LOR Precast Twinwall
LOR Precast Twinwall
LOR Precast Twinwall
Design guide
Foreword
This publication is intended to assist Structural The objective is to develop an integrated capability for
Engineers commissioned to design hybrid concrete Structure, Mechanical and Electrical, and Envelope.
structures. It forms part of a suite of publications and
This document is concerned with design of the structure and
deals with detailed guidance for twin walls.
in the context of this document, the Contractor is the party
Detailed design guides for other key components of the responsible for constructing the building. This may be either
structure are also available from Explore. a Laing O’Rourke Business Unit with Expanded responsible
for assembly and temporary works design or a Contract
Readers should be aware that where a standard is referred
executed by Expanded acting as Contractor and temporary
to without a date, they should consult the latest available
works designer.
version. Where a date is used, this refers to a clause from that
specific version.
2
Contents
1 Introduction 3
2.1 Introduction 5
2.2 Structural scheming 5
2.3 Planning and coordination 5
2.4 Durability and fire resistance 6
2.5 Robustness 6
3 Structural overview 7
3.1 Summary 7
3.2 Structural behaviour 7
3.3 Analysis methods 8
3.4 Interaction of the temporary and permanent conditions 8
3.5 Design at the ULS 8
3.6 Design at the SLS 9
3.7 Design of joints 9
3.8 Detailing 12
5 Manufacture 23
5.1 General 23
5.2 Materials 23
5.3 Manufacturing tolerances 23
5.4 Manufacturing process 23
5.5 Storage, transportation and handling 26
6 Construction 27
6.1 General 27
6.2 Materials 27
6.3 Installation methods and tolerances 27
6.4 Lateral pressure during concrete pouring 29
7 References 32
1
Precast Twin Wall
2
1 Introduction
1 Introduction
1.1 Purpose and scope
This Explore Design Guide aims to assist in the understanding of the design issues relating to the use of
precast twin wall (sometimes called double wall) units. It is intended for use by Structural Engineers who are
commissioned to design such wall systems and Structural Engineers overseeing such designs, for example
as client’s representatives or Building Control Officers. It discusses issues that require liaison with Explore
Manufacturing during design and development.
This guidance is provided on the basis of design to the Eurocodes and the UK National Annexes; however,
where appropriate, reference is made to other applicable publications, including BS 8110-1(1). The IStructE
publication Manual for the design of concrete building structures to Eurocode 2(2) and the Concrete Centre
publication How to design concrete structures using Eurocode 2(3) are also recommended background
reading.
The advice contained within this Explore Design Guide is limited to the common use of structural precast
twin wall applications for hybrid construction. This typically includes load-bearing twin wall units connected
to in-situ or precast lattice slabs. Non-structural applications of precast twin wall, where the core is not
filled with in-situ concrete or where the wall is not load bearing (infill panels) are not covered by this guide.
Non-standard applications of twin wall (e.g. functioning as part of a deep beam or transfer system) require
additional attention and whilst many of the issues presented in this guide may be relevant, other aspects of
the design may warrant more detailed analysis.
Precast twin wall is commonly used for basement construction; but specific advice related to watertightness
is not covered by this guide. Design and detailing for basements should follow industry standard guidelines
with specific attention given to the joint locations. Explore will be able to advise on typical details.
Precast twin wall is also well suited to high-rise construction; however, the design aspects specific to this
type of unit should be carefully considered, particularly in the context of both the lateral stability and vertical
load system. This may warrant more detailed analysis methods. The design and construction issues relating
to high-rise buildings are not explicitly covered in this guide.
3
Precast Twin Wall
In-situ concrete
Precast panel
In-situ topping to floor slab
Embedded
reinforcement
Figure 1
Typical arrangement of Starter bars from foundation
hybrid twin wall construction,
showing connections
between floors and walls
4
2 Scheme design stage
Precast twin wall functions in essentially the same way as monolithic reinforced concrete. The most significant
additional structural consideration is the design and detailing for effective transfer of force across the panel
joints. In most situations, however, this aspect of the design is not limiting and the potential for applying
precast twin wall is typically wide ranging.
The Structural Engineer should consider the design issues described in Section 3 and Section 4 at all the
levels and positions of interest throughout the structure. Particular consideration should be given to the
following at scheme stage:
■ Due to a reduced reinforcement lever-arm and possible reduction of effective joint width, transverse
(minor axis) bending at the joints may govern the wall thickness, particularly where the axial force is
relatively low (at the upper storeys). This may be particularly pertinent if a precast lattice slab system
is adopted, and joint details should therefore be carefully considered at the outset to ensure wall
thicknesses remain efficient.
■ In situations where the resulting stiffness of the wall/slab base joint is significantly lower than a gross
elastic section (due to joint opening), the impact on connecting elements such as slabs should be
assessed as part of the design process.
■ To ensure that the reinforcement details remain practicable, care should be taken in the scheming of
openings and doorways where lintel beams or coupling beams contribute to overall stability.
The Structural Engineer should also allow sufficient time to check and review the Explore component
drawings to ensure they are in accordance with the design intent and that he has allowed for detailing all in-
situ reinforcement to complete the permanent works.
5
Precast Twin Wall
Therefore there are no additional durability or fire resistance requirements relating to the design of precast
twin wall compared with in-situ wall construction, although the joints require particular attention.
Materials and cover should be specified appropriately in accordance with BS EN 1992-1-1, BS 8500-1(5) and
BS EN 1992-1-2: 2004(6) cl. 5.3.
2.5 Robustness
An important aspect of modern structural design is to ensure robustness. Most buildings will come into class
2B, which is adopted as a minimum standard. Buildings in class 3 should also meet the class 2B standard,
together with any additional requirements arising from a risk assessment. The requirements are generally
complied with by providing horizontal ties in floors and vertical ties in columns and walls, typically making use
of reinforcement already provided for other purposes. However, reinforcement is not always continuous in
hybrid construction and it is necessary to rely on interface shear in some locations.
The requirements for vertical tying are defined in BS EN 1992-1-1: 2004 cl. 9.10 and PD 6687(7). The principle
is well known, and is shown in Figure 2.
T
T
Figure 2
Structural action of
vertical tying
In the case of precast twin walls, the tying capacity is provided by vertical splice bars acting together with
the reinforcement cast into the panels. This must be designed such that the tying force can be effectively
transmitted in interface shear. The design of this connection is discussed in Section 4.2.
6
3 Structural overview
3 Structural overview
3.1 Summary
This section provides an overview of the key issues for the analysis and design of hybrid precast twin walls
(as defined in Section 1.2 and within the scope defined in Section 1.1), and discusses the factors influencing
the design over and above those required for in-situ wall construction. Where required, these issues are
developed in further detail in the context of the design process in Section 4.
The design of the horizontal spliced joints is the most critical factor in the bending and axial capacity, and
should be coordinated carefully at an early stage to ensure the joint details are buildable whilst remaining
reasonably efficient. Interface shear adjacent to the joints needs specific consideration.
In the case of walls subject to shear forces, in-plane bending and shear forces are manifest through a
variation in axial force along the length of the wall and a combination of vertical and horizontal shear stress
(see Figure 3). These shear forces are carried by a combination of the embedded reinforcement and in-situ
and precast concrete. At the joints these forces are transferred through interface shear to splice reinforcement
(see Section 4.2).
Floor slab
Precast panels
Figure 3
b) Vertical stress distribution
In-plane forces in a precast at base of wall
twin wall resisting shear and
overturning forces
7
Precast Twin Wall
A linear elastic calculation based on gross section properties, as would be assumed for in-situ construction,
is generally suitable for the design of precast twin wall and is in accordance with BS EN 1992-1-1: 2004(4)
cl. 5.4. The following assumptions for elastic analysis should therefore be reviewed for appropriateness:
■ Where joint opening at the SLS in expected, a cracked stiffness may be appropriate for SLS design to
ensure deflections of adjacent elements are conservatively considered. Alternatively it may be simpler
to model the base of the wall as pinned to check deflections of adjacent elements (the design of the
wall itself should still be undertaken using a connection with a finite rotational stiffness).
■ The reduced flexural stiffness at vertical joints is not usually significant as the out-of-plane (in-plan)
bending is inconsequential.
In between prop locations, this lateral pressure is resisted through a combination of tying action of the
vertical lattices and bending of the horizontal embedded reinforcement. ‘Locked-in’ stresses will therefore be
apparent in these elements in the permanent condition. In most situations such stresses will be low and will
not affect the ULS capacity of the composite section.
If, owing to the nature of the project, the Structural Engineer believes a specific check is warranted, Explore
can provide further information on the reinforcement stresses from the temporary condition.
In this respect, the only additional checks required for twin walls are those necessary to demonstrate the
assumed monolithic behaviour as follows:
ULS calculations should be compatible with the chosen joint details, particularly at the horizontal joints where
the available ultimate capacity can be significantly affected. Refer to Section 3.7 for further discussion of joint
design.
8
3 Structural overview
The main bars of the lattices embedded into the precast elements can be considered to contribute to the
wall capacity.
Where the in-situ and precast elements have different concrete strengths it is recommended that, for simplicity,
the ULS design should utilise the minimum concrete compressive strength. With this in mind, consideration
should be given to the specifications of the in-situ and precast concrete to improve compressive strength
compatibility and reduce inefficiencies.
