MS FOR T&C OF 22kV Switchgears
MS FOR T&C OF 22kV Switchgears
TO : ASK-JV
2. References
5. General Checks
6. Functional Checks
14. Records
15. Responsibilities
This document covers the procedures/methods for carrying out the site acceptance tests on
the GMA MV Switchgear panels.
The purpose of the document is to control the testing of GMA panels in line with
project commissioning specification requirements to achieve the optimum results.
a) General Checks
b) Functional checks
c) Tests on Circuit Breaker
d) Tests on Current Transformer
e) Tests on Over current and earth fault relay
f) Tests on Auxiliary relays
g) Tests on Ammeter
h) IR & Power frequency voltage test on Busbars
5. General Checks
6. Functional Checks
A functional test of all low-voltage circuits shall be made to verify the proper functioning
of auxiliary and control circuits in conjunction with the other parts of the Circuit breaker.
Test Instruments required: Primary current injection kit & Clamp meter
This test will be conducted on Switchgear panels, where CTs are used to ensure the
CT ratio, functioning of Relays and meters.
Incoming & Outgoing busbar terminals of the switchgear panel to be connected to
the primary injection kit.
By Injecting current/voltage from the injection kit to required value, reading of meters
and relays to checked.
6.3 Breaker & Earth switch aux. contacts and potential free contacts check
Auxiliary contacts of the breaker & earth switch’s to be checked in respect to the
close / open and test / service positions breaker and close / open positions of the
Earth switch.
Manual closing & opening of the earth switch using the handle provided along with the panel to be verified.
6.7. Mechanical & Electrical interlocking between circuit breaker and Isolator with Earth
Switch
Mechanical & Electrical interlocks for CB and Isolator switch with respect to
open/close of Earth switch to be verified. Refer schematic drawings of the respective
project for detailed information.
Voltage presence relay is used for blocking the earth switch operation when HT lines
are live. Relay operation to be checked with line VT supply presence and earth switch
operation.
Trip circuit supervision shall be used for the monitoring of the trip circuit. The trip
circuit healthy lamp will be provided on the panel for indicating the trip circuit
supervision.
Breaker close / open operations to be verified by operating the push buttons provided
on the breaker chamber.
Manual spring charging to be checked by using spring charging rod provided along
with the breaker.
Circuit breaker and Isolator mechanical interlocking to be checked by operating
breaker and Earth switch.
In this test, closing and opening time taken by the circuit breaker to be measured Test
Procedure:
Connect the CB analyser kit, time measurement probes to incoming and outgoing
terminals of the circuit breaker.
Connect close / trip coil and spring charging motor supply terminal of the test kit to
close / trip coil of the Circuit breaker
Switch on the AC/DC supply to the test kit and operate the breaker for 2 to 3 close /
open operations
CB analyser kit records the all closing and opening operations with operating timings.
7.5 Combined Circuit Breaker and connecting Busbar contact resistance test of
adjacent Panels
In this test, the resistance of the each phase shall be measured at ambient temperature
Test Instruments required: Micro-ohm meter
Procedure:
Connect the micro-ohm meter measuring terminals to the R-phase bottom pole of first
panel and R-phase bottom pole of adjacent Panel.
Switch on the micro-ohm meter and measure the contact resistance at 100A DC.
Similarly repeat the procedure for Y & B phase also.
8. Tests on Current Transformer
Switch on the supply to CT analyzer and note the CT ratio of the Secondary winding at
ambient temperature.(All the values recorded in the kit memory card)
Verify the Make, Model and name & rating plate details
Check the physical condition of the component
Test Procedure
Configure the pick up (current/voltage/frequency) and tripping time values
Check the pick up value by gradually varying input and note the pickup value.
Check the operating time with a specific abnormal quantity of current / Voltage /
Frequency and it should be within the acceptable value to the configured value
Check the BI & BO contacts and LED indications.
Test procedure
Connect the measuring terminals of the meters to an injection kit or respective
external source.
Inject the measuring parameter and note down the indicating values of the meter.
Check the indicating values are in respect to meter ratios.
Test Instruments required: Primary current injection kit ISA & Clamp meter
Test Procedure:
Test Procedure
Measure the winding resistance on secondary of the VT
Check the resistance of the each phase shall be measured at ambient temperature.
12.4 Measurement of Insulation Resistance
Test Procedure:
Short the secondary terminals and connect to the VT body frame and to earth
Short the primary terminals and connect the Insulation tester measuring between
primary and earthed secondary terminals.
