0% found this document useful (0 votes)
133 views73 pages

MS FOR T&C OF 22kV Switchgears

Uploaded by

Jeffry M.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
133 views73 pages

MS FOR T&C OF 22kV Switchgears

Uploaded by

Jeffry M.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 73

155-SAADIYAT ROTANA HOTEL & RESORT

COMPLEX, ABU DHABI


METHOD STATEMENT
Project number Doc Number Rev
Document Ref No:
JC 390 MSTC EL- 06 0

TO : ASK-JV

Attn : Project Director

From : Verger Delporte

Subject: Method of Statement for Testing and Commissioning of MV


Switchgear including DC, RTU & DMS

Purpose of submission: X for approval for information

Total Number of pages:


Content
1. Scope and Purpose

2. References

3. Tools and Testing Instruments

4. Tests covered in this statement

5. General Checks

6. Functional Checks

7. Tests on Circuit Breaker

8. Tests on Current Transformer

9. Test on Over current & Earth Fault Protection Relay

10. Tests on Auxiliary Relays

11. Tests on Meters

12. Tests on Voltage Transformer

13. IR and Power Frequency High voltage test on


Busbars

14. Records

15. Responsibilities

16. Health & Safety

17. TEST Formats


1. Scope and Purpose

This document covers the procedures/methods for carrying out the site acceptance tests on
the GMA MV Switchgear panels.

The purpose of the document is to control the testing of GMA panels in line with
project commissioning specification requirements to achieve the optimum results.

Location of activity will be on Susbstation1 and Substation 2 (Zone 1 & 4).

2. References: IEC 62271-200, IEC 60694,IEC 60044-1.

3. Tools and Testing Instruments


a) Primary Injection Kit
b) HV Kit
c) Insulation Resistance Kit
d) CB Analyzer
e) Micro-ohm meter
f) Multimeter
g) Clampmeter
h) CT Analyzer
i) Secondary Injection Kit
j) Timer
k) Spanner Set & Tool Kit
l) Industrial Junction Box

4. Tests covered in this statement are

a) General Checks
b) Functional checks
c) Tests on Circuit Breaker
d) Tests on Current Transformer
e) Tests on Over current and earth fault relay
f) Tests on Auxiliary relays
g) Tests on Ammeter
h) IR & Power frequency voltage test on Busbars

5. General Checks

 Availability of auxiliary AC & DC supply’s to checked


 Connection to the main earthing bar of the Cubicle to station earthing to be
checked.
 The conductors and cables shall be checked for proper routing. Special attention
shall be given to ensure that no mechanical damage can occur to conductors and
cables due to the proximity of sharp edges or heating elements, or to the
movement of moving parts.
 Voltage presence indicator to be checked

6. Functional Checks

A functional test of all low-voltage circuits shall be made to verify the proper functioning
of auxiliary and control circuits in conjunction with the other parts of the Circuit breaker.

6.1 Primary injection test on meters and protection relays

Test Instruments required: Primary current injection kit & Clamp meter

 This test will be conducted on Switchgear panels, where CTs are used to ensure the
CT ratio, functioning of Relays and meters.
 Incoming & Outgoing busbar terminals of the switchgear panel to be connected to
the primary injection kit.
 By Injecting current/voltage from the injection kit to required value, reading of meters
and relays to checked.

6.2 Lamp and Push button checks

 Various colored indication lamps and push buttons to be checked by switching


the AC/DC control supplies.

6.3 Breaker & Earth switch aux. contacts and potential free contacts check

 Auxiliary contacts of the breaker & earth switch’s to be checked in respect to the
close / open and test / service positions breaker and close / open positions of the
Earth switch.

6.4 Heater & Illumination circuit check

 Heater functioning along with thermostat & Hygrostat to be checked at


different temperature and humidity settings.

6.5 Circuit Breaker Operational check

 Circuit breaker operation by mechanical & electrical operations to be checked.


6.6 Earth switch operational check

 Manual closing & opening of the earth switch using the handle provided along with the panel to be verified.

6.7. Mechanical & Electrical interlocking between circuit breaker and Isolator with Earth
Switch

 Mechanical & Electrical interlocks for CB and Isolator switch with respect to
open/close of Earth switch to be verified. Refer schematic drawings of the respective
project for detailed information.

6.8 Voltage presence relay operation

 Voltage presence relay is used for blocking the earth switch operation when HT lines
are live. Relay operation to be checked with line VT supply presence and earth switch
operation.

6.9 Trip circuit supervision check

 Trip circuit supervision shall be used for the monitoring of the trip circuit. The trip
circuit healthy lamp will be provided on the panel for indicating the trip circuit
supervision.

7. Tests on Circuit Breaker

7.1 General checks

 Mechanical open/close indication for the breaker to be checked by operating the


breaker for 2 to 3 cycles.
 Operational counter of the breaker to be checked by operating the breaker for 2 to 3
cycles.
7.2 Mechanical Operational check of breaker

 Breaker close / open operations to be verified by operating the push buttons provided
on the breaker chamber.
 Manual spring charging to be checked by using spring charging rod provided along
with the breaker.
 Circuit breaker and Isolator mechanical interlocking to be checked by operating
breaker and Earth switch.

7.3 Electrical operation of the breaker

 Electrical spring charging by motor provided on the breaker to be verified by


switching the electrical supply to the motor.
 Local / Remote mode, closing and tripping operations of the breaker to be verified in
line to the schematic drawings of the respective project.
 Electrical interlocks between Circuit breaker and isolator to be checked with reference
to the drawings of the respective project.
.
7.4 Circuit breaker operational timing test

In this test, closing and opening time taken by the circuit breaker to be measured Test

Instruments required: CB Analyser kit

Procedure:

 Connect the CB analyser kit, time measurement probes to incoming and outgoing
terminals of the circuit breaker.
 Connect close / trip coil and spring charging motor supply terminal of the test kit to
close / trip coil of the Circuit breaker
 Switch on the AC/DC supply to the test kit and operate the breaker for 2 to 3 close /
open operations
 CB analyser kit records the all closing and opening operations with operating timings.