Where transverse reinforcement (through the thickness of the wall) is required in accordance with
BS EN 1992-1-1: 2004(4) cl. 9.6.4, it may not be possible to demonstrate that the lattice provides suitable
restraint to the vertical reinforcement. In this situation the only viable option may be to use an in-situ wall. The
requirement for transverse reinforcement is specified only when the vertical reinforcement exceeds 2% of
the plan area of the wall for each face; therefore it is unlikely that this will provide a restriction in the majority
of cases.
The horizontal joints between panels are typically located in zones of high moment. The reduced reinforcement
lever arm and the non-homogeneity of the precast-to-in-situ bedding joint makes the potential magnitude
of joint opening more significant than cracking in an equivalent in-situ wall. It is therefore recommended to
estimate the joint opening in order to mitigate underperformance at the SLS.
Owing to the splice bar location, joint opening should be calculated at the appropriate position for assessment
of durability crack width limits. Two calculations of joint opening may therefore be required; one at the tension
face and one at a position of minimum cover from the edge of the splice bar. This is discussed further in
Section 4.2.
As mentioned in Section 3.3, the opening of joints may increase the magnitude of deflections of adjacent
elements, and elastic models should be adjusted accordingly if the influence is anticipated to be significant.
Bedding joint details of less than 30 mm are not recommended due to the significantly more onerous designs
that result from the assumption of a complete loss of concrete shear capacity and compressive capacity in
the panels (affecting bending, axial force, in-plane shear and interface shear design).
9
Precast Twin Wall
Splice bars
b b
Dry bearing
a) Twin wall and in-situ slab; b) Twin wall and precast slab;
top and bottom of wall full effective width at top of
full effective width floor, but reduced at soffit
Splice bars
b b b
b
Thixotropic
high-strength
grout, 10 mm
c) Twin wall and precast slab; d) Twin wall and precast slab; e) Horizontal joint
30 mm joint provides full 10 mm thixotropic joint provides with no slab junction;
effective width for wall joint full effective width for wall joint 30 mm bedding joint
provides full effective
width for wall joint
Note: full concrete cross section can be
Figure 4
taken as load bearing when b > 30 mm
Wall and slab junctions,
showing various joint details
At the top of the wall, if an in-situ slab is specified, the precast panels should extend to the soffit (Figure 4a)
where the subsequent casting of in-situ concrete will provide effective load bearing onto the panels’ edge.
If a lattice slab system is specified, a dry bearing (between the precast lattice plank and precast wall panel)
(Figure 4b) will not facilitate efficient transfer of internal actions. Therefore a 30 mm bedding joint at the top
of the wall should be specified (see Figure 4c). Alternatively, a 10 mm bed of thixotropic high-strength mortar
may be used (Figure 4d).
Where the wall is on a slab edge (Figure 4b), the external precast panel often provides the side shuttering to
the slab concrete. A bedding joint must be provided between the precast panel and the wall panel above to
ensure transfer of compressive force. If post-tensioned slabs are specified, a detail of this type will need to be
coordinated carefully in order to accommodate stressing access requirements.
Joints at upper (roof) slab and ground slab connections follow the same logic as outlined above and should
be designed accordingly.
10
3 Structural overview
At horizontal joints where there is no slab junction, as shown in Figure 4e, where two wall panels are stacked
to achieve the necessary height, a bedding joint should be provided to facilitate transfer of compressive force
and to maximise the lever-arm efficiency for minor axis bending. Such walls may be classed as slender and
the addition of second-order effects may prove critical for joints at mid-height.
Continuity reinforcement is provided at horizontal joints with splice bars lapped with the embedded
reinforcement, as shown in Figure 5. Splice bars should be positioned so as to avoid touching the inside
face of the precast panels as any unfavourable manufacturing and construction tolerances may make it
impossible to lower the panels over the in-situ starter bars. To achieve full bond strength, the splice bar
position should enable full flow of concrete between the bar and the inside face of the panel in accordance
with BS EN 1992-1-1: 2004(4) cl. 8.2. This will be no less than 20 mm.
Therefore, depending on the width of the wall, the width of the precast panels, the diameter of the splice
reinforcement, the maximum aggregate size and the precast manufacturing and installation tolerances, it
may not be possible to specify two rows of reinforcement with confidence.
In this case, the Structural Engineer should review the design requirements, dimensions and tolerances and
determine the most efficient splice arrangement. In general, for walls of less than 225 mm total width, single
rows will usually be more practicable. Where transverse moments are high relative to the axial force, the
maximum lever arm offered by two rows of reinforcement may, however, be desirable.
Panel mesh
SIngle row reinforcement Two rows
of continuity of continuity
reinforcement reinforcement
laps with panel lap with panel
mesh reinforcement mesh reinforcement
Figure 5
Vertical section of wall/
floor joint showing continuity
reinforcement provided by a)
single layer or b) double layer a) b)
of splice bars
Suitable cover should be provided to the splice reinforcement from the edge of the effective joint in accordance
with BS EN 1992-1-1: 2004 Section 4, BS 8500-1(5) and BS EN 1992-1-2: 2004(6) cl. 5.3. Where a fully
effective (i.e. >30 mm) horizontal bedding joint is specified this can contribute to cover; however, a dry or
ineffective joint (i.e. <30 mm) between panels cannot contribute to the cover. A thixotropic high-strength grout
may be used to provide an effective joint between precast elements.
When determining vertical splice reinforcement quantities it is often useful to allow an additional 10–20% to
account for clashes with the vertical lattice locations. Where a clash is apparent and a starter bar must be
cut, then a bar either side of the lattice is typically needed.
11
Precast Twin Wall
Vertical joints differ from horizontal joints in that they are not usually load bearing. Out-of-plane bending in plan
is usually inconsequential as the diaphragm action of the supporting slab restrains any movement.
Vertical joints are not usually detailed to be filled with concrete, and the joint is nominally detailed as open and
dry (i.e. does not contribute structurally). A 20 mm gap is usually detailed to accommodate manufacturing
tolerances, and the resulting residual gap is usually partially filled during the pouring of in-situ concrete. Any
remaining joint is usually filled with non-structural filler material to achieve an acceptable finish.
Continuity reinforcement is typically provided using a prefabricated single (Figure 6a) or double (Figure 6b)
layer of reinforcement, which is lowered into place between the lattices after the precast wall units are in place.
If the twin wall is required to function as a shear wall, checks should be carried out to ensure that sufficient
shear capacity exists to transmit the vertical shear between panels. Minimum reinforcement requirements will
often be the governing criteria.
20 mm Continuity 20 mm
reinforcement
Lattice
girder
Horizontal splice bars should be fully lapped with the embedded wall reinforcement. The available space
between the vertical lattices should be checked to avoid clashes on site and smaller diameter splice bars
may be preferable to minimise bond lengths. As a guide, the centre of the lattices are typically located
350 mm from the panel edge. Minimum cover should always be maintained from the edge of the effective
joint width (usually the in-situ wall width).
3.8 Detailing
Explore should be consulted for the latest standard details that should be employed in the structure, as they
are subject to review as a process of continual improvement.
Various construction options are available, each of which has different design implications. It is suggested
that the options are discussed with Explore and the Contractor at an early stage of development to ensure
the design remains compatible with the chosen detail.
12
3 Structural overview
Care should be taken to ensure that the necessary reinforcement (longitudinal and shear) can be placed
as required in the beam section, giving due regard to the precast element width, bar spacing rules and
tolerances. All horizontal bars should be lapped with splice bars and any additional bars in the in-situ concrete
should be fully anchored into any adjacent shear wall panels. All vertical shear reinforcement should be fully
anchored at the top and bottom of the beam. In some instances, where the width of the in-situ wall section
permits, it may be prudent to specify an internal beam reinforcement cage.
13
Precast Twin Wall
The following sections provide further background on each of the steps, highlighting key assumptions and
making reference to Section 3 for background theory where appropriate. In addition, Appendix B contains
answers to Frequently Asked Questions.
Joints require explicit consideration in the design process and influence other aspects of the design. It is
therefore recommended that before detailed design commences the Structural Engineer agrees a preliminary
panel layout with Explore and the Contractor.
2 Analyse structure
The analysis of twin walls should initially be based on gross elastic stiffnesses using FE methods or hand
calculations. Modifications to stiffness may be appropriate where opening of the horizontal joints is anticipated,
and may indeed be necessary to improve design efficiency or determine the impact of joint rotations on
adjacent elements such as slabs.
Forces factored appropriately for the ULS and SLS should be extracted for design from the analysis software.
Owing to the interaction of the bending and axial force, critical load combinations will need to be identified
taking into account the range of the resulting forces in each panel. If the analysis software includes the
capability to undertake reinforced concrete design (and if its use is appropriate for twin wall) this step will
usually be internal to the software.
As with normal good practice, it is recommended that results for individual load cases are interrogated to
ensure structural behaviour is as expected.
14
4 Detailed design process
Where a twin wall is designed to contribute to the lateral stability system (i.e. a shear wall), the ULS design
must incorporate a check of in-plane shear capacity.
Horizontal in-plane shear forces should be averaged over the length of the wall, and checked in accordance
with BS EN 1992-1-1: 2004(4) cl. 6.2 to determine the requirement for vertical reinforcement. Similarly,
vertical in-plane shear forces should be averaged over the height of the wall and checked to determine the
requirement for horizontal reinforcement.