Now, Check the IR with a test voltage of 500V between secondary terminals to earth
by shorting the primary terminal to earth.
The switchgear bus bar system should withstand the power frequency withstand voltage for
one minute without any disruptive discharges. If any disruptive discharge occurs during the
test, then the test shall be repeated on the same apparatus with some maintenance.
14. Records
The measured parameters for the above mentioned tests shall be recorded in the SAT formats
for reference and verification.
15. Responsibilities:
To ensure that all the preparation and application works are carried
out according to the Contract Specification.
To ensure and confirm that latest approved drawings are used for testing
&commissioning.
To ensure that the switchgears are new and undamaged and as per approved
submittal and as per specification.
To check the installation layout and location is as per approved drawing
and workmanship is acceptable, complete and in compliance with
project documents.
To facilitate the submission of ITR and ensure that the documentation
is complete and duly signed by all concerned parties.
To follow up the approval of the ITR with the consultant and logging the
status to the inspection.
16.1 All work shall be controlled as per site HSE procedures and OSHAD SF.
16.2 Site Engineer / Supervisor will check and ensure all safety precautions are
taken prior to commencement of work. Also, to ensure a pre-task brief is
conducted to personnel involved in the task.
16.3 Task specific PPE must be worn at all times during work including hard hat,
gloves, safety glasses, safety shoes, dust mask and coveralls.
16.4 Safe access to work location shall be provided at all times. Working on
scaffolding platform greater than 1.8m high, personnel must ensure it is green
tagged “safe to use” (by certified scaffolding foreman) & also done a full
body harness & observe 100% tie off.
16.5 Permit to work must be obtained from ASK-JV HSE Department.
16.6 Any injury sustained whilst at work must be treated by a trained First Aider and
also by site Nurse. The Site Nurse will determine if hospital treatment is
required.
16.7 The HSE Officer/Inspector shall verify the hazard and risk assessment form and
make sure that the controls are being implemented as per the approved Risk
Assessment.
16.8 The HSE Officer/Inspector shall conduct HSE Induction for new workers and all
HSE related toolbox talks.
16.9 HSE Officer shall ensure that all needed Personal Protective Equipments (PPEs)
are available.
16.10 The Engineers/Foreman shall ensure that PPEs (Coverall, Safety Shoes, Helmet,
High Visibility Vest & task specific such as Mask, Gloves, Safety Glass,
Goggles & Ear Plug) issued to the workers are worn at all times while
performing the task. HSE operatives will randomly verify the same.
16.11 The following OSHAD SF Codes of Practices will be strictly followed:
16.12 OSHAD SF- COP 2.0 – Personal Protective Equipment – V 3.0 July 2016.
16.13 OSHAD SF- COP 11.0 – Safety in Heat – V 3.0 July 2016.
16.14 OSHAD SF- COP 14.0 – Manual Handling and Ergonomics – V 3.0 July 2016.
SWITCHBOARD NAME:
FEEDER NAME:
MAKE: CLASS:
RATIO: SR.NO :
L1 L2 L3 L1 L2 L3 L1 L2 L3
1.
CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. RELAY TEST KIT PROGRAMMA
2. MULTIMETER FLUKE
SIGNATURE:
DATE:
SECONDARY INJECTION TEST ON ANALOG VOLTMETER
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
ANALOG VOLTMETER
MAKE: CLASS:
RATIO: SR.NO :
U1 U2 U3 U1 U2 U3 U1 U2 U3
1. 50 75 110 10 15 22
CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. Relay Test Kit Omicron
2.
WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:
SIGNATURE:
DATE:
MEASUREMENT OF BUSBAR CONTACT RESISTANCE
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
R
Y
B
SIGNATURE:
DATE:
CIRCUIT BREAKER TESTS
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
2. FUNCTIONAL CHECKS:
GENERAL CHECKS:
3. FUNCTIONAL CHECKS:
SIGNATURE:
DATE:
MEASUREMENT OF CIRCUIT BREAKER CONTACT
RESISTANCE
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
RATED CURRENT:
BAYS:
SL.NO’S:
SIGNATURE:
DATE:
CURRENT TRANSFORMER PRIMARY INJECTION TEST
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
2. TRIP TEST
RELAY SETTING CURRENT
TRIP CURRENT ON
PHASE REFERENCE (A) PHASE OPERATED
CURVE I> t> PRY (A)
R PHASE SI 0.5 0.1 328.0 OK
RY PHASE SI 0.5 0.1 330.7 OK
RB PHASE SI 0.5 0.1 327.0 OK
Earth Fault SI 0.2 0.1 132.0 OK
WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
2. TRIP TEST
RELAY SETTING CURRENT
TRIP CURRENT ON
PHASE REFERENCE (A) PHASE OPERATED
CURVE I> t> PRY (A)
R PHASE SI 0.5 0.1
RY PHASE SI 0.5 0.1
RB PHASE SI 0.5 0.1
Earth Fault SI 0.2 0.1
WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
2. TRIP TEST
WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:
SIGNATURE:
DATE:
CURRENT TRANSFORMER TEST
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
CT-1
MAKE: SCHNEIDER CLASS: TYPE Core-1 Core-1
1FS10 5P20
TAP 1
RATIO: BURDEN:
TAP 2
TYPE: PURPOSE: PROTECTION & METERING
SERIAL NO.
APPLIED
TEST POINTS VOLTAGE R Y B
(VOLTS)
PRIMARY TO EARTH 5000
SECONDARY(Core-1)TO EARTH 500
SECONDARY(Core-2)TO EARTH 500
Core-1 TO Core- 2 500
PRIMARY TO SECONDARY 5000
3. POLARITY TEST:
TEST POINT R Y B
AT CT SEC. (CT- 1-1)
AT CT SEC. (CT- 1-2) REFER OMICRON CT ANALYZER TEST REPORTS
-
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
6. RATIO CHECK:
TEST POINT CT RATIO R Y B REMARKS
PRIMARY INJECTED
CURRENT (A)
MEASURED REFER OMICRON CT ANALYZER TEST REPORTS
SEC. CURRENT
(A)
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY TH E MANUFACTURER
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
CT-1
MAKE: SCHNEIDER CLASS: TYPE Core-1 Core-1
1FS10 5P20
TAP 1
RATIO: BURDEN:
TAP 2
TYPE: PURPOSE: PROTECTION & METERING
SERIAL NO.
APPLIED
TEST POINTS VOLTAGE R Y B
(VOLTS)
PRIMARY TO EARTH 5000
SECONDARY(Core-1)TO EARTH 500
SECONDARY(Core-2)TO EARTH 500
Core-1 TO Core- 2 500
PRIMARY TO SECONDARY 5000
3. POLARITY TEST:
TEST POINT R Y B
AT CT SEC. (CT- 1-1)
AT CT SEC. (CT- 1-2) REFER OMICRON CT ANALYZER TEST REPORTS
-
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
6. RATIO CHECK:
TEST POINT CT RATIO R Y B REMARKS
PRIMARY INJECTED
CURRENT (A)
MEASURED REFER OMICRON CT ANALYZER TEST REPORTS
SEC. CURRENT
(A)
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY TH E MANUFACTURER
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
CT-1
MAKE: SCHNEIDER CLASS: TYPE Core-1 Core-1
1FS10 5P20
RATIO: BURDEN: TAP 1
SERIAL NO.
