Method Statement For FA
Method Statement For FA
Contractor:
MALAIH INVESTMENT & PROJECT DEVELOPMENT L.L.C.
Consultant:
Document Title
Method Statement for Installation, Testing & Commissioning of Fire alarm System
with voice evacuation and CO detection
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 2 of 28 Rev.00
with voice evacuation and CO detection
INDEX
Contents
1. PURPOSE............................................................................................................................3
2. SCOPE OF WORKS...............................................................................................................3
3. REFERENCES...................................................................................................................... 3
4. RESOURCES........................................................................................................................4
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 3 of 28 Rev.00
with voice evacuation and CO detection
8. QUALITY REQUIREMENTS..................................................................................................23
9. ATTACHMENTS................................................................................................................ 23
1. PURPOSE
This document describes the methodology for the Installation, Testing and Commissioning of fire
alarm system for “RADIANT SQUARE AT CITY OF LIGHTS" and to ensure that all concerned
persons are familiar with the sequence of activities, utilization of resources, and execution of the
works in compliance with the Project Specification and drawings.
2. SCOPE OF WORKS
This Method statement covers the Installation, Testing and Commissioning of fire alarm system
within “RADIANT SQUARE AT CITY OF LIGHTS” project including one-year free maintenance,
liability for rectification of defects, and handing over of the subject works at the above-mentioned
project as per the specifications and drawings transmitted to us.
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 4 of 28 Rev.00
with voice evacuation and CO detection
The objective is, to ensure that the construction plan is executed, controlled and documented in
compliance with the approved drawings and specifications.
Commissioning is the process of testing the performance of equipment and systems to determine
their capability to meet performance requirements as defined in the specification prepared by the
manufacturer. It may also include the provision of training and documentation necessary for the
owner’s personnel to competently operate and maintain the equipment or system.
Testing is the period that takes place following the contractor start-up program and the Consultant
Verification Program and after a formal training seminar for the system operators has been held.
Testing is a series of operating tests carried out by the owner (performance Testing Program). These
tests are carried out independent of the project team and should be performed under simulated
operating conditions.
3. REFERENCES
4. RESOURCES
The Construction Manager in conjunction with experience Manager will assess the manpower
requirements for the Installation, Testing and Commissioning of Fire alarm System to meet the
schedule. Typically, these will include:
Construction Manager
Site Supervisor
QA/QC Engineer/Supervisor
Foreman
Electricians
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 5 of 28 Rev.00
with voice evacuation and CO detection
General Labourers
HSE Supervisor
T&C Engineer
4.1 Competency
The competency of all construction personnel shall be controlled in accordance with the Competent
Persons Designation Procedure below;
Prior commencement of activity, HSE engineer will brief the work force induction talk on
project site safety requirements.
Maintain records of accidents & enforce PPE on all staff.
Inspecting Sites and making sure all the machines and equipment deployed at site are
comply with fitness standard.
Monitoring and providing support during construction of facilities and equipment.
Identifying hazardous situations and safety controlled actions.
Keeping and maintaining company safety records.
Identify & manage risks associated with the project environment and processes while
complying with regulatory requirements & corporate standard.
Responsible for Maintain a proactive and demonstrable safety performance that includes
compliance with all safety, health & environmental policies and procedures.
Manage & submit HSE reports as required.
Work effectively with various departments throughout the project to resolve compliance
issues.
General Foreman
General Foreman is responsible for following.
Site Surveyor
The site surveyor is responsible for the following.
Check layout and level for form work as per drawings.
Report to CM/PM if any discrepancy found in site condition & drawings and take advice for
further action prior proceeding with next activity.
Making sure all the equipment used in survey must be calibrated as per planned interval.
The list of the machinery to be used in the job is as per the following:
Portable Hand Tools
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 7 of 28 Rev.00
with voice evacuation and CO detection
TESTING TOOLS
General Tool Box (Pliers, Screw Drivers etc.)
Calibrated Multi-meter for continuity checks
Solo Testing Aerosol – This is UL listed test gas which universally used to test smoke
detectors and comes in 200ml containers.
Heat Generator – This is a battery operated UL listed heat generator
Smoke Pole
Simplex key (for manual call point)
CO Detector testing kit
Proper labelling shall be done for the identification of the loops, telephone & speaker
circuits.
The loop cables to be terminated in the IDNET Terminal block. Cables to be terminated
in the A+, A- shield and B+, B- , shield.
The fire rated loop cable to be installed inside the 25mm G.I conduits on the concrete
slab fixed by clips each at a distance of 1m. Circular G.I back box to be installed on the
slab to mount the detector base.