In most instances, owing to complementary shear stresses, these shear forces will be similar in magnitude,
although horizontal shear design will benefit from the coexistent axial force.
Horizontal joints with at least a 30 mm bedding detail will provide the same concrete shear capacity as the
composite wall section and will therefore not require a separate check. Vertical joints, typically with only the
in-situ cross section effective, may be critical and should be checked explicitly.
Design loads should include an allowance for geometric imperfections and, if applicable, second order effects
in accordance with BS EN 1992-1-1: 2004 cl. 5.2 and 5.8.
In determining the effective length of the wall for transverse bending, the appropriate support conditions at
the top and bottom of the wall should be considered. The effective length factors listed in the Manual for the
design of concrete building structures to Eurocode 2(2) Table 5.14 are appropriate in most instances and the
approach is quicker and more familiar to Structural Engineers than that described in BS EN 1992-1-1: 2004
cl. 5.8.3.2.
Where transverse moments are subject to reversal within the storey height (most frame buildings) it is
recommended that the factor rm (used to calculate parameter C) is determined from the analysis results to
maximise the slenderness limit llim. Calculated in this way most walls should be classed as non-slender.
6&7 Design wall panels for combined moments and axial forces
Provided full composite behaviour can be demonstrated (see Step 12 and Step 16), wall panels should be
designed in accordance with BS EN 1992-1-1: 2004 cl. 6.2 for the worst case combined moments and axial
forces (determined in Step 3).
In practice, this can be carried out using spreadsheets, commercially available design software or the column
charts in the Manual for the design of concrete building structures to Eurocode 2(2) Appendix C.
The horizontal joints can be designed in exactly the same manner as vertical joints for wall panels. In practice,
this can be carried out using either spreadsheets or commercially available design software. The column
charts in the Manual for the design of concrete building structures to Eurocode 2 Appendix C will not normally
be appropriate due to the reduced lever arm.
The design of the joint itself should reflect the position of the splice reinforcement (see Section 3.7.1). Owing
to the reduced internal lever arm, the joint will always be a critical location (see Figure 7).
15
Precast Twin Wall
Fst Fst
Fcc Fcc
Wall stress blocks
Fsc Fsc
Fst Fst
Where FE-based design methods are used, care should be taken to ensure the cover (usually the means to
define the reinforcement position) is appropriate for the anticipated bar position.
To a certain degree, the concrete compressive strength may be increased to enhance the moment capacity
of the base joint. Where it is impracticable or inefficient to increase the material strengths further, other
options should be investigated. These may include:
■ Carry out further calculations to demonstrate a reduced moment due to the redistribution caused by
the rotation.
■ Improve the efficiency of the joint by providing multiple splice bar layers, as in Figure 7b (where it is
practicable to do so).
Wall and joint reinforcement will normally meet the requirements for vertical tying and minimum reinforcement
but should be confirmed in accordance with BS EN 1992-1-1: 2004(4) cl. 9.10 and cl. 9.6. Owing to the
arrangement of the splice reinforcement at the joints, tying capacity and minimum reinforcement at these
locations will need to be checked explicitly. Minimum reinforcement will often be the governing criteria at
vertical joints.
16
4 Detailed design process
It is particularly important that the joint opening at the horizontal joints is checked at the SLS. The discontinuity
of a jointed section and reduced reinforcement lever arm will focus rotations at a single location. The calculation
of joint opening is not, therefore, a crack width calculation.
An upper bound of joint opening can be estimated from the assumption that the total base rotation will be
due to those tensile strains apparent in the zone of the splice bar that are released at the joint. In this lap
zone, the bending moment reduces with height and the lapped panel and splice reinforcement exchange
effectiveness. This behaviour is complex, but the net effect can usually be approximated using the product of
the peak strain (at the joint) and half the splice bar lap length (see Figure 8).
Where the splice reinforcement remains in compression, the strain distribution at the joint can be easily
determined by hand; however, if the splice reinforcement is anticipated to be in tension, sectional analysis
software or spreadsheet methods will be needed.
C
L
Splice bar
l0
a) Section
c d
Joint opening at cover distance
from splice bar
h Dcov = Dct (d + c + f/2 – x) / (h – x)
where f = diameter of splice bar
b) Strain distribution
Figure 8
Calculation of joint opening
17
Precast Twin Wall
Joint opening should be limited according to the specific aesthetic and durability requirements of the project.
In the absence of further guidance, joint opening should be limited to the crack widths defined in Table NA.4
of the UK National Annex(9) to BS EN 1992-1-1: 2004(4). These crack width limits usually assume the bar
to have normal concrete cover to the tension face; however, in the case of a typical wall splice joint, the bar
has significantly more cover. In terms of durability therefore, joint opening at the face of the wall is somewhat
irrelevant, and it should be assessed at a distance equal to minimum cover from the edge of the splice bar.
Where the ULS design is unsatisfactory (either unachievable or uneconomic) or the joint opening at the SLS
is deemed to be excessive, then as described in Sections 3.3 and 3.6, benefit may be gained by using a
joint stiffness more representative of the physical behaviour under the anticipated loads. This is likely to be
particularly appropriate for upper storey edge walls where the ratio of axial force to bending moment is low.
The flexural stiffness of the open horizontal joint can be estimated using the neutral axis depth determined
from an analysis of the section at the SLS (see Figure 9). As discussed in Steps 11 to 12, where the dowel
bar is predicted to be in tension this will require the use of sectional analysis software or spreadsheets. The
2nd moment of area can be calculated from Figure 8.
ecc sc
x Fcc
d
d – x/3
Fst
h
es
b ect
This ‘cracked’ stiffness should not be applied to the full height of the wall, but a nominal height of wall at
the base sufficient to represent the reduced flexural stiffness apparent at the joint. Within reasonable limits
(typically a height less than the wall width) the results will not be very sensitive to the exact height over which
the reduced 2nd moment of area is applied.
Stiffness factors of between 10–30% are typical for edge walls on upper storeys.
18
4 Detailed design process
13-2-1 & 13-2-2 Improve joint efficiency with multiple splice bar layers
Where a reduction in joint stiffness has already been applied, but the design remains uneconomic or
unachievable, a joint detail with more than one layer of splice reinforcement can be considered to improve
efficiency. Typical single and double layer details are discussed in Section 3.7.1.
Sufficient interface shear capacity is essential to achieve composite behaviour. Forces applied to the wall
must be effectively transferred between the in-situ and precast concrete components to engage the full
available section stiffness and ultimate capacity.
The design process for interface shear in twin wall follows the same principles as for composite floors and
is described in Composite floor structures: guide to good practice(10). In the case of precast twin wall, the
bending moment diagram is usually linear with peak moments of opposite signs at the top and bottom of the
wall. Conveniently this gives rise to a constant interface shear stress, which can be calculated from the in-
plane force in the precast panel distributed evenly over the length over which the force is transferred; usually
the distance between the peak moment and the point of zero moment (at the point of inflection). This concept
is demonstrated in Figure 10.
However, as the horizontal joints coincide with the peak moment locations, the interface shear capacity
required to achieve the non-contact lap for the splice reinforcement (see Steps 15 to 18) will always be
critical. An explicit check for overall composite action is not therefore necessary provided the lattice provision
is detailed throughout the full height of the wall.
Fpan2
M2
+ + + Fpan2
h2 tL =
h2
Fpan1
h1 tL =
h1
–
M1 V tL
Fpan1
Figure 10 a) Cross section b) Bending moment c) Shear force d) Longitudinal
of wall diagram diagram shear stress
Typical interface shear
distribution
19
Precast Twin Wall
There may, however, be other situations that could be critical for interface shear capacity and these should
be considered for composite behaviour of the panel. In some instances peak bending moments may be
apparent remote from the spliced joints. Examples are:
■ Where second order effects result in a moment diagram with a significant value in the mid-height zone
of the wall (i.e. very slender walls with low applied moments at each end). Note that second order
effects for moments at the joint positions should be considered in the interface shear capacity check.
■ Where forces are applied at intermediate positions in the wall resulting in high bending moments
outside the splice bar anchorage zone (e.g. accidental loads).
In such cases the interface shear stress should be assessed over an appropriate height of wall required to
transfer the force to the precast element. This will be apparent from the particular bending moment and shear
force diagrams.
The subsequent calculation of interface shear capacity should be undertaken in accordance with BS EN
1992-1-1 2004(4) Exp. (6.25) that includes a contribution from chemical cohesion, mechanical friction and
tension in the lattice reinforcement. For standard manufacturing processes the parameters c (cohesion) and
m (friction) should be taken from the ‘Smooth’ definition in cl. 6.2.5(2) (i.e. 0.2 and 0.6 respectively). In the case
of walls the normal stress across the joint, sn, will usually be zero.
As a guide, a ‘smooth’ interface with lattices at a standard spacing of 600 mm will have a shear capacity of
approximately 1.0–1.5 N/mm2 (depending on concrete strength) split almost evenly between the interface
and the lattice.
To maintain design efficiency, it is suggested that the maximum lattice spacing for the assumed temporary
condition (based on the pouring pressure) is used as the starting point for any calculations; however, the
lattice girder spacing generally needs to be reduced if interface shear is significant.