7.5 Combined Circuit Breaker and connecting Busbar contact resistance test of
adjacent Panels

In this test, the resistance of the each phase shall be measured at ambient temperature
Test Instruments required: Micro-ohm meter

Procedure:
 Connect the micro-ohm meter measuring terminals to the R-phase bottom pole of first
panel and R-phase bottom pole of adjacent Panel.
 Switch on the micro-ohm meter and measure the contact resistance at 100A DC.
 Similarly repeat the procedure for Y & B phase also.
8. Tests on Current Transformer

8.1 Visual Checks


 Verify the Make, Model and name & rating plate details
 Check the physical condition of the component
8.2 Measurement of CT ratio
Test Instruments required: Primary current injection kit & Clamp meter Test
Procedure:
 Connect the CT analyzer kit in measuring terminals to Secondary winding
terminals of the CT

 Switch on the supply to CT analyzer and note the CT ratio of the Secondary winding at
ambient temperature.(All the values recorded in the kit memory card)

8.3 Measurement of Winding Resistance


Test Instruments Required: CT Analyzer
Test Procedure:
 Connect the CT analyzer kit in measuring terminals to Secondary winding
terminals of the CT
 Switch on the supply to CT analyzer and note the resistance of the Secondary winding
at ambient temperature.(All the values recorded in the kit memory card)

8.4 Measurement of Insulation Resistance

Test Instruments required: Insulation tester / Megger Test


Procedure
 Short the secondary terminals and connect to the CT body frame and to earth
 Short the primary terminals and connect the Insulation tester measuring between
primary and earthed secondary terminals.
 Now, Check the IR with a test voltage of 500V between secondary terminals to earth
by shorting the primary terminal to earth.

8.5 Magnetizing current test

Test Instruments required: CT analyzer


Test Procedure
 Connect the CT analyzer kit in measuring terminals to Secondary winding
terminals of the CT
 Switch on the supply to CT analyzer and note the values of magnetizing characteristic
curve of the Secondary winding at ambient temperature.(All the values recorded in the
kit memory card)

9. Test on Over current & Earth Fault Protection Relay


9.1 Visual Checks

 Verify the Make, Model and name & rating plate details
 Check the physical condition of the component

Test Procedure
 Configure the pick up (current/voltage/frequency) and tripping time values
 Check the pick up value by gradually varying input and note the pickup value.
 Check the operating time with a specific abnormal quantity of current / Voltage /
Frequency and it should be within the acceptable value to the configured value
 Check the BI & BO contacts and LED indications.

10. Tests on Auxiliary Relays

10.1 Visual Checks


 Verify the Make, Model and name & rating plate details
 Check the physical condition of the component
Test procedure
 Check the pickup value of the relay coil by gradually increasing the voltage. Note
the value at which the relay coil picks up

 Check the relay contacts changeover during the relay operation


 If the relay is provided with a flag then check the flag operation.

11. Tests on Meters

11.1 Visual Checks

 Verify the Make, Model and name & rating plate


details

Test procedure
 Connect the measuring terminals of the meters to an injection kit or respective
external source.
 Inject the measuring parameter and note down the indicating values of the meter.
 Check the indicating values are in respect to meter ratios.

12. Tests on Voltage Transformer

12.1 Visual Checks


 Verify the Make, Model and name & rating plate details

 Check the physical condition of the component

12.2 Measurement of VT ratio

Test Instruments required: Primary current injection kit ISA & Clamp meter

Test Procedure:

 Inject the voltage on primary side of the VT


 Measure the voltage on secondary of the VT
 Check the measured values are in respect to VT ratios

12.3 Measurement of Winding Resistance

Test Instruments Required: Micro ohm meter

Test Procedure
 Measure the winding resistance on secondary of the VT

 Check the resistance of the each phase shall be measured at ambient temperature.
12.4 Measurement of Insulation Resistance

Test Instruments required: Insulation tester / Megger

Test Procedure:

 Short the secondary terminals and connect to the VT body frame and to earth
 Short the primary terminals and connect the Insulation tester measuring between
primary and earthed secondary terminals.
 Now, Check the IR with a test voltage of 500V between secondary terminals to earth
by shorting the primary terminal to earth.

13. IR and Power Frequency High voltage test on Busbars


 Short Y-Ph, B-Ph busbar and connect to the earth bar.
 Connect Megger measuring terminals between R-Ph & earth bar and apply 5kV for
one minute.
 After one minute, record the Insulation resistance value for between R-ph & Earth bar.
 Repeat the same procedure for measuring the Insulation resistance between Y-ph &
Earth and B-ph & Earth.
 Now, Short Y-Ph, B-Ph busbar and connect to the earth bar to conduct AC High
voltage test on R-ph to earth.
 Apply a power frequency voltage to R-ph busbar for one minute using the AC high
voltage test kit.
 Discharge the R-ph bubar to earth potential using earth rod after application of High
voltage.
 Repeat the same procedure for Y-ph & Earth and B-ph & Earth.
 To ensure the insulation healthiness measure the Insulation resistance between R-ph &
earth, Y-ph & earth and B-ph & earth in similar procedure as described for Insulation
resistance measurement before High voltage test.

The switchgear bus bar system should withstand the power frequency withstand voltage for
one minute without any disruptive discharges. If any disruptive discharge occurs during the
test, then the test shall be repeated on the same apparatus with some maintenance.

14. Records

The measured parameters for the above mentioned tests shall be recorded in the SAT formats
for reference and verification.

15. Responsibilities:

15.1 The Project Engineer will be responsible for the following:

 To ensure that all the preparation and application works are carried
out according to the Contract Specification.

 To ensure that the progressing of works is carried out according to the


planned program and as per the approved Method Statement.
 To ensure that all the equipments and materials required executing the work
are available according to the planned construction program
 To provide all necessary information and distribute responsibilities to
his construction team.
 To coordinate with the Main Contractor MEP Coordinator & Safety Officer
for a safe and proper execution of the works.
15.2 The Site Engineer will be responsible for the following:
 To ensure that the works are carried out according to the
Contract Specifications, approved method statement and the manufacturer’s
material data sheets.
 To ensure that latest approved drawings are used testing & commissioning.
 To provide all necessary information and distribute responsibilities to his team.
 To monitor the progress of work in relation with the work program and to
report to the Project Engineer.
 To co-ordinate with the safety officer and to ensure that the works are
carried out in safe practicing methods.