The cables are entered in to the circular G.I. back box and then terminated in the +ve
and –ve terminals of the detector base.
Ceiling-Mounted Smoke Detectors: Not less than 100 mm from a sidewall to the near edge.
On smooth ceilings, install not more than 9 m apart in any direction. The selection and
placement of smoke detectors shall take into account both the performance characteristics of the
detector and the areas into which the detectors are to be installed to prevent nuisance alarms or
improper operation after installation. Smoke detectors shall not be installed in areas where air
velocity is greater than 1.5m/sec, and shall not be located in a direct airflow. If sitting of
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 9 of 28 Rev.00
with voice evacuation and CO detection
detectors in such areas is unavoidable, use detectors specifically designed for use in such
conditions Spacing of detectors for irregular areas, for irregular ceiling construction, and for high
ceiling areas shall be determined according as shown on the drawings. Locate detectors not
closer than 300 mm from any part of a lighting fixture.
The fire rated loop cable shall be installed inside the 25mm PVC conduits which is
embedded on the concrete slab. Circular G.I back box to be installed on a steel rod/ thread
above the detector location in the false ceiling
The loop cables to be brought down to the G.I. mounting box on the false ceiling. Extra
lengths of cable to be considered for relocation.
The detector base to be installed on the G.I. mounting box on the false ceiling and the
cables are terminated in the +ve and –ve terminals of the detector base.
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 10 of 28 Rev.00
with voice evacuation and CO detection
The selection and placement of smoke detectors shall take into account both the performance
characteristics of the detector and the areas into which the detectors are to be installed to prevent
nuisance alarms or improper operation after installation. Smoke detectors shall not be installed in
areas where air velocity is greater than 1.5m/sec, and shall not be located in a direct airflow. If
sitting of detectors in such areas is unavoidable, use detectors specifically designed for use in such
conditions.
Before installing the detectors binary address need to be assigned in the DIP switch located at the
rear side of the detectors as per the approved schematic diagram.
Void detectors shall be used if the ceiling void is greater than 80cm.
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 11 of 28 Rev.00
with voice evacuation and CO detection
6.1.3 Heat Detector: Control panel to select alarm to be per sensor as fixed temperature, or rate-of-
rise temperature, or the combination of both.
Exact location and mounting height shall be marked as per the approved shop drawings.
Fix the G.I. standard back box- approved & recommended by the manufacturer, in place
based on approved shop drawings and as per manufacturer recommendations.
The Fire fighter’s telephone jack, manual call points, and wall mounted speakers shall be
mounted separately fastening it to the provided G.I. back box - approved & recommended
by the manufacturer with mounting plate flush mounted in the wall for all the locations as
mentioned in the approved drawings.
Install the devices and terminate the cable properly by using fire rated cable glands.
Fixing shall be done as per manufacturer recommendations.
Device identification / label should be provided as per the approved device addressing
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 13 of 28 Rev.00
with voice evacuation and CO detection
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 14 of 28 Rev.00
with voice evacuation and CO detection
Install the sounders with Flashers at 2300 mm above the finished floor as indicated on the fire
alarm drawings.
Install the strobe light as per the approved shop drawings and manufacturer’s instructions.
Install the sounders with Flashers not more than 2300 mm above the finished floor in
coordination with the false ceiling, as indicated on the fire alarm drawings and wall
coordination drawing of internal and External. Sounders with Flashers are installed on back
boxes with the device-operating mechanism concealed behind a grille. Combine audible
and visible alarms at the same location into a single unit.
Check the installation and alignment of the device.
Terminate cabling to the device
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 17 of 28 Rev.00
with voice evacuation and CO detection
Install the speakers and sounders not more than 2300 mm above the finished floor
as indicated on the Approved fire alarm drawings.
Fire Cables shall be terminated into the fire dome using fire rated glands as per
manufacturer’s recommendation.
Termination shall be done using approved fire rated glands
Speakers shall be spaced as per standards/coverage calculation and in coordination
with approved RCP layouts/shop drawings
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 18 of 28 Rev.00
with voice evacuation and CO detection
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 19 of 28 Rev.00
with voice evacuation and CO detection
Ensure that no power is applied to the 4100ES fire alarm panel and that all wiring is
properly connected.
Use the green grounding lug in the control panel for all measurements to ground. Each
circuit must test free of all grounds and extraneous voltages.
Use the volt/ohm meter to check each circuit type.
At the control panel, locate wires from each initiating device or indicating appliance circuit.
Check each circuit for extraneous voltage by setting the volt / ohm meter to 300VAC. The
meter must read 0 volts.
Set the volt / Ohm meter to 60 VDC .The measurements must read 0 volts.
Check all other system wiring to verify that each circuit is free of grounds and extraneous
voltages.
Continuity Test
Continuity test shall be done on all the circuits before the fixing of devices to ensure that
there is no breakage in the conductor of cables. A multi meter shall be used for the purpose.
Plug the multi meter terminals between the two cores keeping it in the continuity mode after
shorting the cables in the loop/circuit end. If there is no breakage a buzzer will be heard
indicating continuity.
6.3.1 Type of initiating devices used in this project and their test methods are as follows:
Smoke detector- Apply SOLO Aerosol in the smoke detector chamber until red LED
glows steady
Heat detector – Switch on and place the heat generator covering the detector until the
red LED glows steady.
CO Detectors – Apply CO Test Gas on the CO Detector till the CO detector is detected.
Manual Call Point – Open the MCP using Simplex key.
Sprinkler Flow switch – Open the Test drain valve until FACP receives FIRE signal.
(Sprinkler Supplier coordination required).
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 20 of 28 Rev.00
with voice evacuation and CO detection
Reset the break glass unit and reset the fire alarm panel by pressing Reset Button.
This test can be combined with the device testing.
Leave the alarm system active for the first device test, check the audible signals
and then silence the alarm system for the remaining device testing.
6.3.8 Function test of devices shall be carried out loop by loop (randomly) as follows:
Activate the devices described in 6.3.1. one by one.
Function test will annunciate to the following panels: 1. Main FACP, Graphics command
center. The annunciation includes panel buzzer, LCD display of location and graphics
annunciation.
Check whether the Speakers, sounders and flashers and Horns are functioning.
If the test result is successful, move to the next device and continue the test up to the
consultant’s or CM’s acceptance.
If the “Alarm Silence” button is pressed, it will stop all audible & visual notifications and
an “ALARM SILENCE IN PROGRESS” message will show in the FACP prior to stop the
appliances.
If the “SYSTEM RESET” button is pressed, “SYSTEM RESET IN PROGRESS”
message will display and reset will take place. Alarm will be cleared after a successful
reset or the panel will show a message that “ALARM PRESENT, SYSTEM RESET
ABORTED”.
An “All speaker evac” toggle button is assigned in the FACP to play the evacuation
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 22 of 28 Rev.00
with voice evacuation and CO detection
message in the building without disturbing the control modules of other interfaces.
Highly Extremely
Corrosive Oxidizing Toxic Irritating Harmful Explosive
flammable flammable
Danger for
Constrained Slippery Danger of Falling from
the Other
Space Surface Electrocution Height
Environment
__________________
__________________
__________________
__________________
The hazards identified above will be controlled under the overall Project Safety Plan which is a
separate document communicated to all parties on the project.
The works subject of this document requires that the following PPE be used:
Gloves Safety Shoes Protective Safety Equipment
Lifejacket Other
Required Required Clothing Harness Guards
Scaffolding is
required______________
____________________
____________________
___________________
_
Before commencing any works, all employees will attend a site safety induction training to
ensure all safety measures are understood and implemented and to cover specific procedures
in case of emergency. If necessary, practical training exercises will be conducted on escape
routes, signage, evacuation and rescue.
Prior to the commencement of site activities, the Supervisor, with support from the HSE
Officer, shall conduct a pre-start toolbox talk with all the crew present. The Supervisor shall
explain this method statement to the appointed trained personnel who will visit the site
regularly focusing on the hazards and risks involved in the activity and the mitigation
measures that shall be taken as detailed in the Risk Assessment.
This will include a practical talk-through of the work to be completed and the delegation of the
individual roles and responsibilities of the team members in conducting the work.
Regular Toolbox talks shall be conducted in order to prevent complacency within the crew.
The Supervisor shall conduct a Pre-start toolbox talk for the new person/s prior to starting
work.
8. QUALITY REQUIREMENTS
Work should be approved by Engineer.
The approved Inspection & Test Plan shall be strictly followed.
9. ATTACHMENTS
ITP
INSTALLATION CHECKLIST
PRE-COMMISSIONING CHECKLIST
T&C CHECKLIST
RISK ASSESSMENT
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 25 of 28 Rev.00
with voice evacuation and CO detection
INSTALLATION CHECKLIST
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 27 of 28 Rev.00
with voice evacuation and CO detection
PRE-COMMISSIONING CHECKLIST
RADIANT SQUARE
AT CITY OF
LIGHTS
Method Statement for Installation, Testing & Commissioning of Fire alarm System Page 28 of 28 Rev.00
with voice evacuation and CO detection
RISK ASSESSMENT