The compressive and shear forces carried by the concrete in the precast panel are transferred through the
joint directly. The magnitude of the interface shear force is therefore limited to the force in the embedded
reinforcement perpendicular to the joint contributing to either tension, compression or shear as appropriate.
The interface shear force for the transmission of a non-contact tension lap should be based on the design
force of the splice reinforcement, Asssd (see Step 16 below).
Interface shear for the non-contact lap of reinforcement required for vertical tying or minimum reinforcement
should be checked for the full force required. As these forces are purely axial, they can be assumed to act
over both interfaces (i.e. lapped with embedded reinforcement in both panels).
Consistent with vertical splice reinforcement, the interface shear force for the transmission of a non-contact
lap should be based on the design force of the splice reinforcement, Asssd.
Again, interface shear for the non-contact lap of reinforcement required for vertical tying or minimum
reinforcement should be checked for the full force required.
20
4 Detailed design process
Splice reinforcement across the joint should be lapped in accordance with BS EN 1992-1-1: 2004(4) cl. 8.7.2
for tension or compression as appropriate, including an additional allowance for a non-contact lap if the clear
distance between the splice bar and the embedded reinforcement is greater than 50 mm or 4 x the diameter
of the bar.
Calculations for splice laps should be based on the reinforcement design stress for the action considered
(i.e. ssd), bearing in mind that reinforcement required for vertical tying or for minimum reinforcement provision
must be assumed to function at the design yield stress, fyd.
The bond calculation should be compatible with the distance of the bar from the inner face of the precast
element. Where the gap between the splice bar and the inner face of the precast panel is less than that defined
in Section 3.7.1, lap lengths should be increased to compensate for the potential reduction in bond.
For horizontal joints, in order to mobilise the shear capacity of the lattice legs, an allowance should be made
for the in-plane distance from the splice bars to the lattices. This can be conservatively estimated as half the
lattice spacing less the lattice width. This is indicated in Figure 11. For a typical lattice arrangement this will
be approximately 250 mm.
For vertical joints in normal situations, the available splice lap length will be limited by the space between the
vertical lattices. The layering and diameter of reinforcement will need to be optimised to ensure the design
remains practical to implement.
Allowance to
mobilise lattices,
llattice
Basic design
lap length, l0
Joint
T Lattice width,
wlattice
Lattice diagonals
Starter bar
Figure 11
Additional lap length to allow Note: Allowance to mobilise lattice legs, llattice = s / 2 – wlattice / 2
for in-plane distance from
splice bar to lattice
21
Precast Twin Wall
Interface shear stresses can be calculated using the forces determined in Step 15, which are assumed to
act over the length of the basic design lap length, l0 (i.e. not including the allowance for the non-contact lap
– see Figure 12).
Precast panel
Allowance for a
45° non-contact lap
45°
Splice bar
Figure 12
Length used to assess
interface shear for a non-
contact lap
The interface shear capacity should be checked in accordance with BS EN 1992-1-1: 2004(4) cl. 6.2.5 as
described in Step 14.
Increasing the interface shear capacity is usually achieved most efficiently by increasing the number of lattices
local to the lap zone. This is best achieved through the addition of short intermediate lattices fitted between
the main lattices.
For vertical joints, however, horizontal splice reinforcement is not able to mobilise the lattice reinforcement
legs; therefore only the concrete cohesion component is effective in resisting the splice bar force. The
roughness of the interface is therefore critical to the effectiveness of the force transmission.
19 Finalise design
Once the design is finalised it can be confirmed in the following deliverables (each project may have its own
requirements in terms of information required and transfer formats):
Please refer to the Explore Model Specification for details of likely deliverables and formats.
22
5 Manufacture
5 Manufacture
5.1 General
This section provides information on the manufacture of precast twin wall by Explore. Further details regarding
the specification for manufacture are also provided in Appendix D, Model Specification.
5.2 Materials
Materials used by Explore for the manufacture of standard precast twin wall comply with the requirements of
BS EN 1992-1-1(4), BS EN 206-1(11) and BS 8500-1(5) for concrete constituents and BS EN 1992-1-1 and
BS EN 10080-1(12) for reinforcement.
Factory mix designs can fulfil any of the strength classes of BS EN 206-1. A minimum preferred strength is
C40/50, but consideration of high-strength classes should take into account the class of adjoining precast
elements, grouts or in-situ concrete.
Preferred bar sizes for main bar diameters are 10, 12 and 16 mm, with 8 and 14 mm also available; this
should be confirmed with Explore.
The Structural Engineer should ensure the materials specified are compatible with the Client’s Brief and are
appropriate for the intended end use. Where non-standard or specific materials are required this should be
discussed with Explore in advance.
The Structural Engineer should advise if more stringent tolerances are necessary for design or to achieve the
Client’s Brief. These should be discussed at the earliest opportunity.
The precast structure is developed as a digital prototype and analysed and designed before being ‘elementised’
into structural precast components. This produces digital manufacturing data for elements. For each element
a set of data according to the Unitechnik CAD/CAM interface description is prepared. Each file contains all
information about the dimensions of the element, its geometry, volume, reinforcement, cut-outs and all other
production-relevant details. The master computer in the factory can read all files prepared for production and
optimise pallet use and throughput.
23
Precast Twin Wall
Straightness/bow (0 m – 3 m) 6 mm TBA
Straightness/bow (3 m – 6 m) 9 mm TBA
Straightness/bow (6 m – 12 m) 12 mm TBA
Notes
Table 1 1 Tolerance for cast-in inserts to be obtained from Explore and compared with the project specification requirements.
Precast manufacturing 2 All the above figures may be subject to change. Always check against the source standards or Explore’s latest
tolerance document.
tolerances for twin wall
24
5 Manufacture
Figure 13
Working on the first shell of
the twin wall, the precast
outline and holes or fixings are
plotted onto the steel pallet
using digital data from the
drawing process to drive the
plotter
Figure 14
Formwork, bottom mesh and
lattice reinforcement in place
ready for concreting
Figure 15
Securing lattice girders in
place on steel pallet fitted
with spacers and mesh
reinforcement
25
Precast Twin Wall
Figure 16
Concrete distributor placing
concrete in formwork. (The
construction of shell 1 of twin
wall is identical to that of
lattice floor pictured here)
Figure 17
After curing the first shell is
inverted and inserted into wet
concrete of the second shell
26
6 Construction
6 Construction
6.1 General
This section provides information on the installation of precast twin wall by the Contractor. Further details
regarding the specification for construction and installation are also provided in Appendix D, Model
Specification.
6.2 Materials
The installation process enables the precast twin wall units to function effectively within the structural frame.
The in-situ concrete and splice reinforcement ensure that the wall will function as intended and are as
important as the constituent materials of the precast twin wall unit itself.
In-situ concrete should be specified by the Engineer in accordance with the requirements for structural
concrete (i.e. BS EN 1992-1-1(4), BS EN 206-1(11) and BS 8500-1(5). The fluidity of the concrete used will
have implications on the temporary stability of the element (see Section 6.3 below) and the Contractor should
propose a suitable mix for the Structural Engineer’s approval. This will require discussion between Explore
and the Contractor regarding methods of compaction and the possible use of self-compacting concrete
(SCC). Explore will be able to provide advice regarding the implications of any particular option with respect
to the temporary works design.
Figure 18
(left)
Twin wall
element
propped prior to
concreting inner
section
Figure 19
(right)
Close up of top
of twin wall
element showing
cast-in lifter
27
Precast Twin Wall
Figure 20
(left)
Twin wall and
lattice slab
elements erected
awaiting steel
fixing before
in-situ concrete
is poured
Figure 21
(right)
Typical
offloading bay
with twin wall
units in racks on
the lorry
6.3.1 Lifting
Under CDM regulations the design of the lifting points should be the responsibility of Explore. Designs should
be checked by Laing O’Rourke temporary works engineers. The project team must ensure that the design
of the lifting points and the design check covers precisely the way the units will be handled on site. Lifting
points and attachments must be:
Consideration must be given to safe access to attach the lifting equipment at the top of the units. Racks with
purpose-made access platforms are available, but limit the number of units transported at a time. Ladders
with an attachment that hooks the top of the unit to provide a secure attachment are an alternative, as shown
in Figure 21.
Storey-height wall units are usually delivered in racks on their sides and need to be turned in an upright
position for installation. They are typically lifted from the rack and placed down on suitable bearers or a sand
bed for turning. Lifting points are required on two sides to allow the unit to be lifted from the ground in the
correct orientation for placing in the structure.
28
6 Construction
In-situ infill
50 mm
Figure 22
Detail at base of twin wall
The industry recommended concrete pressure of 30 kN/m2 for standard twin wall design equates to pouring
at the rate of approximately 750 mm per hour. However, site logistics and size of pours often require pours
to be made quickly. This can be accommodated by design of additional lattice in the wall. Accordingly this
information should be provided to the Explore at an early stage.
Research has shown that by reducing the centres of the lattice girders and increasing lattice embedment (by
increasing shell thickness) it is possible to design twin walls to take full hydrostatic pressure. This will increase
the allowable rate of rise but does mean that joints will require temporary support (tying).
29
Precast Twin Wall
Lattice bottom
bars dia. = f b
Lattice top
bars dia. = ft
Lattice diagonals
≥ 55 mm dia. = fd
Shell 1 Shell 2
thickness = t1 thickness = t2
250 65 65 14 10 10 5 5 19.80
Table 2 300 65 70 18 12 10 6 5 21.90
Wall and lattice girder
350 70 75 21 12 10 6 6 24.40
parameters
Pour rates
4.00 Key
3.50 Wall widths and
concrete slump
3.00
Rate of rise, m/hr
200 mm, F4
2.50
200 mm, F3
2.00 250 mm, F4
1.50 250 mm, F3
1.00 300 mm, F4
Notes
Figure 24
1 The lattice girder capacity (and resulting wall capacity) is determined by top bar diameter, ft and cover, c.
Relationship between pour
2 Pressures are in accordance with BS EN 14992: F3 slump = 120–180 mm approx; F4 slump >180 mm approx.
rate and lattice girder
spacing
30
6 Construction
Lattice bottom
bars dia. = f b
Lattice top
bars dia. = ft
Lattice diagonals
≥ 55 mm dia. = fd
Shell 1 Shell 2
thickness = t1 thickness = t2
250 65 65 15 10 10 5 5 19.80
Table 3 300 65 70 17 12 10 6 5 21.90
Wall and lattice girder
350 70 75 22 12 10 6 6 24.40
parameters
Hydrostatic pressure
4.00 Key
3.50 Wall widths
200 mm wall
3.00
250 mm wall
Pour height, m
2.50
300 mm wall
2.00
350 mm wall
1.50
1.00
0.50
0.00
200 250 300 350 400 450 500 550 600
31
Precast Twin Wall
7 References
1. BSI. BS 8110-1: 1997. Structural use of concrete – Part 1: Code of practice for design and construction.
2. The Institution of Structural Engineers. Manual for the design of concrete building structures to
Eurocode 2, 2006.
3. The Concrete Centre. How to design concrete structures using Eurocode 2, 2006.
11. BSI. BS EN 206-1: 2004. Concrete – Part 1: Specification, performance, production and conformity.
12. BSI. BS EN 10080-1: 2005. Steel for the reinforcement of concrete – Weldable reinforcing steel - General.
13. BSI. BS EN 13369: 2004. Common rules for precast concrete products.
32
Appendix A: Design process maps
This is a detailed design process map, showing the analysis and calculation process for twin walls. The
numbers allocated to the steps are used to take the reader through the twin wall worked examples in
Appendix C and are referred to in the twin wall design guide.
The process map for design for manufacture and assembly sets out the general design process, showing
how the responsibility for the various steps is allocated to the parties involved.
33
34
Inputs Outputs
and modelling
Agree preliminary panel Revise structural arrangement
Panel layout
LOR/Contractor preferences Preliminary joint layout
layout with LOR/Contractor or thicken wall.
2 Analyse structure
Geometry and loads
assuming gross elastic stiffness
5 Add geometrical
Critical ULS load combinations, imperfections and 2nd order
Critical ULS load combinations
geometrical imperfections and effects to ULS moments as
including additional effects
2nd order effects appropriate in accordance with
BS EN 1992-1-1
details, concrete and steel combined moments and axial forces thickness and reinforcement details
design strengths, fyd, fcd
9
Horiz. joint design, buildability, Horiz.
joint design No Confirmation of ULS
client’s requirements,
acceptable horiz. joint design
cost efficiency
at ULS?
Yes
10
Yes
Tying check
11
Vertical tying force
Sufficient
(BS EN 1992-1-1:2004 No 11.1 Additional reinforcement to meet
reinforcement for
cl. 9.10.2 and minimum Add reinforcement tying or minimum reinforcement
vert. tying and
reinforcement requirements requirements
As,min?
(BS EN 1992-1-1:2004 cl. 9.6)
Yes
Yes
12 13.2.1
Estimate horiz. Joint opening
from critical SLS load combinations Efficiency
Critical SLS load combinations significantly improved No Expected joint opening
with multiple
SLS checks
layers?
19 18.1.2
Finalise wall design Add
Revised lattice spacing, s
and panel layout additional lattices
No
Submit BIM Prepare schedule of
structural model all requirements
inclusive of for execution;
Determine/revise: precast outline, joint steel schedules;
Establish: Precast wall outline Does the positions of doors concrete
and wall thickness manufacturing advice and windows specifications
Architect/engineer
Standard details
Explore manufacturing
for proposed
elements
Prepare/revise 3D
model with
elementised twin
wall components, Approved for
Review panel Determine lattice incorporating Prepare/revise manufacture
arrangement height and spacing temporary works manufacturing
and advise on and shell requirements Manufacture
details and send
element shape for thickness for and specification for approval
manufacture final design requirements
Yes
Are the
Advise on propping Maximum weight requirements
Constructor
No
Appendix B: Frequently asked questions
4. Why is the width of the element ineffective if the joint width is less
than 30 mm?
The 30 mm limit is set in BS EN 14992(8). This limit is defined to facilitate flow of concrete constituents fully
into the joint. Any joint less than this cannot be considered as fully effective, as the efficacy of the concrete
underneath the element cannot be guaranteed.
37
Precast Twin Wall
7. I have been told that the walls can pull apart when the concrete is
poured. How will Explore and the Contractor ensure this will not happen?
Using the method statements and proposed concrete mix from the Contractor, Explore will consider the
height of concrete poured, rate of pour and positions of the lattice to ensure that the wall will never experience
an unacceptable internal pressure. In addition, it has been demonstrated that the lattice embedment is
a critical factor in such pull-out failures. Explore manufacturing tolerances will ensure that the minimum
embedment as recommended by BS EN 14992(8) is always achieved. Resulting reinforcement stresses are
not significant for the permanent condition design.
38
Appendix C:
Example calculations
Precast Twin Wall
40
Appendix C: Example calculations
SECTION
Precast twin wall
Explore Manufacturing Ltd
Steetley Works CALCULATED BY: SH CHECKED BY: PJM SHEET NO.
WORKSOP S80 3DT W1
DATE: Jan 2010 DATE: March 2010
Key: The following symbols are used in the left hand column:
This is a typical building concept design for manufacture and assembly (DfMA)
using precast components from Explore’s precast component set.
In following this design for twin walls, readers should refer to the Twin Wall Design
Guide, to the marked up process design map on page 71 that shows the two cases
considered, and to the process flow chart on page 36. The Concrete Centre’s
spreadsheets* can be used for part of this design (see page 72).
Figure C.1
Model of structure
Two separate cases will be checked (see process design map on page 71):
1. Botom storey; where axial force is greatest
2. Top storey; where axial force is least and moment will have a greater effect
Wall section
Trial wall section at h = 300 mm min thickness
Precast element thickness = 50 mm
fck = 50 MPa (C50/60) for precast panels, fck = 40 MPa (C40/50) for in-situ.
Design will be conservatively based on the lower value of fck = 40 MPa fck = 40 MPa
fyk = 500 MPa fyk = 500 MPa
The layout agreed with Explore consists of spliting the wall into 4 panels.
Therefore, the loads taken from the FE model are based on 4 x 1.95 m panels
with average results being extracted for each.
* RC spreadsheets: V3. User guide and CD. CCIP-008. The Concrete Centre 2006. Excel
spreadsheets for design to BS 8110 and Eurocode 2 and its UK National Annex.
41
Precast Twin Wall
My
A B C D 3200 mm
Figure C.2
Bottom storey wall
with panel locations
7800 mm
A B C D
A B C D
43 kN/m
32 kN/m
A B C D
37 kN/m
42
Appendix C: Example calculations
The full height of the wall is effective (3500 mm). A maximum vertical shear
force can be taken from the FE model as 43 kN (Panel B/C).
The maximum shear stress in the plane of the wall,
EC2 6.2.2
vEd = (43 × 3.5) ×103 / (300 × 3500) = 0.143 MPa vEd = 0.143 MPa
43
Precast Twin Wall
CASE 1 cont.
vRdc = 0.53 MPa vRdc = 0.53 MPa
0.53 > 0.143
vRdc > vEd
Shear reinforcement not required horizontally for ULS strength vRdc > vEd OK
Joint design – vertical in-plane shear forces
Splice bars between vertical joint
Note:
For design purposes, joints
are considered to be unfilled
Figure C.3
Plan view on vertical
joint showing horizontal
splice
This calculation is similar to the wall panel design; however, at vertical joint
locations the depth of wall decreases to 200 mm.
vEd = (43 × 3.5) ×103 / (200 × 3500) = 0.215 MPa vEd = 0.215 MPa
This means that the minimum design shear strength
vRdc = vmin + k1 scp
= 0.035k1.5fck0.5 + k1scp
scp = 0 N/mm2 conservative
k1 = 0.15 recommended
k = √(200/d) + 1
= 2 ≤ 2 OK
vRdc = (0.035 × 21.5 × 400.5)
= 0.63 MPa vRdc = 0.63 MPa
0.63 > 0.215
∴vRdc > vEd vRdc > vEd
Shear reinforcement is not required in vertical joints for ULS strength OK
5 Slenderness
The wall section is to be designed as a non-sway structure with axial load
IStructE and bending to be applied. Using the clear height between floors (3200 mm),
EC2 Manual 2.2
slenderness can be calculated:
IStructE
EC2 Manual
Effective height L0 = b lw
Table 5.14 = 0.85 × 3200
= 2720 mm
44
Appendix C: Example calculations
45
Precast Twin Wall
CASE 1 cont.
NA
IStructE
EC2 Manual
Appendix A
By inspection, Panel D is critical i.e. has the
maximum moment with a minimum axial load.
Mt/bh2fck = 43 × 106 / 1000 × 3002 × 40
= 0.012
NEd/bhfck = 579 × 103 / 1000 × 300 × 40
7 = 0.048
Fc
Figure C.4
Force diagram in panel Z
Ft Z
x
30 mm s
bedding joint
Fc
A A d
Splice bar
required
to provide
Figure C.5 continuity
Forces acting on
horizontal joint Section A–A
46
Appendix C: Example calculations
The previous method of using IStructE manual charts is not appropriate due
to a small d/h ratio.
47
Precast Twin Wall
CASE 1 cont.
Maximum ULS axial load (taken from FE model with an accidental load case),
Nac = 386 kN/m
As,tie = Nac / (gS fyk)
gS = 1.0 (accidental load case)
As,tie = 386 × 103 / (1.0 × 500)
As,tie = 772 mm2/m > 670 mm2/m splice reinforcement FAILS Tie provision FAILS
< 393 × 2 = 786 mm2/m panel reinforcement PASSES
The bars chosen earlier for the vertical splice reinforcement are insufficient;
therefore steel needs to be increased. H16 @ 250
2
Adopt H16 @ 250 c/c (804 mm2/m) for vertical splice c/c (804 mm /m)
vert. splice
12 SLS CHECKS
A B C D
48
Appendix C: Example calculations
A B C D
The middle third of wall is / either side of centreline. Therefore for the reaction
to be in the middle third, the eccentricity should be less than or equal to / of
the wall width.
b = 300
eallow = 300 / 6
= 50 mm < 52 mm
ect / (h – x) = ecc / x
es ect = ecc(h – x) / x
ect ect = [ (h – x) / x](sc / Ec)
ecc
Figure C.6
Average strain,
x
Strain at ectave = [ (h – x) / 2x ](sc / Ec)
design section d
Joint opening at face, Dcf = ect (l0/2)
Ecm = 17 N/mm2 h
e = 52 mm
1/3x = (300/2) – 52
Therefore, ∴x = 294 mm (splice bar
remains in compression)
49
Precast Twin Wall
CASE 1 cont.
N 0.5sc x = 240 × 103
sc = (2 × 240 × 103) / (294 ×
1000) = 1.6 N/mm2
M
ect = [(300 – 294) / (294)] ×
1/3 2/3
[1.6/17 × 103]
sc = 2 × 10–6
l0 = 51f (conservatively using
Figure C.7 x IStructE EC2 Manual)
Stress at
design section
300 l0 = 51 × 16 = 816 mm
Dcf = 2 × 10–6 × 816/2
= 8.16 × 10–4 mm < 0.3 mm
Joint opening OK D < 0.3 mm OK
As the tying force, T, is a pure tension force, the non-contact lap acts on both
faces to transfer force to reinforcement in both panels.
50
Appendix C: Example calculations
Allowance for non-contact lap is required due to the distance between the
reinforcement in the precast panels and the splice reinforcement.
EC2 8.7.2 states that the clear distance between lapped bars should not be
EC2 8.7.2 greater than 4f or 50 mm, otherwise the lapped length should be increased by
the clear space.
Allowance = (150 – 25) –50
= 75 mm
Total lap, lt = 903 +75
= 977 mm + 25 mm end cover
= 1002 mm (Figure C.8) lt = 1002 mm
vertically
An additional lap length is required to allow for in-plane distance from splice
bar to latice (to mobilise the capacity of the latice legs in interface shear).
Assuming latice spacing, s, is 600 mm and latice width, wi , is 100 mm.
Allowance to mobilise latice legs, llat = s/2 – wi /2
= 250 mm
Provide 1252 mm lap length total
Therefore,
Total bar length = (2 × 1252) + 30 mm joint + 300 mm (slab) Total bar length =
= 2834 mm, say 2850 mm 2850 mm
51
Precast Twin Wall
CASE 1 cont.
Total lap length
Allowance for Design lap length, l0
non-contact lap Design anchorage length, l bd
Figure C.8
Diagram showing Interface shear length, based on l0
non-contact lap End cover, C Joint width, W
As shown in Figure C8, the interface shear length is approximately equal to the
basic lap length, l0;
l0 = 903 mm
therefore,
vEdi = T / (l0 × width)
= 193 × 103 / (903 × 1000)
= 0.21 MPa vEdi = 0.21 MPa
18 From EC2 6.2.5.1 the interface shear resistance can be calculated for
concrete cast at different times.
vRdi = cfctd + msn + rfyd (msina + cosa)
EC2 Exp. (6.25)
Assuming that the upper surface of the precast element has been formed as
standard, the values for ‘smooth’ should be used for the coefficients c and m.
EC2 6.2.5 (2) c = 0.2
m = 0.6
fctd = actfctk,0.05 / gC
act = 1.0
EC2 2.4.2 gC = 1.5
fctk,0.05 = 2.5
fctd = 1 × 2.5 / 1.5
EC2 Table 3.1
= 1.67
sn = 0 (no normal force)
52
Appendix C: Example calculations
We will assume latice girders at 600 centres and approx. 250 high with H8
side bars. Therefore, 4 legs of H8 every 250 mm (standard latice spacing).
Area of bar / m = 4 × 50.3 × 1000/250
= 805 mm2
EC2 6.2.5
Limiting value of vRdi:
EC2 3.1.6 vRdi lim = 0.5vfcd
fcd = acc fck / gC
NA EC2 acc = 1.0
Table NA1
EC2 Table 2.1
fck = 40 (for grade C40/50 concrete)
gC = 1.5
fcd = 1.0 × 40 /1.5
= 26.67 MPa
v = 0.6(1 – fck/250)
EC2 6.2.2
= 0.6(1 – 40/250)
= 0.504
vRdi, lim= 0.5 × 26.67 × 0.504
= 6.72 MPa
53
Precast Twin Wall
CASE 1 cont.
As the force, T, is a pure tension force, the non-contact lap will act on both
faces to transfer load to the reinforcement in both panels.
fctd = actfctk,0.05/gC
fbd = 2.25 × 1 × 1 (0.85 × 2.5/1.5)
= 3.19 MPa
ssd = 0.87fyk
(assuming bars are at full stress)
54
Appendix C: Example calculations
EC2 8.7.2 states that the clear distance between lapped bars should not be
EC2 8.7.2 greater than 4f or 50 mm, otherwise the lapped length should be increased by
the clear space
Allowance = (150 – 25) – 50
= 75 mm
Total lap, lt = 410 + 75
= 485 mm + 25 mm end cover
= 510 mm (Figure C.8)
The lap length specified above is too long to fit in between vertical latices;
therefore 2 layers of reinforcement will have to be used.
Using the same bar size and spacing with half the stress applied previously
(2 layers)
lb,rqd = 137 mm
l0 = 205 mm
Non-contact lap allowance = 50 mm
Therefore, lt = 205 + 50
= 255 mm + 25 mm end cover
= 280 mm l t = 280 mm
Total bar length = (2 × 280) + 25 mm joint horizontally
with 2 layers of
= 585 mm
reinforcement
For the vertical joint, no latice legs contribute to the shear capacity therefore,
by taking only the concrete into account, the expression becomes;
55
Precast Twin Wall
CASE 1 cont.
Assuming that the upper surface of the precast element has been formed as
EC2 6.2.5 (2) standard, the values for ‘smooth’ should be used for the coefficients c and m.
c = 0.2
m = 0.6
fctd = actfctk,0.05 / gC
act = 1.0
EC2 2.4.2
EC2 Table 3.1 gC = 1.5
fctk,0.05 = 2.5 MPa
fctd = 1 × 2.5 / 1.5
=1.67 MPa
sn = 0 (no normal force)
vRdi = (0.2 × 1.67)
vRdi = 0.334 MPa vRdi = 0.334 MPa
Limiting value of vRdi, calculated earlier:
vRdi, lim = 6.72 MPa
vRdi as calculated: = 0.585 < vRdi, lim = 6.72
so, use: vRdi = 0.334 MPa
56
Appendix C: Example calculations
Panel reinforcement
H10 @ 200 c/c EF vertically
H8 @ 250 c/c EF horizontally
Splice reinforcement
H16 @ 250 c/c
vertically 3050 mm
Vertical latices
@ 600 c/c
Figure C.9
Tying requirements
at horizontal joint
Figure C.10
Splicing requirements
at vertical joint
57
Precast Twin Wall
A B C D
A B C D
22 kN/m
A B C D
– 5 kN/m
58
Appendix C: Example calculations
5 Slenderness
The wall section in the top storey is identical to the botom storey therefore:
Slenderness ratio l = 31.4 l = 31.4
EC2 5.8.3.1 Min. slenderness lmin = (20 A B C ) / √(n)
A = 0.7
B = 1.1
rm = M01 / M02
where M01 and M02 represent the moments at the top and botom of the
member. These moments can be read from the analysis model (Panel C).
rm = – 47/ +62
= – 0.76 (Minimum rm for all panels)
C = 1.7 – rm
= 1.7 – (– 0.76)
= 2.46
Maximum ULS axial load (Panel D),
Nsd = 142 kN/m (Maximum for all panels)
59
Precast Twin Wall
CASE 2 cont.