15.3 The Foreman will be responsible for the following:


 The foreman will carry out his duties by maintaining continuous
coordination with the Site Engineer on daily basis and ensure proper
distribution of the workforce in the required and planned locations.
 To ensure that his assistant foreman/ charge hand are aware of the
job requirements and they have enough information to carry out their
duties properly.
 To ensure that the daily work is progressing as planned and as advised by
the Site Engineer of any requirement for additional resources.
 To control disposal of waste materials according to the instructions
received from the Site Engineer.
 To ensure full coordination with the Safety Officer to maintain safe working
and proper housekeeping of the site, following the approved safety measures
and further ensure that all his working team are aware of the same to prevent
accident and losses.
 To inform the Project Engineer of the areas ready for inspection.
15.4 The QA QC Engineer will be responsible for the following:

 To ensure and confirm that latest approved drawings are used for testing
&commissioning.
 To ensure that the switchgears are new and undamaged and as per approved
submittal and as per specification.
 To check the installation layout and location is as per approved drawing
and workmanship is acceptable, complete and in compliance with
project documents.
 To facilitate the submission of ITR and ensure that the documentation
is complete and duly signed by all concerned parties.
 To follow up the approval of the ITR with the consultant and logging the
status to the inspection.

16. Health and Safety:

16.1 All work shall be controlled as per site HSE procedures and OSHAD SF.
16.2 Site Engineer / Supervisor will check and ensure all safety precautions are
taken prior to commencement of work. Also, to ensure a pre-task brief is
conducted to personnel involved in the task.
16.3 Task specific PPE must be worn at all times during work including hard hat,
gloves, safety glasses, safety shoes, dust mask and coveralls.
16.4 Safe access to work location shall be provided at all times. Working on
scaffolding platform greater than 1.8m high, personnel must ensure it is green
tagged “safe to use” (by certified scaffolding foreman) & also done a full
body harness & observe 100% tie off.
16.5 Permit to work must be obtained from ASK-JV HSE Department.
16.6 Any injury sustained whilst at work must be treated by a trained First Aider and
also by site Nurse. The Site Nurse will determine if hospital treatment is
required.
16.7 The HSE Officer/Inspector shall verify the hazard and risk assessment form and
make sure that the controls are being implemented as per the approved Risk
Assessment.
16.8 The HSE Officer/Inspector shall conduct HSE Induction for new workers and all
HSE related toolbox talks.
16.9 HSE Officer shall ensure that all needed Personal Protective Equipments (PPEs)
are available.
16.10 The Engineers/Foreman shall ensure that PPEs (Coverall, Safety Shoes, Helmet,
High Visibility Vest & task specific such as Mask, Gloves, Safety Glass,
Goggles & Ear Plug) issued to the workers are worn at all times while
performing the task. HSE operatives will randomly verify the same.
16.11 The following OSHAD SF Codes of Practices will be strictly followed:
16.12 OSHAD SF- COP 2.0 – Personal Protective Equipment – V 3.0 July 2016.
16.13 OSHAD SF- COP 11.0 – Safety in Heat – V 3.0 July 2016.
16.14 OSHAD SF- COP 14.0 – Manual Handling and Ergonomics – V 3.0 July 2016.

Chris Irwin Engr. Shaher Al Tatar


Project Director Project Director
ASK - JV Verger Delporte
TEST FORMATS
SECONDARY INJECTION TEST ON ANALOG AMMETER
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

SECONDARY INJECTION TEST ON ANALOG AMMETER


1. NAME PLATE DETAILS:

MAKE: CLASS:

TYPE: REF NO:

RATIO: SR.NO :

2. SECONDARY INJECTION TEST ON METER:

INJECTED SEC. CALCULATED PRIMARY METER DISPLAY


CURRENT (AMPS) CURRENT (AMPS) (AMPS)
S.NO.

L1 L2 L3 L1 L2 L3 L1 L2 L3

1.

3. TESTING INSTRUMENT DETAILS:

CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. RELAY TEST KIT PROGRAMMA
2. MULTIMETER FLUKE

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SECONDARY INJECTION TEST ON ANALOG VOLTMETER
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:
ANALOG VOLTMETER

1. NAME PLATE DETAILS:

MAKE: CLASS:

TYPE: REF NO:

RATIO: SR.NO :

2. SECONDARY INJECTION TEST ON METER:

INJECTED SEC. CALCULATED PRIMARY METER DISPLAY


VOLTAGE (VOLTS) VOLTAGE (KILOVOLTS) (KILOVOLTS)
S.NO.

U1 U2 U3 U1 U2 U3 U1 U2 U3

1. 50 75 110 10 15 22

3. TESTING INSTRUMENT DETAILS:

CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. Relay Test Kit Omicron
2.

WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:

SIGNATURE:

DATE:
MEASUREMENT OF BUSBAR CONTACT RESISTANCE
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

MEASUREMENT OF BUSBAR CONTACT RESISTANCE

1. NAME PLATE DETAILS:


MAKE: SCHNEIDER ELECTRIC
TYPE: GMA (SF6) RATED VOLTAGE: 24 kV
BUS BAR RATED CURRENT: TYPE GMA

FROM POINT TO POINT VIA BUS BAR CONTACT


BAYS
(PRY CABLE (PRY CABLE POLE REF RESISTANCE VALUES IN REMARKS
ENTRY) ENTRY) (µΩ)

R
Y
B

2. TESTING INSTRUMENT DETAILS:


S.NO. PARTICULARS MAKE TYPE SR.NO. CAL. DUE DATE
1. MICRO OHM METER

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
CIRCUIT BREAKER TESTS
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

1. NAME PLATE DETAILS:

MAKE: SCHNEIDER ELECTRIC SL.NO:

TYPE: GMA (SF6) RATED CURRENT:

2. FUNCTIONAL CHECKS:

SL. NO. DESCRIPTION RESULT

GENERAL CHECKS:

1 MECHANICAL INDICATOR FOR BREAKER OPEN/CLOSE


2 COUNTER OPERATION 01
MECHANICAL OPERATION CHECKS OF BREAKER:
1 OPEN/CLOSE OPERATION OF CIRCUIT BREAKER
2 SPRING CHARGING BY HANDLE

3. FUNCTIONAL CHECKS:

PHASE POLE OPENING TIME(ms) POLE CLOSING TIME(ms)


R
Y REFER MEGGER CIRCUIT BREAKER ANALYZER REPORT
B

4. TESTING INSTRUMENT DETAILS:


S.NO. PARTICULARS MAKE TYPE SR.NO. CAL. DUE DATE
CIRCUIT BREAKER
1. PROGRAMMA
ANALYZER

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
MEASUREMENT OF CIRCUIT BREAKER CONTACT
RESISTANCE
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

MEASUREMENT OF CIRCUIT BREAKER CONTACT RESISTANCE

1. NAME PLATE DETAILS:


MAKE: SCHNEIDER ELECTRIC

TYPE: GMA (SF6) RATED VOLTAGE: 24 kV

RATED CURRENT:

