Revanta Option - 1

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

GORANA FACADE SOLUTION

72-73, Shiv Nager, Nr. Golden Motors, Bhatar Gandhi Kutir U.M. Road To 80ft. Bamroli Road
Pandesra, Surat, Gujarat-394221, Phone +91 98241 68203. +91 99099 91127
TO,
Revanta Date- 15-10-24
Surat Option - 01
Sub: Quotation for façade
Dear Sir,
With reference to the discussions we had your associates regarding the requirement of the erection of the façade at the
address as above, we are detailing you on the specifications and the rates of the same, and we hope the same is in accordance with your
requirements.

Sr.No. Particular Unit Qty Rate Amount


1 Aluminum Composite panel providing & fixing Sqft. 650 450 292,500.00
Specification
ACP Sheet 4mm thick (Metallic & Solid color only)
Foil thickness 0.50 mm both side
Framing aluminum pipe 50mm x 25mm x 1.50 Kg. /12feet
Hardware SDS PTA Screw
Brackets Aluminium & M.S.
Weather Silicon DC 789 / McCoy
Grid size 4’ X 4’
System Tray fitting
2 Structural Glazing for Curtain wall Providing & Fixing Sqft. 3500 850 2,975,000.00
Specification
Center Mullion 101mm X 56mm X 2mm (Weight 8.0kg/12Ft)
Transom Section 63mm X 56mm X 2mm (Weight 5.530kg/12Ft)
Clip & Cover 18mm X 56mm X 1.2mm (Weight 2.75kg/12Ft)
EPDM Osakha
Hardware SDS PTA screw
Brackets M.S. Hot dip Galvanized / Powder coating
Weather Silicon DC 688 / DC 789 / MacCoy
Coating Pawder coatting (Jotun/Akzonable) 60-80
micron
Glass 6mm Reflective toughened glass
2.1 Black Back Painted glass basic Rate Sqft. 1 250 250.00
3 Scafolding work Sqft. 1 20 20.00
Total 3,267,770.00

PAYMENT TERMS
1 50% advance along with order.
2 20% on receipt of aluminum materials.
3 20% on receipt of finish material.
4 10% within 10 days of completion.

TERMS & CONDITION


1 GST - 18% Extra .
2 Actual Measurement Will be on site
3 If any Change made in work done than Material & Labour change will be paid by owner.
4 This above Rate includes Scaffolding Charge.
5 MS & GI fabrication 140/- per Kg. Extra
If any glass openble window in glazing extra charge top hang 5000/- Rs. Per pcs. &
6 Parellel Window 10500/- per pcs extra.
7 Work will start only after receiving of purchase order & advance
8 Electricity and water supply will be in client scope.
9 Material storage space & labour accommodation provided by client.
10 This Quotation Valid 30 days.

Thanking you