= 6.8 mm
Mi = Nsd ei
= 142 × 0.0068
Mi = 1.0 kNm/m Mi = 1.0 kNm/m
According to clause 5.8.3.1 in EC2 where the column is non-slender, it should
EC2 5.8.3.1
be designed for first order internal moments and forces (ignoring second order
effects).
Summarising design forces for all panels (conservatively using maximum
moment and minimum axial force for each panel)
Panel A Mt = 81 + 1.0 = 82 kNm/m Nsd = 137 kN/m
Panel B Mt = 61 + 1.0 = 62 kNm/m Nsd = 48 kN/m
Panel C Mt = 62 + 1.0 = 63 kNm/m Nsd = 48 kN/m
Panel D Mt = 84 + 1.0 = 85 kNm/m Nsd = 142 kN/m
Input for column interaction charts, checking Panels C and D
Panel C,
Mt/bh2fck = 63 × 106 / 1000 × 3002 × 40
= 0.018
NEd/bhfck = 48 × 103 / 1000 × 300 × 40
IStructE = 0.004
EC2 Manual Panel D,
Appendix A
Mt/bh2fck = 85 × 106 / 1000 × 3002 × 40
= 0.024
NEd/bhfck = 111 × 103 / 1000 × 300 × 40
= 0.00925
Using IStructE EC2 Manual, an area of steel can be estimated from column
design charts.
Panel C,
Asfyk/bhfck = 0.03
As = (0.03 × 1000 × 300 × 40) / (500)
= 720 mm2/m (360 mm2 EF)
Panel D,
Asfyk/bhfck = 0.04
As = (0.04 × 1000 × 300 × 40) / (500)
= 960 mm2/m (480 mm2 EF)
H12 @ 200 c/c
Therefore, (565 mm2/m)
2
Use H12 @ 200 c/c EF (565 mm ) vert. steel
7 Wall reinforcement quantities are acceptable therefore proceed with joint design.
60
Appendix C: Example calculations
NA
Ft Z
x
30 mm s
bedding joint
Fc
A A d
Splice bar
required
to provide
Figure C.11 continuity
Forces acting on
horizontal joint Section A–A
Using Concrete Centre Spreadsheet TCC12, it can be shown that the H20 @ 200 c/c
reinforcement needed is H20’s @ 200 c/c (1570 mm2/m) for the vertical (1570 mm2/m)
splice (see page 73). vert. splice
61
Precast Twin Wall
CASE 2 cont.
Or 25 % vert. reinforcement:
Ashmin2 = 0.25 Asvprov
= 0.25 × 565
H8 @ 250 c/c
= 141 mm2/m EF (201 mm2/m)
2
Use H8 @ 250 c/c EF (201 mm /m) horiz. steel
This shows that the vertical steel reinforcement chosen for the splice and
panel are sufficient.
12 SLS CHECKS
A B C D
62
Appendix C: Example calculations
A B C D
A section analysis on the existing section with the existing SLS forces gives
the following for H20@200 c/c (N = 78 kN/m, M = 60 kNm/m);
ecc = 0.0005977
ect = – 0.002968
Neutral axis depth, x = 50 mm
as, Dcf = ect (l0/2)
l0 = 51f (conservatively using IStructE
EC2 Manual*)
= 51 × 20
= 1020 mm
13 By inspection this joint opening is excessive and we must adjust the design to
reduce this estimated value.
* The Institution of Structural Engineers. Manual for the design of concrete building structures to
Eurocode 2. 2006.
63
Precast Twin Wall
CASE 2 cont.
The model is adjusted so that the top storey wall has a top and botom joint
modelled as only 150 mm deep (applied to a nominal height of 300 mm)
A B C D
As the ULS bending values have changed we need to recalculate previous steps.
5 (pass 2) Slenderness
Slenderness ratio l = 31.4
rm = –22/ +35
= –0.63
lmin = 322
31.4 < 322
l < lmin ∴ Wall is non-slender
64
Appendix C: Example calculations
Using IStructE EC2 Manual, an area of steel can be estimated from column
design charts.
9 (pass 2) Wall reinforcement quantities are acceptable therefore proceed with remaining
design.
65
Precast Twin Wall
CASE 2 cont.
A section analysis on the existing section with the existing SLS forces gives
the following for H16@200 c/c (N = 78 kN/m, M = 32 kNm/m)
ecc = 0.0003469
ect = – 0.001933
Neutral axis depth, x = 46 mm
13.2.1 Further joint efficiency can be gained by using two rows of splice reinforcement.
We will try 2 no. rows of H16@200 mm to see if there is sufficient reduction in
calculated joint opening.
50 mm
2 no. rows 25 mm
H16@200 mm
splice 150 mm
reinforcement
25 mm
Figure C.12 50 mm
Plan section
66
Appendix C: Example calculations
A revised section analysis with the same SLS forces gives the following:
ecc = 0.0001966
ect = – 0.0007345
Neutral axis depth, x = 63 mm
as, ∆cf = ect (l0 /2)
l0 = 51f (conservatively using
IStructE EC2 Manual)
= 51 × 16
= 816 mm
Joint opening at face, Dcf = 0.007345 × 816/2
= 0.29 mm < 0.3 mm D < 0.3 mm OK
This joint opening on the wall face is acceptable for both aesthetics and durability.
8 to 13 By inspection, joint ULS capacity, tying and minimum reinforcement are acceptable. Use two layers
[Note: for ULS strength only H12@200 c/c are required] H16 @ 200 c/c
(Pass 3)
vert. splice
EC2 8.4.3
Anchorage length, lb,rqd = (f/4)(ssd/fbd)
EC2 8.4.2 fbd = 2.25n1n2fctd
EC2 Table 3.1
fctd = actfctk,0.05/gC
67
Precast Twin Wall
CASE 2 cont.
fbd = 2.25 × 1 × 1 (0.85 × 2.5/1.5)
= 3.19 MPa
ssd = 565 / 1005 × 0.87fyk
= 245 N/mm2
therefore, lb,rqd = (16/4)(245/3.19) lb,rqd = 307 mm
= 307 mm
vertically
Provide 545 mm anchorage length min. past the joint
EC2 8.7.3
Lap length, l0 = a1a2a3a5a6 lb,rqd
a1 = 1.0
EC2 Table 8.2 a2 = 1 – 0.15(Cd – f) / f
a2 = 1.0 conservative
a3 = 1.0
a5 = 1.0 conservative
EC2 Table 8.3 a6 = 1.5
EC2 8.7.2 EC2 8.7.2 states that the clear distance between lapped bars should not be
greater than 4f or 50 mm, otherwise the lapped length should be increased by the
clear space
Allowance = (150 – 25) – 50
= 75 mm
Total lap, lt = 461 + 75
= 536 mm + 25 mm end cover
= 561 mm
An additional lap length is required to allow for in-plane distance from splice bar to
latice. Assuming the latice spacing, s, is 600 mm and latice width, wi, is 100 mm.
Allowance to mobilise latice legs, llat = s/2 – wi /2
= 250 mm
Provide 811 mm lap length total
Therefore,
Total bar length = (2 × 811) + 30 mm joint + 300 mm (slab) l = 811 mm
= 1952 mm say 2000 mm vertically
68
Appendix C: Example calculations
defined as the area over which the force is transmited. Interface shear between
the in-situ and precast elements transmits the forces from the joint splice
reinforcement to the reinforcement in the precast panels. Therefore we must check
that there is sufficient capacity at the interface to allow this to occur.
therefore,
vEdi < vRdi
0.53 < 2.12
vEdi < vRdi therefore steel sufficient for interface shear
69
Precast Twin Wall
Panel reinforcement
H12 @ 200 c/c EF vertically
H8 @ 250 c/c EF horizontally
Splice reinforcement
H16 @ 200 c/c
vertically 2875 mm
Vertical latices
@ 600 c/c
Figure C.13
Tying requirements at
horizontal joint
Figure C.14
Splicing requirements
at vertical joint
70
Appendix C: Example calculations
Key 1
and modelling
Agree preliminary panel Revise structural arrangement
Panel layout
LOR/Contractor preferences Preliminary joint layout
layout with LOR/Contractor or thicken wall.
Case 1
2 Analyse structure
Geometry and loads
Case 2 assuming gross elastic stiffness
CASE 2
5 Add geometrical
Critical ULS load combinations, imperfections and 2nd order
Critical ULS load combinations
geometrical imperfections and effects to ULS moments as
including additional effects
2nd order effects appropriate in accordance with
BS EN 1992-1-1
details, concrete and steel combined moments and axial forces thickness and reinforcement details
design strengths, fyd, fcd
9
Horiz. joint design, buildability, Horiz.
joint design No Confirmation of ULS
client’s requirements,
acceptable horiz. joint design
cost efficiency
at ULS?
Yes
10
Yes
CASE 1
CASE 2
CASE 2 – Pass 2
CASE 2 – Pass 1
Tying check
11
Vertical tying force
Sufficient
(BS EN 1992-1-1:2004 No 11.1 Additional reinforcement to meet
reinforcement for
cl. 9.10.2 and minimum Add reinforcement tying or minimum reinforcement
vert. tying and
reinforcement requirements requirements
As,min?
(BS EN 1992-1-1:2004 cl. 9.6)
Yes
Yes
12 13.2.1
Estimate horiz. Joint opening
from critical SLS load combinations Efficiency
Critical SLS load combinations significantly improved No Expected joint opening
with multiple
SLS checks
layers?
19 18.1.2
Finalise wall design Add
Revised lattice spacing, s
and panel layout additional lattices
71
Precast Twin Wall
8000
7000
Mmin
6000
5000
Axial compression, NEd kN
4000
3000
2000
0.1 A c f ck
1000 866
734
69579
0
SECTION OK
–1000
–400 –300 –200 –100 0 100 200 300
Moment, MEdxx kNm
72
Appendix C: Example calculations
8000
Mmin
7000
6000
5000
Axial compression, NEd kN
4000
3000
2000
0.1 A c f ck
1000
142
137
4848
0
–1000
SECTION OK
–2000
–400 –300 –200 –100 0 100 200 300
Moment, MEdxx kNm
73
Precast Twin Wall
8000
7000
Mmin
6000
5000
Axial compression, NEd kN
4000
3000
2000
0.1 A c f ck
1000
111
91
48
0
SECTION OK
–1000
–400 –300 –200 –100 0 100 200 300
Moment, MEdxx kNm
74
Appendix D: Model specification
1.1 Scope 76
1.2 Definitions 76
1.3 Associated information 76
1.4 Time periods 76
2.1 Responsibilities 76
2.2 Transfer of design information 76
2.3 Provision of vertical ties 77
2.4 Health and safety 77
2.5 Detailed drawings 77
3.1 General 77
3.2 Materials 78
3.2.1 Concrete 78
3.2.2 Reinforcement 78
3.3 Formed finishes 78
3.4 Tolerances 78
3.5 Curing 78
3.6 De-moulding 78
3.7 Marking 79
3.8 Records 79
3.9 Quality system 79
5.1 General 81
This model specification offers guidance to organisations that are producing specifications for precast twin wall. It is intended to cover
additional considerations for the use of precast twin wall within building structures, and does not represent a concrete specification. It shall be
the specifier’s responsibility to ensure that the contract specification is suitable and meets the requirements of the contract.
75
Precast Twin Wall
1 General
1.1 Scope
This model specification is intended to provide guidance on the manufacture, supply and erection of the
precast double wall panels within the building.
1.2 Definitions
For the purposes of this document the following definitions shall apply:
The Specialist Precast Concrete Contractor shall produce detailed drawings and manufacture and supply the
precast twin wall panels for erection by the Main Contractor as detailed herein. The Engineer shall produce
drawings for continuity reinforcement at joint locations separately.
76
Appendix D: Model specification
The Specialist Precast Concrete Contractor shall provide the locations of all horizontal and vertical joint
positions to allow the associated design checks to be completed by the Engineer.
These drawings shall be issued in accordance with the agreed protocols and programmes.
The Specialist Precast Concrete Contractor shall carry out an assessment of risk throughout the detailing
process and shall include mitigating measures wherever it is deemed reasonably practicable to do so (see
Section 5).
The Specialist Precast Concrete Contractor shall carry out all necessary design checks for lifting and handling
in accordance with the relevant health and safety legislation.
The Specialist Precast Concrete Contractor shall add details of the maximum rate of concreting to the
detailed drawings/information issued to the Main Contractor.
The Specialist Precast Concrete Contractor shall give due regard to the location and interaction of the precast
panels relative to penetrations and panel connections.
Wall panel reinforcement shall be detailed in accordance with the relevant parts of BS EN 1990, BS EN 1991,
BS EN 1992, and their corresponding UK National Annexes.
Drawings shall be submitted for the Engineer for review no later than 2 weeks prior to the date necessary
for manufacture.
77
Precast Twin Wall
3.2 Materials
3.2.1 Concrete
The Engineer shall advise the Specialist Precast Concrete Contractor of the strength and durability
requirements for the precast concrete, and any special requirements regarding the concrete specification,
on transfer of the design information (see Section 2.2). The Specialist Precast Concrete Contractor shall
submit confirmation of concrete mix details for review by the Engineer no later than 2 weeks prior to the date
necessary for manufacture.
All precast concrete shall comply with the project Structural Specification. The Specialist Precast Concrete
Contractor shall advise the Engineer of any practical requirements or limitations regarding the precast
concrete specification and the Engineer shall ensure that the project Structural Specification is revised to
include necessary amendments where appropriate.
The Specialist Precast Concrete Contractor shall arrange for sampling and conformity testing of the precast
concrete in accordance with BS EN 206-1, BS EN 12350 and BS EN 12390 or as defined in the project
Structural Specification where more onerous.
3.2.2 Reinforcement
All reinforcement shall comply with the project Structural Specification.
Reinforcement cages and lattice girders shall be made up and securely fixed in accordance with the Engineer’s
design information to provide adequate rigidity and to ensure that the specified cover and fit within the mould
are achieved.
Reinforcement up to 12 mm in diameter that projects from the face of the units may be bent to facilitate the
casting or de-moulding of the unit subject to agreement for each case. The reinforcement shall not be re-bent
to its final position in the structure without the approval of the Engineer.
For concrete surfaces to be exposed in the completed structure the type of spacer blocks used shall be
agreed with the Engineer in advance.
3.4 Tolerances
Permitted dimensional deviations shall be in accordance with the relevant requirements of BS EN 14992,
BS EN 13369 and BS EN 1992-1-1 or the project Structural Specification if more onerous. Before manufacture
the Specialist Precast Concrete Contractor shall ensure that adequate allowances have been made for all
construction tolerances to ensure proper fit.
3.5 Curing
Curing of precast units shall be carried out in accordance with BS EN 13369: 2004.
3.6 De-moulding
For precast concrete units cast under factory conditions the minimum period before removal of the formwork
shall be at the discretion of the Specialist Precast Concrete Contractor on the basis of the assessed
compressive strength of the unit.
No unit shall be lifted from the base on which it was cast before the concrete has attained its design de-
moulding strength and is strong enough to prevent the unit from being damaged, overstressed or distorted
78
Appendix D: Model specification
having due regard for the de-moulding equipment to be used. In no case shall the assessed compressive
strength be less than C6/8 N/mm2 at de-moulding.
3.7 Marking
Each precast unit shall be marked or labelled in accordance with BS EN 13369: 2004 cl. 7. Reference should
also be made to Annex ZA of BS EN 14992: 2007.
All marks shall be positioned so that they are hidden from view in the completed structure or may be removed
without marking the concrete surface.
3.8 Records
The Specialist Precast Concrete Contractor shall keep records of the unit mark, the composition of the unit,
the date of manufacture, the date of release from the mould and the curing regime. These records shall be
kept on site and made available for inspection by the Engineer.
Storage instructions for precast units shall include the storage position, the allowable support points, the
maximum height of any stack and any protective measures required.
Unit faces to be exposed in the completed construction shall be protected from mechanical damage, dirt,
staining, rust marks or other disfiguration.
The Specialist Precast Concrete Contractor shall transport the precast units to site in a safe and secure
manner. During transport the precast units shall be protected from mechanical damage, dirt, staining or
disfiguration.
Any inserts or fixings required by the Specialist Precast Concrete Contractor to be cast in the concrete and
permanently exposed either externally or within the cavity of the building envelope shall be of stainless steel
unless agreed otherwise with the Engineer.
79
Precast Twin Wall
The Main Contractor shall ensure that any precast concrete unit to be incorporated into the structure is kept
stable in its erected position until such time as the element can safely carry the construction loads without
distress. The overall stability of the structure shall be maintained at all times during erection.
The Main Contractor shall ensure that the rate of concreting for the in-situ concrete does not exceed the
recommendations of the Specialist Precast Concrete Contractor.
Any shims provided for temporary support, and remaining in the completed structure, should be sufficiently
deformable with a stiffness less than that of the concrete at its 28-day strength. Details of the shims shall be
submitted to the Engineer by the Main Contractor for agreement prior to installation.
■ Procedures for lifting of the precast units and positioning to tolerance (including fitting over the starter
bars).
■ Methods of providing temporary stability including coordination with the pour sequence.
■ Methods for shimming/bedding and achieving verticality to tolerance (if required).
■ Methods of fixing continuity reinforcement at wall joints and corners.
■ Procedures for cleaning and preparing the internal faces of the precast panels prior to concreting.
■ Methods of placing concrete to achieve suitable compaction at the base of the wall and to limit
pressure on precast formwork.
■ Methods of casting at corners and openings.
■ Details of records kept.
4.5 Materials
4.5.1 General
All in-situ concrete and reinforcement installed on site shall be in accordance with the project Structural
Specification.
4.5.2 Testing
The Main Contractor shall arrange for sampling and conformity testing for all cementitious products used
during installation in accordance with BS EN 206-1, BS EN 12350 and BS EN 12390 or, where more onerous,
as defined in the project Structural Specification.
80
Appendix D: Model specification
The Main Contractor shall document and implement all necessary precautions for safe working during
installation operations.
81
Laing O’Rourke plc
Bridge Place
Anchor Boulevard
Admirals Park
Crossways
Dartford
Kent
DA2 6SN
T +44 (0)1322 296200
F +44 (0)1322 296262
E [email protected]
www.laingorourke.com
Readers should note that all Laing O’Rourke publications are subject to
revision from time to time and should ensure that they are in possession
of the latest version.