BAYS:

SL.NO’S:

FROM POINT TO POINT MAIN CIRCUIT CONTACT RESISTANCE


POLE REF
(PRY CABLE ENTRY) (PRY CABLE ENTRY) VALUES IN (µΩ)

2. TESTING INSTRUMENT DETAILS


CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. MICRO OHM METER MEGGER

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
CURRENT TRANSFORMER PRIMARY INJECTION TEST
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

CURRENT TRANSFORMER PRIMARY INJECTION TEST FOR INCOMER

1. MEASUREMENT OF CT’s CT RATIO: 600-400/ 1A

INJECTED PRIMARY CURRENT(A) MEASURED IN ANALOG METER (PA1) DISPLAY


PHASE REF
CURRENT(A) R Y B N
R-N
R-Y
R-B

CURRENT(A) MEASURED IN OC EF RELAY (K01) DISPLAY


PHASE REF
R Y B N
R-N
R-Y
R-B

MEASURED SECONDARY CURRENT (A) – CORE


PHASE
REF IN CT TERMINALS FUTURE TERMINALS
X308 X309 X310 X311 X9.1-1 X9.1-2
R-N
R-Y
R-B

WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

MEASURED SECONDARY CURRENT (A) – CORE


PHASE CT TERMINALS TEST TERMINAL BLOCK RELAY TERMINALS
REF
K01- K01- K01- K01-
X319 X320 X321 X322 P01-21 P01-23 P01-25 P01-27
49 51 53 55
R-N
R-Y
R-B

NOTE: PA1 - ANALOG AMMETER


K01 - OC / EF PROT.RELAY
P01- TEST TERMINAL BLOCK

2. TRIP TEST
RELAY SETTING CURRENT
TRIP CURRENT ON
PHASE REFERENCE (A) PHASE OPERATED
CURVE I> t> PRY (A)
R PHASE SI 0.5 0.1 328.0 OK
RY PHASE SI 0.5 0.1 330.7 OK
RB PHASE SI 0.5 0.1 327.0 OK
Earth Fault SI 0.2 0.1 132.0 OK

3. TESTING INSTRUMENT DETAILS:

S.NO. PARTICULARS MAKE TYPE SR.NO. CAL. DUE DATE


1 Primary Injection Kit Programma

2 Clamp meter Amprobe

WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

CURRENT TRANSFORMER PRIMARY INJECTION TEST FOR BUS COUPLER

1. MEASUREMENT OF CT’s CT RATIO: 600-400/ 1A

INJECTED PRIMARY CURRENT(A) MEASURED IN ANALOG METER (PA1) DISPLAY


PHASE REF
CURRENT(A) R Y B N
R-N
R-Y
R-B

CURRENT(A) MEASURED IN OC EF RELAY (K01) DISPLAY


PHASE REF
R Y B N
R-N
R-Y
R-B

MEASURED SECONDARY CURRENT (A) – CORE


PHASE
REF IN CT TERMINALS FUTURE TERMINALS
X313 X314 X315 X316 X9.1-1 X9.1-2
R-N
R-Y
R-B

WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

MEASURED SECONDARY CURRENT (A) – CORE


PHASE CT TERMINALS TEST TERMINAL BLOCK RELAY TERMINALS
REF
K01- K01- K01- K01-
X35 X36 X37 X38 P01-21 P01-23 P01-25 P01-27
49 51 53 55
R-N
R-Y
R-B

NOTE: PA1 - ANALOG AMMETER


K01 - OC / EF PROT.RELAY
P01 - TEST TERMINAL BLOCK

2. TRIP TEST
RELAY SETTING CURRENT
TRIP CURRENT ON
PHASE REFERENCE (A) PHASE OPERATED
CURVE I> t> PRY (A)
R PHASE SI 0.5 0.1
RY PHASE SI 0.5 0.1
RB PHASE SI 0.5 0.1
Earth Fault SI 0.2 0.1

3. TESTING INSTRUMENT DETAILS:

S.NO. PARTICULARS MAKE TYPE SR.NO. CAL. DUE DATE


1 Primary Injection Kit Programma

2 Clamp meter Amprobe

WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

CURRENT TRANSFORMER PRIMARY INJECTION TEST FOR TRF FEEDER

1. MEASUREMENT OF CT’s CT RATIO: 50-100/ 1A

INJECTED CURRENT(A) MEASURED IN ANALOG METER CURRENT(A) MEASURED IN RELAY (K01)


PHASE PRIMARY (PA1) DISPLAY DISPLAY
REF
CURRENT(A) R Y B N R Y B N
R-N 100
R-Y 100
R-B 100

MEASURED SECONDARY CURRENT (A) – CORE 1


PHASE
REF IN CT TERMINALS FUTURE TERMINALS
X308 X309 X310 X311 X9.1-1 X9.1-2
R-N
R-Y
R-B

MEASURED SECONDARY CURRENT (A) – CORE 2


PHASE CT TERMINALS TEST TERMINAL BLOCK RELAY TERMINALS
REF
K01- K01- K01- K01-
X319 X320 X321 X322 P01-21 P01-23 P01-25 P01-27
49 51 53 56
R-N
R-Y
R-B

NOTE: PA1- ANALOG AMMETER


K01- OC / EF PROT.RELAY
P01- TEST TERMINAL BLOCK

WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

2. TRIP TEST

RELAY SETTING CURRENT


TRIP CURRENT ON
PHASE REFERENCE (A) PHASE OPERATED
CURVE I> t> PRY (A)
R PHASE SI 0.36 0.1 OK
RY PHASE SI 0.36 0.1 41.30 OK
RB PHASE SI 0.36 0.1 40.54 OK
Earth Fault SI 0.2 0.1 22.18 OK

3. TESTING INSTRUMENT DETAILS:

S.NO. PARTICULARS MAKE TYPE SR.NO. CAL. DUE DATE


1 Primary Injection Kit Programma

2 Clamp meter Amprobe

WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:

SIGNATURE:

DATE:
CURRENT TRANSFORMER TEST
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

CURRENT TRANSFORMER TEST FOR TRANSFORMER FEEDER

1. NAME PLATE DETAILS:

CT-1
MAKE: SCHNEIDER CLASS: TYPE Core-1 Core-1
1FS10 5P20
TAP 1
RATIO: BURDEN:
TAP 2
TYPE: PURPOSE: PROTECTION & METERING

SERIAL NO.

