaft
E071 hr 2 1 2 93.08 186.15
Type 2" Head Dia.
E061 Pumpcrete, Trailer Mounted hr 1 0.3 0 5,072.46 1,521.74
TOTAL B 1,813.70
TOTAL A + B 2,871.83
READY MIX CONCRETE 3000PSI (21 Mpa) @ 28 DAYS cum 1.05 7,000.00 7,350.00
TOTAL D 8,452.50
E. ESTIMATED DIRECT COST P/cum 9,349.95