APPLIED
TEST POINTS VOLTAGE R Y B
(VOLTS)
PRIMARY TO EARTH
SECONDARY(Core-1)TO EARTH
SECONDARY(Core-2)TO EARTH
Core-1 TO Core- 2
PRIMARY TO SECONDARY
3. POLARITY TEST:
TEST POINT R Y B
AT CT SEC. (CT- 1-1)
AT CT SEC. (CT- 1-2) REFER OMICRON CT ANALYZER TEST REPORTS
-
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
SIGNATURE:
DATE:
OVER CURRENT AND EARTH FAULT RELAY TESTING
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
2. METERING CHECK:
INJECTED PRIMARY CURRENT READ ON RELAY DISPLAY
INJECTED
PHASE CURRENT EXPECTED READING (A) ACTUAL READING (A)
(A) R Y B N R Y B N
RY 1.0
YB 1.0
BR 1.0
RN 1.0
YN 1.0
BN 1.0
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
3. IDMT CHARACTERISTICS:
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
OUTPUT-1 (RL1)
OUTPUT-2 (RL2)
OUTPUT-3 (RL3)
OUTPUT-4 (RL4)
OUTPUT-5 (RL5)
OUTPUT-6 (RL6)
WD
6. CHECK THE STATUS INPUTS:
INPUT L2
INPUT L3
7. TESTING INSTRUMENT DETAILS:
CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. RELAY TEST KIT
2. MULTIMETR
SIGNATURE:
DATE:
STANDBY EARTH FAULT RELAY TESTING
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
2. METERING CHECK:
INJECTED PRIMARY CURRENT READ ON RELAY DISPLAY
INJECTED
PHASE CURRENT EXPECTED READING (A) ACTUAL READING (A)
(A) R Y B N R Y B N
N (SUM I) 1.0
3. IDMT CHARACTERISTICS:
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
OUTPUT-1 (RL1)
OUTPUT-2 (RL2)
OUTPUT-3 (RL3)
OUTPUT-4 (RL4)
OUTPUT-5 (RL5)
OUTPUT-6 (RL6)
WD
6. CHECK THE STATUS INPUTS:
INPUT L2
INPUT L3
CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. RELAY TEST KIT
2. MULTIMETR
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
SIGNATURE:
DATE:
SCHEME CHECKS FOR BUS COUPLER AND INCOMER
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
3. FUNCTIONAL CHECK
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching Device
component Versus Operating Device's
Circuit Breaker Checked Checked Checked
Disconnector (Q11) Earthing Switch (Q16) Earthing Switch (Q16)
(Q0) Status Status Status
If Any one of Bus-2 If Any one of Bus-1
DS's ON DS's ON
ON Blocked Blocked Blocked
If BR DS Q12 OFF If BR DS Q12 ON
If BC DS Q11 ON If BC DS Q11 OFF
Blocked if ES Q16 If Any one of Bus-2
ON DS's ON
OFF Blocked Blocked
Unblocked If ES If BR DS Q12 OFF
Q16 OFF
If BC DS Q11 ON
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching Device
component Versus Operating Device's
Circuit Breaker Checked Checked Checked
Disconnector (Q11) Earthing Switch (Q16) Earthing Switch (Q16)
(Q0) Status Status Status
If Any one of Bus-1
DS's ON
ON Unblocked Blocked Blocked
BR DS Q12 ON
If Any one of Bus-2
DS's ON
OFF Unblocked Blocked Blocked
If BR DS Q12 OFF
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching Device
component Versus Operating Device's
Circuit Breaker Checked Checked Checked
Disconnector (Q12) Earthing Switch (Q16) Earthing Switch (Q16)
(Q0) Status Status Status
If Any one of Bus-2
DS's ON
ON Unblocked Blocked Blocked
If BC DS Q11 ON
If Any one of Bus-1
DS's ON
OFF Unblocked Blocked Blocked
If BC DS Q11 OFF
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching
Device Versus Operating Device's
component
Earthing
Circuit Checked Disconnector Checked Disconnector Checked Bus 1 Checked Bus 2 Checked
switch
Breaker (Q0) Status Q11 (B/C) Status Q12 (B/R) Status DS’s Status DS’s Status
(Q16)
Blocked for
ON Unblocked Blocked
OFF - - Blocked
Unblocked If
BC-CB OFF Blocked for
OFF Unblocked OFF if BC-CB Unblocked Unblocked
Blocked If BC- ON
CB ON
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching
Versus Operating Device's
Device
component
Earthing Circuit Breaker Checked Disconnector Checked Disconnector Checked Checked Checked
Bus 1 DS’s Bus 2 DS’s
switch (Q15) (Q0) Status Q11 (B/C) Status Q12 (B/R) Status Status Status
ON Blocked for OFF Blocked for OFF Blocked Blocked - -
Unblocked If
BC-CB OFF
OFF Unblocked Unblocked Unblocked Unblocked
Blocked If BC-
CB ON
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
SCHEME CHECKS
1. GENERAL CHECK
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
3. FUNCTIONAL CHECK