2. INSULATION RESISTANCE TEST:

APPLIED
TEST POINTS VOLTAGE R Y B
(VOLTS)
PRIMARY TO EARTH 5000
SECONDARY(Core-1)TO EARTH 500
SECONDARY(Core-2)TO EARTH 500
Core-1 TO Core- 2 500
PRIMARY TO SECONDARY 5000

3. POLARITY TEST:

TEST POINT R Y B
AT CT SEC. (CT- 1-1)
AT CT SEC. (CT- 1-2) REFER OMICRON CT ANALYZER TEST REPORTS
-

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

4. WINDING RESISTANCE TEST: TEMP: º C


MEASURED RESISTANCE (Ω)
CT-1-1 CT-1-2 -
PHASE REMARKS
1S1 – 1S1 – 2S1 – 2S1 –
-
1S2 1S3 2S2 2S3
R
Y REFER OMICRON CT ANALYZER TEST REPORTS
B
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY THE MANUFACTURER

5. MAGNETIZING CURRENT TEST:


Magnetizing Current measured in mA at variable volts V at
Ratio Terminal Ph
1A
R
Y REFER OMICRON CT ANALYZER TEST REPORTS
B
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY THE MANUFACTURER

6. RATIO CHECK:
TEST POINT CT RATIO R Y B REMARKS
PRIMARY INJECTED
CURRENT (A)
MEASURED REFER OMICRON CT ANALYZER TEST REPORTS
SEC. CURRENT
(A)
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY TH E MANUFACTURER

7. TESTING INSTRUMENT DETAILS:


CAL. DUE
S.NO PARTICULARS MAKE TYPE SR.NO.
DATE
CT
1. CT TEST KIT OMICRON
ANALYZER
INSULATION RESISTANCE
2. MEGGER MIT 520/2
TEST KIT

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

CURRENT TRANSFORMER TEST FOR INCOMER FEEDER

1. NAME PLATE DETAILS:

CT-1
MAKE: SCHNEIDER CLASS: TYPE Core-1 Core-1
1FS10 5P20
TAP 1
RATIO: BURDEN:
TAP 2
TYPE: PURPOSE: PROTECTION & METERING

SERIAL NO.

2. INSULATION RESISTANCE TEST:

APPLIED
TEST POINTS VOLTAGE R Y B
(VOLTS)
PRIMARY TO EARTH 5000
SECONDARY(Core-1)TO EARTH 500
SECONDARY(Core-2)TO EARTH 500
Core-1 TO Core- 2 500
PRIMARY TO SECONDARY 5000

3. POLARITY TEST:

TEST POINT R Y B
AT CT SEC. (CT- 1-1)
AT CT SEC. (CT- 1-2) REFER OMICRON CT ANALYZER TEST REPORTS
-

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

4. WINDING RESISTANCE TEST: TEMP: º C


MEASURED RESISTANCE (Ω)
CT-1-1 CT-1-2 -
PHASE REMARKS
1S1 – 1S1 – 2S1 – 2S1 –
-
1S2 1S3 2S2 2S3
R
Y REFER OMICRON CT ANALYZER TEST REPORTS
B
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY THE MANUFACTURER

5. MAGNETIZING CURRENT TEST:


Magnetizing Current measured in mA at variable volts V at
Ratio Terminal Ph
1A
R
Y REFER OMICRON CT ANALYZER TEST REPORTS
B
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY THE MANUFACTURER

6. RATIO CHECK:
TEST POINT CT RATIO R Y B REMARKS
PRIMARY INJECTED
CURRENT (A)
MEASURED REFER OMICRON CT ANALYZER TEST REPORTS
SEC. CURRENT
(A)
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY TH E MANUFACTURER

7. TESTING INSTRUMENT DETAILS:


CAL. DUE
S.NO PARTICULARS MAKE TYPE SR.NO.
DATE
CT
1. CT TEST KIT OMICRON
ANALYZER
INSULATION RESISTANCE
2. MEGGER MIT 520/2
TEST KIT

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

CURRENT TRANSFORMER TEST FOR BUS COUPLER


1. NAME PLATE DETAILS:

CT-1
MAKE: SCHNEIDER CLASS: TYPE Core-1 Core-1
1FS10 5P20
RATIO: BURDEN: TAP 1

TYPE: PURPOSE: PROTECTION & METERING

SERIAL NO.

2. INSULATION RESISTANCE TEST:

APPLIED
TEST POINTS VOLTAGE R Y B
(VOLTS)
PRIMARY TO EARTH
SECONDARY(Core-1)TO EARTH
SECONDARY(Core-2)TO EARTH
Core-1 TO Core- 2
PRIMARY TO SECONDARY

3. POLARITY TEST:

TEST POINT R Y B
AT CT SEC. (CT- 1-1)
AT CT SEC. (CT- 1-2) REFER OMICRON CT ANALYZER TEST REPORTS
-

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

4. WINDING RESISTANCE TEST: TEMP: 38.2 º C


MEASURED RESISTANCE (Ω)
PHASE CT-1-1 CT-1-2 - REMARKS
1S1 – 1S2 2S1 – 2S2 -
R
Y REFER OMICRON CT ANALYZER TEST REPORTS
B
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY THE MANUFACTURER

5. MAGNETIZING CURRENT TEST:


Magnetizing Current measured in mA at variable volts V at
Ratio Terminal Ph
1A
R
Y REFER OMICRON CT ANALYZER TEST REPORTS
B
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY THE MANUFACTURER 6. RATIO CHECK:
TEST POINT CT RATIO R Y B REMARKS
PRIMARY INJECTED
CURRENT (A)
MEASURED 1S1 – 1S2 REFER OMICRON CT ANALYZER TEST REPORTS
SEC. CURRENT 2S1 – 2S2
(A) -
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY TH E MANUFACTURER

7. TESTING INSTRUMENT DETAILS:


CAL. DUE
S.NO PARTICULARS MAKE TYPE SR.NO.
DATE
1. CT TEST KIT
INSULATION RESISTANCE
2.
TEST KIT

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
OVER CURRENT AND EARTH FAULT RELAY TESTING
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

OVER CURRENT AND EARTH FAULT RELAY TESTING

1. NAME PLATE DETAILS:

TYPE. SERIAL NO:


AUX.VOLTAGE : NOMINAL CURRENT:
MAKE: CT RATIO:

2. METERING CHECK:
INJECTED PRIMARY CURRENT READ ON RELAY DISPLAY
INJECTED
PHASE CURRENT EXPECTED READING (A) ACTUAL READING (A)
(A) R Y B N R Y B N
RY 1.0
YB 1.0
BR 1.0
RN 1.0
YN 1.0
BN 1.0

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

3. IDMT CHARACTERISTICS:

STANDARD INVERSE CURVE [I> ]:

RELAY PICK UP OPERATING TIME AT OPERATING TIME AT


PHASE SETTING CURRENT 2 X IS (SEC) 5 X IS (SEC) LED
TMS
(A) (A) EXPECTED ACTUAL EXPECTED ACTUAL
R
Y
B
E/F

4. HIGHSET DEFINITE TIME [I>>]:

RELAY PICK UP INJECTED SETTING OPERATING


PHASE SETTING CURRENT CURRENT TIME TIME LED
(A) (A) IN (A) (SEC) (SEC)
R
Y
B
E/F

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

5. DETAILS OF OUTPUT TERMINALS:

OUTPUT NUMBER RELAY TERMINAL NUMBER PURPOSE STATUS

OUTPUT-1 (RL1)

OUTPUT-2 (RL2)
OUTPUT-3 (RL3)
OUTPUT-4 (RL4)
OUTPUT-5 (RL5)
OUTPUT-6 (RL6)
WD
6. CHECK THE STATUS INPUTS:

TERMINAL PICK UP DROP OFF


INPUT NO. NUMBER VOLTAGE VOLTAGE TEST RESULT
( VOLTS) ( VOLTS)
INPUT L1

INPUT L2

INPUT L3
7. TESTING INSTRUMENT DETAILS:

CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. RELAY TEST KIT
2. MULTIMETR

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
STANDBY EARTH FAULT RELAY TESTING
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

STANDBY EARTH FAULT RELAY

1. NAME PLATE DETAILS:

TYPE. SERIAL NO:


AUX.VOLTAGE : NOMINAL CURRENT:
MAKE: CT RATIO:

2. METERING CHECK:
INJECTED PRIMARY CURRENT READ ON RELAY DISPLAY
INJECTED
PHASE CURRENT EXPECTED READING (A) ACTUAL READING (A)
(A) R Y B N R Y B N
N (SUM I) 1.0

3. IDMT CHARACTERISTICS:

STANDARD INVERSE CURVE [Ie> ]:

RELAY PICK UP OPERATING TIME AT OPERATING TIME AT


PHASE SETTING CURRENT 2 X IS (SEC) 5 X IS (SEC) LED
TMS
(A) (A) EXPECTED ACTUAL EXPECTED ACTUAL
N

4. HIGHSET DEFINITE TIME [Ie>>]:

RELAY PICK UP INJECTED SETTING OPERATING


PHASE SETTING CURRENT CURRENT TIME TIME LED
(A) (A) IN (A) (SEC) (M SEC)
N

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

5. DETAILS OF OUTPUT TERMINALS:

OUTPUT NUMBER RELAY TERMINAL NUMBER PURPOSE STATUS

OUTPUT-1 (RL1)

OUTPUT-2 (RL2)
OUTPUT-3 (RL3)
OUTPUT-4 (RL4)
OUTPUT-5 (RL5)
OUTPUT-6 (RL6)
WD
6. CHECK THE STATUS INPUTS:

TERMINAL PICK UP DROP OFF


INPUT NO. NUMBER VOLTAGE VOLTAGE TEST RESULT
( VOLTS) ( VOLTS)
INPUT L1

INPUT L2

INPUT L3

7. TESTING INSTRUMENT DETAILS:

CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. RELAY TEST KIT
2. MULTIMETR

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SCHEME CHECKS FOR BUS COUPLER AND INCOMER
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: Buscoupler and Busriser

SCHEME CHECKS For Bus Coupler and Bus Riser


1. GENERAL CHECK

SL. NO. DESCRIPTION RESULT


1. Auxiliary AC supply check
2. Auxiliary DC supply check
3. Cubicle main earthing check
4. Cable tightness check
5. Voltage presence indicator check

2. ELECTRICAL OPERATION CHECKS OF BREAKER:

SL. NO. DESCRIPTION RESULT


1 Electrical Spring Charging of Breaker
2 Local closing and tripping of breaker
3 Remote closing and tripping of breaker

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: Buscoupler and Busriser

3. FUNCTIONAL CHECK

SL. NO. DESCRIPTION RESULT


1. Lamp Test push button Check
2. Potential Free contact check
3. Breaker Aux contact Check
4. Heater operation check
5. CB electrical operation check by giving open and close command in local and remote mode
6. Remote signal on terminal block check
7. Cubicle lamp with door limit switch check
8. Trip circuit supervision operation check
9. Thermostat and hygrostat operation check
10. Indication circuit check

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: Buscoupler and Busriser

4. MECHANICAL / ELECTRICAL SWITCHING INTERLOCK CHECKS:

Switching Device
component Versus Operating Device's
Circuit Breaker Checked Checked Checked
Disconnector (Q11) Earthing Switch (Q16) Earthing Switch (Q16)
(Q0) Status Status Status
If Any one of Bus-2 If Any one of Bus-1
DS's ON DS's ON
ON Blocked Blocked Blocked
If BR DS Q12 OFF If BR DS Q12 ON
If BC DS Q11 ON If BC DS Q11 OFF
Blocked if ES Q16 If Any one of Bus-2
ON DS's ON
OFF Blocked Blocked
Unblocked If ES If BR DS Q12 OFF
Q16 OFF
If BC DS Q11 ON

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: Buscoupler and Busriser

Switching Device
component Versus Operating Device's
Circuit Breaker Checked Checked Checked
Disconnector (Q11) Earthing Switch (Q16) Earthing Switch (Q16)
(Q0) Status Status Status
If Any one of Bus-1
DS's ON
ON Unblocked Blocked Blocked
BR DS Q12 ON
If Any one of Bus-2
DS's ON
OFF Unblocked Blocked Blocked

If BR DS Q12 OFF

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: Buscoupler and Busriser

Switching Device
component Versus Operating Device's
Circuit Breaker Checked Checked Checked
Disconnector (Q12) Earthing Switch (Q16) Earthing Switch (Q16)
(Q0) Status Status Status
If Any one of Bus-2
DS's ON
ON Unblocked Blocked Blocked
If BC DS Q11 ON
If Any one of Bus-1
DS's ON
OFF Unblocked Blocked Blocked
If BC DS Q11 OFF

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: Buscoupler and Busriser

Switching
Device Versus Operating Device's
component
Earthing
Circuit Checked Disconnector Checked Disconnector Checked Bus 1 Checked Bus 2 Checked
switch
Breaker (Q0) Status Q11 (B/C) Status Q12 (B/R) Status DS’s Status DS’s Status
(Q16)
Blocked for
ON Unblocked Blocked
OFF - - Blocked
Unblocked If
BC-CB OFF Blocked for
OFF Unblocked OFF if BC-CB Unblocked Unblocked
Blocked If BC- ON
CB ON

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: Buscoupler and Busriser

Switching
Versus Operating Device's
Device
component
Earthing Circuit Breaker Checked Disconnector Checked Disconnector Checked Checked Checked
Bus 1 DS’s Bus 2 DS’s
switch (Q15) (Q0) Status Q11 (B/C) Status Q12 (B/R) Status Status Status
ON Blocked for OFF Blocked for OFF Blocked Blocked - -
Unblocked If
BC-CB OFF
OFF Unblocked Unblocked Unblocked Unblocked
Blocked If BC-
CB ON

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: Buscoupler and Busriser

5. INTERLOCK BETWEEN BUS COUPLER AND INCOMER’S:

Switching Device component Versus Operating Device's


Circuit Breaker (Q0) In Incomer-1 CB Checked Status In Incomer-2 CB Checked Status
Blocked If I/C-2 CB ON or Blocked If I/C-1 CB ON or
TRIP Operated TRIP Operated
ON
Unblocked If I/C-2 CB OFF Unblocked If I/C-1 CB OFF
and Trip Not operated and Trip Not operated

Unblocked If Trip Not Unblocked If Trip Not


OFF operated in BC & IC-2 CB operated in IC-2 & BC CB
Closed Closed

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: INCOMER FEEDER

SCHEME CHECKS
1. GENERAL CHECK

SL. NO. DESCRIPTION RESULT


1. Auxiliary AC supply check
2. Auxiliary DC supply check
3. Cubicle main earthing check
4. Cable tightness check
5. Voltage presence indicator check

2. ELECTRICAL OPERATION CHECKS OF BREAKER:

SL. NO. DESCRIPTION RESULT


1 Electrical Spring Charging of Breaker
2 Local closing and tripping of breaker
3 Remote closing and tripping of breaker

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: INCOMER FEEDER

3. FUNCTIONAL CHECK

SL. NO. DESCRIPTION RESULT


1. Lamp Test push button Check
2. Potential Free contact check
3. Breaker Aux contact Check
4. Earth switch Aux contact check
5. Heater operation check
6. CB electrical operation check by giving open and close command in local and remote mode
7. Remote signal on terminal block check
8. Cubicle lamp with door limit switch check
9. Earth switch operation check
10. Trip circuit supervision operation check
11. Thermostat and hygrostat operation check
12. Indication circuit check

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: INCOMER FEEDER

4. MECHANICAL / ELECTRICAL SWITCHING INTERLOCK CHECKS:

Switching Device
component Versus Operating Device's
Checked Checked Cable compartment Checked
Circuit Breaker (Q0) Disconnector (Q1) Earthing Switch (Q8)
Status Status cover Status
Blocked If ES Q8
Blocked If DS Q1 ON
OFF
ON Blocked
Unblocked If DS Q1 Unblocked If ES Q8
OFF ON
Blocked If ES Q8
Blocked If DS Q1 ON
Blocked If ES Q8 ON OFF
OFF
Unblocked If ES Q8 Unblocked If DS Q1 Unblocked If ES Q8
OFF OFF ON

Note : ES – Earth switch DS- Disconnector Switch

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: INCOMER FEEDER

Switching
Device Versus Operating Device's
component
Cable
Disconnector Circuit Breaker Checked Earthing Switch Checked Checked BUS Earth Checked
compartment
(Q1) (Q0) Status (Q8) Status Status (Q15) Status
cover
ON Unblocked Blocked Blocked N/A N/A

Blocked If ES
Q8 OFF
OFF Unblocked Unblocked N/A N/A
Unblocked If
ES Q8 ON

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: INCOMER FEEDER

Switching Device
component Versus Operating Device's
Circuit Breaker Checked Disconnector Checked Cable compartment Checked
Earthing Switch (Q8)
(Q0) Status (Q1) Status cover Status
ON Unblocked Blocked Unblocked
OFF Unblocked Unblocked Blocked

Switching Device
compponent Versus Operating Device's
Cable compartment Circuit Breaker Checked Checked Checked
Disconnector (Q1) Earthing Switch (Q8)
cover (Q0) Status Status Status
Blocked to ES Q8
OFF
Removed Unblocked Blocked
Unblocked to ES Q8
ON
Blocked if ES Q8 ON Blocked If DS Q1 ON
Fixed Unblocked Unblocked if ES Q8 Unblocked If DS Q1
OFF OFF

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SCHEME, ELECTRICAL AND MECHANICAL CHECKS FOR
TRANSFORMER FEEDERS
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: TRANSFORMER FEEDER

SCHEME CHECKS
1. GENERAL CHECK

SL. NO. DESCRIPTION RESULT


1. Auxiliary AC supply check
2. Auxiliary DC supply check
3. Cubicle main earthing check
4. Cable tightness check
5. Voltage presence indicator check

2. ELECTRICAL OPERATION CHECKS OF BREAKER:

SL. NO. DESCRIPTION RESULT


1 Electrical Spring Charging of Breaker OK
2 Local closing and tripping of breaker OK
3 Remote closing and tripping of breaker OK

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: TRANSFORMER FEEDER

3. FUNCTIONAL CHECK

SL. NO. DESCRIPTION RESULT


1. Lamp Test push button Check
2. Potential Free contact check
3. Breaker Aux contact Check
4. Earth switch Aux contact check
5. Heater operation check
6. CB electrical operation check by giving open and close command in local and remote mode
7. Remote signal on terminal block check
8. Cubicle lamp with door limit switch check
9. Earth switch operation check
10. Trip circuit supervision operation check
11. Thermostat and hygrostat operation check
12. Indication circuit check

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: TRANSFORMER FEEDER

4. MECHANICAL / ELECTRICAL SWITCHING INTERLOCK CHECKS:

Switching Device
component Versus Operating Device's
Checked Checked Cable compartment Checked
Circuit Breaker (Q0) Disconnector (Q1) Earthing Switch (Q8)
Status Status cover Status
Blocked If ES Q8
Blocked If DS Q1 ON OK OK
OFF
ON Blocked OK
Unblocked If DS Q1 Unblocked If ES Q8
OK OK
OFF ON
Blocked If ES Q8
OK Blocked If DS Q1 ON OK OK
Blocked If ES Q8 ON OFF
OFF
Unblocked If ES Q8 Unblocked If DS Q1 Unblocked If ES Q8
OK OK OK
OFF OFF ON

Note : ES – Earth switch DS- Disconnector Switch

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: TRANSFORMER FEEDER

Switching
Device Versus Operating Device's
component
Cable
Disconnector Circuit Breaker Checked Earthing Switch Checked Checked BUS Earth Checked
compartment
(Q1) (Q0) Status (Q8) Status Status (Q15) Status
cover
ON Unblocked Blocked Blocked N/A N/A

Blocked If ES
Q8 OFF
OFF Unblocked Unblocked N/A N/A
Unblocked If
ES Q8 ON

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-T&C-001
Contractor Revision: 00
Client Consultant MV subcontractor
Al Diya Hospitality Project No : 155
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME: TRANSFORMER FEEDER

Switching Device
component Versus Operating Device's
Circuit Breaker Checked Disconnector Checked Cable compartment Checked
Earthing Switch (Q8)
(Q0) Status (Q1) Status cover Status
ON Unblocked Blocked Unblocked
OFF Unblocked Unblocked Blocked

Switching Device
compponent Versus Operating Device's
Cable compartment Circuit Breaker Checked Checked Checked
Disconnector (Q1) Earthing Switch (Q8)
cover (Q0) Status Status Status
Blocked to ES Q8
OFF
Removed Unblocked Blocked
Unblocked to ES Q8
ON
Blocked if ES Q8 ON Blocked If DS Q1 ON
Fixed Unblocked Unblocked if ES Q8 Unblocked If DS Q1
OFF OFF

TESTED BY WITNESSED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME: VALANTO PEERIS

SIGNATURE:

DATE: 29-08-2016
POWER FREQUENCY WITHSTAND TEST ON BUSBARS
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

POWER FREQUENCY WITHSTAND TEST FOR BUSBAR

1. INSULATION TEST: AMB. TEMP: °C


INSULATION RESISTANCE IN TΩ WITH 5kV MEGGER
PHASE REFERENCE
BEFORE HV TEST AFTER HV TEST
5 kV APPLIED TO R PHASE FOR 60
SEC (PHASES Y & B SHORTED TO
EARTH)
5 kV APPLIED TO Y PHASE FOR 60
SEC (PHASES B & R SHORTED TO
EARTH)
5 kV APPLIED TO B PHASE FOR 60
SEC (PHASES R & Y SHORTED TO
EARTH)

2. HIGH VOLTAGE TEST:

PHASE REFERENCE WITH STAND STATUS LEAKAGE CURRENT (mA)

40kV APPLIED TO R PHASE FOR 60


SEC (PHASES Y & B SHORTED TO
EARTH)
40 kV APPLIED TO Y PHASE FOR 60
SEC (PHASES B & R SHORTED TO
EARTH)
40 kV APPLIED TO B PHASE FOR 60
SEC (PHASES R & Y SHORTED TO
EARTH)
NOTE: 11kV SYSTEM VOLTAGE WILL BE APPLIED
ALL FEEDERS ARE IN CLOSED POSITION (DISCONNECTOR & BREAKER)
ALL VTs ARE ISOLATED & CAPACITIVE VOLTAGE INDICATORS ARE SHORTED
ALL BAYS SF6 PRESSURES ARE NOTED ALL BAYS MANOMETERS ARE IN SAFE REGION (GREEN)

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

3. TESTING INSTRUMENT DETAILS:


CAL. DUE
S.NO. PARTICULARS MAKE TYPE SR.NO.
DATE
1. HV KIT Phenix
INSULATION
2. Sonel
TESTER

TESTED BY WITNESSED BY WITNESSED/APPROVED BY


COMPANY : PEME
NAME:

SIGNATURE:

DATE:
TESTS ON VOLTAGE TRANSFORMER
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

VOLTAGE TRANSFORMER TEST

1. NAME PLATE DETAILS:

MAKE: CLASS: 3P 0.5

RATIO: BURDEN: 10 10

TYPE : PURPOSE:
SERIAL NO. Y: 16 / 31051323

2. INSULATION RESISTANCE TEST:

APPLIED
TEST POINTS VOLTAGE R Y B
( VOLTS)
PRIMARY TO EARTH
SECONDARY CORE 1 TO
EARTH
SECONDARY CORE2 TO
EARTH
CORE 1 TO CORE 2

3. POLARITY TEST:

TEST POINT R Y B
AT VT SEC. CORE 1
AT VT SEC. CORE 2

WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME PIVOT JACOBS ADAC
NAME:

SIGNATURE:

DATE:
SAADIYAT ROTANA HOTEL & RESORT COMPLEX PROJECT
TESTING AND COMMISSIONING REPORT FOR 24kV MV SWITCHGEAR
Doc no. PEME-J30090-
Contractor Consultant T&C-001 Revision: 00
Client MV subcontractor
Project No : 155
Al Diya Hospitality
Investment
Manufacturer :Schneider
Electric (GMA)

SWITCHBOARD NAME:

FEEDER NAME:

4. WINDING RESISTANCE TEST: TEMP: C

MEASURED RESISTANCE (Ω)


PHASE CORE 1 CORE 2 REMARKS
1a-1n 2a-2n
R
Y
B
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY THE MANUFACTURER 5. RATIO CHECK:

TEST POINT VT RATIO R Y B REMARKS


PRIMARY INJECTED
VOLTAGE(V)
MEASURED 1a – 1n REFER CPC100 TEST REPORTS
SEC. VOLTAGE
(V) 2a-2n
NOTE: MEASURED VALUES SHOULD BE WITHIN THE LIMITS SPECIFIED BY THE MANUFACTURER

6. TESTING INSTRUMENT DETAILS:

CAL. DUE
S.NO PARTICULARS MAKE TYPE SR.NO.
DATE
Insulation Resistance Test
1 Kit
2 Transformer Test set

WITNESSED/APPROVED
TESTED BY WITNESSED BY WITNESSED BY
BY
COMPANY : PEME
NAME:

SIGNATURE:

DATE:

You might also like