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching Device
component Versus Operating Device's
Checked Checked Cable compartment Checked
Circuit Breaker (Q0) Disconnector (Q1) Earthing Switch (Q8)
Status Status cover Status
Blocked If ES Q8
Blocked If DS Q1 ON
OFF
ON Blocked
Unblocked If DS Q1 Unblocked If ES Q8
OFF ON
Blocked If ES Q8
Blocked If DS Q1 ON
Blocked If ES Q8 ON OFF
OFF
Unblocked If ES Q8 Unblocked If DS Q1 Unblocked If ES Q8
OFF OFF ON
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching
Device Versus Operating Device's
component
Cable
Disconnector Circuit Breaker Checked Earthing Switch Checked Checked BUS Earth Checked
compartment
(Q1) (Q0) Status (Q8) Status Status (Q15) Status
cover
ON Unblocked Blocked Blocked N/A N/A
Blocked If ES
Q8 OFF
OFF Unblocked Unblocked N/A N/A
Unblocked If
ES Q8 ON
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching Device
component Versus Operating Device's
Circuit Breaker Checked Disconnector Checked Cable compartment Checked
Earthing Switch (Q8)
(Q0) Status (Q1) Status cover Status
ON Unblocked Blocked Unblocked
OFF Unblocked Unblocked Blocked
Switching Device
compponent Versus Operating Device's
Cable compartment Circuit Breaker Checked Checked Checked
Disconnector (Q1) Earthing Switch (Q8)
cover (Q0) Status Status Status
Blocked to ES Q8
OFF
Removed Unblocked Blocked
Unblocked to ES Q8
ON
Blocked if ES Q8 ON Blocked If DS Q1 ON
Fixed Unblocked Unblocked if ES Q8 Unblocked If DS Q1
OFF OFF
SIGNATURE:
DATE: 29-08-2016
SCHEME, ELECTRICAL AND MECHANICAL CHECKS FOR
TRANSFORMER FEEDERS
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
SCHEME CHECKS
1. GENERAL CHECK
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
3. FUNCTIONAL CHECK
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching Device
component Versus Operating Device's
Checked Checked Cable compartment Checked
Circuit Breaker (Q0) Disconnector (Q1) Earthing Switch (Q8)
Status Status cover Status
Blocked If ES Q8
Blocked If DS Q1 ON OK OK
OFF
ON Blocked OK
Unblocked If DS Q1 Unblocked If ES Q8
OK OK
OFF ON
Blocked If ES Q8
OK Blocked If DS Q1 ON OK OK
Blocked If ES Q8 ON OFF
OFF
Unblocked If ES Q8 Unblocked If DS Q1 Unblocked If ES Q8
OK OK OK
OFF OFF ON
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching
Device Versus Operating Device's
component
Cable
Disconnector Circuit Breaker Checked Earthing Switch Checked Checked BUS Earth Checked
compartment
(Q1) (Q0) Status (Q8) Status Status (Q15) Status
cover
ON Unblocked Blocked Blocked N/A N/A
Blocked If ES
Q8 OFF
OFF Unblocked Unblocked N/A N/A
Unblocked If
ES Q8 ON
SIGNATURE:
DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
Switching Device
component Versus Operating Device's
Circuit Breaker Checked Disconnector Checked Cable compartment Checked
Earthing Switch (Q8)
(Q0) Status (Q1) Status cover Status
ON Unblocked Blocked Unblocked
OFF Unblocked Unblocked Blocked
Switching Device
compponent Versus Operating Device's
Cable compartment Circuit Breaker Checked Checked Checked
Disconnector (Q1) Earthing Switch (Q8)
cover (Q0) Status Status Status
Blocked to ES Q8
OFF
Removed Unblocked Blocked
Unblocked to ES Q8
ON
Blocked if ES Q8 ON Blocked If DS Q1 ON
Fixed Unblocked Unblocked if ES Q8 Unblocked If DS Q1
OFF OFF
SIGNATURE:
DATE: 29-08-2016
POWER FREQUENCY WITHSTAND TEST ON BUSBARS
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
SIGNATURE:
DATE:
TESTS ON VOLTAGE TRANSFORMER
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
RATIO: BURDEN: 10 10
TYPE : PURPOSE:
SERIAL NO. Y: 16 / 31051323
APPLIED
TEST POINTS VOLTAGE R Y B
( VOLTS)
PRIMARY TO EARTH
SECONDARY CORE 1 TO
EARTH
SECONDARY CORE2 TO
EARTH
CORE 1 TO CORE 2
3. POLARITY TEST:
TEST POINT R Y B
AT VT SEC. CORE 1
AT VT SEC. CORE 2
WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME PIVOT JACOBS ADAC
NAME:
SIGNATURE:
DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)
SWITCHBOARD NAME:
FEEDER NAME:
CAL. DUE
S.NO PARTICULARS MAKE TYPE SR.NO.
DATE
Insulation Resistance Test
1 Kit
2 Transformer Test set
WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:
SIGNATURE:
DATE: