Technical Manual
Technical Manual
Rev No. : 15
Date : 30-Nov-23
APPROVAL Page : 1 of 1
TECHNICAL MANUAL
EDITION II
Notes:
1. This manual is valid from the issue date.
2. This manual is not to be altered or marked in any way.
3. Any review or alteration to this manual is to be carried out as per the system
procedures.
4. Any revisions of this manual will be recorded on the Revision sheet.
Approved By:
Issued By:
DOC Head
Rev No. : 15
Date : 30-Nov-23
RECORD OF REVISION Page : 1 of 6
RECORD OF REVISION
This procedure was first released as Edition 0, in 2006 and the first major revision was released as
Edition 1 on 21st Oct 2009, after which various revisions were released for multiple chapters. The
second major revision to the manual was released as Edition II on 31st Jan 2013.
Record of all previous revisions are maintained at the office by the QHSE team
Rev No. : 15
Date : 30-Nov-23
RECORD OF REVISION Page : 2 of 6
Rev No. : 15
Date : 30-Nov-23
RECORD OF REVISION Page : 3 of 6
Rev No. : 15
Date : 30-Nov-23
RECORD OF REVISION Page : 4 of 6
Rev No. : 15
Date : 30-Nov-23
RECORD OF REVISION Page : 5 of 6
Rev No. : 15
Date : 30-Nov-23
RECORD OF REVISION Page : 6 of 6
Rev No. : 15
Date : 30-Nov-23
TABLE OF CONTENT Page : 1 of 1
TABLE OF CONTENT
Chapter Title Revision Revision Date
1 General 9 30-Nov-23
2 Engine Room Watchkeeping 12 30-Nov-23
3 Planned Inspection & Maintenance 14 30-Nov-23
4 Procurement and Inventory Control 8 15-May-22
5 Engineering Operations 12 15-Dec-22
6 Dry Docking 8 30-Nov-23
Annex 1 Guidelines on Hull Structure 4 14-Dec-18
Inspection
Annex 2 Class Survey Report 1 15-May-22
Annex 3 List of Minimum Mandatory Safety 0 15-May-22
Critical Spares
Annex 4 Generic List of Compliance Critical 0 15-May-22
Spares
Annex 5 Generic List of Business Sensitive 0 15-May-22
Spares
Appendix 1 CE’s Standing Order Book 2 15-Dec-22
Rev No. : 9
Chapter: 01 Date : 30-Nov-23
GENERAL Page : 1 of 9
1. GENERAL
1.1 OVERALL MAINTENANCE AND OPERATION POLICY
It is the policy of the company to always maintain the vessels under the company’s
technical management in a seaworthy and cargo ready condition, minimising the risk of
breakdown and resultant off-hire, to high safety / quality standards and in accordance
with satisfactory structural, operational, and cosmetic standards as agreed with the
owners. Vessels shall be classed with recognised IACS Member Classification Societies
who are also Recognised Organisations of the ship's Flag, maintained as per their Rules
and certified always. Maintenance shall be carried out in a cost-effective manner, the
intention being to maintain the managed vessels in accordance with Company policies,
the requirements of the Owner, ISM, National and International regulations, and industry
standards.
Rev No. : 9
Chapter: 01 Date : 30-Nov-23
GENERAL Page : 2 of 9
The Master and the Chief Engineer must ensure that inventory of all Drawings and
Manuals is always kept updated. The missing Drawings and Manuals should be
immediately notified to the Superintendent for replacement.
Rev No. : 9
Chapter: 01 Date : 30-Nov-23
GENERAL Page : 3 of 9
Rev No. : 9
Chapter: 01 Date : 30-Nov-23
GENERAL Page : 4 of 9
Rev No. : 9
Chapter: 01 Date : 30-Nov-23
GENERAL Page : 5 of 9
In case of newly delivered ships, ‘Guarantee Claim’ (GC) is to be used during the guarantee
period. In Shippalm under the reporting of ‘Hull and Machinery Defect’ there is an option
to select ‘Guarantee Claim’, while reporting such defects. The defect report when
generated after the vessel fills in the requisite details, will indicate whether that particular
defect is part of the said guarantee claim. Also, the Monthly GC Status is to be sent to the
office.
For such a defect if there is any existing purchase requisition, same can be linked using
the ‘Add’ PR No., or a new purchase requisition can also be raised using the same feature.
Rev No. : 9
Chapter: 01 Date : 30-Nov-23
GENERAL Page : 6 of 9
1. All engine room staff should be suitably dressed as per the PPE Matrix. They shall
wear overalls, safety shoes, gloves, goggles, ear protection equipment and
helmets as appropriate to the jobs they perform. Refer to HSM manual Appendix
03
2. Engine room and machinery spaces must be kept clean and tidy and free of oil
leakages. Any leakage identified should be eliminated as early as possible.
3. To prevent fires, heat sources must be shielded and oil leaks eliminated.
4. Oil leak collection tins, trays or other temporary means of collecting leaks should
not be allowed. Save-alls around tanks and machinery must always be kept clean
with their plugs tightened and drainage trays clean.
5. Dirty rags and cotton waste must be removed and collected for disposal as
directed in the garbage management plan.
6. All lines for transfer and circulation of lube oil/fuel oil systems should be
maintained in good order by attending to any leaks around the gauging pockets
etc. which can lead to sprays and drips onto hot surfaces. All pressurised
distribution piping for lube oil/fuel oil should be protected by anti-splash tape of
approved type on the flanges, pressure gauge connections, unions/adaptors to
prevent spray.
7. All lagging and shielding should be maintained in good order. Missing/damaged
laggings must be replaced/renewed.
8. Workshops must be maintained in a clean and tidy condition with all tools kept in
good working order. The area used for welding must be clearly defined and
provided with the necessary means to prevent accidents and fires.
9. Oxygen and Acetylene bottles must be stored outside the engine room and
accommodation. They must be stored in separate compartments open to
atmosphere and securely lashed in position. For vessels carrying dangerous cargo,
the pipe connections for the oxygen and acetylene bottles must be disconnected
while the vessel is in port undertaking cargo and/or bunkering operations.
10. Oxygen and acetylene hoses must be connected to the piping by use of ferrules
and adaptors. An alternative arrangement can be use of band-it clamps. Use of
jubilee clips to connect these hoses to the gas cutting equipment is not acceptable.
11. Lockers containing gas bottles must be well ventilated and clearly identified.
12. Chemicals are to be used in accordance with the maker’s instructions including
any guidelines regarding the use of protective clothing. Information on medical
care to be followed in case of accidents is to be posted in appropriate places.
Material Safety data sheets are to be kept adjacent to the chemicals. Appropriate
protective clothing (chemical resistant gloves, eye protection goggles) shall be
made available nearby. Acids/Alkalis should be stored separately from each other.
Storage space to be away from sources of heat.
Rev No. : 9
Chapter: 01 Date : 30-Nov-23
GENERAL Page : 7 of 9
13. Care is to be taken when securing stores, bottles, drums and spares to avoid their
breaking free and giving rise to damage and injuries.
14. All engine room staff should be aware of the danger of using faulty electrical
equipment. This applies especially to portable tools. The electrical officer or
person in charge of the electrical equipment should be directed by the Chief
Engineer to check for potentially dangerous equipment and repair them.
15. The electrical engineer or person in charge of the electrical equipment should
perform regular checks of the accommodation areas to prevent potentially
hazardous situations that can result from the use of unauthorised electrical
equipment or alterations to the electrical wiring.
16.To ensure that people are protected from injury when working on or around
switchboards, insulating matting is required at the front and rear of
switchboards.
Individual machinery starter boxes throughout the machinery space are not
considered switchboards and do not require insulating matting in front or behind
them.
Some decks are made from composite insulating material and will not need extra
insulation. Where this is the case and insulation matting is not provided, ship’s
drawings should be available to demonstrate the extent and safe working
voltage of the composite deck covering installed.
Insulation matting should be suitable for the specific switchboard voltage but
should be rated not less than IEC 61111:2009 Class O or equivalent which has a
safe working voltage of up to 1000 volts. Switchboards with voltages higher than
1000 volts should be protected with matting of a higher rating as appropriate,
for example Class 1 with a safe working voltage up to 7500 volts.
17. All lifting equipment must be regularly tested according to the applicable rules and
the maker’s recommendations. Records of these inspections and relevant
certificates must be maintained. Blocks, slings and similar equipment must be
maintained in good condition and stored separately. Safe working loads must be
indicated with permanent highlighting.
18. All rotating machinery components such as pump couplings etc.,should have
shield guards in place at all times.
19. Critical measuring equipment must be calibrated according to rules and the
maker’s recommendations.
20. Chief engineer to ensure that no gagging devices are made to keep gauge glasses
or DB tank sounding pipes permanently open.
21. Purifier, hydraulic room and steering gear doors shall be kept in closed position at
all times.
Rev No. : 9
Chapter: 01 Date : 30-Nov-23
GENERAL Page : 8 of 9
22. Acetylene and Oxygen Regulators for gas welding are to be inspected annually and
replaced once every 5 years. The use of propane in gas burning and welding
systems is prohibited.
23. Inspection of all components linked to the oxy-acetylene gas cutting system
should be annually inspected by the maker’s representative.
24. Modifications to any electrical circuit if being considered, must be done by
conducting a proper MOC, in consultation with the office at the proposal stage.
No unauthorised modifications to any pipelines and electrical circuits are allowed,
without office approval.
25. Electrical Safety- All new joiners shall ensure that their personal electrical
equipment is safe to use on board and do not pose a fire hazard. All personal
equipment must be checked for voltage rating and condition. Vessel staff to be
aware of Ship’s electric supply socket rating in accommodation. Any multi-socket
adapters used must have a fuse in-built. Overloading of the sockets might result
in the initiation of accommodation fire. Personal electric heaters are not allowed.
An appliance such as a mobile phone or laptop should not be left for charging
when the cabin or space is not attended.
26. For an engine room fitted with engines consuming LNG or other low flash point
fuel, the gas monitoring system is fitted on board and operated continuously while
the ship is in service. It is composed of fixed gas detectors and gas sampling points.
In the event of gas detection, alarms are activated simultaneously at the ICMS
stations on the wheelhouse, cargo control room and engine control room, and on
the repeater units in the wheelhouse and engine control room. Immediate action
needs to be taken which may require to trip the engine and evacuate engine room
as required.
27. Care should be taken to see that no SW pipe flanges or bulkhead opening for such
pipes are located above an electrical transformer or switchboard.
28. For the vessel’s fitted with lathe machine in the ER workshop, loose emery paper
is not to be used for polishing workpiece. Instead, bow sander should be used for
similar task. Each lathe must have an emergency pedal stop arrangement fitted. It
is further recommended to install safety cover with limit switch interlock for the
rotating chuck of the lathe machine. If the vessel is not fitted with such
arrangement, Master/CE to contact office for initiating engineering design change
MOC.
29. For the safety of operator, it is recommended to fabricate grease extension points
for the accommodation air-conditioning system blower/compressor motor. This is
to avoid injury to personnel due to proximity of the rotating parts while carrying
out greasing.
Rev No. : 9
Chapter: 01 Date : 30-Nov-23
GENERAL Page : 9 of 9
30. When vessel is within the limits of the terminal/port authority, the boiler, main
engines, steering machinery and other equipment essential for manoeuvring
should normally be kept in a condition that will permit the ship to be moved away
from the berth/anchorage during an emergency. A terminal/port authority may
allow some degree of immobilization of the propulsion plant whilst the ship is
alongside/at anchorage. However written permission must be obtained before
commencing subject job and mentioned in the ship shore safety checklist. Any
unplanned condition that results in the loss of operational capability should be
immediately communicated to the terminal/authorities.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 1 of 22
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 2 of 22
During planning the manpower for passage, if it is observed that complying with minimum
manning level matrix results in violation of the rest hours, then a level II RA is to be made
in consultation with the office and the required deviation is to be obtained.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 3 of 22
The Chief Engineer will ensure that whenever the main engines are placed on standby,
sufficient electrical generators are run in parallel to share the electrical load. Thus, loss of
one machine will not result in total loss of electrical power. Standby conditions will
include the following:
▪ Navigation in harbours, rivers, canals, anchorages, or their approaches.
▪ Navigation in ice or restricted visibility.
▪ Navigation in Special Areas.
▪ Any other Situation as deemed necessary by the master, including:
▪ Navigation in Traffic Separation Schemes;
▪ Navigation in Coastal or Restricted Waters.
The Chief Engineer shall ensure that the engine department manning is adequate for safe
operation of machinery and assign extra personnel, if required. The minimum manning
level for Engine Room during Navigation is given in the “Manning Level Matrix”.
The Electrical Officer shall be in attendance in the engine room at the discretion of Chief
Engineer when the vessel is entering/leaving port or manoeuvring.
Manning Level Matrix
Navigation Light Minimum Minimum UMS Minimum
Visibility Weather
Scenario’s Conditions BWL ERWL Permitted operational
machinery
Main engine
(ME)-Sea speed,
Daylight Clear Normal I I Yes
Auxiliary
Engines (AE) for
sea load, Single
Steering motor
(SM)
ME-Sea speed,
AE for sea load,
Darkness Clear Normal II I Yes
Single SM
Open
water’s
ME-Sea speed,
Multiple AE,
All Clear Heavy II II No
Multiple SM
ME-Ready for
maneuvering,
All Restricte Normal II II MD
d
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 4 of 22
Multiple AE,
Multiple SM
ME-Ready for
maneuvering,
All Restricte Heavy III III No
Multiple AE,
d
Multiple SM
ME-Sea speed,
AE for sea load,
All Clear Any II II MD
Single SM
Coastal
ME-Ready for
water
maneuvering,
All Restricte Any III III No
Multiple AE,
d
Multiple SM
ME-Ready for
maneuvering,
Restricted All Any Any III III No
water Multiple AE,
Multiple SM
Navigation ME-Ready for
Special Area maneuvering,
All Any Any III III No
Multiple AE,
Multiple SM
Pilotage, ME-Ready for
Entering / maneuvering,
All Any Any III III No
Leaving Port
Multiple AE,
Multiple SM
ME stopped at
notice decided
Daylight Clear Normal I I Yes
by Master,
Single AE*,
Single SM
At Anchor
ME stopped at
notice decided
Darkness Clear Normal II I Yes
by Master,
Single AE*,
Single SM
ME-Ready for
maneuvering,
Helicopter III III No
Operations Multiple AE,
Multiple SM
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 5 of 22
ME-Ready for
maneuvering,
STS III III No
maneuverin Multiple AE,
g Multiple SM
HRA/Piracy
prone area
II I MD MD
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 6 of 22
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 7 of 22
▪ Test running the emergency diesel generator and emergency fire pump (if done
during the watch)
▪ Running/testing of lifeboat motors (if done during the watch)
▪ Testing alarms and shut down systems (if done during the watch)
The engine watchkeeping officer is not to hand over the watch to the relieving officer if
he has reason to believe that the latter is not capable of carrying out his duties effectively
and must notify the Chief Engineer immediately.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 8 of 22
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 9 of 22
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 10 of 22
Except in the case of an emergency the watchkeeping engineer is to consult with the
bridge officer on watch before any speed change is made, as the safety of the ship is
paramount. However, in circumstances beyond his control when the engine must be
stopped immediately, he is to take the following actions: -
1. Ring “STOP” on the engine room/bridge telegraph
2. Stop the engine
3. Sound the engineers call alarm
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 11 of 22
No erasures shall be permitted in the log books & movement books. Any
errors/alterations shall be neatly crossed out and the correct entry should be made
alongside, both entries initialled by the officer making the correction. No corrections shall
be made using a whitener.
The logbooks and movement books shall be signed daily by the Chief Engineer and
retained aboard as a permanent record.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 12 of 22
▪ Lower engine room - check all motors and pumps that are operating, including
lube oil and fuel oil purifiers.
▪ Heat exchangers- check temperature and water level and cooling water pressures.
▪ Bunker tanks - check temperatures and note which tank and suction is in service.
▪ Tail shaft - check mechanical seal, temperature, and leakage, if any.
▪ Main lube oil sump - check level, oil colour and smell.
▪ Double bottoms - sound.
▪ Inert Gas System - if operating, check scrubber, fan, overboard valves, operating
pressures, and temperatures.
▪ Fuel oil tanks in service -- check level and drain off water.
▪ Fresh water header tanks level to be checked and replenished as necessary. Any
abnormal consumption to be brought to the notice of the duty engineer.
▪ Synthetic LO grades from different makers should NOT be mixed. In case of
unavoidable circumstances, entire LO shall be renewed to the available grade.
While making this round, attention must be paid to the condition of the bilges, whether
they are dry or not and whether any oil is visible. Any steam, water or oil leaks must be
reported immediately to the engine watch officer.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 13 of 22
▪ Safety systems
▪ Remote control systems
▪ Automatic control systems
▪ Emergency lighting systems in engine room
▪ Communication systems
▪ Fire alarm and fire protection systems
▪ All equipment operating parameters are as per Maker’s recommendations
▪ E/R Bilge Alarm to be test by Electrical officer before UMS
▪ TME and ratings are not to acknowledge alarms under UMS condition
2. Chief Engineer is to then seek authorization from the Master, who should take the
following external conditions into account.
▪ Weather.
▪ Navigation through restricted, shallow, and or traffic zones.
3. Chief Engineer will then initiate unmanned condition after having reassured himself
of the UMS duty roster and night orders to his engineers. A suitable entry to be made
in both the deck and the engine Log Books.
4. Duty Engineer must ensure compliance with the guidelines provided for assuming
watch and watch keeping guidelines. Checklist for take over watch and unmanned
machinery shall be used (Form TE-34). The UMS check list shall be a laminated sheet
which can be used daily and logged in the engine logbook.
5. Duty Engineer must have full understanding of the procedure for changeover of all
the automatic controls to manual system in case of an emergency.
6. Duty Engineer must inform the Bridge each time the engine room is manned or
unmanned.
7. If a Dead Man Alarm system is not provided, any person entering the machinery space
alone must inform the Duty Officer and maintain contact every 15 minutes. If contact
is not maintained from the engine room, the duty officer should try establishing
contact to ascertain personnel’s safety, failing which he should inform the Chief
Engineer or Second Engineer as appropriate. The system and the response to be well
understood by all Bridge watchkeeping officers. Prior leaving the machinery space, he
must inform the Duty Officer.
8. Where fitted, the use of the Dead Man Alarm should be activated each time an entry
is made in the unmanned machinery space. The alarm must not be set for an interval
greater than 15 minutes.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 14 of 22
9. In port, when the Bridge is unmanned, the duty Deck Officer must be informed prior
to entering or exiting from the engine room by any person. A shipboard procedure is
to be drawn up and a form of communication established, e.g. VHF/UHF. Allowance
should be made for the duty Deck Officer to be on deck at time of entry.
10. Duty Engineers are to conduct Inspection rounds after work hours and at night hours
before retiring to bed. The maximum period between checks is not to exceed 8 hours.
Around the same time Chief Engineer will also take a complete round of the engine
room to ensure it is safe to continue with UMS operation.
11. The remote indicators for pressure, temperature etc must be compared with the local
instruments to confirm the correct operating parameters of the machinery.
12. Duty Engineer shall be responsible for taking proper action in the event of alarms /
failures of equipment. Failures of a serious nature are to be immediately brought to
the notice of the Chief Engineer & Bridge.
13. The Duty Engineer shall be available within the audible range of the UMS extension
alarm. When his presence is required outside the machinery or accommodation
spaces, he shall be suitably relieved by another engineer.
14. Whenever the Master feels the safety of the vessel is at stake, he has the ultimate
authority to order manning of the engine room.
15. Equally, whenever the Chief Engineer feels the risk of running unmanned is high, he
will order manning of the Engine Room.
16. After all major overhauls, engine room must be kept manned for at least 24 hours or
till the normal working of the overhauled equipment is fully established.
17. The engine room is to be kept manned, as relevant, during special operations as
ballasting de-ballasting, loading / discharging, tank cleaning, inerting, gas freeing,
bunkering etc.
18. When using freshly supplied bunkers, engine room must be manned for sufficient
time to ensure that no problem is being encountered with engine
performance/parameters and settling, purification, separating and filtering systems.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 15 of 22
Waiting Time
Waiting time in port with only the diesel generator operating may be carried out with
unmanned engine room during night time.
Standby conditions
It is the responsibility of the Chief Engineer to ensure that the machinery spaces are
adequately manned during all standby conditions. If necessary, extra engineer officer
manning must be utilised during standbys to ensure that all operational requirements are
effectively dealt with and that any necessary remedial actions are promptly taken.
Mooring, Unmooring, and Shifting
Mooring, unmooring, or shifting ship operations shall be carried out with manned engine
room.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 16 of 22
When an alarm condition develops, the duty engineer must proceed to the engine control
room, acknowledge the alarm and take corrective action. If the duty engineer does not
respond to the alarm within three minutes, it is the responsibility of the officer on watch
on the bridge to call the duty engineer and the Chief Engineer immediately. The duty
engineer must log acknowledgement of the alarm in the UMS alarm register.
Shortly before 2300 hrs the Duty Engineer should conduct a round of the engine room
with the unattended engine room checklist.
At his discretion, the Chief Engineer may instruct the duty engineers to make additional
rounds in the engine room to confirm that it is in satisfactory condition. In this regard,
the Chief Engineer should consider recent maintenance and/or alarm history.
The Duty Engineer Officer on duty should record and enter engine data in the engine room
logbook at noon each day.
It is the Chief Engineer's duty to organize the duty engineers effectively. He may normally
choose to rotate the duty engineers every night. The most efficient organization may vary
with length and type of voyage. Balancing overtime requirements for maintenance
and/or night inspection rounds may also influence the organization and chief engineer
should consider this during this when planning.
Note: All engine room personnel engaged in UMS rounds must strictly adhere to the
company’s PPE Matrix while entering the engine room.
1. Safety requirements (including the use of Dead Man Alarm) clearly posted at the
entrance to the unmanned machinery space.
2. Engineer’s call alarm operates when the machinery alarm is not acknowledged
within 5 minutes. For a ship constructed before 18th Jan 2010, this time limit may
be different.
3. The following entries are to be done in Engine logbook:
• For UMS operations, the time of each changeover between manned and
unmanned modes.
• Bunkering operations and major internal oil transfers
• Fuel and lube oil ROB's
• Changeover of fuel / entering ECA
• Machinery operating parameters (RPM, load, temperature and pressures)
• Chief Engineers’ signature on a daily basis
4. The use of emergency equipment in engine room to be known to all and
instructions for their use posted at their respective locations (use of photographs
for starting procedures)
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 17 of 22
2.5 MANOEUVRING
Manoeuvring a ship in restricted waters constitutes a critical operation, in that any
operator errors are likely to cause an immediate accident or create a threat to the ship,
its crew and cargo as well as the environment and other property.
Consequently, engineering plant operations during manoeuvring shall be conducted in
accordance with the following procedures.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 18 of 22
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 19 of 22
2.6.1 TESTS
The following equipment must be tested for proper operation shortly before entering
confined waters or getting underway. The test should be carried out in conjunction with
the Deck Watch Officer.
▪ Main engines, both ahead and astern (slow speed is enough).
▪ Rudder action using both bridge steering control systems and all hydraulic steering
pumps.
▪ Internal communications systems, including telegraphs, between the bridge, the
engine room, and the steering station in the steering gear room.
▪ Engine room and bridge propulsion and steering failure alarms, where fitted, using
installed lamp and alarm test buttons.
▪ Storage batteries for emergency lighting and power systems in ship control and
machinery spaces (test for voltage).
▪ Bridge and engine room clocks must be compared and synchronized if necessary.
▪ Vessel Entering or Leaving US Waters to be tested as per 33 CFR 164.25
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 20 of 22
2.6.3 ARRIVAL
Deck Machinery
Upon notification from the bridge one hour prior to arrival, steam, electric power or
hydraulic power shall be supplied to the deck machinery until the vessel takes departure.
Refer to later sections on maintenance of mooring equipment.
Cargo Equipment
In case of oil / chemical tanker inert gas system or nitrogen plant, such equipment has to
be tested for the normal operation for a minimum of 30 mins duration at the minimum
O2 Content which the plant can produce, before entering port.
2.6.4 DEPARTURE
Securing for Sea
Before leaving port, the Chief Engineer must ensure that those parts of the vessel under
the authority of the engine department are secured for sea. Stores and spare parts must
be removed from decks and alleyways and stowed. Heavy material must be properly
lashed. Engine room cranes and monorail cranes (if fitted) must be secured with locking
pins in place.
Manning
Before departure from port, the Chief Engineer must ensure that the engine room is
adequately manned. One hour before sailing time, a check must be made by engine room
personnel. The engine watch officer must notify the Chief Engineer accordingly.
Tests and Log entries
Main Engine tests
Before testing the main engine, the engine watch officer must obtain permission to turn
the propeller from the deck watch officer.
In the event of an emergency, the engine watch officer must be prepared to stop the
engine immediately. Before getting underway, the engine watch officer must:
▪ Blow the main engine over on air and ensure no water or vapour is ejected from
the indicator cocks.
▪ Ensure that the engine temperatures are in the normal range.
▪ Turn the engine using turning gear.
▪ Lubrication of fuel racks and VIT racks.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 21 of 22
For vessels subject to IGF Code, the main engine cannot be tested on LNG mode. Engine
can be tested on standby fuel mode only.
Other Tests
These tests should be carried out in conjunction with the Deck Watch Officer:
▪ Test the engine order telegraph.
▪ Test the steering gear.
▪ Synchronize the engine room clock with the bridge clock.
Log Entries
Departure from port, preparation for sea checks and compliance with checklists must be
entered in the engine log.
2.7 IN PORT/ANCHOR
2.7.1 ENGINE WATCH OFFICER
The chief engineer officer, in consultation with the master, shall ensure that engine
watchkeeping arrangements are adequate to maintain a safe watch while in port. While
on duty, the engineer(s) shall not undertake any task that would interfere with their
supervisory duty in respect of the ship's machinery system. When deciding the
composition of the engineering watch which may include appropriate engine-room
ratings, the following points are among those to be considered:
• on all ships of 3,000 kW propulsion power and over there shall always be an officer
in charge of the engineering watch
• on ships of less than 3,000 kW propulsion power there may be, at the master's
discretion and in consultation with the chief engineer officer, no officer in charge
of the engineering watch and
during stay in anchorage in consultation with the Master, it is the Chief Engineer’s
discretion to maintain watches outside normal day work. Chief Engineer may consider the
planned maintenance during the port and anchor stay. Also access to machinery spaces
needs to be controlled as per the company approved ship security plan.
Rev No. : 12
Chapter: 02 Date : 30-Nov-23
ENGINE ROOM WATCHKEEPING Page : 22 of 22
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 1 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 2 of 151
The overall responsibility for monitoring maintenance on board vessels rests with the
Fleet Manager.
The technical superintendent is responsible for the routine monitoring and verification
of planned maintenance on board vessels placed under his direct charge, including the
status of overdue items. He shall respond to overdue jobs by a separate email to each
vessel on a monthly basis, or through monthly safety meeting minutes. The status of
overdue items will be checked thoroughly by the respective superintendent before
providing data to the monthly technical meeting.
The status of maintenance standards is to be discussed in monthly technical department
meeting. The Master and Chief Engineer is responsible for the implementation of and
compliance with the PMS and other maintenance routines on board his vessel. Chief
Engineer shall be responsible to check the status of overdue tasks prior sending weekly
updates to office.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 3 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 4 of 151
PREDICTIVE MAINTENANCE
Though our endeavour is to ensure that all equipment PMS is adhered to, it has been
our experience that in spite of such maintenance, equipment have failed at critical times.
To address this issue, the Company has initiated a Predictive Maintenance Scheme for
the maintenance routines of the ship’s Main Engine.
Based on latest service experience and engine development we have revisited the
guiding overhaul intervals of the Main Engine, which apply to MAN B&W MC/MC-C, ME,
ME-B/C engine and Wartsila Sulzer RTA / RT Flex type of engines.
Longer overhaul intervals can be obtained with a condition-based overhaul strategy
which can predict the ensuing maintenance interval. The means to obtain and document
this are described in engine specific service letters issued by the respective engine
makers.
The procedure for implementation of the above-mentioned scheme is described at Para
3.15.6 of this Manual.
Depending on a favourable evaluation of the benefits of this system, the Company would
then include more machinery as practicable at a later stage. We also encourage Chief
Engineers onboard to use various data to predict any flaw in the system/machinery and
bring it to the notice of the office for further investigation and action.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 5 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 6 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 7 of 151
No
No
A “Safety Critical” generic list of equipment & systems given below has been identified
basis a high-level risk assessment of the key vessel specific “Safety Critical” functions. An
industry-standard design has been used as the basis for a single point failure analysis to
arrive at the generic list of “Safety Critical” equipment & systems.
Each vessel shall make the below recommended list ship specific in consultation with the
Technical Supdt by following the above flowchart. Equipment may be added to the below
list as felt necessary based on the result of applying the above flow chart.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 8 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 9 of 151
Function Check 2E 2E
8. Cargo Hold (Container ships) Fixed Fire Fighting system
Function Test CO CO
9. Fixed Gas Detection System (Pump Room, Gas Compressor & Motor Room)
Test Test Master Master
10. Fire Detection & Alarm System
Annual check fire
Check EO EO
detection system
11. Fixed CO2 Fire Extinguishing System
Level check /
Record Approved Shore Facility
Record
Lines Blow Through CE CE
Release system Inspect CE CE
12. Fixed CO2/Nitrogen Fire Extinguishing System for Vent Mast (For Gas Carriers)
CO2 / N2
Hydraulic Testing Approved Shore Facility
Cylinders
Level check /
Record Approved Shore Facility
Record
Release system Inspect CE CE
13. Fixed DCP firefighting system Deck (For Gas Carriers)
Inspection of
Check CO CO
piping system
DCP Powder
Agitation (as per Check
CO CE
flag/class
requirement)
14. Deck Water Spray System (For Gas Carriers)
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 10 of 151
Inspection of
Check CO CO
piping system
Pump Function Test 2E 2E
15. Fixed Foam Fire Extinguishing System Deck/ER
Inspection of
Check CO CO
piping system
Pump Function Test 2E 2E
Foam Analysis Check CE CE
17. Fixed Water Based System (Hyper Mist) for Engine Room
Inspection of
Check 2E 2E
piping system
Pump Function Test 2E CE
18. Fixed Gas Detection System (For Tankers and Gas Carriers)
3 monthly inspect
Inspect gas detection CO CO
system
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 11 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 12 of 151
DCP Powder
Agitation (as per Check CE
CO
flag/class
requirement)
31. Gas Detection System for IGF Code vessels - Fuel Preparation Room and LNG Pipelines to
Machinery
Monthly check/test
E/O
Inspect of gas detection E/O
system
Test Gas detection
alarms in FPR and
LNG double pipes. C/E
Check E/O
Test Loss of
ventilation alarms in
the double pipes.
32. Fixed CO2 System for Fuel Preparation Room on IGF Code vessels
Approved Shore Facility
CO2 Cylinders Hydraulic Testing
Level check / Approved Shore Facility
Record
Record
CE
Release system Inspect CE
33. Fire Alarm, Fire Push buttons & General Emergency Alarm
CE
Test Check E/O
35.Emergency Trips for Ventilation & FO/LO pumps
CE
Test Check E/O
37.Fire Flaps & Dampers
Inspect /visually C/E
Check 2/E
examine
38.Fire Lines & Isolation Valves
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 13 of 151
Inspection of fire
2/E
lines and the Check 2/E
isolation valves
39.Rescue Boat & Engines
2/E
Test Test 2/E
40.Rescue Boat & Launching device
CO
Test Test CO
41.Emergency Bilge Injection Valve
CE
Test Test CE
42.Main Engine Individual Unit Components
2/E
Test Test 2/E
43.Electronic Main Engine Control System
2/E
Test Test 2/E
44.Cargo Hold Fire Detection & Alarm System
CO
Test Test CO
45.Emergency Shut down/Cargo Oil Pump Shutdown
CO
Test Test CO
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 14 of 151
No
No
Reference is drawn to the Annex 3 of this manual which is a list of “minimum mandatory
spares” for the safety critical equipment, the ROB of which should always be maintained
on board. In addition to the above flowchart, this list can also be used to finalise the
vessel specific list of minimum mandatory spares.
The approved “Safety Critical” minimum mandatory spares list is not a static document
and needs to be reviewed for additions frequently for improvement.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 15 of 151
No
No
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 16 of 151
• Oily Water Separator & Oil Content Monitor (OWS & OCM)
• Oily Discharge Monitoring Equipment (ODME)
• Bilge Pump
• Sludge Pump
• Sewage Treatment Plant
• Incinerator
• Marine Exhaust Gas Scrubber Cleaning Systems (EGCS)
• Exhaust Gas Selective Catalytic Reactor Systems (EGSCRS)
• Ballast Water Treatment Systems (BWTS)
• Cargo Hold Water Ingress Detection & Alarm System (for bulk carriers)
• Magnetic Compass
• Hose Handling Cranes
• Portable Gas detection
• UTI Tapes
• SCBA Compressor
• Cargo Oil Turbine pumps (COPs)
• Echo Sounder/Depth Finder
• GMDSS (Global Maritime Distress & Safety System)
• EPIRB
• ECDIS as primary navigation system (2 fitted)
• X and S band Radar
• Gyro & Repeaters
• Speed log
• Course Recorder
• VDR – Voyage Data Recorder
• AIS – Automatic Identification System
• GPS – Global Positioning System
• ROT indicator
• Rudder angle Indicator
• RPM Indicator
• BNWAS – Bridge Navigation Watch Alarm System
• VHF Radio
• Communications
A vessel-specific “Compliance Critical” spares list is to be drawn by the vessel’s Master,
Chief Engineer in consultation with the technical superintendent. The flowchart given
below is to be used as guidance for preparing this vessel specific list –
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 17 of 151
No
No
Reference is drawn to Annex 4 of this manual which is a generic list of spares for the
compliance critical equipment. In addition to the above flowchart, this list serves as
guidance to finalise the vessel specific list of the required spares. The ROB of the spares
as per the vessel specific list is mandated to be maintained at all times.
NOTE - In case of any vessel acquisition, all efforts should be made to ensure that vessel
complies with the required ROB of Safety Critical and Compliance Critical spares within
one (01) month of vessel takeover date.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 18 of 151
The MOC for vessel takeover shall include a reference to these lists and the desired date
of compliance with it.
In case of any logistical problems in supplying the Safety Critical and Compliance Critical
spares within the stipulated time, a deviation must be sought from the management. In
the interim, a risk assessment must be carried out, with mitigating measures in place, to
handle the shortfall of these spares.
*Note: There are certain items mandated by the Company in the Business Sensitive
spares list.
The flowchart given below can be used as guidance for finalizing the ship specific list of
“business sensitive” spares.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 19 of 151
Given below is a list of “Business Sensitive” equipment and systems as determined by the
Company.
Each vessel shall make this list ship specific in consultation with the Technical Supdt by following
the above flowchart.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 20 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 21 of 151
• Centre ramp
• Movable ramp
CRITICAL EQUIPMENT MAINTENANCE
When the critical system, alarms or equipment needs to undergo planned or unplanned
maintenance as part of the PMS routine and/or breakdown rectification, the Technical
Department shall be notified immediately and approval sought for the desired
maintenance activity. A defect report to be made along with a Risk Assessment (SF 23)
and TE-22/TE-22A form, as applicable.
The below table clarifies the applicability of TE-22, SF-23 (RA), TE-22A and approving authority as
per the type of critical equipment and different operating situations on board the vessel.
TASK SAFETY CRITICAL COMPLIANCE CRITICAL BUSINESS SENSITIVE
EQUIPMENT EQUIPMENT EQUIPMENT
Doc Approving Doc Approving Doc Approving
required authority required authority required authority
Function test As per As per As per
PMS PMS As per PMS PMS
As per PMS As per PMS
Planned TE-22; TSI As per As per PMS As per As per PMS
Maintenance as per SF-23 PMS PMS
PMS (RA)
Unplanned TE-22; Approval by SF-23 SF-23 TSI
Maintenance/Repairs SF-23 Tech (RA) (RA)
by ship staff (no (RA) Manager TSI (and MSI
shore resources where
required) required)
Breakdown requiring TE-22A; Approval by TE-22A; Approval by SF-23 Approval by
shore SF-23 Tech SF-23 Tech (RA) Tech
Technician/spares (RA); Manager (RA); Manager Manager
(notify senior (notify senior (notify senior
management) management) management)
While in drydock, for maintenance jobs on any of the above type of critical equipment,
form SF-23 is to be submitted for review and approval by TSI.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 22 of 151
The test and performance data for all “Safety Critical Equipment & Systems” shall be
carried out as per the PMS to ensure the high reliability and good maintenance. These
tests and performance data are to be recorded in PMS using Form TE-44 on a quarterly
basis and after any planned/unplanned maintenance on this equipment.
3.4.1.1 TEST AND PERFORMANCE OF SAFETY CRITICAL EQUIPMENT NOT IN CONTINUOUS USE
From the list of Safety Critical Equipment, the Emergency Generator, Emergency Fire
Pump and Emergency Air Compressor are identified as those not in continuous use.
The following general guidelines are applicable for the performance test of these
equipment.
Emergency Generator –
A running test of the emergency generator on load is to be carried out once in each
quarter. The test load should be at least equal to the total of essential loads specified in
the electrical load analysis table available on board each vessel. The test should be run
for a minimum of 30 mins. Duration and parameters recorded in Form TE-44 is to be
compared with those available in the engine’s shop trial reports.
Prior to testing all equipment sensitive to power supply fluctuations such as Gyro,
Radars, ECDIS, Cargo/Ballast Tank Level gauging systems, ODME etc., should be switched
off to prevent damage due to power surge.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 23 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 24 of 151
For calendar based jobs, the following grace periods are allowed
The guidelines below pertain to overdue jobs and deferment of PMS jobs.
• Request for deferment of a scheduled PMS job should be raised well before the
job becomes overdue or is in the grace period.
• When the vessel is scheduled for drydocking/major repairs, provision for extended
deferment must be considered.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 25 of 151
• The number of jobs falling under the grace period and deferred jobs together
should never exceed 3% of the total PMS jobs for that period.
The process of deferment approval is mentioned below, based on Risk assessment and
justifications provided -
• Deferment duration up to 10% of the scheduled interval will require Technical
Superintendent’s approval
• Deferment duration above 10% and up to 25% will require Technical Manager’s
approval. No deferment beyond 25 % is allowed under normal circumstances.
• For reasons unforeseen, if deferment is to exceed 25% of the scheduled interval,
Technical Head/Head of Shipmanagement to be informed.
• Once the job is deferred, the vessel must put in all efforts to complete the job well
before the target date assigned by the Technical team.
In case the vessel estimates that the deferred job cannot be completed within the target
date due to various reasons, then it should be communicated to the technical
department well before the target date requesting extension of deferment with a risk
assessment and justifications.
A job cannot be left overdue beyond deferred date without Technical department’s
approval.
For the deferment of Main Engine unit piston ring replacement, attention is drawn to Ch
3.15.6 of this manual.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 26 of 151
All measuring instruments on board are to be identified. A list is to be made and included
in the ship’s Planned Maintenance System.
Such important instruments shall be -
• calibrated and adjusted periodically or prior to use, as per international or
national standards. Where no such standards exist, the basis used for
calibration shall be recorded
• protected from adjustments that would invalidate the calibration
• protected from damage and deterioration during handling, maintenance and
storage
• having records of their calibrations
• recalibrated if they are subsequently found to be out of calibration
Calibration should be done on board by ship staff where possible and the results
recorded in the PMS system. Those items that cannot be calibrated by ship staff should
be sent ashore for calibration and a certificate issued.
A record of calibration must be maintained on board for all the items which have been
identified. The record must clearly state the identity of the equipment and the location.
The Master and Chief Engineer of each vessel is responsible for maintaining records to
ensure that measuring and testing equipment used on board are calibrated in
accordance with the requirements.
Please refer to the generic list below for the calibration intervals and requirements of
specific instruments.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 27 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 28 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 29 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 30 of 151
All officers are to familiarize themselves with the overrides and emergency stops
provided in the equipment, especially in the main propulsion system. Their functions
and the importance should be well understood. These are to be used only in
emergencies where the safety of the vessel is considered more important than the
possible damage to the equipment. Except when there is a requirement for actual
emergency stops to be tested, these must not be simulated.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 31 of 151
Mohm. Though these values are good enough for running any electric motor, the cause
of drop in value should be taken seriously.
Weather tightness
Every electrical unit installed anywhere on board (including paint or sample lockers and
stores) should be airtight. This is to prevent water, moisture, dirt / dust, or inflammable
/ explosive gases from entering the sealed units. Ingress of dust, moisture or gas will
indicate a change in insulation values. Typical examples of ingress prevention measures
are cable glands, shades of light fittings, gaskets of junction boxes, seals of cable
penetrations, etc.
There are exceptions to this. Alternators, for example, have ventilation louvres for
cooling the alternator coils. However, a felt filter mat placed at the louvres reduces the
extent of dust that accumulates at the windings. Similarly, electrical switch boards may
have ventilation louvers. It is essential that dust/dirt accumulated on the circuits within
the equipment is removed to the maximum extent possible.
5. SF forms related to safety meetings must detail the discussions held in case of above
jobs and submitted to office for review.
7. At no time should Low insulation alarm setting be reduced for the insulation meters
of 440 V, 220/110 V and 24 V DC switchboards to less than Yard setting to avoid
alarms, especially for UMS ships.
8. In addition, monthly work done reports by CE and EO must include the extent of
inspections done on board and change in insulation values of equipment tested. The
goal should be to ensure NIL electrical incidents.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 32 of 151
9. The above-mentioned IEC Standards must also be included / attached in the handing
over notes of personnel.
Maintenance of the intrinsically safe circuit should be done regularly. The continued
safe operation of the apparatus certified as intrinsically safe depends upon the
electrical circuit being maintained exactly as it was designed. The value of resistors,
condensers and characteristic of the rectifiers and the diodes should be regularly
checked.
The removal or inadvertent disconnections of a resistor, condenser or a rectifier
intended to discharge the circuit inductance may not apparently affect the operation
of the apparatus, but it will render it unsafe. The continued use of the equipment in
this condition may lead to an accident. The exact value and rating of shunt resistor
or condenser is very important. If a component of the wrong value or rating is
connected in its place, the apparatus may no longer be safe for use.
Similarly, a change in the circuit inductance may also destroy the intrinsic safety of
the apparatus. The circuit inductance depends not only on the windings connected
into it, but also upon the cores, yokes and armatures associated with those windings.
A loose screw or a damaged part will affect the inductance and negate the intrinsic
safety of the circuit.
Another point is that any alteration to the circuit (i.e., an extension in which a second
piece of apparatus is connected in series or parallel) may also destroy its intrinsic
safety. The certificate of intrinsic safety for a type of apparatus states whether it can
be connected in series or in parallel with other similar units.
As there is no actual test which can be used to determine whether a piece of
apparatus or circuit is intrinsically safe or not, the best safeguard is to ensure that
the circuit continues to conform exactly with the specification for which a certificate
of intrinsic safety has been granted.
• No maintenance on live equipment should be carried out in hazardous zones.
• ‘Work Permits’ and ‘electrical isolation permits’ to be observed and use only approved
test instruments.
• When replacing any glands, the approved “Ex-d” glands and sealing compound of
approved type should be used. This sealing compound forms a barrier between the
individual conductors and prevents entry of explosive products from the enclosure
entering the cable.
• When replacing any components, light fittings and luminaries, only approved type of
spare parts should be used.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 33 of 151
• The hazardous area should be rendered safe to work, or the electrical equipment
removed from the area, prior conducting insulation resistance test using a 500 V tester
which is of intrinsically safe design and certified.
• On board all Tankers, LPG/LNG vessels, only intrinsically safe type walkie talkies should
be used. Batteries should be changed only in gas safe areas.
Maintenance routines that are required to be included in PMS -
Weekly -
• Earthing and Bonding in Hazardous Areas - integrity to be checked. All bonding
conductors should be free from wastage and well connected.
• Zener barrier earth and fuse - check for tightness of connections. Fuse should be intact.
The cause for any blown fuse is to be further investigated to ascertain the reasons.
• Visual inspection of all electrical fittings in hazardous areas - no light enclosure should
have any moisture or dirt ingress. Any such ingress would obviously indicate leakage of
enclosure seals/gaskets.
▪ Any replacement should be carried out with approved parts and
assembled/checked in non- hazardous area. All fittings should be checked
for signs of corrosion and any damage.
Connections should be checked for tightness. All protections against corrosion,
vibration, weather etc. should be checked for proper integrity and suitability as originally
intended. All fittings should be checked for unauthorized modifications. Any doubts
should be promptly clarified with the Technical Supdt.
Monthly -
• Inspection of cables and cable glands/stuffing boxes - all cables should be checked
for proper support as originally intended with no sharp turns or visible
deformities. All cable glands and stuffing boxes should be checked for proper
sealing with no signs of leakage. Close up inspections would reveal any change in
integrity. Wherever a cable passes through bulkheads, the sealing integrity of
putty/cementing/stuffing box should be checked as well.
• Inspection of ducts, pipes, and conduits for satisfactory sealing.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 34 of 151
Quarterly –
Insulation testing and equipment inspection - all electrical equipment in hazardous areas
to be tested for proper insulation using either an approved tester or transported to non-
hazardous area and tested as per manufacturer’s recommendations. Portable
equipment can be easily transported to non-hazardous areas and testing carried out.
For fixed equipment, proper electrical isolation procedures to be adopted and relevant
permits obtained.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 35 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 36 of 151
Cement/sealing -
Examine the cement/sealing used around lamp glass assemblies both inside and outside.
If the cement/sealing material is eroded, soft or damaged in any way, advice should be
sought from the manufacturer regarding repair. If deterioration of the cement/sealing
material has occurred, a new lamp glass assembly should be fitted.
Lamp glass -
Check and clean the lamp glass. If cracked or broken, a new lamp glass assembly should
be fitted.
When re-assembling an “Ex-d” enclosure, you must ensure that the following points are
covered:
• Lightly grease all flame paths and threaded components with an approved form
of non-setting silicone grease. Care must be taken to ensure that blind tapped
holes are free from accumulated dirt or excessive grease which can prevent the
correct closure of flame paths or cause damage to the tapped components. Fit
new lamp of the correct rating.
• Ensure bolts are not over-tightened as this can distort flame paths, cause
excessive stress on lamp glass or distort weather proofing gaskets, allowing the
ingress of liquid and dust.
• Check that light fitting is installed in accordance with the requirements of the
installation, particularly the classification of the area if it is hazardous and that the
correct rating of lamp is fitted.
• Remove any build-up of dust on the light fitting as this can cause overheating and
corrosion.
• Before attempting any maintenance work on Ex-d equipment check for any
inspection and overhaul instructions given by the manufacturer.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 37 of 151
All cargo holds, ballast tanks, void spaces, inter barrier spaces (hold spaces) including
independent tank foundations are to be structurally inspected as per the schedule
below. The result of inspection should be sent to office using photographs. On tankers,
only intrinsically safe cameras shall be used for taking photographs.
Inspections conducted during Superintendent visit and during drydocking are to be
credited in the PMS.
All cargo holds are to be inspected soon after every unloading operation to ascertain
stevedore damages and make necessary claims.
The inspection schedule should be maintained in the PMS.
The vessel’s Superintendent should be consulted for alternate inspection schedules, if
owing to the type of vessel or its trade, the below mentioned frequency of inspections
is impracticable -
• On tankers– all ballast tanks to be inspected every 9 months and within 3 months
from the date of take over from yard or from another manager
• Dry cargo vessels – ballast TST to be inspected every 6 months and ballast DB tanks
to be inspected every 12 months.
• All void spaces to be inspected every year.
• All cargo holds to be inspected every 6 months.
• On crude oil tankers and gas carriers, cargo tanks should be inspected whenever
there is an opportunity. In no case shall the interval between successive
inspections exceed 30 months for crude oil tankers and 60 months for gas tankers.
• On oil/chemical tankers, the opportunity after mopping/tank cleaning should be
utilized for tank inspection. However, in no case shall the interval between
successive inspections exceed 30 months.
• Cargo tanks on pure chemical tankers need to be inspected once in six (06)
months.
• Domestic fresh water tanks to be inspected once a year or at lesser intervals if
required as per flag state regulations.
The result of inspection should be updated in PMS with risk assessment, enclosed space
entry permit, tank/hold condition report (Form Number OP-12) and photographs. On
tankers only intrinsically safe cameras to be used. For guidance refer Annex 1 – Guidance
for hull structure inspections.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 38 of 151
Any defect noted shall be recorded in the ShipPalm and informed to the company with
the repair plan.
MAINTENANCE OF COMMUNICATION AND NAVIGATION EQUIPMENT
The Master shall liaise with the vessel’s superintendent for routine maintenance and
service of navigation and communication equipment. The superintendent shall arrange
attendance by authorised service personnel as necessary.
For vessels fitted with VSAT, the alternate means of communication such as FBB is to be
tested once in a month or as per maker’s recommendation.
Any breakdown of communication and navigational equipment shall be immediately
reported to the superintendent in charge of the vessel.
The report may be over telephone but shall be followed up in an email with following
information.
• Nature of Equipment
• Make / Model / Serial No. of Equipment
• Nature of Trouble
• Error / Alarm code displayed
• Trouble shooting instructions in the maker’s manual
• Any history of similar equipment breakdown (from past service records)
• Details of trouble shooting attempted by ship staff.
• Information on spares available on board.
• Details of agents at next port / ETA / ETD.
Master shall prepare a risk assessment for navigating with defective equipment and
send it to office. Shore management will review the risk assessment, provide input and
guide the vessel accordingly. Port state / flag state shall be informed about the
malfunction as required.
The shore management shall seek guidance from equipment manufacturer and arrange
a service technician at the earliest.
The defect shall be reported in ShipPalm and followed up till the issue is closed.
The master shall maintain records of service reports of navigation and communication
equipment.
For details on maintenance interval for various navigation equipment, reference is made
to QHSE Circular 014/2022.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 39 of 151
The job description provided in the PMS in Shippalm gives adequate guidance on the
maintenance jobs to be carried out on various navigation equipment.
SURVEYS, CERTIFICATION, MONITORING AND RECORD KEEPING
A survey is an inspection of items of a ship relating to a certificate to ensure that they
are in a satisfactory condition and fit for the service for which the ship is intended.
Therefore, surveys are an important element of control to ensure that a ship complies
with the relevant provisions.
All ships must be surveyed and verified by officers of the Flag State Administrations or
their recognized organizations (ROs)/ recognized security organizations (RSOs)/
nominated surveyors so that relevant certificates can be issued to establish that the
ships are designed, constructed, maintained, and managed in compliance with the
requirements of IMO Conventions, Codes, and other instruments
Class Survey status should be updated to vessels once in 15 days. The vessel’s Technical
Superintendent (TSI) should download the latest survey status as of date from the
respective web portals of the Classification Societies as applicable to the vessel. The TSI
should review this survey status and send it to the vessel’s Master with his comments
on the upcoming surveys. The Master should take note of this updated information and
include the same in the survey planning activity.
It is a legal requirement under ISM Code Section 11, to keep all documents and records
relevant to the vessel’s certification updated. The certificates and documents issued to
the vessel by the Flag are subject to inspection by port state control officers (PSCOs). All
certificates / documents required for safe and legal trading of the ship are maintained
in the safe custody of the Master of the respective ship.
Company effectively uses the support of “SHIPPALM” software to maintain, control and
monitor shipboard activities, surveys and certification.
In Shippalm user can monitor all the certificates, surveys deficiencies, conditions of class,
dispensation including their expiry date and window period. The ShipPalm software
provides reminders of due date with a predefined notice period. Responsibility for
maintaining and updating vessels certification is shared between the Master and the
relevant office staff.
Changes made in information by the users are reviewed by the respective
Superintendent and upon approval the data is updated in the system.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 40 of 151
Survey
Depends on
Depends on Depends on Laws
Contracts &
Classification Rules and Regulations
Agreements
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 41 of 151
b. Master must ensure that the steps are implemented on the vessel and submit status
reports to the Marine Superintendent / Technical Superintendent. A change in load
line marking can be done only when the vessel is in ballast condition and free of
cargo.
c. Technical Superintendent shall arrange for class endorsement of load line change &
verify if class surveyor attendance is required. He shall arrange for the same at arrival
port, if applicable. For vessels having an IOPP Supplement Form B, the Class surveyor
shall be requested to reissue the Form B indicating the deadweight corresponding
to the assigned load line.
d. Master shall record the Change of load line into Logbooks as prescribed by the flag
state.
e. Master shall intimate all the stake holders about the change of load line.
f. The Technical Superintendent shall maintain all records regarding change of load line
of the vessel.
GENERAL GUIDELINES:
Following are the general guidelines for the Master regarding operational procedure of
Multiple Load Line:
a) The Load Line marks corresponding to the deepest draft of the vessel, as well as
other assigned drafts, are permanently marked on the side shell.
b) Stability Information for the relevant statutory loading conditions corresponding to
each load line mark, is approved by the Administration and is available onboard.
c) Only one load line certificate is in use at any given point. Other load line certificate(s)
is/are kept in a sealed envelope under safe custody of the master.
d) Only one set of marks associated with load line certificate in use, (i.e. is actually
“painted in” and visible at any given time). Other Load line marks are obliterated or
painted over with the same colour as its background.
e) The new summer freeboard on each side shall be physically measured each time and
recorded in the “Multiple Load Line Assigned Booklet” (if supplied by the
Administration) along with other relevant details. This booklet is verified/endorsed
during annual/renewal load line surveys.
f) An official entry is made in the ship’s logbook about the change in load line marking.
g) During annual/renewal load line surveys, regardless of the deadweight value
applicable at the time, the vessel is surveyed for compliance with the most severe
statutory requirements corresponding to the greatest deadweight the vessel can
carry. The Master is to ensure that all the full-term multiple load line certificates are
endorsed/renewed on completion of the surveys, as applicable.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 42 of 151
h) The GT and NT of the vessel remains unaltered and shall be those corresponding to
the deepest draft.
i) The statutory certificates issued under SOLAS MARPOL show only the greatest
deadweight of the ship. Lower Deadweight may not be indicated on the statutory
certificates.
IMO has adopted the harmonized system of survey and certification which most of the
Administrations have implemented. Ships of a flag state which has not adopted the
harmonized system should follow the flag requirements.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 43 of 151
Intermediate
Survey
NO Issuing
Annual Survey Certificates
Is
Intermediate
Initial Survey / Issuing
Annual Survey Survey carried Annual Survey Renewal Survey
New Build Certificates out on 2nd
Annual
Intermediate
survey
YES
Annual Survey
- 3 month + 3 month - 3 month + 3 month - 3 month + 3 month - 3 month + 3 month - 3 month Annual /
Intermediate Survey
1st Year 2nd Year 3rd Year 4th Year 5th Year
Surveys of ships
in operation
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 44 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 45 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 46 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 47 of 151
The enhanced survey programme (ESP) expands and emphasizes on the existing survey
requirements for the special, intermediate surveys and annual surveys. The attention is
focused upon the hull structure within the cargo length for oil tankers and bulk carriers.
In the ESP, it is a requirement for new ships to apply a protective coating to the structure
in water ballast tanks which form part of the hull boundary, side shell structure and
transverse watertight bulkheads in holds. The condition of the coating will be assessed
and recorded at the special survey. The scope of future annual and intermediate surveys
will depend on this assessment. The ESP also requires identification of what are termed
“suspect areas”. These are structural areas showing substantial corrosion, considered
by the surveyor to be prone to rapid wastage. The suspect areas, if not suitably dealt
with during the special survey, will be examined during every subsequent survey.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 48 of 151
• Reporting the status of ship’s certificates and surveys at the end of each month to
the office.
The Survey Co-ordinator, in liaison with the technical superintendent, is responsible for
planning, tracking and managing the survey activity. He is responsible for identifying the
best location suited for carrying out the surveys in the most cost-effective manner
without affecting the vessel schedule.
The Technical Superintendent is responsible for:
• obtaining the Class listing of survey status and sending them to vessel
• arranging / coordinating surveys and inspections in a timely manner
The Technical Executive is responsible for updating the due dates of ship’s certificates
and surveys.
The process flow chart given below is to be followed for the surveys –
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 49 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 50 of 151
Master must update details of all services and supplies which are to be arranged for
satisfactory completion of surveys. Once the surveys/ certificates are in the window
period or coming due, the technical superintendent must closely follow with vessel
schedule to arrange the surveys.
The survey and associated services are to be arranged without affecting the operations
of the ship. The following factors are to be considered for selecting convenient port.
• Availability of surveyor and service facility
• Distance between the port and service facilities
• Terminal / port restriction
• Anchorage distance and cost of launch facilities
• Block fee agreement terms and condition
• Cargo operation
• Water visibility for in-water surveys
Special care must be taken to ensure that any Condition of Class (COC) is closed well
within the due date.
Surveys/COC becoming overdue can lead to suspension or automatic cancelling of the
classification of the vessel, with serious commercial / legal / insurance implications.
Surveys planned in conjunction with the major overhauls must consider sufficient time
required for arranging the spares. The requisitions for the same must be raised
accordingly.
The office shall keep a track of any new regulation which is due for compliance and shall
make necessary arrangements to comply with it well before the due date.
For oil tankers and bulk carriers, the ESP planning documents are to be submitted well
in advance for review and approval by the RO. The technical superintendent in
consultation with the ship staff shall prepare and submit the ESP documents for
approval.
Preparation: -
As far as possible, surveys are to be completed in the same port, preferably with not
more than two survey visits. Surveys are to be carried out in the normal working hours
without affecting the crew rest hours. Master / Chief Engineer should confirm
functionality of the equipment, follow the survey checklist and refer to guidance
provided in ShipPalm. Deficiencies if any, must be reported well in advance to office.
Preparation such as staging, thickness measurements, mandatory servicing, open-up
examination and calibration etc. are to be arranged during or prior to the survey.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 51 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 52 of 151
11. Update contact details of all parties involved in the surveys to vessel, surveyor,
service companies and agents
Conducting Surveys.
Prior to the commencement of survey and measurement, it is preferable to carry out an
opening meeting to ensure the safe and efficient conduct of the survey and
measurement. The participants in the meeting shall include the surveyor, the owner’s
representative, the thickness measurement company’s representative, and ship staff.
Following essentials details are to be discussed in the meeting.
1. Vessel safety instructions
2. Vessel schedule and time for completing surveys.
3. Cargo operation and restriction to test equipment
4. Terminal / port restrictions
5. Clarity on the scope and method of survey
6. Additional requirements if any
Master has all the rights to stop the survey progress which may compromise the safe
operation of the vessel and the protection of the environment. Master shall ensure that
Surveyor is always accompanied by a senior officer.
Master / Chief Engineer shall ensure that all functional tests are demonstrated without
any delays and are offered for survey in a sequential way as planned.
All authorized documents including log books, ORB, garbage record books are made
available and are controlled in accordance with company procedure. CSM items
examined in the past are to be offered for crediting.
Master shall immediately communicate (preferably over phone) with office if any
deviations (COCs or recommendations) are reported during the course of the survey.
Office along with Master shall establish communication with attending surveyor (prior
disembarking) on the nature and scope of rectification job to be carried out. Office as
far as possible shall ensure that deficiencies are cleared prior vessel departure and if not
possible shall discuss with attending surveyor on the additional time required to clear
the deficiency
Recording Keeping and Uploading in Shippalm.
It is the Master’s responsibility to ensure that all certificates are endorsed and data of
the newly issued certificates are in order. All original certificates and service reports are
to be filled in the respective folder and kept under safe custody.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 53 of 151
Master shall ensure that endorsed / new certificates are uploaded in Shippalm as soon
as possible, within 48 hours after completion of survey. Superintendent should ascertain
the credibility of details uploaded in Shippalm and approve.
ESP File:
As per IMO resolution A.744(18), an ESP file must be maintained on board and should
contain following:
1. ESP – Survey programme.
2. ESP – Questionnaire
3. Condition Evaluation report
4. Thickness measurement
5. Class survey report of structural surveys
Only items 1 and 2 are generated prior commencement of special survey whereas 3 and
4 are generated during and after completion of special survey. Item 5 is generated when
there is an occasional survey related to structural condition of Hull.
Vessels which are less than 5 years old must have items 1 and 2 in ESP file. Vessels above
5 years old must have items 1 to 4 in ESP file and item 5 if there is an occasional survey
related to Hull structure.
In addition to above the following supporting documents need to be kept in ESP file:
1. Main structural plans of Holds, Cargo tanks and Ballast tanks.
2. Previous Hull repairs history if any
3. Cargo and Ballast history
4. Inspections by ship staff with reference to:
• Structural deterioration if any
• Leakages in bulk heads and piping
• Condition of coating or corrosion preventive system.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 54 of 151
Any recommendations
No
/COC to vessel
Arrange to rectify the issues either Send survey report to office with
by guidance to master (or) Master
proposed Corrective Action Plan
providing external assistance
Verify effectiveness of
implementation during next visit
END
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 55 of 151
Applying for the condition of class: Application for the condition of class shall be
supplemented by the following documents:
a. Company’s level 2 risk assessment.
b. A plan containing mitigating measure (including alternative arrangements).
c. Detailed plan of repairs along with supportive documents (if applicable)
Conditions of Class shall be received in writing with a time limit for completion. Details
are to be clearly stated on the
1. Certificate of Class or
2. An attachment to the Certificate of Class and/or
3. Class survey status or
4. Class Survey report.
On receiving the survey report, the vessel shall immediately inform the respective
technical superintendent along with the report and supporting documentation.
The following points are to be implemented –
1. Where required, temporary management of change (MOC) to be initiated.
2. Seek dispensation from flag where required. SMT to initiate the request for
dispensation.
3. Vessel to send corrective action report to office within one week for observation
or Condition of Class set out by the Class Surveyor.
4. Technical Superintendent (TSI) must verify corrective action plan from vessel.
5. TSI shall follow up with vessel for implementation of corrective action. (Raise work
order).
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 56 of 151
3.13.6 DISPENSATIONS
Dispensations are to be applied for when a vessel does not comply with the statutory
requirements of the IMO Convention or specific requirement of the flag applicable to
it.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 57 of 151
The deficiency is to be recorded in Shippalm under deviations along with the following
details -
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 58 of 151
1. The Lifeboat and Liferaft operating instructions should be with the IMO
recommended symbols and displayed near the Lifeboat and Liferaft respectively and
located under / near an emergency light in order that they are readable at night.
They shall be maintained in a good condition.
2. The boat suspension bolts and nuts are to be examined for corrosion.
3. The release gear must be maintained in accordance with the manufacturer’s
instructions. It is to be subject to a thorough examination annually as per Flag
requirements and overhauled accordingly. The operating instructions must be
clearly posted next to the mechanism.
4. If rudder is provided with a remote steering mechanism, the linkage must be kept
well lubricated and checked for movement. Where remote operation is through the
hydraulic actuator, the system should be checked for oil level every week.
5. The winch brake assembly is to be examined every 6 months or as suggested in the
maker’s manual.
6. Plastic coating for the wire of the lifeboat gripes is not allowed as the corrosion of
the gripes goes unnoticed.
7. The Davit limit switches are to be checked for operation every time the boat is
lowered and hoisted.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 59 of 151
The lifeboat engine starting procedure is to be posted clearly next to the engine. The
requirements demand the engine should be capable of starting at an ambient
temperature of –15oC within 2 min of commencing the start procedure. Same is to
be tested for starting every week. Use of quick start sprays should normally be
avoided. If, however required, should be used very sparingly and only in extreme
cold weather. These sprays have explosive properties and are dangerous if used in
abundance and / or during warm conditions.
SOLAS requires that “the engine should be run weekly ahead and astern for a total
period of not less than 3 min provided the ambient temperature is above the
minimum temperature required for starting the engine”
8. If provided with a sea water cooling arrangement the engine should not be run
outside the water for very long. If fitted with fresh water cooling system then
antifreeze levels are to be maintained at the correct levels during cold weather
periods.
9. Short movements may be given to check propeller movement in ahead and astern
direction. Too long movements outside water must be avoided as these may damage
the shaft bush.
10. The Fuel tank must always be kept topped up with distillate fuel compliant with the
sulphur content limit of 0.1% as per Marpol Annex VI.
▪ SOLAS requires that “sufficient fuel, suitable for use throughout the temperature
range expected in the area in which the ship operates, shall be provided to run the
fully loaded lifeboat at 6 knots for a period of not less than 24hrs.”
▪ Additional fuel in portable cans must be kept handy at a suitable place (safe from
fire hazard) and carried to the boat in emergency.
11. While topping up engine fuel tank , the MDO supplied as diesel bunkers should not
be used. Only HSD capable of cold start must be used. Vessels trading in cold weather
conditions to use only ‘WINTER GRADE GAS OIL’ such as DMX grade or Arctic grade.
As an alternative vessel may carry a low temperature fuel additive which can be
added to HSD.
12. The Engine crankcase oil and gear case oil is to be renewed every year.
13. Where battery start is provided, the alternative source of starting is to be tested at
least once a month. The battery, starter / dynamo, and the charger are to be
maintained in good working order at all times. The battery log is to be maintained
for charge and density of the electrolyte.
14. Always maintain sufficient spares for the lifeboat engine, as per critical spare parts
list.
15. The maintenance of the engine should be time based rather than hourly based.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 60 of 151
16. Check the searchlight and it’s wiring thoroughly during the routine inspections. The
searchlight must be of the type originally provided with the approved lifeboat or
rescue boat. It is recommended to provide one spare bulb for the searchlight,
depending on the design.
IMPORTANT: - For the ships having liferafts which are type approved in accordance with
the IMO regulations permitting an extended service interval of 30 months for the first
ten years from manufacture, below to be followed-
1. For such liferafts, the annual onboard inspection should only be undertaken by
qualified persons who have been adequately trained and certificated by the
liferaft manufacturer.
2. The annual onboard inspection is to be conducted with accurate tools and
measuring equipment capable of -
a. evaluating the humidity around the life raft and behind its protective barrier.
b. detecting possible leakages of inflation gas from the gas cylinder.
3. The annual inspection must also provide for the replacement of expired items in
the liferafts, as applicable.
4. If the annual inspection reveals a loss of inflation gas, the liferaft should undergo
a full service immediately by the manufacturer. If excess humidity is detected, the
liferaft should be serviced and repacked by the manufacturer within three months
of the date of the annual inspection.
1. During replenishing of fuel tanks of Rescue boat engines, gasoline and 2T oil should
be mixed in the ratio 50:1. For example, if 5 Litres of gasoline is being added to the
fuel tank, same should be thoroughly premixed with 100 ml of 2T oil prior topping
up. Fuel used should have a max allowable sulphur content of 0.1% as per Marpol
Annex VI.
2. Where the ship is in urgent need of topping up the fuel tank but do not have 2T oil
in stock, same should be procured on urgent basis from company /local agent.
3. All vessels must ensure that their lube oil inventory has enough stock of 2T oil
commensurate with the spare gasoline quantity. Where such stock is not available,
vessel superintendent should be promptly informed and procurement arranged at
the earliest available opportunity.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 61 of 151
Important: - If vessel is equipped with rescue boat having outboard motor type engine,
special attention to be given for inspecting cooling water pump Impeller. The local
operating procedure as per maker is to be displayed in a laminated wallet. The engine
to be tried out, as required in a half-cut drum filled with sufficient quantity of water
ensuring that engine does not run dry at any point of time during the trial.
1. Emergency fire pump must be tested for operation, every week. The priming pump
and associated piping near valve should be confirmed functioning well.
2. In addition, whenever the ship is in light draught condition, the pump is to be tested
with two fire nozzles and hoses, with one hose connected forward and one aft.
Following is to be recorded and included in the Form TE-44 and sent to the office–-
• Pump running duration (pump to be operated for at least 30 minutes)
• Pump suction and discharge pressure at the local indicators and on the bridge.
• Priming pump operation, if fitted.
• Electrical load, if driven by electric motor.
• Load on the engine, parameters and condition of exhaust, if driven by a diesel
engine.
• Vessel’s forward and aft drafts.
• Position of engine fire line isolation valve, whether open or shut and operation
of valve.
• The discharge pressure at the pump should be such that the pressure at each
of the nozzles should be at least 2.7 bar as per SOLAS Ch II-2 Reg 10.2.1.6
3. The suction and discharge valves of emergency fire pump are to be tested for
operation every week. Where the suction valve is provided with remote operating
devices or extension spindles, operation of the same to be tested every week.
4. The position of the valves isolating the section of the fire main of the machinery
spaces from the rest of the line must be clearly marked and tested for operation every
week.
5. The position of deck fire main valve is to be similarly marked and it is to be operated
every week.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 62 of 151
6. Where the emergency fire pump is driven by a diesel engine, high speed diesel capable
of readily starting the engine in its cold condition down to a temperature of 0 o C,
should only be used. The fuel tank should always be kept topped up. The regulation
requires the fuel tank of sufficient capacity to run on full load for at least 3 hrs.
Sufficient reserves of fuel should be available outside the main machinery space to
enable the pump to be run on full load for additional 15 hrs.
Fuel used should have a max sulphur content of 0.1% as per Marpol Annex VI.
7. Sufficient spares, as per the critical spares part list, are to be maintained for the main
and the priming pump at all times.
1. The access to the CO2 installation room must be kept clear always
2. The ventilation fan is to be started at least 10 minutes prior to entering the room.
3. The operating instructions to start releasing CO2 must be posted near the remote and
local stations.
4. The release station cabinet door operated alarm and its associated trips are to be
tested every three months. All ship staff must be familiar with the audible alarms. All
other audible alarms in the releasing system, including gas approach alarm are also to
be tested every three months.
5. Where low pressure bulk CO2system is provided, the rated amount of liquid carbon
dioxide is to be stored in vessel under the working pressure in the range of 18 to 22
bar. High pressure alarm (22 bar), low pressure (18 bar) and low-level alarms to be
tested every three months. The reservoir pressure / temperature and cooling system
parameters are to be recorded in the engine room log book.
6. The piping for the distribution of fire-extinguishing medium is so arranged and
discharge nozzles so positioned that a uniform distribution of medium is obtained.
The requirements demand that 85 per cent of the gas can be discharged into the space
within 2 minutes
• To ensure that the piping and the nozzles are clear to meet the above
requirements, these must be blown through by clean dry air, once in three
months and recorded.
7. The Flag administration may sometimes require the onboard annual weighing or level
check of the individual bottles of the gang release system. Same is to be confirmed
with the vessel’s Superintendent and complied with.
8. System examination and servicing by approved workshop is to be carried out as per
regulations.
9. For maintenance purposes, the PMS routines are to be referred to.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 63 of 151
10. The securing arrangement for the cylinders in a gang release system should be
periodically checked.
Special attention should be paid in re-tightening the clamps when the cylinders are
removed for weighing or replenishment. The cylinders may otherwise shift due to
vibration and result in malfunction or rupturing of pipe connections and in some cases
to the premature release of the CO2 gas. The shift may also cause misalignment
making the operation difficult or even impossible when required.
11. When work is to be carried out on any part of the CO2 system, including remote
controls, all precautions should be taken to prevent accidental release of gas. Risk
assessment shall be made prior to the work.
12. When nature of the work requires the system be made inoperative to permit safe
working, consideration to the various fire risks in the spaces normally protected by
the CO2 system should be given. In addition, during the period while the system is not
available, work which would increase the fire hazard within the protected spaces
should not be permitted. It should be ensured that the system is restored to its
operating condition on the completion of the work
13. It will be prudent to mention that unless there is a clear written agreement which
delegates the responsibility to the ship repairer or the company undertaking the work,
the responsibility of the accidental release remains with the ship. When the
responsibility has been delegated in writing to the repairer, the Master should ensure
that the system is restored to its operating condition on completion of the work.
14. To prevent unauthorized use, the space containing the CO2 cylinders or the CO2 bulk
storage unit should normally be kept locked always, with one of the keys being readily
available in a glass fronted case near the entrance to the space.
Emergency generators are required to be put into service quickly in the event of an
emergency and to be operated under a wide variety of climatic conditions. It is,
therefore, essential that they are always maintained in good working order.
1. Starting arrangement using battery, hydraulic or air, should all be maintained well
and tested for operation every week.
When testing weekly on battery starting arrangement – the engine should be started
on EACH set of batteries once. i.e. start on battery No.1 – Stop engine, changeover to
battery No.2 and start. This procedure will enable assess the condition of each set of
batteries.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 64 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 65 of 151
started automatically upon failure of the main source of electrical power supply
and shall be automatically connected to the emergency switchboard and the
essential services required by the Administration to maintain an adequate
standard of safety
▪ Automatically started and supply the required load as quickly as is safe and
practicable subject to a maximum of 45 seconds.
The engine should be capable of being started in its cold condition at a
temperature of 0°C. If this is impractical or if temperatures below 0°Care likely to
be encountered, provisions must be made for heating the engine so that it will
start readily.
It should, as a general guideline on cargo ships be capable of supplying the essential
supplies as per SOLAS for 18 hrs.
9. It should be ensured that antifreeze is used in the Jacket water coolant when
temperatures below sub-zero are expected to be encountered. Room heaters, if
provided, should be used.
10. Automatic starting under black out, within specified time and connecting to all
essential working loads is tested during annual survey. The test should be logged in
the ER log book.
11. After auto start of the engine, ensure that ventilators are open.
12. All maintenance carried out on the emergency generator is to be time based rather
than hourly based. All engine maintenance routines must be regularly carried out as
per the maker’s instructions. Crankcase L.O should be renewed once in six months
as a regular practice even though the running hours may be less, due to the possible
deterioration in the quality of the oil because of biological degradation.
The dedicated fuel tank for the emergency generator engine must be inspected,
cleaned and refilled with fresh fuel to the required capacity once in 30 (thirty) months.
Fuel used should have a max sulphur content of 0.1% as per Marpol Annex VI.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 66 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 67 of 151
8. Correct cylinder L.O rate should always be maintained. On Engines not fitted with
“Load Dependent Lubrication” system, care should be taken to ensure right
lubrication during start up and increased load condition. The lubricator low level
alarms and non-flow alarms must be tested regularly. The Lubricator drive coupling
bolts must be checked for tightness every six months. The timings must be recorded
and compared with the specifications.
9. Pay attention to the following when the main engine is running.
• Running condition of the fuel pump
• Amount of drainage from the drain valve on the air side of the air cooler
• Physical properties of the system oil
• Quantity, foaming, turbidity of lubricating oil for the turbo charger
• Oiling of joint at the fuel pump and cylinder lubricator drive gear systems
• Cylinder head cleaning and early detection of various kinds of leakage
• Inspection of seal ring when the amount of leakage from the stuffing box exceeds
the standard specified by the maker.
10. Fuel oil pressure must be maintained as recommended by the engine maker, normally
between 7-8 bar. The increased fuel pressure is observed to have negative effect on
functioning of shock absorbers and VIT racks of pumps fitted on B&W engines. When
required, the pressure should be adjusted by the pressure regulating valve at the
engine outlet and not by adjusting the bypass safety valve of the booster pump.
The shock absorbers of these pumps are designed to work optimally at 7 – 8 bar inlet
pressure. Due to improper functioning at high fuel inlet pressure, the high peak
pressure which is created when the cut-off edge of the plunger passes the cut-off
holes, will not be absorbed. This might thus have a damaging effect on pipes and other
components in the low-pressure system.
At increased fuel oil inlet pressure, the force required by the air positioner to move
the VIT rack is higher than at low fuel pressure.
11. The back-up rings for jacks in the hydraulic ring on cylinder covers (where fitted), must
be changed at each overhaul. Specially, those closer to the exhaust manifold are
observed to deteriorate fast and consequently cause difficulty in loosening of the
nuts.
12. Heavy sludge sometimes may accumulate on the top of fuel pump barrels in B&W
engines. On pumps fitted with VIT, this may prevent the movement of the barrel
causing excessive increase of Peak pressures. The accumulated sludge must be
periodically cleaned while running using compressed air / light diesel, and by
removing the top cover at recommended intervals during stoppages.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 68 of 151
13. Care must be taken while handling the cross head and crank pin bearing caps. The
bearing shells have sometimes fallen off due to breakage of the locking screws. The
precautions are most important on the larger engines. Additional support must
therefore be provided for securing the bearing shells during inspections by using the
tool, if provided by some makers.
14. Where multiple fuel injectors are fitted on a unit, it must be ensured that the
difference between their opening pressure is not more than specified by the maker.
The fuel injectors must be maintained in a good operating condition to avoid improper
combustion, loss of thermal efficiency and excessive burn out on piston crowns. The
nozzles of right specification must be used always. The dribbling of the injectors can
cause deep burn spots on the piston crown.
The maker’s instructions for the interval of reconditioning of nozzles, spindle / spindle
guides must be adhered to. When reconditioned ashore, the maintenance reports and
records must be maintained. All fuel valves on board to be numbered so that the
maintenance interval can be monitored.
While fitting the fuel injectors, care should be taken to ensure that maker’s
instructions are followed for proper tightening. Excessive tightening may cause
deformation of components in the fuel valve.
15. Reversing link for fuel pump roller guide on B&W MC engines must be inspected for
cracks by pulling out the roller guide. After first inspection, this can be done along
with the fuel pump actuator overhaul.
16. Fuel pump puncture valves (B&W MC Engines) are known to sometimes get stuck
during starting. The valves are therefore to be overhauled at maker’s recommended
interval or less and monitored closely for correct operation. A lifting tool should be
fabricated onboard which can be used for checking in the event of problems.
17. Condition report of the exhaust valves should be maintained. All exhaust valves,
including the spare ones must be marked with identifying number. Record for the
complete assembly,
Seat, spindle, housing, and seal rings must be maintained. Wear status / limits against
each of these should be recorded. Sample forms drawn by the maker in their service
notes or manuals may be used for this purpose.
Care must be taken to ensure that the exhaust valves are overhauled as per the
maker’s instructions and all bolts and nuts tightened to the specified torque. Over
tightening of the actuator bolts have sometimes caused the air piston cylinder of B&W
exhaust valves to deform causing the failure of air piston sealing leading the valve to
remain open.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 69 of 151
Where Nimonic valves are used, maker’s special instruction for grinding using the
special grinding wheel provided must be adhered to.
18. Inspection must be carried out through the scavenge ports every month to ascertain
the piston and the liner condition. The rings must be checked for lubrication, deposits,
springing action and micro seizures. Assessment can be made of the piston ring radial
wear by checking the butt clearance, where visible and accessible. Where POP rings
are fitted, clearance to be measured with maker’s supplied tool. The piston skirt bolts
and locking must be checked. The piston top must be examined for deposits and
burning. The lubricator should be operated manually, and each quill checked for
operation. The liner surface, as much as visible must be examined for lubrication,
scoring marks and micro seizures. The piston cooling must be kept on and piston
checked for leakage. The under-piston spaces must be cleaned thoroughly, and the
drains cleared off blockage. After the inspection, all data should be entered in form
TE-08 and sent to office along with month end mail.
19. The shaft earthing device must be maintained in good order. Improper maintenance
may cause arcing between the shaft and bearing leading to bearing damage. The band
surface should be regularly polished and the brush tension maintained to ensure good
contact. A spare set of brushes must be maintained on board. The reading should be
recorded daily and checked to be in compliance with the specified limits depending
upon the operating condition i.e. draught, S.W temperature, and S.W density.
Maker’s Log to be sent and feedback requested.
20. The top stays and braces must be checked regularly for cracks at the fastening points.
21. The dynamic forces which are imposed by the engine are taken by the engine seating.
The bedplate bolts (holding down bolts) to the seating should be checked for tightness
to ensure that no dynamic movement is possible between the bedplate and the
seating. All bedplate chocks, side and end-chocks are also to be examined as per
maker’s maintenance intervals.
22. Main engine fitted with BWMS (Bearing wear Monitoring Sensor) has to follow the
Makers instruction.
23. In case of any deviation on the wear limit or slowdown of engine, it has to be dealt
with extra caution while trouble shooting. This is to be reported to the respective
technical superintendent.
24. Vessel may carry out scrape down oil analysis (SDA) every 1000 hours of ME running.
Same to be recorded in TE-55 and TE-55 A . Vessels without Scrap down analysis kit
should contact their respective Technical Superintendent for supply. Those vessels
which do not have SDA test kit should land sample for lab analysis at least once every
3 months.
Additionally, vessel should carry out SDA test after any of the following operations: -
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 70 of 151
i. Any change of bunker: - Vessel to conduct SDA test of all ME units after 24 hours
of bunker change.
ii. Post ME unit decarbonisation: - Vessel to conduct SDA test of that individual ME
unit post decarbonisation.
The scrape down analysis test is an essential tool for improving engine reliability, reducing
associated maintenance and repair costs.
On-board kit or shore lab support can analyse scrape down oil and provide a complete
picture of engine and lubricant performance.
It can contribute towards extending piston overhaul intervals and help optimise feed
rates. In some cases, it also provides the data needed to tackle cold corrosion. Vessel may
require switching between fuels and lubricants in complying IMO 2020 Sulphur cap.
The scrape down analysis programme comprises tests to analyse two key parameters,
Iron Content and Base Number (BN) in the oil. In some case water content also can be
ascertained in sample drain oil.
The tests identify: -
1. The concentration of ferrous iron in the scrape down oil, which provides an indication
of an engine’s liner wear rate due to abrasion.
2. The BN level indicates the level of engine liner protection from the effects of the acidic
products of combustion. It also provides the indication if one or more liners are in danger
of suffering from corrosive wear.
3. Some test kits can also analyse presence of iron salts in the sample which indicate the
engine’s liner wear rate due to corrosion.
4. This test also provides early indication of the dangers of over-lubrication whereby
deposit build up can cause significant engine wear.
5. The test can identify cat fines, which can cause abrasive wear if not treated. With scrape
down analysis, fuel will immediately be identified by a spike in metal content (and analysis
of laboratory results in some case). This can be used to take preventive steps before the
fuel is used.
Through regular testing, results can be plotted and trends established to gain a full
understanding of cylinder oil and engine condition. The results can help vessel to identify
the most appropriate BN cylinder oil and feed rate to protect engines from cold corrosion.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 71 of 151
Some of the values listed below maybe subject to change and careful reference should
be made to manufacturer’s service manuals and latest service bulletins.
When the engine must be operated for a prolonged time period (longer than two hours),
careful observation of the following measures is to be taken: -
1. The fuel injectors must be in good condition, i.e. atomization should be good and
their spray holes must not be eroded.
2. Careful preparation of the heavy fuel is essential.
3. The temperature of the fuel is to be set to the upper limit i.e. a viscosity of 10-12
mm2/s (cst) is to be maintained at the fuel pumps of the engine. In addition, the
tracer steam to the fuel injector pipes is to be kept open to maintain adequate fuel
temperature at the fuel injectors.
4. The jacket temperatures are to be kept on the higher side, so that the combustion
air in the cylinder does not cool down unnecessarily.
5. To keep the combustion air and in turn also the exhaust temperature at a higher level
during slow running, the seawater inlet temperature to the air coolers must also be
kept as high as possible maintaining the normal flow rate. (The seawater outlet
temperature should, however, not exceed 45o C).
6. The exhaust gas temperatures after the cylinders should not drop below 200 oC.
Should it for some reason not be possible to maintain an exhaust temperature of
200o C after the cylinders due to operational reasons, then the engine must be run
up to a higher power level at least twice within 24 hours until an exhaust temperature
of 275o C is reached.
7. The run-ups should be executed in small steps, during which the Turbocharger
tachometers must be kept under close observation. Once an exhaust temperature of
275o C after the cylinders has been reached, the respective engine speed should be
maintained for at least 20 minutes.
8. Soot blowing should be carried out in frequent intervals
1. Indicator diagrams are to be recorded at least once during each loaded and ballast
passages in the month.
2. These must preferably be recorded on departure during normal weather conditions.
3. The wind, current and the swell condition is to be recorded for the comparison.
4. The repairs / overhauls carried out since last set of cards recorded should also be
mentioned to analyse improvements through overhauls.
5. In addition, a set of cards must be recorded prior to and after dry-docking to estimate
improvements through underwater hull maintenance
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 72 of 151
6. The differential between the Pmax between units should be within the makers
recommended limits.
7. If the average Pmax for the units is higher / lower than specified or as compared to
test records for the similar rpm / load condition, the cause is to be analysed and
attended on priority. The ‘shop trial’ performance curve should be used as a
reference for analysis.
8. The difference between Pmax and Pcomp should not be more than that specified by
the maker. Too high a difference would cause the piston rings to collapse.
9. All other engine parameters are to be recorded and compared with the test records
for similar load conditions.
10. Main Engine performance should be sent to office every month using form TE-07 on
the following occasions:
▪ Once every month for normal operating parameters
▪ Immediately upon change of bunker fuel
▪ Immediately upon major overhaul of components
11. Data from TE-07 should be reviewed by TSI and uploaded to the designated engine
performance software to assess the engine condition.
The most dependable method of estimating the engine power developed is T/C RPM.
From Turbocharger RPMs readout, refer to Engine power/load diagram and estimate
the power developed ~ say BHP say at engine rpm N
As per propeller curve, calculate N1, i.e.
N1 = (BHP / BHPMCR) 1/3 X NMCR
Apply calculated value of N1 and derive M, i.e.
M = {(N – N1) / N1} x 100 (%)
If M<0 (Minus value): M/E is operating under torque rich condition.
If All OK, M>0 (Positive value).
Chief Engineer should always assess the torque running conditions of the engine and
should be familiar with the use of the above formula.
Torque Rich Condition:
Using efficiently energy in order to save fuel on board ships is a long term objective in
worldwide scale due to the environment protection and the limitation of energy natural
resources.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 73 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 74 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 75 of 151
6. The cooling water space must be regularly examined to check the efficiency of the
corrosion protection. The spaces must be checked for corrosion, corrosion fatigue,
cavitation, and scale formation.
7. Chromate based inhibitors are not to be used due to the possibility that the cooling
water may leak into drinking water circuit via the freshwater generator.
8. Only nitrite-borate based inhibitors are to be used. When using these inhibitors, no
pipe section of fresh water cooling system is to be renewed with galvanized pipe
during repairs, as this may lead to zinc sludge deposits.
9. When increase in the chloride content is observed, the salt-water leakage is to be
traced and repaired at first opportunity. The upper chloride limit specified by the
inhibitor supplier must not be exceeded, and additional inhibitor must be added as
per the maker’s recommendations.
10. A decrease in the pH value, or an increase of the sulphate content, may indicate
exhaust gas leakage into the water system. In such an event, the leakage must be
identified and rectified.
11. Vessel should enter analysis result in TE-03 or in chemical supplier’s analysis form
and send to office along with the month end report.
MARPOL Annex VI requires all diesel engines installed after 1st January 2000, with a
power output of more than130 kw to be tested and issued with an Engine International
Air Pollution Prevention (EIAPP) certificate and an approved NOx Technical File. The
approved Technical File provides details of the original engine components settings,
operating values and allowable adjustments which ensure the engine will continue to
operate within the acceptable NOx emission limits. This EIAPP certificate and approved
Technical File stays with the engine and remains valid for its life. Periodic verification
surveys are carried out by the Class to confirm the engine continues to operate within
the on-board NOx emission limits.
If any adjustment, part replacement and modifications, which influence NOx emission
characteristics, are carried out, then this should be recorded chronologically in the
engine’s record book. ID numbers of all such components used are to be recorded.
The ID numbers are stamped on these parts and record the numbers before fitting the
component to the engine.
For E.g.: the ID number of a cylinder liner usually stamped just above the scavenge ports,
on the injection nozzle of a fuel injector valve. The location of ID numbers of these
components will be mentioned in the NOx technical code.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 76 of 151
When adjustments are made on FQS (Fuel Quality Setting) and injection timing for
operational reasons, the limits mentioned in the NOx Technical file should not be
exceeded.
The following are the list of components and settings that normally influence the NOx
Emission. For ship, specific list please refer to the NOx Technical file: -
• Fuel injection timing
• Fuel injector nozzle
• Fuel pump plunger & barrel
• Fuel cam
• Exhaust cam
• Cylinder cover
• Piston crown
• Cylinder liner
• Turbocharger
• Compressor wheel / turbine rotor
• Diffuser / nozzle ring
• Aux blower
• Scavenge air cooler
• Governor
• Shim thickness to change the compression ratio and if shims used on the fuel
pump
The above guidelines are applicable for the auxiliary engines and hydraulic power pack
engines also.
1. Based on latest service experience and engine development we are revising the
guiding overhaul intervals of Main Engine. The revised guiding overhaul intervals
apply to MAN B&W MC/MC-C, ME/ME-B/C engine and Wartsila Sulzer RTA, RT
Flex type of engines. Longer overhaul intervals can be obtained with a condition-
based overhaul strategy. The means to obtain and document this are described in
engine specific service letters.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 77 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 78 of 151
• Piston under side scrape down oil analysis for residual BN, Iron (Fe) content etc.
• Evaluate Piston ring Ceramic coating thickness measurements, as relevant.
• Piston ring groove axial clearance, CPR depth etc.
• Regular performance recording and monitoring the engine parameters.
Basis the above evaluation, a deferral of 2000 hours may be granted if all criteria are
deemed satisfactory. If results are not in line with the Maker’s guidelines, the Main Engine
decarb is to be planned and as an interim, a suitable Risk Assessment to be in place with
frequent inspection established. The frequency of inspection to be agreed case by case
for each engine.
5. Once the deferral of ME decarb is agreed, vessel’s Technical Superintendent to
continue monitoring engine condition through–-
• Monthly under piston scavenge space Inspection (TE-08/08A)
• Monthly ME performance recording (TE-07)
• SDA schedule as per Para 3.15 Point 24 of this Manual and Forms
TE-55/55A/55B, as applicable.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 79 of 151
The L.O pumps must be checked for proper L.O flow after each stoppage and especially
after overhaul and oil change, as these have been known to lose suction under such
conditions. A can of L.O must be kept handy to prime the pump by pouring oil on to the
filling cup.
3.17 BOILERS
The general condition under which any particular vessel’s machinery is required to
operate will be advised in maker’s manual.
There are different boiler designs of high pressure water tube boiler types in service, but
the principles of care and attention are generally similar. Detailed requirements for
specific boilers on individual vessels are to be obtained by reference to the Maker’s
Instruction book.
Gauge glass readings and the operation and function of boiler alarms, trips, and the low
water level fuel shut-off, must be clearly understood by all personnel appointed to tend
boilers.
Personnel shall be instructed that: -
▪ If there is any doubt regarding the adequacy of water in boilers, fires must be shut
off immediately
▪ Feed water must not be added to a boiler in an overheated condition
Raising Steam
Manufacturer’s recommendations on time scale, fuel firing rate and general precautions
to be taken when raising steam must be followed as closely as possible.
A Senior Engineer Officer shall check that all valves are correctly set (open or closed as
appropriate) before a boiler is lit and be present when a boiler is first lit after a period
of shutdown or maintenance.
The Senior Engineer Officer is to ensure that the water level is satisfactory, gauge
glasses, pressure gauges, and all necessary air vent are open and drain valves are shut
prior to a boiler being lit.
These valves are to be kept open until such time as the boiler has been fully warmed
through and steam raised. The attending engineer Officer must ensure that the water
level is satisfactorily maintained whilst raising steam. These valves should only be shut
when flow through the super heater has been established by other means.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 80 of 151
It is essential that the super heater vent valve be opened prior to firing the boiler, and
be kept open until the boiler has been placed in service.
The super heater vent valve may be referred to as the “Starting Valve” in some
manufacturer’s literature.
Prior to the initial lighting of any burner, it must be ensured that the furnace is clear of
all debris and any accumulated oil residues, and that air purging of the furnace has been
carried out in accordance with the Makers recommendations.
For boilers using LNG as fuel, the local procedure for operating the boiler on different
modes and fuel is to be followed.
When operating on LNG mode, first the boiler is to be fired in fuel oil mode, then put to
dual mode. It is to be put on gas mode when LNG tanks are gassed up and HC content is
above 30-50%. If boiler is stopped, it can be changed over to gas mode directly provided
tank contents are above 30-50% HC.
When Boiler trips on gas mode, the nitrogen purge is initiated by the boiler control panel
before the boiler can be restarted.
Boiler cannot be fired on LNG mode unless controlled from the ECR operating panel. The
boiler is changed over to fuel oil mode on the boiler control panel and fired after carrying
out the Nitrogen purging.
Once firing on fuel oil is successful, operator can then changeover to dual fuel/gas mode.
The combustion control panel parameter for stabilizing of gas and oil burners to 70%
Oil-30% Gas ratio is to be checked before changing over to gas mode.
When flashing from cold, the following must be observed:
• The boiler will be flashed in timed steps to reduce thermal stress.
• If the boiler FD fan is not available, check that the boiler purge is on a ‘number of
air volume changes’ and note that longer purge time will be required.
• If initial firing is with Gas oil, as soon as the plant is warmed through sufficiently
to heat Fuel oil, changeover to Fuel oil. Extra care should be taken for purging
when flashing on gas oil, due to the greater quantity of gas generated.
Similarly, after a burner failure in service, or failure to light during initial firing, it must
be ensured that the recommended minimum purge period is completed before the
burner is re-lit.
After raising steam and prior to placing the boiler on continuous service, all gauge
glasses, alarms, trips, and the low water level fuel shut-off are to be tested in operation.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 81 of 151
A Senior Engineer Officer is to supervise the operation of putting a boiler into service.
He is to ensure that all level, pressure, and flow sensing lines are open and that the
emergency fuel shut off valve is correctly set.
When the boiler is running and delivering its required load, the Senior Engineer is to
ensure that the feed water regulator, combustion control equipment and other
automatic duties are operating correctly. He is to verify that all relevant gauges and
indicators are functioning.
Alarms and Shutdowns
All alarms and shutdowns shall be tested regularly in accordance with a schedule for
testing all machinery alarm systems. At each boiler shutdown, boiler trips shall be
tested.
Combustion
Good combustion is a prerequisite for maximum boiler efficiency.
The combustion process is to be considered as including everything from the receipt and
storage of bunkers to the emission of flue gas.
Fuel is to be heated to a maximum of 50oC for pumping. Fuel is to be retained in settling
tanks and allowed to settle for as long as possible to obtain optimum separation and
extraction of water and sludge.
Standby fuel oil service pumps are to be maintained in good operating order and set for
automatic cut in when applicable.
Suction and discharge fuel oil strainers are to be changed over and cleaned regularly.
Operating cycles for self-cleaning strainers are to be checked similarly.
Oil burning equipment designs usually require viscosity at the burner of between 15 and
65 centistokes. The requirements for each vessel’s installation are to be obtained from
the Makers Instruction Book and temperature or viscometer settings adjusted to
achieve it.
When bunkering different grades or viscosities of fuel, all reasonable measures are to
be taken to avoid mixing of grades. Where mixing of grades is unavoidable however,
due allowance is to be made for the resulting variations in viscosity during the pre-
heating of the fuel prior to burning.
Fuel Heaters
Fuel heaters must be maintained in good condition ready to meet the outlet
temperature required at full load.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 82 of 151
Burners
In principle, burners are to be treated with the same degree of care as is usually
accorded to diesel engine fuel valves.
The dismantling, inspection and re-assembly of burner parts is always to be done by, or
under, the supervision of an Engineer Officer.
Incorrect cleaning of important parts, such as cleaning sprayer holes with hard wire, may
cause considerable damage and must be avoided.
Fireside fouling, tube impingement damage and severe local over heating can be caused
by a distorted fuel spray pattern often the result of damaged edges of sprayer plate
holes.
Sprayer plates with damaged or oversize holes are to be discarded.
Close attention to the mating faces of sprayer plates can reduce burner tip leakage and
the deterioration of quarls which results from fuel dripping onto them.
To obtain a balanced operation with efficient combustion in a multi burner furnace the
fuel throughput of all burners must be the same. To ensure that this is so, the holes in
sprayer plates are to be checked regularly for size using a taper gauge or shank of a
parallel twist drill.
Mixed burner tip sizes are not to be employed in a furnace.
During steady steaming conditions burners are to be kept in the boiler for as long as is
possible without changing to reduce damage sustained by unnecessary handling.
Cooling air should be open to burners not in use.
Carbonized fuel adhering to burner barrels attracts yet more fouling. Polishing the
barrels before use will diminish this tendency.
For greater efficiency at reduced load the greatest number of burners utilizing small tips
are to be kept in operation, with the fuel pressure maintained in the upper range of the
permitted limits.
Air/fuel ratio and air temperatures have a marked influence on combustion efficiency
and are to be regularly checked against design figures.
If good combustion is to be achieved the only supply of air into the furnace should occur
through the burner register. To assist in maintaining good combustion care is to be taken
to ensure that casing doors fit tightly and that joints and gaskets are not damaged.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 83 of 151
Uptake Temperature
To avoid ‘cold corrosion’ in uptakes resulting from the condensation of sulphuric acid,
final flue gas temperatures must be kept above the prevailing dew point (usually about
150oC)
Automatic Combustion Control
The various components and systems installed for the efficient and safe operation of the
combustion process are to be maintained to the highest standard.
Manufacturer’s/Buililder’s instructions and settings based on design and trials
parameters for burner management and combustion control are to be adhered to as
closely as possible.
Adjustments or alterations to settings are not to be made without the knowledge and
approval of the Chief Engineer.
Super heater vents to be opened
▪ Low water alarm / trip and safety cut outs are to be tested. The float chambers for
the same are to be blown through once a month in port to ensure that the steam
/ water side valves and the drains are not blocked at any time.
▪ All other alarms and safety cut outs are to be tested every month.
▪ Burners are to be overhauled every month.
▪ Proper combustion is to be maintained at all times to ensure that emission is clear
and within the limits and requirements laid by the port or terminal authorities.
Ch/Engr should always check the colour of the smoke and assess the air/fuel ratio.
Smoke discoloration is often and indication of a problem inside the boiler.
▪ The soot blowing must be carried out once every watch or at least 4 times a day
when the machinery spaces are kept unmanned.
Permission must be obtained from the Bridge duty officer prior carrying out soot
blowing.
On tankers, soot blowing may not be permitted whilst the vessel is at the terminal
or within port limits. Tankers fitted with Inert gas system the interlock between
soot blowing & I.G. plant is operational.
▪ All mountings should be maintained in good condition. All steam leakages must
be attended to on priority.
▪ The supporting stays and hangers must be regularly checked for cracks and
tightness.
▪ The foundation must be regularly inspected.
▪ While the boiler is in operation check that the flame is not impinging on the tubes.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 84 of 151
▪ BURNERS SHOULD NOT BE FIRED BEFORE THE FURNACE HAS BEEN PROPERLY
PURGED
▪ On tankers, the boiler furnace must be inspected during each shut down. The
furnace of other auxiliary boilers must be inspected at least once in three months.
Boilers burning waste oil must be cleaned every two months and furnace
inspected at this time.
▪ During fireside inspection, ensure that the tube bank is clean and free of any
accumulation of soot or slag. Surfaces of water drum exposed to combustion
gases, including tube and areas along the sides of the drum underneath the last
row of tubing between drum and casing must be closely examined.
▪ Check that there is no heavy accumulation of slag or crusted ash on the screen
tubes.
▪ Ordinarily the screen and water wall tubes can be cleaned by scraping or with a
wire brush.
▪ Inspect the water wall tubes and front row tubes for any indication of cracking,
blistering, or overheating.
▪ Inspect the furnace refractory for slag, flame impingement, or inadequate
provision for expansion. Failure of refractory to be repaired in accordance with
the instructions in the manufacturer’s technical manual.
▪ Carry out inspection of the waterside whenever a boiler is opened for any reason,
to be certain that the methods of analysis and treatment of the feed water and
boiler water are satisfactory.
▪ Check the appearance of the drum and tubes carefully, looking for the presence
of corrosion, scale, and other deposits. Open the water wall hand holes nearest
the ends of the water wall headers and see that water wall supply tubes and
headers are free of sludge or other foreign material which may restrict the
circulation
▪ Boiler and water wall tubes must be kept free of scale deposits, oil, and corrosion.
Water wall tubes and the boiler screen tubes which are exposed to the radiant
heat of the furnace wall can overheat with even a very thin layer of scale deposit.
Scale deposits are caused by failure to maintain correct chemical conditioning of
boiler water, failure to vent the boiler when starting to raise pressure, or improper
lay-up and care of the boiler when out of service. If pitting or localized corrosion
is present, the cause is most likely oxygen in the feed water.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 85 of 151
On tankers, there is a common practice of reducing the Air ratio to achieve 5% oxygen
content in the flue gas, while operating the boiler at low load. This results in incomplete
combustion of the fuel and causes:
▪ Excessive soot formation
▪ Risk of cargo contamination (especially on product and chemical tankers)
▪ Excessive froth formation at scrubber outlet
What is LOW LOAD operation of boiler?
Operation of Aux Boiler at any load less than 30% of full load is considered as LOW LOAD.
Why below 30% load is considered as LOW LOAD?
Please refer to the below graph showing relation between boiler load and oxygen
concentration for a typical marine boiler.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 86 of 151
At 20 % load, the ideal O2 in flue gas should be about 6.5%. If the EXCESS AIR ratio is
reduced to achieve 5% O2 (to meet Inert Gas requirement) at 20% load, the combustion
enters SMOKE ZONE.
We can also note that, at all loads below 30%, ideal O2 content is always above 5%. Only
at and above 30% load, O2 content in flue gas can be at or below 5% without entering in
to SMOKE ZONE.
Hence operating boiler below 30 % load is considered as LOW LOAD operation.
Why EXCESS air is required?
Theoretically, perfect combustion occurs when there is just enough O 2 in the supplied
air to react with all the carbon in the fuel supplied. This quantity of supplied air is often
referred to as the “Theoretical Air”.
To ensure there is enough oxygen to completely react with the fuel, extra combustion
air is usually supplied. This extra air, called “Excess Air”, is expressed as the percent air
above the amount theoretically needed for complete combustion.
Percent of Excess Air required to obtain a particular O2content can be roughly
determined using the following formula:
%𝑂2 measured
% Excess Air = x 100
(20.9 − %𝑂2 measured)
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 87 of 151
By rule it is mandatory to maintain oxygen level of flue gas below 5%, when flue gas is
used for inerting cargo tanks. This is achieved by adjusting the Air/ Fuel ratio (most of
the boilers it is pre-adjusted) to achieve the desired O2 content.
Applying the above formula, the “Excess Air” required for achieving 5% O 2comes to
about 31 % (about 131 % of theoretical air). Below graph indicates the relationship
between %O2, CO and CO2. We can note, as excess air percentage increases, there is
drop in CO and CO2
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 88 of 151
▪ Boiler Burner settings should never be tampered. Any change in the settings to be
carried out only after taking approval from office. Changes in the setting value
should be properly documented (Before and After).
▪ When using the boiler in IGS mode the minimum load on the boiler is limited
(factory set) to above 30%. This setting should not be changed.
▪ Engineers and Deck officers must understand that it is not necessary to maintain
Oxygen content below 5% when flue gas is not used for inerting cargo tanks.
▪ Pre-discharge meeting between Engineers and Officers must discuss about cargo
discharge rate, expected load on boiler, IG pressure to be maintained and plan
should be made accordingly.
Above instruction is applicable only to vessels where auxiliary boiler flue gas is used for
inerting cargo tanks.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 89 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 90 of 151
9. The water side of the economizer must be inspected annually for oxygen corrosion
or pitting.
10. The overboard discharge of Exhaust Gas Economiser wash water shall be
undertaken as per EMS Chapter 3 section 3.5.6.
1. Boilers should be opened only under the direction of a Senior Engineer. Care should
be taken to check, after emptying, that the vacuum is broken before the manhole
doors are removed. Even if an air cock has been open the practice should always be
to loosen the manhole door nuts and break the joint before the removal of the dogs
and knocking in the doors. The top manhole doors should be removed first.
Personnel should stand clear of hot vapor when the doors are opened.
2. Entry should not be made in drums, furnace, or flue space until it has cooled
sufficiently. Enclosed Space Entry Permit must also be obtained prior to entry.
3. When an entry is to be made in a boiler which is a part of two or more boilers, it
should be ensured that: -
▪ All inlets through which steam or water might enter the boiler from any other part
of the range have been disconnected, drained, and left open to the atmosphere.
or, where that is not practicable
▪ All valves or cocks, including blow down valves controlling entry of steam or water,
have been closed and securely locked, and notices posted to prevent them being
opened again until authorization is given.
1. Safety valves differ from the relief valves in that they are designed to open completely
(pop) when the set pressure is reached, and to stay open until the boiler pressure is
reduced below the set pressure. The difference between the pressure at which the
valve opens and the pressure at which it closes is called blow down.
2. The safety valves must be adjusted to lift at the pressure in accordance to the maker’s
specification and under the supervision of the Class surveyor.
Where boilers are not fitted with super heater, the safety valves are normally to be
set to open at a pressure of not more than 3% above the approved working pressure.
The correct lifting pressure for the boiler fitted on the vessel must however be verified
from the specifications.
3. Blow down ratio in accordance with the specification must always be maintained.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 91 of 151
4. The location of the easing gear, provided for floating the safety valve should be clearly
marked. The gear should be maintained well and tested for operation at least once a
month.
5. Drain pipes leading from the drain Safety valve chest to the bilge or to a tank, must be
maintained clear.
ITEM UNIT
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 92 of 151
HYDRAZINE
6 ppm - - 0.03 ~ 0.1 0.03 ~ 0.1
(N2 H4)
▪ As far as possible shore supplied water should be avoided as boiler water feed.
Sufficient quantity of distilled feed water from the ship’s Fresh water generator
should be maintained. When filling the feed water from FWG, special attention
should be paid to the salinity.
▪ Short blow down and scum blow downs to be given every day to avoid sediments
and floating scum.
▪ Prolonged blow downs to be done once a week and or when the chlorides level is
found increased.
▪ All steam and condensate losses must be checked and controlled.
▪ Condensate returns should be regularly checked for oil. Under no circumstances
must oil be allowed to reach the boiler. Any oil in the returns should be
immediately identified, coils or heat exchangers isolated and repaired before
being put into use again. All oil from the surface of the observation tank should be
removed and the tank kept attended till the clean feed is established.
▪ The boiler water is to be tested every day on board by Third Engineer, Same to be
verified weekly by Chief or Second Engineer. Proper records of dosing level and
quantity to be maintained using the suitable forms supplied by the Chemical
supplier and sent to the office every month. Owners limits will have to be followed
where available.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 93 of 151
Thermal oil heater is normally operated below the boiling point of thermal oil. The
operating pressure is the pump pressure to circulate the thermal oil through the heater
with sufficient flow to prevent overheating of thermal oil. Thermal oil is a flammable
substance which can produce flammable mist to induce fire and explosion hazards at
high temperature. Control of the working temperature of thermal oil is important for
the safe operation of thermal oil heaters. The furnace for the fired thermal oil heater is
the high-risk space in which an explosive gas may accumulate when thermal oil or fuel
oil is leaked into the furnace. Thermal oil heaters have been involved in serious accidents
on board. This equipment should be operated with great care. The personnel engaged
in operation and maintenance of these heaters should be fully conversant with correct
operating procedures and safety devices as given in the manufacturer’s manual.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 94 of 151
2. Where disposable paper cartridges are used as the discharge filter, sufficient stock for
at least one change of all engines is to be maintained on board. Under no
circumstances should these filters be washed and reused. Auxiliary Engine Fuel oil
duplex filter shall be fitted with fabricated GI cover, which can contain the spray or
leak from filter vent/drain. This modification is to be subjected to the MOC procedure.
3. All maintenance to be carried out as per the maker’s instructions and ship’s planned
maintenance schedules. Tightening torque and methods, as instructed by the maker
to be strictly adhered to.
4. With regards to the procedures for Auxiliary Engines Inspection and Maintenance, the
following to be adhered to:
I. Renewal of main bearing needs to be done at maker recommended service life
(generally 24000 - 36000 hrs) irrespective of the bearing condition. Renewal of
main bearings should be planned during vessels docking and accordingly carried
out in the presence of authorized service engineer.
II. During every crankcase inspection, lube oil flow from all bearings to be checked
without fail.
III. Checking /retightening of main bearing keep nuts to be compulsorily carried out,
at maker specified intervals.
IV. During every docking, it is recommended to have the following inspected by
Makers Representative:
• Alignment between alternator and AE;
• Crankshaft deflections are checked by Maker’s representative.
When lube oil sample analysis alerts about high metal content, same to be discussed
with technical superintendent. Depending upon the severity/trend of metal content
and laboratory recommendations, random inspection of bearings and/or re analysis
of lube oil sample must be undertaken. In case of doubt, concerned laboratory and/or
maker are to be consulted with.
5. Functioning of the rotocaps at the inlet and outlet valves must be ensured. Non-
rotating rotocaps cause increased deposits at the valve seat, constant one-sided
bending stresses and involve the risk of spindle failure. Worn-out and non-rotating
rotocaps must be exchanged or the worn-out parts replaced (spring cap, ball race ring,
balls, tangential springs)
6. Proper valve clearances must be maintained at all times. Excessive clearance causes
contact of the valve cone at the cage to become too heavy during dropping. The seat
surface then becomes too hardened and brittle, resulting in cracks.
7. The camshaft inspection must be carried out regularly at recommended intervals. The
rollers of both Exhaust valve and Fuel pump driving gear must be inspected for
rotation.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 95 of 151
The sliding of these without rotation may damage both roller and cam surface and
cause heavy wear. The roller guides must be withdrawn periodically to clean the
accumulated sludge, more particularly on engines run on IFO or Blend oil.
8. The seal leakage tell-tale holes on the engine driven F.O booster pumps or tandem
pumps must always be kept clear to and checked daily for leakage. The lip seals
separating F.O from the L.O system must be examined once a year.
9. As a standard practice, Bottom end bearing bolts and hydraulic nuts are to be
renewed at 20,000 hours of running or as prescribed by the maker. Special care must
be taken while tightening the bottom end bolts, and proper procedures as
recommended by the maker must be followed. If the bolts must be used over 20,000
hours, check carefully its threaded portion and seat surface as well as its trunk portion
to ensure the following items: -
▪ No signs of damage due to hitting or bitten marks by foreign matters.
▪ No peeled and rough surface.
▪ No deformed ridge of thread, or inclined and indented seat surface.
▪ No cracks or other defects.
10. The standby generator is to be barred and blown through every day, as a check for
normal condition.
11. Unless starting on auto standby mode or emergency, the engine is to be started
locally, after barring and blowing through the engine. Starting and stopping from
remote control also to be tested at least once a week.
12. Auto standby cut in function of the generator to be tested once in three months. Care
should be taken to put off all navigational, radio equipment and computers. Under no
circumstances should these tests be carried out when safety of the vessel and
equipment is at risk and or cargo or any other operation is affected.
13. When the engine is operated on Heavy Oil, low load operation may lead to unburned
hard and adhesive carbon residue that may hinder piston ring seal function. It must
therefore be ensured:
▪ Low load running is avoided as far as possible to reduce unburned residue on the
combustion chamber.
▪ Air intake temperature is maintained on higher side of the recommended value,
ensuring the exhaust gas temperature at each cylinder outlet is within limits.
▪ Fuel injectors are maintained in good order.
▪ Before stopping, the engine is run at least 30 minutes over specified low load limit
plus 5%.
14. Turbo Charger turbine side, wherever possible and recommended by the maker, is to
be water washed every 250 hours of operation, when the engine is run on Heavy Oil.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 96 of 151
15. The peak pressures are to be recorded at full load as far as practicable at least once
every month. In addition, these are also to be recorded before and after the piston
and/or cylinder head decarb, and Fuel pump overhauls and / or timing adjustments,
to monitor the changes.
ALL PERFORMANCE REPORTS, DEFLECTIONS MEASUREMENTS AND OVERHAUL
RECORDS MUST BE PROMPTLY UPLOADED IN SHIPPALM.
16. Vessel should record the AE performance data in form TE-12. TSI should review this
data and upload it to the designated engine performance software to assess the
engine condition.
Following for guidance to ensure safe and efficient operation of Auxiliary diesel engines:
1. Understand the running characteristics and monitor the performance.
2. Compare the running characteristics and shop/sea trial data, and when running at
75% or more of the rating is impossible, check the cause and take corrective
measures.
3. Even if there is no measuring point by the data logger, keep the running record of
important characteristics.
4. Check the performance before and after overhauling the turbo charger.
5. Pay attention to the fuel oil change at the time of S/B when the engine does not run
exclusively on heavy fuel oil or blended oil.
Over speeding and other defects frequently occur due to sticking of fuel pump and
fuel valve at the time of changing over. Always keep the fuel pump rack moving
smoothly.
6. Set the controlling conditions so that the specified blended oil mixing rate can be
maintained. Correctly provide lagging for the fuel system.
7. Check the operation of exhaust/intake valves equipped with a valve rotator.
8. Uniformly lubricate the rocker arm.
9. When running is remote-controlled, check the machine-side starting/stopping
operation regularly.
10. Pay attention to the follow-up performance of the governor.
11. Even for automatic synchronization, turn on the synchro. Indicator and check the
synchronizing point. When the load fluctuates, pay attention to the automatic load
controller.
12. Check the quantity and colour of the generator-side bearing oil, as well as the
existence of water drops on the sight glass.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 97 of 151
13. Certainly, carry out air running before running the generator except at an
emergency.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 98 of 151
10. Motor compressor coupling, if directly driven to be examined regularly. A spare set of
bolts and coupling pad or bushes to be maintained. Foundation to be checked
periodically without fail.
11. The reservoirs must be drained off water regularly.
3.20 PURIFIERS
1. F.O purifiers (conventional – Non ALCAP/HIDENS) where possible are to be run in
series as purifier clarifier combination from settling tank to service tank at all times.
Throughput should be kept minimum, (lowest possible) sufficient to maintain full level
in the service tank with the daily consumption on the engines.
2. For L.O purifiers running on main engine sump to sump, the continuous centrifuging
is to be maintained at optimum throughput. Since main engine system oil is
continuously being contaminated with combustion by-products, the purification
system should be always being kept running, including during port stays.
3. All alarms and trips are to be tested every month. Discharge pressure / no flow alarm
should be set @abt. 0.3 kg/cm2 below the steady discharge pressure.
4. To achieve efficient separation of oil from water, the interface between the two
liquids must rest just outside the disk stack, so that the oil utilizes the whole length of
all the separation channels. Small changes in temperature, flow, density, and viscosity
may cause the interface to move inwards, resulting in a blocked disc stack, or
outwards giving a broken liquid seal. Optimum operating conditions must therefore
be maintained at all times and correct size gravity disc must be selected as per the oil
specifications. Purifiers that do not use gravity discs should be operated as per
manufacturer’s instructions.
5. In order that a separation can take place, a density difference between oil and water
must exist. The change in density of oil and water when heated are not same. For IFO,
the maximum density difference between oil and water exist when oil, is at a
temperature of 98o C.
The highest level of separation efficiency exists at this temperature when cleaning
heavy fuel oils. To maintain optimum level of separation and correct interface
position, the oil temperature should not deviate by more than +/- 2o C.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 99 of 151
6. Long intervals between sludge discharges can cause compaction and hardening of the
sludge cake. It may then break up unevenly on discharge and cause the bowl to
become unbalanced. To check if the interval is appropriate, the bowl should be
inspected after a certain time of operation. The period before inspection depends on
the oil being separated and on operating conditions. If no noticeable amount of hard
sludge is found, the interval may be prolonged somewhat, but must not exceed the
maximum recommended interval. If hard sludge has accumulated, the interval must
be shortened.
7. During overhauls, assembling and disassembly is to be carried out as per the maker’s
instructions and procedure, using only appropriate tools provided by the maker.
8. When overhauling the vertical and the horizontal shafts, bearings supplied by the
makers should be used.
9. This being a high speed dynamically balanced machine, care should be taken not to
interchange rotary parts of the similar makes of purifiers fitted on board. No welding
repairs are to be carried out on any of the rotating parts.
10. Shaft revolutions are to be regularly monitored from the manual counter, where
fitted, and compared with the specified speed.
11. Where the electronic automatic control systems are provided with the backup
battery, proper records of battery renewal dates, battery life and next renewal should
be maintained. When renewing the same, maker’s instructions must be referred to
and the change should be effected within the specified time.
12. During routine rounds with purifier in operation, no inspection cover should be
opened without ascertaining the desludging cycle from the timer. Hot oily mixtures
discharge under force through the open covers may cause injury to the person
inspecting.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 100 of 151
The oil separator must be regularly checked for proper functioning. Special attention
must be paid during low loads when the speed of movement and agitation of the
evaporating refrigerant is insufficient for proper oil separation. The float operated
drain valve must be examined for operation and leakage once in six months by
dismantling the separator.
5. The refrigerant charge must be collected into the condenser / receiver before opening
the system to the atmosphere. The system should be purged of air each time it is
opened to atmosphere for repairs.
After repairs, and initial purging, the entire charge must again be collected in the
condenser and cooled sufficiently to attain the sea water temperature.
The condenser pressure may then be compared with the saturation pressure of the
refrigerant at sea water temperature to check for air in the system. The air may then
be vented out till the corresponding pressure is achieved. Care must be taken to
ensure that refrigerant is not vented into the atmosphere.
6. Expansion valve once properly set for the right working condition must not be unduly
adjusted without proper reason and understanding. Improper adjustments may lead
to the liquid carry over and cause severe damage to the compressor and its parts. The
bulb should be regularly checked for proper fastening and capillary must be examined
for breakage and/or kinks. For the refrigeration system, the expansion valve filter
must be cleaned, and orifice examined. When effecting change, right size orifice
should only be used.
7. The fridge room door rubber packing must be maintained free of ice, to maintain
proper sealing and prevent damage to the packing. Door heaters, where fitted, must
be maintained in good working order.
8. The fridge room drain sealing should be maintained to minimize cooling losses.
9. Defrosting efficiency of the timer-controlled system must be checked periodically by
examining the evaporators of the fridge room. If required same is to be defrosted
manually.
10. The evaporation efficiency of air conditioning plant is greatly affected in the event of
icing on the evaporator coils. This would happen if heat exchange were effected at
temperatures below zero. To avoid this, suction pressure must be maintained
between 4 to 4.5 bar, when using R22.
11. The air conditioning system for the accommodation space is to be kept on partial re-
circulation during cargo operations on tankers and re-circulation on bulk carriers
when the cargo is dusty.
12. The accommodation Blower flaps are to be maintained for easy operation.
13. The accommodation Blowers are to be checked for vibration and the bearing
lubrication to be maintained.
14. The evaporator is to be checked for corrosion and cleaned manually every six months.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 101 of 151
15. The maintenance of Air Cond. Compressor and Domestic Fridge Compressor should
be an integral part of the ship’s PMS.
Sufficient spare parts for air conditioning plant should be maintained on-board at all
times. This includes blower fan driving belt, thermostatic expansion valve and required
consumable gaskets.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 102 of 151
All vessels must maintain a Vibration measuring instrument in good working condition
and the measurements must be carried out on monthly basis for all running machineries.
The measurement must be carried out every time at the same location on the
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 103 of 151
machinery. The historical data must be maintained in the company form TE – 10 for
future reference and must be sent to office with the month end documents.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 104 of 151
▪ Inspection and calibration of the Auto synchronizing system, Auto load sharing
system, Auto governor control systems, as well as tests for reverse power relays,
over current relays, etc.
▪ Where fitted, the thermal seals should be replaced.
▪ ACB’s for large electric equipment such as Bow thrusters, large ballast pumps etc.,
should be overhauled.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 105 of 151
High voltage system training is part of STCW 2010 (Manila amendment) as mentioned
in section B- III/2, the convention covers the responsibility for operating and maintaining
the high voltage (above 1000 Volts) electrical power plants on board ships and process
platforms.
Note: On board, any voltage above 1000V is to be treated as high voltage.
General inspection and maintenance
1. Daily inspection
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 106 of 151
▪ Check appearance for any damage. Pay special attention for noise, bad odour, and
discoloration
2. Periodic inspection
▪ Check each bus bar fixing section, device mounting section and wiring section for
any looseness. If any looseness is found then fasten the fixed bolts again.
▪ Check appearance of each device (vacuum circuit breaker, vacuum contactor,
protective relay, current and potential transformer, fuse, module card etc.) for
noise, bad odour, discoloration. If any abnormality is found then replace it with
appropriate spare part
NB: High voltage switch gear normally does not require any maintenance, VCB’s are
designed for large no’s of operations and these are well suited for repeated operation of
almost all type of loads (approx. 30,000 operations)
Do’s:
▪ Correct PPE should be worn; Ensure the person doing the inspection checks his
PPE. PPE should fit the person properly should be comfortable to wear
▪ Wear a helmet, safety shoes and work clothes when working on the equipment,
always use proper PPE, certified for high voltage system
▪ Ensure PPE are maintained in good order and checked prior every use.
▪ No electrical conductors should be regarded as being safe unless it has been
isolated earthed, secured and proved dead
▪ Ensure all electrical safety standards while handling any electrical equipment
▪ Cut off the power supply, otherwise there is the danger of electric shock from live
bus-bars and other current carrying parts when the switchgear or other electrical
panel is opened.
▪ Precautions should be taken to ensure that isolated equipment cannot be re-
energized. Isolation procedure should be followed (refer HSM chapter 4). Put up
warning and caution notices
▪ When not attended, the barriers should be placed around live conductors
▪ Treat electrical equipment as highly flammable material at all times
▪ Voltage indicators should always be tested before and after use
▪ Use only certified test instruments when taking high voltage measurements
▪ Make sure there is no voltage in the circuit before any electrical work is done. The
panel should be ground. (Use equipment such as voltmeter, circuit tester etc.)
▪ Before working think carefully about the steps, you will take, inspect the
surroundings for any possible dangers, inform your associates of what you plan to
do. Then work quickly and efficiently
▪ Provide sufficient lighting for the work area
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 107 of 151
▪ Maintain an orderly work area. Avoid scattering tools or other articles around
▪ Learn the proper way to use a circuit tester and necessary tools
▪ Use safety locks, key exchange and lock out boxes
▪ If isolation is done by other than competent person, then it should be
demonstrated to the competent person
▪ Documentation – Electrical work permits must be used. (permits should be in
writing & not verbal /telephones/walkie talkies)
▪ Ensure proper electrical connection before charging any switch gear
▪ On completion of the work the competent person shall demonstrate to the
authorized person that all work has been completed in line with the work
instruction.
▪ On completion of the work, the permit to work shall be cancelled and all personnel
should be made aware that it is no longer safe to work on the high voltage system
or apparatus
▪ On completion of the work where necessary a sanction for test shall be issued an
all persons involved shall be made aware of any danger that may arise during the
test and made aware of any points of isolation that may be necessary
▪ On completion of tests the competent person in charge of the test shall
demonstrate to the authorized person that all the equipment used in the test has
been removed and that the sanction for test has been cancelled
▪ Once the permit to work or sanction for tests have been cancelled the authorized
person shall ensure that all isolators and earths have been removed and that it is
safe to energize the system
Don’ts
No work shall be carried on any high voltage system or apparatus until an assessment has
been carried out to highlight the dangers or consequences of that work (Risk assessment)
▪ No work shall be carried on any high voltage system or apparatus by persons not
authorized or qualified to do so
▪ No work shall be carried out on any high voltage system or apparatus until a high
voltage permit to work has been issued
▪ No high voltage permit to work shall be issued until all competent persons who
carry out work have been:
a. Made aware of the full extent of the work to be carried out
b. Made aware of the points of isolation and earthing
c. Made aware of any dangers that may be present in the immediate vicinity
of the work
▪ No work shall be carried on any high voltage system or apparatus until:
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 108 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 109 of 151
3.26 INCINERATOR
Reference is made to Ch 3 of the EEMS (Environment and Energy Management System)
Manual
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 110 of 151
1. Since main engine system oil is continuously being contaminated with combustion
by-products, the main engine crankcase oil is to be purified continuously from sump
to sump tank including during port stays. The oil temperature for this treatment is
92 oC -95 oC with the lowest possible LO throughput. The purifier must be opened
and cleaned strictly following PMS schedule.
2. The automatic lubricating oil filters back flush counter should be recorded, to
monitor any abnormality in lube oil condition. The auto back flush filter elements
are to be cleaned regularly including the flushing filter. Cleaning of auto filters
should be planned when there is sufficient time to carry out proper thorough
cleaning. While cleaning the filter screen & filter seating condition is to be specially
checked for any damage / tear which may cause lube oil to bypass the filter. There
is also risk of filter screen torn bits entering the lube oil system and damaging the
bearings.
3. The main engine sump tank must be cleaned manually at least once in 5 years,
preferably during dry dock. The sump diaphragm must also be renewed.
4. The main engine stuffing boxes are to be overhauled at every piston overhaul or
earlier if required if the oil loss increases. IT MUST BE UNDERSTOOD THAT IT IS NOT
ADVISABLE TO RENEW STUFFING BOX RINGS WITH EVERY OVERHAUL, IF THE BUTT
CLEARANCES ARE WITHIN LIMITS, AS THE RINGS HAVE ALREADY RUN IN.
5. Reuse of stuffing box drain tank oil should be avoided. If the same is required to be
reused, extensive purification through purifiers and other filters provided should be
carried out in consultation with the superintendent.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 111 of 151
6. If the sump oil is also being used for camshaft, indication of reduction in the viscosity
and flash point indicate leaky fuel pumps and seals. The Camshaft oil must be
landed for analysis and renewed as required. The camshaft oil filters to be inspected
for metal debris regularly.
The oil analysis parameters as laid down by the manufacturer are to be followed and
deficiencies with regard to water content, TBN or viscosity must be investigated and
rectified. For higher water contamination, the source must be eliminated as soon as
possible with measures such as intensified purification or settling out in a
renovating tank must be considered.
7. Aux engine sump oil, as a standard practice is to be renewed at 3000hrs, if sump oil
capacity is less than 1000 litres. However technical superintendent approval must
be obtained, prior carrying out such renewals. If auxiliary engine sump oil capacity
exceeds 1000 litres, all efforts to be made to maintain sump oil in good condition
by continuous purification. If oil analysis report warrants oil renewal, same to be
done in consultation with office. It is advisable to time sump oil renewal in such a
way that it falls due after Aux major overhaul.
8. Auxiliary engine lube oil must be purified preferably sump to sump with the engine
in stop condition. For vessels equipped with overflow method, office approval to be
obtained prior using same.
9. All filters in a hydraulic system to be checked and cleaned every three months, with
oils landed for analysis every 6 months. Cartridge filters must be renewed as per
maker’s recommendation. The hydraulic oil tank internals must be cleaned at least
yearly.
1. Always double check the hose connection to the respective bunker flange before
starting the bunkering to avoid oil contamination with wrong grade.
2. Rain water or sea water can enter the storage tanks through corroded air vents.
3. Avoid storing lubricating oil drums on the weather deck as they easily corrode and
could be a source of water ingress. Ensure the drums are placed on wooden pallets
and covered with plastic/tarpaulin to protect them from damage.
4. Extra care should be taken to avoid mixing of different grades of oil while
transferring drums into the storage tanks or replenishing into machinery. Pumps and
flexible hose used for transferring oil should be completely drained.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 112 of 151
Various Lube oil and Hydraulic oil samples from ships are to be landed ashore for shore
analysis at set intervals as per below guidelines-
Sample to be landed at 3 monthly intervals from the following equipment-location.
• Main engine crankcase oil - Inlet to engine
• All AE Sump lube oil- Inlet to individual engine
• EAL (Environmentally Acceptable Lubricant) Stern tube oil – Suitable tagged
sample point
• SDA sample for each main engine unit (only for vessel not having SDA test kit)
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 113 of 151
Inform the Office if you have not received the analysis result within 7 days of mailing
the sample. If there is an adverse report, immediate action to be initiated by the Chief
Engineer.
If test result is either “Caution” or “Attention”, action to be taken basis trend analysis
and in consultation with office. While arriving at a decision, the recommendations by
the oil company to be taken into consideration.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 114 of 151
If the analysis report states that “Oil is fit for further use”, subject oil must be tested on
board using onboard test kits after taking appropriate corrective action. If onboard test
results are normal, next shore analysis can be done at next due date. For vessels which
are not provided with on-board lube oil test kits, resampling to be done at the first
available opportunity.
If test result is either “Action” or “Urgent”, root cause to be identified and corrective
action to be put in place at the earliest in consultation with office. If necessary partial or
complete oil renewal must be carried out. Resampling must be done at first available
opportunity once the corrective action has been taken.
An up-to-date file encompassing analysis results and corrective actions taken as
applicable must be maintained on board by the Chief Engineer.
Lube Oil Quality Control:
The lube oil quality is to be maintained based upon the recommendations in the shore
analysis reports. Appropriate control measures require to be taken when the quality of
oil falls beyond the Alarm/Critical range.
Prolonged contact with lubricating oil (used / fresh) may cause dermatitis (skin rash).
Material Safety Data Sheets are to be followed.
3.30 STEERING GEAR
1. All means of communications provided between the navigation bridge and the
steering gear compartment to be maintained in good working condition and tested
regularly. (Prior every arrival and departure.)
2. Emergency steering drills, involving all ship’s personnel to be carried out once in
three months. Proper records for the same to be maintained.
3. Emergency steering gear changeover procedures are to be displayed clearly in the
steering compartment and in the wheelhouse.
The administration requires:
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 115 of 151
5. The auto isolation system, where provided to be tested once in three months.
▪ The main steering gear of every tanker, chemical tanker, or gas carrier of 10,000
GRT and upwards shall be so arranged that in the event of loss of steering
capability due to single failure in any one part of the power actuating systems,
excluding the tiller, quadrant or components serving the same purpose, or seizure
of the rudder actuators, steering capability shall be regained in not more than 45
seconds.
Where manual isolation system is provided, all isolation and by-pass valves must be
clearly marked. Change over procedure must be posted and included in the shipboard
training program.
6. Hydraulic oil to be maintained clean. Line filters are to be inspected / renewed as
required and proper records to be maintained.
7. Low level alarm of the hydraulic oil reservoir is to be tested every three months.
8. Fixed storage tank having sufficient capacity to recharge at least one power actuating
system including the reservoir to be always kept full.
Instructions “to be kept full at all times” is to be posted on the reservoir tank.
9. Safe accessibility to the compartment is to be maintained at all times
10. Proper safe working access to steering gear machinery and controls are to be
maintained at all times. This will require maintaining the handrails, gratings and or
anti-skid surfaces to ensure suitable working conditions in the event of hydraulic fluid
leakage.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 116 of 151
11. All rudder angle indicators are to be maintained in good working and in synchronism
to the local angle indicator.
12. Local rudder angle indicator markings are to be kept legible and clear at all times.
13. Ensure that Hydraulic system relief valves are set at correct value and never
tampered. As a guideline note that the relief valve setting should never exceed design
pressure, which is at least 1.25 times the maximum working pressure of the system.
14. All pressure gauges in the main and control hydraulic system are to be maintained in
good working order.
15. Auto standby function of both motors is to be tested regularly. (prior every departure
port or at least once a month)
16. Overload alarm, phase failure alarm, excess current protection (if provided) are to be
tested every three months and as per CFR. Please note that protection against excess
current, including starting current, if provided, shall be for not less than twice the full
load current of the motor or circuit so protected, and is arranged to permit the
passage of appropriate starting currents. These set values should therefore be noted
carefully and never be tampered with.
17. Chain type coupling, when fitted, for steering main pump and motor are to be
examined once in six months. Same are to be checked for grease, seal, and chain link
condition also.
18. Motor should be checked to start automatically upon the restoration of voltage after
a power failure (sequential start).
19. Remote control system power failure alarm is to be tested regularly. (every month)
20. The access door from engine room to the steering gear room and / or emergency fire
pump room should be kept shut at all times as a fire precaution.
21. The system fed from the Emergency generator (ESB) to be clearly marked and
understood well by all ship’s personnel.
22. When duplicate identical system is provided as a general practice the system should
be changed over every day.
23. Hydraulic circuit / piping should be regularly checked for leaks and attended
immediately.
Inspection of the Steering Gear for possible oil leaks should be done daily and
recorded.
24. Proper lubrication should be maintained for the rudder carrier at all times.
Accumulation of excess grease should be cleaned up at regular intervals. Rudder trunk
spaces to be inspected regularly and excess grease removed.
25. Foundation bolts should be regularly checked for tightness. Positioning chocks should
be examined.
26. Limits for the maximum rudder angle should be checked.
27. Arrangement for disposal of Steering Room bilge water to be tested every month.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 117 of 151
28. For carrying out any troubleshooting on Steering gear system, vessel’s chief engineer
to consult shore office and steering gear maker’s manual.
• The windlass and mooring winch hydraulic system should be maintained clean.
• Hydraulic line filters are to be cleaned every 3 months or more frequently if
required. These must be checked for metallic fines, which give the first indication
in wear and tear in the hydraulic pumps and motors.
• The system pressure on ‘no load’ and under ‘full load’ must be carefully recorded
and compared with the specifications every 6 months.
• The system pressure should not be adjusted to overcome the excess force that
may be encountered while heaving. Additional hydraulic pump may be used on
the same line instead, by changing over the valve arrangement. All officers must
be fully conversant in the flexibility of the hydraulic system to put a different
pump or additional pump on a line.
• The safety valve must be maintained at the correct set value.
• The lube oil cooler must be periodically cleaned in accordance with
Manufacturer’s instructions, to ensure effective cooling of the oil in the system.
• The shaft must also be checked for wobbling and shaft seal leakages underload.
3.32 STEEL HATCH COVERS AND OPERATING SYSTEM
1. A chronological record of all maintenance work carried out on hatch covers and
coamings must be maintained. It could be required as evidence to defend cargo
claims.
2. Prior each loading, the following checks to be made -
• Inspect evidence of any unauthorized use of hatch tape sealing at the joints,
inform company and remove remnants.
• Ultrasonic Tightness testing to be carried out prior each loading.
• Pass UT probe over all joints and openings including vents, booby hatches and
cement manholes.
• If UT test not possible, a hose test shall be carried out during each hold cleaning
operation or prior loading and a chalk test to be carried out if any leaks found to
identify the exact location of the leaks and repair them.
• A suitable entry of ultrasonic test or the hose and/or chalk test as carried out
must be made for records in the deck logbook.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 118 of 151
• Vessels on short runs may do the weather tightness test once every quarter on
the most suitable ballast leg.
3. The following inspections are detailed in the PMS and should be followed as per the
specified intervals –
• Hatch cover closure inspection
• Hatch coaming inspection
• Hatch cover monthly inspection
• Check of hatch cover emergency operation and hydraulic system
4. All rollers, wheels, idlers, and sheaves must be kept free and well lubricated. The
bushes must be checked for wear. Cargo dust, sand blasting grit, dried grease or rust
must not be allowed to set in. This increases the operating resistance considerably.
For the chain operated covers, the hydraulic system would have to work against a
considerably high added resistance, if a chain was to be dragged along a seized
sheave, rather than being rolled. Also, if the pontoon had to be dragged out rather
than being rolled out.
5. The track way must be examined for deformation and wear. All wheels must make
rolling contact with the track way.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 119 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 120 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 121 of 151
5. Spare packing for the type and size of expansion joints must always be maintained on
board.
6. Hydrostatic testing of Bunker pipeline is to be carried out once in 12 months to MAWP
and twice in every five-year period to 1.5 x MAWP that is specified in the vessel’s
piping diagram. Pressure testing using compressed air or inert gas is not acceptable.
Pipelines should be marked with the date of test and the test pressure. If the
hydrostatic test is done using a medium which is not the ship’s fuel oil, then the
medium used and the disposal after testing should be recorded in the engine log book.
All pressure testing records should include the date of test, the test pressure and the
method and testing medium used. Where applicable, the shore receipt for disposal
should be maintained as a record on board.
7. All Pipelines should be colour coded as per original shipyard colour scheme and
direction of flow marked as a best practice.
8. Use of Denso tape and equivalent protective tapes on deck piping is not
recommended as the corrosion of the pipe due to water seepage past the protective
tape goes unnoticed. Instead, effective anti-corrosive coatings offered by paint
makers in lieu of ordinary paints, can be considered.
3.34 CABLE CONDUIT
1. Cable conduits on deck must be regularly examined for corrosion and wastage.
Special attention must be paid to the underside of junction boxes to check for
corrosion wastage, and cracks at pipe connections.
2. The drains must be regularly checked for water.
3. The expansion joints must be maintained and checked regularly for movement,
during the flexing of the deck plating.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 122 of 151
5. Vent pipes for Double Bottom Tanks passing through the Cargo Holds must be
inspected regularly for their condition.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 123 of 151
12. Any repairs carried out by using mild steel on aluminium gangways must have a rubber
buffer in between to prevent galvanic corrosion.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 124 of 151
In this respect, Company’s policy is to ensure that subcontractors have a policy and
perform all work under a formal management system to ensure quality and safety.
The system should include:
▪ Measures to demonstrate that all contractors’ personnel are medically fit and
competent to perform their tasks safely.
▪ Procedures that all personnel are familiar with the working conditions, the rules
and standards related to the working environment and the hazards and risks
associated with the work programme.
▪ Means that hazards have been identified, assessed, and eliminated where
possible are being controlled / mitigated through formal planning methods and
procedures.
Visible commitment by the subcontractor to the mitigation or reduction of risks is critical
and it can be demonstrated by:
The contractor prepares a project specific plan.
The contractor appoints a project specific leader with sufficient authority and resource.
Regardless of the controls and safeguards identified within the plan, the contractor
should confirm that the ship’s personnel are authorized to interrupt or terminate all
works if, in the sole opinion of the Master or the Owner’s representative, the
contractor’s personnel fail at any time to comply with the requirements of the agreed
safety management System. Generally, this will be as a result of ship’s personnel
identifying the existence of unsafe act or condition. For this purpose, there should be a
periodic joint inspection tour of the contractor’s leader and the ship’s safety officer to
observe and respond to any potentially unsafe act and condition.
It is imperative that contractor’s personnel to comply with Company’s policy, the rules
and regulations of ship’s flag, the state where the ship is as well as with Master’s advice
and instructions.
In this respect contractors must accept the following:
• Company’s Permit to Work Systems
• Alcohol and drugs policy
• Emergency preparedness
• Personal Protective Equipment
▪ Smoking Regulations
▪ Safety meetings
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 125 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 126 of 151
Many times, additional crew are placed on board for short duration ranging from few
weeks to few months to assist ship staff in maintenance work like cosmetic upgrade of
main deck / Engine room, Cargo, and bunker tanks cleaning etc. In such cases, the
additional / riding crew to be handled in same way as other crew on board.
The crew should undergo ship specific familiarisation at office and on board like other
permanent crew on board. Prior placing additional crew on board, work plan to be
discussed with vessel, duration to be finalised, budgetary estimate to be submitted to
owners for approval. Once approved, crewing team to be informed for arranging
additional crew at convenient port. During their stay, vessel should send weekly work
done report by additional / riding crew and same to be submitted to vessel owners.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 127 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 128 of 151
The Ships Lifting Plant must be operated by trained Personnel or a person authorized by
a responsible ship’s officer. The same applies to the operation of a ship’s ramp or a
retractable car deck. The only exception is in the event of an emergency endangering
health and safety.
Marking of Lifting Equipment
Ship staff must ensure that each lifting appliance and each item of lifting gear carried is
clearly marked with its safe working load and a means of identification. Where such
marking is not reasonably practicable, the safe working load shall otherwise be
ascertainable by other means.
Where the safe working load of a crane varies with its operating radius, it is required to
be fitted with an accurate indicator, clearly visible to the operator, showing the radius of
the load lifting attachment at any time and the safe working load corresponding to that
radius.
Lifting Equipment Register Including Certificates and Reports
Latest certificates and maintenance reports for lifting plant and associated gear should be
kept readily available on board for inspection by PSCO / third parties.
A register of lifting appliances and items of loose gear should be maintained in a form
based on the specification given below (as per ILO recommendation)
Records of reports may be kept in either paper or electronic form on the following
recommended format.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 129 of 151
PART - 1
PART – 2
Serial Condition of loose Signature and date of person Remarks relating to the
No. gear including the carrying out the inspection inspection
distinguishing
numbers/marks
3.42 CRANES
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 130 of 151
6. Condition of the wire ropes is to be examined prior arrival port, prior to handing
over controls to the shore operator. Crane running hours’ record must be
maintained. Hoisting wires must be renewed once in 500 hours of operation and
luffing wires to be renewed once in 1800 hours of crane operation. For Hose
handling crane, irrespective of number of operational hours, hoisting wire must be
renewed once in 5 years prior to load test.
7. Test certificate of all wires on board must be carefully maintained on board.
Certificate for each wire in use must be available and identified separately.
8. Test certificate of every shackle, block, and any other gear used for cargo lifting
must similarly be individually identified.
9. For cargo cranes parking or by-pass keys are to be kept with Chief Officer. He must
ensure that the key is removed prior commencement of Cargo Operations.
10. All blocks, sheaves, etc. must be maintained free. The ones that are accessible, to
be overhauled at least once a year. Remaining to be planned for quintennial (5
yearly) surveys or dry-docking.
11. The chain coupling, where fitted, of hydraulic pump / motor are to be examined for
lubrication, grease seal, and the wear and tear in the chain links, at least once in six
months. Slewing test / Rocking test to be carried out as per PMS.
12. The seating and the hull reinforcement for the cranes should be checked for cracks.
13. The SWL of the stopper used for lashing of crane hooks, should be lesser than that
of the system.
Please refer to Safety Circular No.02/19 for guidance on crane checks.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 131 of 151
10. The Provision cranes are to be load tested at least once every 5 years.
11. The SWL of the stopper used for lashing of crane hooks, should be lesser than that of
the system
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 132 of 151
The test is to be carried out to confirm the performance of the re-liquefaction plant. This
test shall be carried out during cargo cooling down, and the following to be verified:
▪ Suction gas volume of re-liquefaction gas compressor
▪ Refrigeration capacity of re-liquefaction plant
▪ Required power of re-liquefaction gas compressor
Re-liquefaction Plant Efficiency Test Procedure
1. Measure the following items and record it.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 133 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 134 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 135 of 151
B 5.0
A 0
0.506 0.495 0.483 0.471 0.459 0.447 0.435 0.423
B 0
Enthalpy kcal/kg 178.5 180.4 182.0 183.6 185.2 186.6 188.3 190.4 192.5
KJ/kg 747.3 755.3 762.0 768.7 775.4 781.3 788.4 797.2 806.0
Enthalpy kcal/kg 94.0 97.0 100.0 103.0 106.2 109.5 113.0 116.5 120.0
KJ/Kg 393.6 406.1 418.7 431.2 444.6 458.5 473.1 487.8 502.4
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 136 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 137 of 151
Inspection Items
▪ Measure the dimensions of the parts, such as the impeller, wear ring, and sleeve,
and measure wear conditions and rotor clearances, and renew the parts the
measurements of which exceed the allowable values.
▪ If there are parts with abnormal flaws, cracks, deformation, detachment, wear,
and the like, repair or replace them
Precautions
▪ Before starting pump check insulation resistance of motor winding and power
cable is higher than 1 M ohm.
▪ Do not run the pump in dry condition
▪ Do not start the cargo pump if the tank level is from the tank bottom is less than
that of what is given in the cargo pump instruction manual.
▪ Confirm the permissible number of restarts and the time gap from the instruction
manual and display the same in the CCR.
▪ Do not operate the pump with discharge pump shut-off for too long. Confirm time
as given in the manual and display prominently.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 138 of 151
▪ Please follow maker’s instruction and prepare vessel specific procedures. (Generic
guidelines: Shut sea water / cooling medium valves and drain condenser.
Pressurise gas side of condenser using cargo compressor. Check for gas leaks using
gas detector from sea water / cooling medium drain pipe.)
▪ Pressure test of the cargo condensers to be carried out as per maker instruction
or every 6 months.
Eddy current test
Cargo condenser tubes to be checked using Eddy current in every docking as per specific
owner’s standing requirements.
Eddy current generated in the tube material and discontinuities in the material due to
the eddy current is observed and analysed to assess the condition of condenser and plan
for necessary repairs.
Valves and Pipelines
Valves
Maintenance during Dry-docking
▪ Overhaul, inspect, and service the valve body.
▪ Carry out a leakage test with N2 (positive and negative pressure).
▪ For a hydraulically driven valve, carry out overhauling the actuator and renewing
the O-rings and packing.
Maintenance Other than Dry-docking Period
▪ Check the hydraulic pipeline for leakage periodically. Tighten the pipe joints
additionally as needed.
▪ Confirm the tightening force of the bonnet block tightening bolts by a torque
wrench periodically, and tighten them additionally as needed.
▪ Check the body and valve handle of the actuator for rust, and treat them as
required.
Pipes and Expansion Joints
▪ Confirm the tightening force of flange tightening bolts by a torque wrench
periodically as per applicable torque and tighten them additionally as needed.
Make a torque check for leakage very carefully when cryogenic conditions have
been recovered after a drydocking, in particular.
▪ Inspect the flange bonding cable, and replace it as needed.
▪ Take the expansion joint ashore and make a penetration test colour check to it.
Check the tie bolts for a bend and the like at the same time.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 139 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 140 of 151
The Inert Gas Generating System shall be maintained in accordance with the relevant
manufacturers’ instructions. All personnel must be aware of and observe the
precautions to be taken before maintenance of system components is commenced. IGG
plant alarms and trips to be tested as per maker instruction or at internal not exceeding
3 months.
Preparations for Work
▪ Confirm the following before the commencement of work.
▪ The equipment is not running.
▪ The power supply to the control panel is off.
▪ The power supply to the devices related to the equipment, such as the air blower,
FO pump, inert gas compressor (LPG carriers), dryer regeneration blower (LNG
carriers), and cooling fresh water pump, is off.
▪ Operate valves necessary for maintenance.
▪ Drain sea water and fresh water in the equipment as needed.
Precautions for Overhaul
For maintenance, inspect, confirm, measure, or replace the following important items in
accordance with the Instruction Book of each equipment, and enter necessary items in
the record.
Combustion Unit Burner and Accessories
▪ Cleaning the flame eye (flame monitor).
▪ Cleaning the burner nozzle tip.
▪ Cleaning the burner cone swirler.
Air Blower and Dryer Regeneration Blower
▪ Inspecting and adjusting the tension of the V-belt.
▪ Renewing the lubricating oil in the gear case.
▪ Renewing the grease or lubricating oil in the drive side bearing case.
▪ Inspecting the oil seal.
▪ Removing the suction side piping and inspecting the impeller and the inside of the
casing.
▪ Opening the gear case and inspecting the gear.
▪ Cleaning or renewing the air suction filter.
Inert Gas Compressor (Gas Carriers)
▪ Inspecting and adjusting the tension of the V-belt.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 141 of 151
On ships where the Nitrogen generator is housed in a separate room having fixed oxygen
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 142 of 151
sensors for the ambient atmosphere, such sensors should be tested and calibrated on a
quarterly basis.
Precautions for N2 Generator Overhaul
For overhauling the generator, clean each part, and inspect and confirm the following
important items in accordance with the Instruction Books.
Membrane Separator Unit
Inspect and clean the line filter and replace the element if required.
Air Compressor
▪ Check filters and replace elements for them if required.
▪ Check the differential pressure or internal pressure of the separator and replace
the filter element if required. And check the property of lubricating oil in use and
renew the oil if required.
▪ Check the LO level, charge lubricating oil if required, or renew it as needed.
▪ Check the tension of the V-belt and renew it if needed.
▪ Overhaul the air compressor in accordance with to the Instruction Books.
Oxygen Analyser
Inspect the analyser in accordance with the Instruction Books and renew the fuse or
sensor if required.
Inspection and Confirmation Items after Assembling
Upon reassembling the unit after the necessary inspection and parts replacement, make
a test run to confirm that such process values as pressures and temperatures are at
desired level and that nitrogen gas with a proper oxygen concentration is being supplied.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 143 of 151
▪ Inspect corrosion conditions of pneumatic piping and supports for the ESDS on
weather decks and take measures for pitting not to lead to holes. If on board
maintenance is deemed impossible, make permanent repairs to, or complete
renewal of, such a portion of the piping during a dry-docking.
▪ Inspect conditions of fusible elements and confirm that no fusible part is covered
by paint, or the like.
Optical ESD System Maintenance
▪ When the ship arrives at a terminal where the optical ESD system is used, connect
the test plug to the optical fibre link connector to confirm normal signal are being
transmitted/received, at an appropriate timing before entering the port.
▪ Clean the optical fibre link connector pin periodically with the chemical agent
provided by the Company.
▪ Apply a protection cover, such as a canvas cover, to the fibre line connector box
for sea water not to penetrate into the box at sea.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 144 of 151
Confirm the number of valves capable of being operated simultaneously and display
precaution plates on the cargo console and the ballast console. Provide adequate training
and make preventive measures known to valve operators.
General
Manufacturers and “SIGTTO, Liquefied Gas Handling Principles on Ships and Terminals
guidelines on maintenance and testing of safety and relief devices” should be consulted
and maintenance scheduled accordingly.
Following is a generic list of cargo plant safety test / trips / alarms. Vessel specific list of
testing of alarms /trips as per manufacturer’s instruction is to be maintained. Cargo
plant alarms and trips are to be tested as per maker instruction or at internal not
exceeding 3 months.
▪ Cargo compressor suction low pressure (1st stage
▪ Cargo compressor discharge high pressure (2nd / 3rd stage)
▪ Cargo compressor discharge high temperature (2nd / 3rd stage))
▪ Cargo compressor discharge very low lube oil pressure
▪ Knockout drum high level
▪ Condenser and receiver level high
▪ Cargo compressor motor overcurrent
▪ Cooling sea water low pressure
▪ Condensate return high pressure
▪ Intercooler level high
▪ Control air low pressure
▪ Glycol / brine pump stop
▪ Glycol / brine low pressure
▪ Cooling fresh water High Temperature
▪ Hold space low pressure alarm
▪ Hold space high level alarm
▪ Cargo booster pump high discharge pressure
▪ Cargo Booster pump low suction pressure
▪ Cargo heater cargo outlet temperature low
▪ Cargo heater sea water outlet low temperature
▪ Cargo heater sea water low flow
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 145 of 151
The cooling medium of the re-liquefaction plant is to be maintained as per the maker
instruction. The specific gravity should be checked every month, and pH value of 7.0 or
more to be maintained.
▪ Where the use of cooling coils is essential for certain cargoes, a mixture of
ethylene glycol and water is normally used.
▪ For ships carrying cargo down to - 55 °C (minus), a 60% volume mixture of glycol
and freshwater should be adequate for all purposes. If the glycol percentage is
more than 60%, the additional glycol will not have practical advantages.
▪ It has been observed that the use of glycol in warm weather conditions can lead
to sludge generation. In such cases, chemical treatment of the cooling water may
be considered in consultation with the company.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 146 of 151
Kcal/m hr C
Viscosity C. P
Kcal/kg C (0oC)
Density (wt %)
Freezing Point
Gravity (15oC)
Specific Heat
Conductivity
(0oC (- (- (-
Thermal
Specific
) 10oC) 20oC) 30o
(0oC)
(oC)
C)
CaCl2 brine -10 14.5 1.128 0.798 0.472 2.6 4.1
-20 21.0 1.194 0.723 0.466 3.4 4.9
-30 25.2 1.236 0.688 0.461 4.2 5.3 10.1
-40 29.0 1.263 0.659 0.456 5.8 9.1 14.7
Nybrine -10 31.0 1.034 0.92 0.43 3.5
-20 48.0 1.054 0.85 0.40 5.0 7.7
-30 61.5 1.070 0.81 0.39 6.2 10.0 16
-40 71.5 1.081 0.80 0.37 8.2 14.0 23 38
3.44
When selecting a BWTS, the risk associated with the following must be considered:
• Location onboard the vessel,
• Chosen technology and Vessel type.
Company has issued standard guidance on management of BWTS in Environment
Management System Manual, Chapter – 3, SECTION 3.7.
The Master must ensure that vessels fitted with a BWTS, use the system as part of
normal ballast and de-ballast operations unless:
• The specific country or state does not allow the use of BWTS.
• There are faults with the equipment that may affect the safe operation, or
the ability to monitor overboard discharges. Faults must be discussed with
the office and local authorities may need to be informed.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 147 of 151
Coastal states requires the ships personal to be familiar with the operation and
that sufficient consumable are available on board.
A thorough risk assessment shall be carried out to ensure that hazard are identified and
mitigated to acceptable levels. Below listed are few generic hazards associated with
different types of BWTS. Maker’s manual must be consulted for detailed hazard analysis.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 148 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 149 of 151
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 150 of 151
The all welded exhaust piping vents for any gases generated in the electro-chlorination
process that could be flammable or harmful to the crew are to be led directly to a place
in the open deck where such discharges will not cause a fire or explosion hazard. The area
within 3 meters (10 feet) around the vent outlet is to be considered to be a hazardous
area.
Arrangements are also to be provided such that the ECU chamber is always filled with
water to avoid creating an explosive atmosphere in the event of ingress of flammable
fluid into the ECU chamber (i.e. Interlock arrangement such that the ECU cannot be
energized if water level/flow is less than an acceptable limit) and also to avoid excessive
surface temperature in the event of a water level drop (i.e. automatic shutdown in case
of excessive temperature or pressure).
A fixed hydrogen gas detection system is to be provided in the space housing the ECU and
arranged such that the activation of the gas detection alarm will result in an automatic
shutdown of all electrical power to the ECU.
Furthermore the potential of any flammable or toxic gas released into the ballast tanks
has to be assessed and if found in a concentration and/or volume that could present a
hazard to the crew or the vessel measures are to be provided (e.g. venting arrangements,
gas gauging system in tank, etc.).
1. A spare set of identified generic and critical spare parts are identified and
maintained on board. As soon as the spare is consumed, Chief /Engineer must
ensure a new set is promptly ordered.
2. The Master must make sure PTW and associated procedures relating to chemical
and high energy electrical systems are complied with when carrying out any
maintenance on the BWTS.
3. When operating and maintaining this equipment the following additional hazards
are present and are to be considered as part of normal PTW and Risk assessment:
• Sodium Hypochlorite.
• Sodium Bisulphite.
• Hydrogen gas.
• High Voltage electricity.
4. The performance of the BWTS is greatly affected by sediments around ship.
Frequent filter cleaning is required when operation is undertaken in dirty water
area.
Rev No. : 14
Chapter: 03 Date : 30-Nov-23
PLANNED INSPECTION & MAINTENANCE Page : 151 of 151
All ships calling US ports and intending to carry out ballast water operation, must use
BWTS type approved by the USCG. Vessel to contact TSI/MSI if this is not the case.
In the absence of a USCG approved BWM system to date, the USCG under its program
has been accepting AMS (Alternate Management System) deemed to be as effective
as Ballast Water Exchange, fitted by a vessel before the vessel's compliance date for
fitting BWTS as per USCG regulations. AMS acceptance by the Coast Guard is a
temporary designation given to a ballast water treatment system approved by a
foreign administration.
3.45
LNG As Fuel- Dual-Fuel engines use technology based on Otto cycle and diesel cycle. X-
DF engine is a 2-stroke slow-speed which uses lean burn principle (Otto Cycle) in which
fuel and air are premixed and burned at a relatively high air-to-fuel ratio – a concept
already used widely on medium-speed engines.
The launch of dual-fuel engines using LNG admitted at low pressure and ignited by a low
volume of liquid pilot fuel was a breakthrough in the marine industry. WinGD has applied
a depth of gas engine expertise and experience to its low-speed engines – a move that
extends the benefits of dual-fuel (DF) technology across the broader marine industry.
As a dual- fuel engine, the WinGD X-DF engine is designed for continuous service in gas
or in diesel operating mode. Refer vessel specific operation manual for details.
All planned and unplanned maintenance to be carried out as per maker’s manual as
mapped in ShipPalm.
Vessel to use “self-shrinking sleeve” of approved type when cable which is not fire
retardant passes through the bulkhead penetrations. The shrinking sleeve melts to seal
off the penetration in case of the wire melting. Only sealant is not approved method as
when the cable melts, it would leave a gap for flame or gas to pass through the
bulkhead. The make/ model and procedure of installing the sleeve to be obtained from
office as part of MOC. An approved fire-retardant putty must be used afterwards to
seal off the entire penetration after using the sleeve.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 1 of 16
PURCHASE DEPARTMENT
The purchase department is committed to the supply of the correct spares and stores to
the vessel. Once the requisition is received in the Office, depending on priority, the
Purchase department will send the requisition for quotations.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 2 of 16
On receipt of the quotations the Purchase Department shall forward the same to the
respective the Superintendent for approval. On receipt of the approval, the Purchase
Department shall order the items required. This shall be converted into the Purchase
Order which the vessel can track when it will be received.
For matters on purchase, the Master has the authority to contact the Superintendent and
/ or the Purchase department of the Company.
PO status - Open
PR rasised in
Shippalm PO confirmation –
Email Trigger to
vendor. TE. TSI
Send REQ to
Vendor
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 3 of 16
RESPONSIBILITIES
The Master is responsible for ensuring that the vessel is well stocked and equipped with
all the items deemed necessary for her proper upkeep and safe and efficient operation.
The Chief Engineer is responsible for ensuring that machinery spares are maintained as
listed in Chapter 3 (Minimum spares and recommended spares for operational
requirement).
Company policy places reliance on the vessel Masters for the accuracy, propriety and
necessity of requisitions originating from their vessels.
The Master and Chief Engineer has the knowledge and authority to determine what their
ships must have, but with this authority comes the responsibility to see that only standard
and necessary items are ordered.
It is to be ensured that the supplied spares & stores are of correct specifications and ready
to use. On new delivered vessels, the original spares supplied by the shipyard requires to
be checked for correct supply and usability.
LOCAL PURCHASE
There shall be occasions where it becomes necessary for the Master to make a local
purchase of stores and spares required to meet emergency requirement whilst in port. In
such cases the Master shall make the necessary purchase up to a limit of USD 500 after
obtaining an approval from the Superintendent.
Any safety/critical items which the Master feels may lead to PSC deficiencies or detention
shall be locally procured via agents / suppliers.
The supplier shall be advised to invoice the bill to the office for payment. If not possible,
same shall be settled in cash by Master and reflected in the monthly “Master’s Cash
Account” statement.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 4 of 16
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 5 of 16
PROCESSING OF REQUISITIONS
After receipt of the Stores Requisition, the concerned Superintendent / Technical
executive shall study it carefully for any irregularities or excesses and send to various
suppliers at the intended port of supply for obtaining their quotation and availability. On
basis of same, a confirmation will be made with a suitable supplier. Vessel can view the
progress of requisition process and can also view the status at any given time in Shippalm.
Vessel will also receive a message giving full details of the order confirmation.
Similarly, spare-part requisitions are scrutinized by the Superintendent, who while
reviewing the same, will check for cost and availability with the manufacturers and
various suppliers worldwide. As far as possible, arrangements are to be made for a
consolidated supply of all spares requisitioned.
The Agents will be suitably informed of all forwarding details in case of supply of spares
in order for them to make necessary arrangements for receiving and delivering the
consignment to the vessel during the vessel's stay in port.
For supply of stores, arrangement for the transport and delivery will be made by the
supplier and the Agent/vessel will also be suitably informed of the arrangements made.
PRIORITY OF REQUISITIONS
Shippalm allows for 3 types of requisitions to be raised from the system. It is very
important to understand the relevance of the different types so that proper follow up can
be done by the Company.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 6 of 16
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 7 of 16
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 8 of 16
NON-CONFORMING PRODUCTS
Supplies which are not satisfactory, or do not conform with the specifications as ordered,
shall not be accepted. They are to be returned to the supplier at their cost. If, for some
reasons, they cannot be returned to the supplier at the port of supply, these non-
conforming items shall be retained on board and returned to the supplier from the next
convenient port at the forwarding address, which will be given by the Office. During these
occasions, it must be ensured that products are suitably packed as necessary with
insulation material, to avoid damages during its transportation. These packages should
be handed over to the Agents for arranging onward delivery and should be appropriately
documented by clearly identifying:
▪ Product content
▪ Purchase Order / Reference Numbers, etc.
▪ Suppliers name and address
▪ Delivery address
▪ Special delivery requirements.
In order to prevent inadvertent use of the non-conforming item during the period of
retention on board, it shall be stowed away from its normal storing compartment and
clearly identified with remarks stating “Not to be used”.
In order to avoid storage of non-conforming products on board, all efforts to be made for
checking the supplies immediately upon their delivery against the requested
specification.
DELIVERY CERTIFICATES
The Head of Department or Officer concerned receiving the supplies shall sign delivery
certificates after satisfying himself that the goods describe therein have been received
and accepted. Appropriate remarks in respect of shortages, inferior quality, non-
acceptance, etc., are to be made on the delivery certificate with the supplier's consent.
Signed delivery certificates shall be returned to the person making the delivery and one
copy retained on board. It is to be understood that the signature is to confirm the quantity
and quality of the supplies and not their price.
When receiving provisions, two copies of bills shall be asked for and retained on board
with the Master.
The Master is encouraged to express his opinion in writing concerning the quality of
supplies, attitude of suppliers and other remarks by submitting form TE-36, as it serves as
a basis for deciding future business with the suppliers.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 9 of 16
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 10 of 16
CARE OF EQUIPMENT
Department Heads must encourage their staff to take proper care of the vessel's
equipment, tools, test equipment, etc.
Items such as boiler suits, wet gear, boots, etc., should be cleaned and dried after use and
stored ready for further use. Items such as photocopiers, computers, printers, scanners,
monitors, cameras etc., should be covered when not in use and should be bolted down
to avoid damage in bad weather. Test equipment should be returned to proper, secure
stowage after use.
Expiry period of standard issue PPE.
All PPE procured must be complying with Synergy standards. If procured locally for any
reasons, the PPE must comply to impact resistant standards and have the ‘CE’ marking on
them and also comply with necessary national standards.
All PPE must be inspected periodically (monthly or less) and before use, by its user and
must be replaced if damaged or found unfit for use due to deterioration or degradation.
The below replacement matrix is to be followed for standard issue PPE in the absence of
manufacturer specific expiry dates. Except for hard hats whose life must be taken from
the date of manufacture, all other PPE must be considered from the date put in use. In
the absence of the date of manufacture, the day the PPE is delivered on board (for hard
hats) or the date it is issued (other PPE) must be taken, as applicable.
For all other PPE (other than those mentioned below), manufacturer’s guidance must be
followed together with a periodic condition-based assessment.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 11 of 16
Additionally, for the below mentioned PPE, the safety officer must check the
manufacturer’s recommended routine and ensure that PMS is updated accordingly and
replace as per the below
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 12 of 16
Any items (store/ spare / LSA/FFA) that are condemned/discarded have to be clearly
marked and stored separately. Condemned LSA/FFA items must not be kept along with
the items that are in regular use or used for training purpose.
Removal report (Form TE-23) should be filled in, giving full details and showing the
purpose of the removal (i.e. for disposal, storage, etc.) stating if scrap, new, repairable,
etc.
In case any item is being landed for repairs or reconditioning, the name and address of
the party to whom same is being forwarded to shall be mentioned and necessary
signature of the concerned party obtained. A copy of this form (Form TE 23) should be
handed over to the party.
INCONSUMABLE PROVISIONS
Provisions and groceries (including beverages) not fit for human consumption shall be
inspected by the Master together with the Chief Cook (and the Chief Engineer in the case
of refrigerated goods), who shall prepare a report giving the following information:
• Date and time of survey,
• Item(s) surveyed,
• Quantity, weight, etc.,
• Nature and extent of spoilage,
• Apparent cause of spoilage,
• Description of storage and stowage,
• Date and place item(s) were received,
• Number of invoice or delivery certificate,
• Name of supplier,
• The manner in which the said goods are, or will be, disposed of,
• Any other pertinent information.
The report shall be signed by the Master and Officer(s) concerned and shall be forwarded
to the Office at earliest opportunity, with one copy being retained in the ship's files.
If the fault or responsibility for “spoilage” can be attributed to the supplier, the goods
shall, if practicable, be returned to the same supplier for replacement or cost-recovery
purposes. Otherwise, they shall be disposed of as the Master may deem best in the
interests of the Company, with authorization being requested from the Head Office
whenever practicable.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 13 of 16
Utmost care shall be taken to separate condemned goods from all other supplies in a
manner which will ensure that food poisoning and/or further damage cannot possibly
occur. All care should be taken to avoid inadvertent consumption of such spoilt
provisions.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 14 of 16
Owing to the high cost of Freon gas, prudent consumption of same shall be exercised and
any abnormality in the refrigeration system should be immediately corrected. Local
refilling of Freon bottles shall not be done at any time as the gas supplied may be of an
inferior quality, which might seriously affect the operation of the plant.
4.5 LUBRICANTS PROCUREMENT & STOCK LEVELS:
LO requisition should never be bundled up with any other requisition and Subject line of
the mail should clearly mention "LO requisition" and vessel name.
Vessel should always raise LO requisition following below guidelines. Any instruction from
vessel superintendent supersedes below guidelines:
Bulk carriers & tankers: Always to have ME Cyl. Oil ROB enough for 70 days of sailing,
calculated basis average of last three months consumption.
Container carriers: At any given day Cyl. Oil ROB must be enough to complete the voyage.
MECC oil ROB is always enough for one sump charge plus 3 months consumption.
AECC oil ROB is always enough for one AE Sump oil renewal plus total 3 months
consumption.
Minor grades ROB is enough for 6 months consumption.
LO Sampling kits cannot be supplied separately. Therefore, whenever required, it should
be included in LO requisition.
As far as possible, requisition for only minor grades should be avoided.
Below ports are most convenient & economical for LO supply -
• Fujairah / Khor Fakkan, UAE
• Singapore
• Rotterdam / Amsterdam, Netherlands
• New Orleans / Houston, USA
• Ulsan / Yeosu / Busan, South Korea
• Yokohama / Chiba / Kawasaki, Japan
• Antwerp, Belgium
• Gibraltar
• Algeciras, Spain
Vessels calling above ports should always request supply such that lubes / greases / LO
sampling kits are adequate for at least 4 months. When raising LO requisition, a remarks
column specifying the maximum safe quantity of main grades should be included.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 15 of 16
For reference, synthetic grades of lubricant are generally used for below equipment:
I. Main Air Compressors
II. Deck Air Compressors
III. Other Air Compressors
IV. Gas Compressors / Refrigeration Compressors / AC Compressors
Before placing requisitions, reference to be made to vessel’s LO Chart for complete list of
synthetic lubricants that are in use. In case of any doubts office to be consulted.
Below precautions to be taken in raising LO requisition:
• PR type selected should always be “Lube oil”
• Communicate with office if LO order confirmation / delivery confirmation or
related communication from office is not received at least 5 working days before
vessel’s ETA.
• In case LO requisition is raised within 5 working days of ETA, send LO requisition
pdf copy with requested grades arrival ROBs to office by E-mail also.
• Mentioned ROBs in LO requisition should always be arrival ROBs at supply port.
• If mentioned ROBs in LO requisition is not arrival ROBs at supply port, mention
date of ROBs in remarks column.
4.6 RECEIVING SHIP'S STORES FOR USE OF ANOTHER SHIP, OR COMPANY'S USE
ELSEWHERE
Such stores should be accepted only on directives received from Office and the following
instructions are to be complied with:
• When these consignments are not manifested, they are to be in the care of the
Chief Officer, who is to arrange their stowage in one place.
• Each consignment is to be marked with the destination (port), the consignee
(address), the shipper's name, and the reference markings.
• Each consignment is to be accompanied by one of the following documents: A
letter, delivery note and invoices, Bill of Lading, if any, etc.
• The Master is to ensure when necessary that a supplementary manifest is
provided before discharge.
• A list of such consignments is to be sent to the Company on receipt of goods.
• Ensure that the contents of these consignments are not a restricted item at ports
enroute and at also at the destination port.
Rev No. : 8
Chapter: 04 Date : 15-May-22
PROCUREMENT AND INVENTORY CONTROL Page : 16 of 16
MARPOL Annex VI limits the main air pollutants contained in ships exhaust gases,
including sulphur oxides (SOx) and nitrous oxides (NOx).
All the engines installed on board for normal duty and with rating more than 130 KW are
provided with a technical file which comprises the NOx test parameters, settings, NOx
critical components and operating parameters pertinent to that engine. Each NOx critical
component and spare part is assigned an IMO Code number and ordering of spare parts
every time with the same IMO Code is important to comply with NOx regulations.
As the engine spare parts are always ordered from engine makers or their authorized
vendors, the correct parts are identified based on the vessel’s IMO number.
The PMS inventory list contains the NOx IMO Codes for the components listed in the
NOx technical file. This data is automatically mentioned in the spare part name when
the vessel raises a spares requisition.
Rev No. : 12
Chapter: 05 Date : 15-Dec-22
ENGINEERING OPERATIONS Page : 1 of 9
5. ENGINEERING OPERATIONS
5.1 COLD WEATHER PROCEDURES
GENERAL
The following outlines, procedures, and precautions to be taken to guard against
damage to vessel and equipment due to cold weather. The Master and Chief Engineer
should take any additional actions he believes necessary as determined by actual
circumstances and conditions. The Chief Engineer should establish a routine for all
departments when it is anticipated that the vessel will be exposed to cold weather.
Protecting the vessel and its equipment from damage during cold weather rests upon
foresight, knowledge of detailed effects of freeszing weather, preparedness, and
constant alertness in combating the effects.
Operations in cold weather constitute special operations, in that any errors may become
apparent only a hazardous situation has been created, or an accident has occurred.
Accordingly, all shipboard personnel should utilize the procedures provided in this
section during any operations in cold weather.
Rev No. : 12
Chapter: 05 Date : 15-Dec-22
ENGINEERING OPERATIONS Page : 2 of 9
Operate main and auxiliary circulating pumps with the crossover open. When securing
the main plant, stop the main circulating pump momentarily to wash back ice from the
main injection system.
Rev No. : 12
Chapter: 05 Date : 15-Dec-22
ENGINEERING OPERATIONS Page : 3 of 9
Whenever there is danger from frost damage, special precautions must be taken with
respect to steam driven deck machinery and systems exposed to the atmosphere. Steam
must be maintained on deck at all times when temperatures are, or are expected to fall,
below 0°C. Steam should be “cracked” on to windlasses and winch engines and their
control levers secured in the neutral position. Open bypasses fitted between steam and
exhaust lines to ensure adequate steam flow in exhaust piping. There will normally be
sufficient leakage through the valves to ensure that the steam cylinders are kept warm.
They should be checked at frequent intervals and the machinery run light for a few
minutes. Engines should not be left running for long periods, even at slow speed, as
serious bearing damage may result.
The deck watch will inform the engine department well in advance of anticipated
temperature changes, together with actual changes in the temperature as it drops to the
freezing point.
The Deck Department will keep watch on the deck machinery to ensure that steam is
flowing through the winches. White stripes painted on winch drum will assist the watch
in observing the winches.
The Deck Department in coordination with the Chief Engineer will ensure that: -
▪ The lifeboat engine's fuel (gas oil or diesel oil) is suitable for use at 15 oC or less
▪ Drinking water containers are temporarily stowed inside the accommodation.
▪ Lifeboat sump oil change of one sump volume of low viscosity oil (5W20 - in view
of Noack volatility) to be considered for cold weather conditions to avoid starting
difficulties
Rev No. : 12
Chapter: 05 Date : 15-Dec-22
ENGINEERING OPERATIONS Page : 4 of 9
▪ Compressed air
▪ Steam eductor system under forecastle head
Any vessel equipped with independent midships water systems should start the system
prior to entering freezing weather. Transfer and isolate wash water and potable water to
midships system and drain deck piping. If this is not possible, put steam tracer on both
systems.
Maintain a minimal flow of water through sanitary systems and soil drains. Tying down
one or more flushometers or fitting jumpers at selected locations will help to prevent
freezing. A small amount of antifreeze can be added in unused drain traps. Put steam
chaser on midship sanitary system and/or open overboard-circulating line.
Increase steam to quarters heating system. Quarters heating traps may be bypassed or
have the internals removed to ensure adequate flow.
Rev No. : 12
Chapter: 05 Date : 15-Dec-22
ENGINEERING OPERATIONS Page : 5 of 9
If sea water temperature falls below zero deg C, all tanks adjacent to the ship's skin, i.e.
double bottoms, peaks, etc., containing fresh water, should be kept slack to prevent
possible rupture from freezing.
The installed heating elements of electronic equipment should be used when equipment
is not in use.
Equipment without heaters should be left on. Some radar scanners have heaters that
may be on when the equipment is in use. Consult your operating instruction manuals for
the best method of protecting your equipment.
Keep decks as ice free as possible to reduce slipping hazards, particularly heavily trafficked
areas. Use deck scrapers and generous amount of rock salt to assist in keeping ice off
decks.
Careful attention should be paid to the air pipes of fresh water tanks. A tank, which has
been filled from the evaporator or freshwater generator in which, the air pipe, has been
filled and the water frozen could collapse when the tank is put into service. Water
sloshing into the air pipe during rolling could also cause an ice plug to form. In freezing
conditions, the air pipes should be rodded out prior to putting the tank into service.
Rev No. : 12
Chapter: 05 Date : 15-Dec-22
ENGINEERING OPERATIONS Page : 6 of 9
▪ In port, circulate heated jacket water and keep main engine lubricating oil pump
in operation, or pump engine sump oil to high tank and bulk purify to maintain
temperature, running oil down to main engine just prior departure.
▪ Where fitted, sea water re-circulation systems should be set up to minimize intake
of freezing water. If a re-circulation tank is available, it should be put into use.
▪ Sufficient ballast should be taken to ensure that the propeller is submerged to
avoid ice damage. Turn rudder and propeller once every day but before turning
check that there is no ice formation around. Do not turn propeller / rudder if ice
formation is noticed. Assistance from shore / tug boat should be arranged if
necessary, to clear the ice formed around the rudder before departure.
▪ Rig space heaters in steering flat.
▪ If not in use, blow bunker tank heating coils with air. Remove plug or bend to
ensure complete drainage. Drain return lines at low points and blow drain traps
clear.
▪ Ensure vessel has sufficient fuel and fresh water reserves to cover additional
steam requirements.
Deck piping and deck machinery
▪ Drain fire main and all branches at lowest points. Fabricate air connection for
blowing lines clear immediately after use. Blow compressed air lines clear.
▪ Prepare steam hose for use in de-icing on deck.
▪ Run hydraulic winch and windlass pump unit continuously. Run Hydraulic deck
crane pump units continuously and ensure heaters are on.
▪ To minimize possible leakage, do not run hatch hydraulic units continuously. As
these units are normally under cover, the aim should be to maintain the
temperature of the space by the best safe means available.
▪ Where applicable, keep heater on whistles and drain strainers. Test whistle daily
using push button; do not use the hand lever without checking the entire length
of wire as it may be frozen.
▪ Lay old wire or rope along hatch cleats, cross joints etc., with an eye left free at
one end. If ice builds up, the eye may be taken to a winch and pulled clear to assist
in breaking the ice.
▪ Fill recesses sockets on hatches for cleats etc., with grease or soft soap.
▪ Lay cargo nets, old wire or rope over stowed gangways and accommodation
ladders to assist in breaking ice deposits. This may also be done on exposed
windlasses and winches.
▪ Drain moisture from deck machinery gearboxes and top up with correct oil.
▪ Keep air hoses, gangway winches, pilot hoists and ladders and all portable
equipment under cover in a warm place when not actually required for use.
Uncontrolled document when printed
TECHNICAL MANUAL
Rev No. : 12
Chapter: 05 Date : 15-Dec-22
ENGINEERING OPERATIONS Page : 7 of 9
▪ Keep radar scanner turning and radars running in port where permitted. If
scanners must be stopped, check that the scanner is free to rotate before
switching on. Drain wave guide to confirm no accumulation of moisture.
▪ Wire aerials and whips may require to be manually cleared of ice to maintain
operational performance.
▪ Drain and isolate any exterior fresh water piping.
▪ Keep mooring ropes and wires under cover for as long as possible, consistent with
operational requirements
Ballast
▪ Change any fresh water ballast for sea water.
▪ Use double bottom and hold ballast only. Do not use topside tanks unless
absolutely essential. If topside tanks are to be filled, only fill up to 80% of tank
capacity.
▪ Do not press up double bottom tanks into air and sounding pipes.
▪ Dose sounding pipes with salt to prevent ice plugs forming. Keep caps screwed on
as much as possible.
Accommodation
▪ Seal external doors with PVC tape and limit normal access to accommodation to
one door. All doors must be available for emergency use.
▪ Rig fan heaters (portable hot air blower on hair dryer will do) in wheelhouse for
window de-icing. Keep clear view screen and window wiper motors running
continuously.
▪ Where deck heads are exposed to outside temperature, remove panels and rig fan
heaters to reduce risk of domestic water pipes freezing.
Safety
▪ Ensure emergency generator cooling system has sufficient anti-freeze and that
fuel tank contains fuel suitable for low temperature operation. This applies also to
lifeboat and emergency fire pumps.
▪ Lower level in lifeboat fresh water containers to allow for ice expansion.
▪ Ensure lifeboat plug holes are clear to prevent water building up in boats.
▪ Rig safety hand lines on main deck, use ropes and not wire. Keep a passage way
on deck clear of ice/snow at all times. It is easier to clear deck immediately after
snowfall when it is soft instead of later.
▪ No open heaters or naked lights are allowed in accommodation area.
Rev No. : 12
Chapter: 05 Date : 15-Dec-22
ENGINEERING OPERATIONS Page : 8 of 9
General
▪ Have ample supplies of sand, salt, and anti-freeze available.
▪ If crew must remain on deck for too long, then it should be organized in such a
way that at regular interval they are allowed to refresh themselves with hot food
and beverages. Ensure adequate warm dry clothing.
▪ The risk of freezing spray is very real. It is caused due to rapid changes in air
temperature in a very short time thus resulting in excessive ice formation on
contact. Ships with low GM must try avoiding same by reducing speed, altering
course or in extreme cases, remain in sheltered waters till safe to continue
voyages.
▪ On returning to warmer weather, ensure that all systems are returned to normal
operation.
▪ Storerooms and lockers at the shipside are liable to have their consents damaged
by frost. E.g. cans / bottles in poorly insulated beer locker break in extreme cold.
Move these into a warmer place if required.
Rev No. : 12
Chapter: 05 Date : 15-Dec-22
ENGINEERING OPERATIONS Page : 9 of 9
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 1 of 24
6. DRY DOCKING
6.1 DRYDOCKING / REPAIRS - GENERAL
The objective of drydocking is to ensure that vessel repairs are carried out in a safe and
cost-effective manner meeting all operational, commercial, technical and regulatory
requirements to maintain the classification of the vessel.
Dry-docking Policy & Planning: Dry-docking intervals planned as per ship and
classification society requirements, keeping owner’s charter party, commercial
commitment, trading pattern, urgency of repairs, total time, and costs in mind. Company
issues dry-docking schedule for the fleet. Superintendent fills in estimation of time and
remarks on dry-docking. Opportunity should be taken during docking to complete all
deferred and outstanding repairs.
To improve the energy performance of the vessel, the company considers fitment of
energy saving devices such as Mewis Duct, PBCF, new design propellers etc and
application of high-performance hull coating.
Variable Frequency Drive (VFD) for large capacity electric motors and new technologies
offered by Yards in the vessel specification are considered at the time of building the
ship or during retrofits.
However, all such energy saving measures are subject to Owner’s concurrence.
Jobs which are to be carried out by ship staff, are not included in the drydock
specifications. A separate list is generated for follow up of such jobs during dry docking
when required.
Technical Superintendent shall take inputs from Marine Team (SMT and QSHE) and
include their requirements into dry dock specification.
On Tankers, Marine superintendent ensures tank cleaning, gas freeing, de-mucking are
done and gas free certificate by chemist is obtained.
The dry-dock specification will be reviewed by the DD coordinator and approved by
Technical Superintendent, Fleet Manager and Head of Technical Team. For
unscheduled dry-docking, the specification shall be adjusted according to requirement.
RESPONSIBILITY
Technical Superintendent is responsible for preparation and execution of drydock.
The Fleet Manager is responsible for:
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 2 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 3 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 4 of 24
If the vessel is a Tanker then arrangement must be made for Slop discharge between the
last discharge port and entering the shipyard. Vessel also to be given instructions BEFORE
the last discharge to carry out full COW if a Crude Oil Tanker and/or full tank cleaning for
Product and Chemical Tankers.
If a vessel is having LNG fuel tanks, then arrangement as per vessel specific manual to be
undertaken in preparing tanks for human entry for inspection or repair. Tank preparation
should be initiated through Tank warm-up as a part of the gas-free operation prior to dry
docking or tank inspection. The most of fuel will be removed from the tank or moved to
other space to reduce the vaporizing time.
Nitrogen is used for warm-up to proceed gas free at the same time. Hot nitrogen gas from
LNG Bunker vessel/terminal is introduced through the filling line to the bottom of the tank
for evaporating of the remaining LNG in the tank. Excess BOG generated during the warm-
up operation is returned to the shore.
Gas freeing is necessary to prevent the possibility of the mixture of air and NG vapor in the
flammable range. The operation is continued until the hydrocarbon content is less than
2% in volume.
Technical Superintendent/Master/Chief Engineer: Inspect jobs/vessel on arrival at dry-
dock port/yard. Ship to prepare and submit crew work lists for the period of the docking.
Protective surfaces to be laid in all accommodation areas where shipyard workers will
have access. All tools to be removed from workshops and placed in secure stores. All
stores to be kept locked and keys to be held with duty officer. Confirm all necessary stores
/ spares including yard supply are ready.
Superintendent shall examine
• the scope of Sub-Contractors and verify their facilities if work is being done
outside the yard.
• Carry out a general survey/ tour of the yard to know the location of relevant
workshops.
• Confirm shipboard Black & Grey water facilities are being stopped during the
repairs and ensure adequate shore facilities are available close to the vessel
• Check yard facilities provided for the Superintendent including phone and internet
facilities.
• Check the yards drydocking procedures and how that will interfere with the
repairs schedule.
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 5 of 24
Re-evaluate items to be done at yard vis à quoted price. Continuously inform yard all
additions/deletions to specification as soon as possible. Obtain time cost quotations
progressively prior to commencement of extra work if possible. Maintain daily
communication channel with Head of Ops & tech team on progress. Communicate
additional works, costs, over-budgets as soon as possible & clear with Technical Manager
/owners as required. Superintendent to inform Accounts of extra costs, if substantial.
Instruct and advise Master/Chief Engineer for required supervision on materials, and to
maintain log of labour/work progress as required.
Reference is made to following Forms for guidance and which shall be adhered to and
completed at each phase of the dry docking as applicable –
• Master/Chief Engineer to be guided by Form TE-51
• Superintendent to be guided by Form OF-TE-024
Vessel to conduct a risk assessment for important maintenance activities during
drydocking to ensure that the reliability of the machinery is not adversely affected by the
maintenance activity. It is to be conveyed to the Yard and the vendors that maintenance
activity undertaken by them w.r.t significant energy uses such as main engine, generators
and boilers should not adversely affect the energy performance of the vessel post the
drydocking.
Technical Superintendent/Master/Chief Engineer/Yard Representative: Maintain
record of all delays, incorrect work, stoppages, labour shortages, interruptions etc. and
arrange to keep detailed accounts by ship staff of work processes where verification on
completion of job is not possible (e.g. sand blast areas for quality and quantity). Maintain
full documentation for items under H&M or P&I claims. Co-ordinate surveys as required.
Maintain progressive records with photographs for all important work. Master / Chief
Engineer must consult with attending Superintendent prior signing / stamping any work
completion reports submitted by yard. Make sure work done reports are endorsed with
relevant facts by Master/Chief Engineer where any discrepancy has been noted.
Superintendent: The first meeting on the vessel, should include all relevant yard
personnel, Ships Officers, Bosun, Specialist Technicians etc. so everybody knows the
concerned persons and Safety Procedures are discussed. Morning meeting shall be
carried out as early as possible with the Ship Repair Manager (SRM), Yard Safety Officer,
Senior Officers plus any other relevant people such as Class, Painting Supervisors etc.
These are an important part of the daily routine where any yard or shipboard problems
can be discussed and sorted out. Morning meeting is also important to Discuss the days
schedule and progress/delays of the previous days. Minutes of the Meeting is to be
recorded
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 6 of 24
TENDERS/QUOTATIONS
Tenders / Quotes need to be obtained (at least 2 quotations), and if intended yard is
decided due to vessel trading pattern or by request of owners, then 1 quotation is
sufficient. Returned quotes shall be compared with each other and with previous
quotes. Negotiations will occur, and the final choice of yard will be based on:
▪ Quality / experience
▪ Price
▪ Location
▪ Timing / schedule
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 7 of 24
The DD coordinator shall review the quotes from respective yards and present the result
to the Fleet Manager who shall in consultation with the Head of Technical Team, select
the yard to be used.
Technical Superintendent with Fleet Manager will prepare the budget for the dry-
docking.
MD will review and approve the final budget. Yard will be informed and asked to
confirm their acceptance of the subject vessel for repairs. Yard gives written
confirmation of acceptance.
Technical Superintendent will summarize the final cost incurred, including shipyard,
subcontractors, and materials and subdivide the information based on the major work
done in the budget on repair specification report.
Actual final costs will be presented along with the budget amount to Fleet Manager and
Head of Technical Team for approval.
Upon approval, the payment will be released.
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 8 of 24
Master, DD
Coordinator, Tech.
Suptd / Marine
Suptd & Fleet Mgr
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 9 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 10 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 11 of 24
• Instruct ship staff to make water tight specs and allot DD Spec numbers for
the essential DD jobs, such as Tail shaft, seal, rudder, propeller, hull
blasting/ painting etc.
• Based on jobs check spares inventory & spares requisition and advice to
raise requisition individually against each DD specs. Boiler man hole doors
and gaskets, Stern seals, Bow thruster seals & Bearings, Steering gear ram
seals.
• Advice to raise requisition for DD stores - Joints, gland packing’s, packing
extractors, valve grinding tool, Apexior 3, zinc anodes, grinding paste,
molykote, silicon, glass wool and insulation, valves general (Only gate,
globe etc. – butterfly valves to make separate requisition for seats and
other spares).
• Every docking all storm valves internals to be inspected and renewed as
necessary.
• As a practice, renew all storm valves alternate docking (i.e. once in 5 years).
• Every docking Main sea water pipe (from sea chest to inlet of sea water
pumps) thickness measurement to be carried out (UT gauging) for ships
which are older than 10 years.
• Port and Starboard Anchor “D” shackle pin to be welded with the body.
• Confirm if the following drawings available on board or office: -
▪ General arrangement
▪ Capacity plan.
▪ Docking plan
▪ Stern tube, propeller, and shafting arrangement
PREAMBLE
• To make preamble for the DD specs - based on above information.
• Compile complete specs for quotations.
• Send for quotations.
• Obtain DD quotes and make cost comparison and work out budget.
SPARES & STORES
• Send RFQ for Stern seals, anodes, paints, bow thruster spares/ seals, ram seals,
butterfly valve seat rings.
• ME spares if required.
• Hatch cover spares if requisition - including rams, cranes, or grabs.
• Stores RFQ & Supply.
• Try to connect at convenient ports.
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 12 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 13 of 24
IMPORTANT
Prior arriving the dock, vessel will be in light condition with low propeller immersion
which may lead to damages to stern tube.
Stern tube failure can happen quickly when low immersion conditions occur. Its main
cause is the loss of the hydrodynamic lubrication film within the white metal bearing,
causing a rapid rise in temperature and overheating.
Conditions in which stern tube failures occur vary and can be affected by the overall
condition of the propeller, rudder, stern tube, and main engine. When looking into the
factors that cause specific failures, a number of issues must be considered as listed:
a. A main consideration is the detrimental effect of wiping the bearing due to loss
of the oil film, causing shaft and bearing contact. Hydrodynamic lubrication
failure will lead to excessive temperatures and other symptoms including
reduced engine performance. Although this failure may not be a direct result of
low immersion, the effect of cyclic loading and shear stress on the stern tube
bearings over time may lead to failures.
b. Pressure conditions within the bearing surfaces should also be considered. The
stern tube manufacturer’s recommended oil supplier should be consulted, as it
will advise the oil grade to be used with the correct viscosity during service.
c. The propeller shaft diameter and weight determine the contact area on the
bearing, but shaft misalignment tolerances will affect the overall bearing load
distribution. This will also be influenced by the propeller’s weight, which will
cause bending moments along the shaft leading to localized pressure
variations.
d. When the propeller is only partially immersed, its performance is usually
another main contributory cause of stern tube problems. Because it is not
operating to its optimum and designed thrust and torque parameters, the
effects of eccentric thrust, cavitation and vibration will create uneven load
distribution and inadvertently lead to bending moments and localized stress
areas, especially in the aft part of the bearing where edge loading may develop
and increase over time. Apart from the stern tube being exposed to damage,
cavitation damage on the propeller may also occur because of operating the
vessel in these conditions over an extended period.
e. Large rudder angles when the propellers are in a low-immersion condition can
also play a part in increasing the risk of damage, as propeller wash efficiency is
reduced causing the vessel to respond to helm orders more sluggishly. In some
instances, this can cause the master to increase main engine power and speed,
exacerbating the situation.
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 14 of 24
To avoid above conditions, ship’s staff must closely monitor the stern tube bearing
temperatures and maintain hourly monitoring parameter sheet during the passage.
The responsibility of the safety of the vessel remains always with the Master.
REFMAN SOFTWARE
REFMAN software is used for managing all dry-docking related activities in all SMPL
vessels.
Overview
REFMAN is designed to allow vessel and office staff to manage the ship repair process.
REFMAN has a specification generator for compiling and printing specification
documents, cost control for comparing shipyard tenders, reporting drydocking costs,
shipboard defect recording, monitoring for managing defects and other jobs initiated
onboard. It provides a comprehensive system for dealing with defects related to yard
repair, identified during ship inspections/ audits, ad hoc defects and or jobs that are
identified following a Superintendents visit to a ship as well as for items that are raised
by ship’s staff
Various planning features in REFMAN are as follows;
• REFMAN’S specification generator
• REFMAN’S cost control
• Ship-board defect recording (Ship Palm remains primary means of defect
reporting and monitoring. Only the defects which are agreed with vessel
Superintendents for Dry Docking repair needs to be manually fed in REFMAN)
• Ship-board defect monitoring as applicable for dry docking
• REFMAN’s drawing module
• REFMAN’S time management
• REFMAN’S yard performance evaluation
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 15 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 16 of 24
When Head of Security of the Yard arrives at the scene of a fire, all available ship crew
and equipment shall be put at his disposal, the Yard taking command of the operation in
conjunction with the Master.
On CO2 systems there are ‘pins’ in the activation assembly, and traditionally, these pins
had to be removed for the system to be ready for immediate use. On some modern
systems, these ‘pins’ remain fitted for the system to be ready for immediate use. When
inspecting the CO2 systems, the inspector should determine from the officer
accompanying whether the pins should be ‘in’ or ‘out’ for the system to be ready for
immediate use. If in any doubt reference should be made to the manufacturers operating
inspections.
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 17 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 18 of 24
If brought ashore for service, the firefighting ability may be reduced / incapacitated.
It is recommended that the air pressure test be performed at a suitable shore-based
facility equipped to make any necessary repairs in accordance with the manufacturer's
recommendations. In view of the wide variety of materials and adhesives used in
immersion suits and anti-exposure suits, it is strongly recommended that any repairs to a
suit be carried out by a facility which has access to the original manufacturer's
recommended servicing instructions, parts and adhesives, and suitably trained personnel.
The air pressure test may be carried out on board ship if suitable equipment is available.
(MSC Circ 1114).
6.8 MEETINGS
Regular meetings must be held during the stay with the ship’s senior staff, the Yard
personnel and sub-contractors participating. The agenda must consist of aspects
regarding the safety of personnel, environment, and property, in addition to work
planning.
6.9 INFORMATION
The ship staff must be regularly informed regarding issues on their personal safety, issues
such as: -
▪ Hot work to be carried out, including location(s)
▪ Danger points, deck openings, etc.
▪ Changes in the alarm systems
▪ Changes regarding the Emergency Plan
▪ Communication
Watch Officers and crew shall carry walkie-talkies, as shall crew have involved in any other
critical operations such as hot work, work in enclosed spaces, etc.
The Ship will normally be connected to the Yard’s telephone system. A list of emergency
numbers must be displayed next to the telephone. The Master must also have a back-up
telephone system, such as a mobile phone.
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 19 of 24
It is not realistic to keep account of Yard personnel. The Officer on Watch must, however,
make sure Yard personnel stay out of areas with no relevance to the work being
performed.
The Ship and the Yard must agree on a procedure for controlling visitors. Normally, the
control system will suffice. However, the Officer on Watch must ensure that unauthorized
personnel stay out of areas with no relevance to their visit on board the ship.
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 20 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 21 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 22 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 23 of 24
Rev No. : 8
Chapter: 06 Date : 30-Nov-23
DRY DOCKING Page : 24 of 24
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 1 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 2 of 45
Types of Corrosion:
Uniform General Corrosion: General corrosion appears as non-protective rust which can
uniformly occur on any surfaces that are uncoated. The rust scale continually breaks
off, exposing fresh metal to corrosive attack. Thickness loss cannot usually be judged
visually until excessive loss has occurred. Failure to remove mill scale during
construction of the vessel can also accelerate corrosion experienced in service.
Impact: With overloading, it can lead to deformation, buckling, cracking, and even
collapse of girders and plates.
Areas to inspect: Ballast Tanks, girders, side plates, inner skin, floors, etc.
Uniform General Corrosion
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 3 of 45
Pitting Corrosion:
It is a localized corrosion that occurs on bottom plating, other horizontal surfaces and at
structural details that trap water, particularly the aft bays of tank bottoms, or on vertical
surfaces in cargo holds due to corrosive nature of certain cargoes, such as Sulphur, salt,
coal etc. For coated surfaces the attack produces deep and relatively small diameter pits
that can lead to hull penetration in isolated random places.
Pitting of uncoated surfaces, as it progresses, forms shallow but very wide scabby
patches (e.g. 300 mm diameter) the appearance resembles a condition of general
corrosion. Severe pitting of uncoated surfaces can affect the strength of the structure
and lead to extensive steel renewals. If the corrosion is more than 75% or if the pitting is
more than 10% of original thickness, affected structure needs to be renewed after
getting approval from class.
Taking into account all the possible factors which might be relevant to a particular cargo
space or ballast tank, special attention should be paid to the following areas when
looking for signs of serious corrosion:
▪ Horizontal surfaces such as bottom plating face plates and stringers, particularly
towards the after end of the structural element. The wastage may take the form
of general corrosion or pitting. Accelerated local corrosion often occurs at the
after bays and particularly in way of suctions.
▪ Deck heads and ullage spaces in uncoated ballast holds or cargo holds and ballast
tanks where anodes may not be effective, the surface temperature is high and
the space has high humidity.
▪ Structure in way of lightening holes or cutouts where accelerated corrosion may
be experienced due to erosion caused by local drainage and flow patterns, or
lack of stripe coating.
▪ Grooving may also take place on both horizontal and vertical surfaces.
▪ Areas in way of stress concentrations such as at toes of brackets, ends of
stiffeners and around openings.
▪ Bulkhead surfaces in ballast tanks adjacent to heated cargo or bunkers.
▪ Areas in way of local coating breakdown.
▪ Impact: Pitting intensity of more than 20% can have an impact on strength.
Refer to the diagram as guidance for assessing pitting corrosion intensity.
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 4 of 45
Pitting Corrosion
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 5 of 45
Impact: Grooving of L-profiles reduces shear capacity and it is critical due to skew
bending. Areas to inspect: Grooving corrosion is often found in or beside welds,
especially in the heat affected zone.
Grooving corrosion at the welded seams
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 6 of 45
EROSION:
Erosion which is caused by the wearing effect of flowing liquid and abrasion which is
caused by mechanical actions may also be responsible for material wastage.
FRACTURES:
▪ In most cases fractures are found at locations where stress concentration occurs.
▪ Weld defects, flaws, and where lifting fittings used during ship construction are
not properly removed are often areas where fractures are found.
▪ If fractures occur under repeated stresses which are below the yielding stress,
the fractures are called fatigue fractures. In addition to the cyclic stresses
induced by wave forces, fatigue fractures can also result from vibration forces
introduced by main engine(s) or propeller(s), especially in the afterward part of
the hull.
Fractures may not be readily visible due to lack of cleanliness, difficulty of access, poor
lighting, or compression of the fracture surfaces at the time of inspection. It is therefore
important to identify, clean, and closely inspect potential problem areas. If the initiation
points of a fracture are not apparent, the structure on the other side of the plating
should be examined. Fracture initiating at latent defects in welds more commonly
appears at the beginning or end of a run of welds, or rounding corners at the end of a
stiffener, or at an intersection.
Special attention should be paid to:
▪ Welds at toes of brackets, at cut-outs, and at intersections of welds.
▪ Fractures may also be initiated by undercutting the weld in way of stress
concentrations.
▪ Although now less common, intermittent welding may cause problems because
of the introduction of stress concentrations at the ends of each length of weld.
Consequences of Fracture:
▪ It should be noted that fractures, particularly fatigue fractures due to repeated
stresses, may lead to serious damages, e.g. a fatigue fracture in a frame may
propagate into shell plating and affect the watertight integrity of the hull.
▪ In extreme weather conditions the shell fracture could extend further resulting
in the loss of part of the shell plating and consequent flooding of cargo hold.
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 7 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 8 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 9 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 10 of 45
COATING CONDITION
Coatings are the first barriers to protect tanks against corrosion. Sacrificial Anodes are
used to complement the coating at areas of exposed steel. During the inspection if the
Coating breakdown is observed and bordering at a Fair rating, the head office should be
informed. The Superintendents in consultation with Anode Manufacturers will have an
Anode system designed to provide adequate Current Density levels.
Zinc and Aluminium anodes are widely used; at times Magnesium anodes are also used.
▪ On Tankers, as far as possible Zinc anodes should be used. Aluminium anodes if
fitted must comply with the height restriction requirement. On Tankers
Magnesium anodes are not to be fitted.
Coating Breakdown
Intact coatings prevent corrosion of the steel surface.
However, a local absence of coating (due to coating depletion, deterioration, damage,
etc.) can result in corrosion rates similar or greater than those of unprotected steel.
Holidays in coating can lead to pitting corrosion rates higher than for unprotected steel.
Periodic inspections at appropriate intervals and repair of coating as required are
effective in minimizing corrosion damage.
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 11 of 45
These pictures represent the condition of coating in GOOD, FAIR, and POOR form.
Good: Condition with only minor spot rusting
Fair: Condition with local breakdown of coating at edges of stiffeners and weld
connections and/or light rusting over 20 per cent or more of areas under consideration,
but less than as defined for poor
Poor: Condition with general breakdown of coating over 20 per cent or more of areas of
hard scale at 10 percent or more of areas under consideration
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 12 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 13 of 45
INSPECTION GUIDELINES
Ship Side (Inspection guidelines)
▪ Shipside is to be inspected after every long voyage, preferably during light
condition for deformation, sea growth and rusting.
▪ Where the Port Authorities permit, accessible areas are to be de-rusted and
touched up, after seeking prior permission from the authorities.
▪ “Working at height Permit” (Form PTW 03) must be used each time such
maintenance is carried out.
▪ All precautions are to be taken to ensure that no pollution is caused during the
use of paint.
Main Deck (Inspection guidelines)
▪ Close up inspection of main deck and its structures are of prime importance. It
must be ensured that no fracture can extend transversely in the deck structure.
▪ Special attention must be paid to the stringer plate and sheer strake joint.
▪ Check plating around the scuppers for corrosion and cracks.
▪ Check for fractures at the weld seam between the deck plating outside the line
of hatchways and the thinner cross deck plate, especially when the difference in
plate thickness is large.
▪ Check hatchway beam for fractures, buckling and corrosion.
▪ Check cross deck strip for buckling.
▪ Check hatch way corners for cracks at welded attachments and shedder plates
close to or on the free edge of the hatchway corner plating.
▪ Check hatch coaming top and coaming top bar at the mid length of hatchway for
fractures.
▪ Check fillet weld connections of the coamings to the Deck for fractures,
particularly at a curved coaming plate at the corner of the longitudinal and
transverse hatchway coaming.
▪ Check the area around the supports for the deck piping and cable conduits for
cracks and detachment.
Double Bottom Tanks (Inspection Guidelines)
Double Bottom Section
▪ Check inner and outer bottom longitudinals, especially the interconnecting
brackets or stiffeners in way of transverse floors, under stool spaces of ballast
holds.
▪ Check Bilge well underside and bracket connection to longitudinals.
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 14 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 15 of 45
▪ Check ship side gussets (brackets) connection to side longitudinals and lower
hopper longitudinal. Also check the ship side gussets for any buckling/excessive
corrosion.
▪ Check ballast trunk access opening in the sloped plate for any possible cracks.
▪ Check drop valves recess & pipe connection to sloped plate, valve opening
extended spindle or hydraulic lines with the fastening.
▪ Check all sounding pipes and for hold bilges passing through topside tank. Check
for thinning around the U clamp fastening area due flexing. Check that none of
the clamps are loose.
▪ Scarphing arrangement in the topside tank adjacent to engine room and fore
peak.
▪ End brackets of all longitudinal to engine room bulkheads and collision bulkhead.
▪ Pitting corrosion under suction bell mouth if topside tanks are not connected to
double bottom tanks.
▪ Water tight division/bulkhead for excessive corrosion/buckling etc.
▪ Excessive corrosion at the lighting holes and for possible cracks.
▪ Check for general wastage. In case of doubt, few ultrasonic measurement should
be taken and recorded vis-a-vis the original thickness. Please mark the location
on the relevant plans
Peak Tank (Inspection Guidelines)
Fore Peak Tank
▪ The scarphing arrangements at collision bulkhead in top and bottom of the tank.
▪ Connection of transverse webs to side longitudinals by horizontal flat bar.
▪ Cracks or severe thinning in way of slots horizontal stringer plating.
▪ Cracks in way of lighting holes on the stringers.
▪ Cracks at toe of web frames bracket connection to stringer deck top and also
under side.
▪ Cracks at the end of faceplates of the stringer platforms.
▪ Cracks in way of flat bars sniped toe on the stringer platforms.
▪ Check for any buckling of center swash bulkheads, breast hooks etc.
▪ All pipe lines and ballast valves with associated extended spindles.
▪ Check shell plating in way of ballast suction bell mouth for pitting.
▪ Check condition of sounding pipes and conduit pipe and fastening U clamps for
tightness.
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 16 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 17 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 18 of 45
Piping Arrangements
▪ Check vent pipes.
▪ Check sounding pipes for wastage due to corrosion, and wear due to rubbing
around the clamps. Check “U”-clamps and nuts.
▪ Check hold temperature pipes.
▪ Check hold cleaning eductor pipes.
▪ Check pipe guards.
Hold Access
▪ Check vertical and Australian ladders.
▪ Check intermediate platforms and stanchions.
General nomenclature of BULK CARRIER
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 19 of 45
MID-Ship Section
STRUCTURAL DAMAGE AND DETERIORATION PRONE AREA
Top Side Tank – Potential Problem Areas
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 20 of 45
Fractures in the connection of hopper sloping plating to tank top and longitudinal to
bulkhead
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 21 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 22 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 23 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 24 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 25 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 26 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 27 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 28 of 45
MID-Ship Section
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 29 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 30 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 31 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 32 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 33 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 34 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 35 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 36 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 37 of 45
MID-Ship Section
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 38 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 39 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 40 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 41 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 42 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 43 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 44 of 45
Rev No. : 5
Annex 1 Date : 15-May-22
GUIDELINES ON HULL STRUCTURE INSPECTION Page : 45 of 45
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 1 of 17
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 2 of 17
CONTENTS
General.......................................................................................................................................................... 3
Preparation for Surveys ............................................................................................................................ 3
Annual Surveys.............................................................................................................................................. 3
Annual Surveys for Hull, Equipment, Fire Extinction and Fittings ............................................................ 3
General Examination................................................................................................................................. 4
Performance Test ...................................................................................................................................... 6
Internal Examinations of Spaces and Tanks .............................................................................................. 9
Docking Survey ............................................................................................................................................ 11
Requirements for Docking Surveys ......................................................................................................... 11
Boiler Survey ............................................................................................................................................... 12
Requirements of Boiler Survey ............................................................................................................... 12
CARGO GEAR SURVEY ................................................................................................................................. 13
CARGO GEAR RETESTING/RENEWAL SURVEY ......................................................................................... 14
Remote Surveys………………………………………………………………………………………………………………………………15
TECHNICAL MANUAL
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 3 of 17
GENERAL
Ship at all time is to be in compliance with Class and Statutory requirements. Surveys are to arranged
well in advance prior to the expiry date. Preparing ad presenting ship in a methodical way will save time
and money.
Prior to the commencement of survey and measurement, a survey planning meeting is to be held by the
surveyor(s), the owner s representative, the thickness measurement company representative, where
involved, and the master of the ship or an appropriately qualified officer of the ship appointed by the
master, ship owner or Company so as to ensure the safe and efficient conduct of the survey and
measurement work to be carried out.
ANNUAL SURVEYS
ANNUAL SURVEYS FOR HULL, EQUIPMENT, FIRE EXTINCTION AND FITTINGS
Examination of Plans and Document
Item Examination
Loading Manual Confirmation that approved manual is available
Stability Information Confirmation that approved manual is available
Booklet
Damage Control Plan, For ships required to have the damage control plan on board, confirmation
Booklet and Damage that the approved plan is exhibited and the booklet containing the
Stability Information information shown in the plan and the damage stability information are
kept on board.
Fire Control Plan Confirmation that the fire control plan is exhibited and properly stored is to
be made.
Operating and For ships required to have the manual and notices on board
Maintenance Manual • Confirmation that the manual is kept on board is to be made.
for the door and inner • Confirmation that the board is exhibited is to be made.
door and notices
TECHNICAL MANUAL
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 4 of 17
Item Examination
indicating procedures
for closing and securing
Instruction Manuals for For ships required to have the manual on board
the Inert Gas System • Confirmation that the manual is kept on board.
Towing and Mooring Confirmation that the Towing and Mooring Fitting Arrangement Plan is kept
Fitting Arrangement on board.
Plan
Ship Structure Access For ships required to have the manual on board, confirmation that the
Manual manual is kept on board and updated as necessary is to be made.
Documents related to Confirmation that the documents are kept on board.
the surveys for bulk
carriers, oil tankers and
ships carrying
dangerous chemicals in
bulk with integral tanks
Coating Technical File Confirmation that the files are kept on board and that maintenance and
and/or Corrosion repair work are properly recorded and kept on the files.
Resistant Steel
Technical File
Noise survey report For ships required to have the manual on board ,Confirmation that the
report is kept on board
GENERAL EXAMINATION
Item Examination
Shell plating Confirmation that areas visible above the load waterline are in good
Weather deck plating condition
Openings on deck and Confirmation that the following are in good condition: coamings and closing
outside of the hull appliances of hatchways and flush deck openings on the exposed deck and
within unenclosed superstructures; gangway ports, cargo ports and coal
ports; and side scuttles below the freeboard or superstructure deck.
Casings of engine room Confirmation that the following are in good condition: exposed engine
casings and their openings; and skylights of the engine room and boiler
room and their closing appliances.
Ventilators Confirmation that coamings and closing appliances of ventilators to spaces
below the freeboard deck or within enclosed superstructures are in good
condition.
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 5 of 17
Air pipes Confirmation that the air pipes on weather deck and their closing
appliances are in good condition
Watertight bulkhead, Confirmation that watertight doors, penetrations and stop valves on
superstructure end watertight bulkheads, and closing appliances of openings in superstructure
bulkhead and end bulkheads, deckhouses or companions protecting hatchways giving
deckhouses access to spaces below freeboard deck are in good condition.
Load line marks Confirmation that deck line and load line markings are appropriate.
Bulwark Confirmation that bulwarks and the shutters of its freeing ports; and hinges
and guard rails are in good condition.
Means of access Confirmation that permanent gangways or other means of access are in
good condition.
Scuppers, inlets, other Confirmation that all areas which can be examined are in good condition.
discharge pipes and
valves
Securing arrangement Confirmation that securing arrangement for on-deck timber including eye
for on-deck timber plates, lashing wires, etc. is in good condition regardless of timber
freeboard markings.
Anchoring and mooring Confirmation that the anchoring and mooring arrangements including their
arrangement accessories are in good condition as far as can be seen.
Fire extinguishing Confirmation that the fire extinguishing arrangement is in good condition
arrangement and the fixed fire extinguishing system, semi-portable and portable fire
extinguishers, fireman s outfits and emergency fire pumps are maintained
in good order.
Fire protection Confirmation that no alteration has been made to these arrangements
arrangement and since the last survey
means of escape
Towing and mooring Confirmation that the mark of Safe Working Load (SWL) on towing and
fittings mooring fittings of ships required to have markings and is clearly visible and
these fittings are in good condition
Emergency towing Confirmation that the emergency towing arrangement of ships, is in good
arrangement condition
Loading computer Confirmation that the computer of ships is maintained in good order.
Ship Identification Confirmation that the markings of the ship s identification number for ships
Number required to be so marked are in good condition.
Means of embarkation Confirmation that the means of embarkation and disembarkation are in
and disembarkation good condition
Bow doors, inner Confirmation that the bow doors, inner doors, side shell doors and stern
doors, side shell doors doors are in good condition
and stern doors
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 6 of 17
Additional Requirement for Tankers, Ships Carrying Dangerous Chemicals in bulk and Ships Carrying
Liquefied Gases in bulk
Item Examination
Piping Confirmation that cargo oil, fuel oil, ballast, vent pipes including vent masts
and headers, inert gas pipes and all other piping in cargo pump room, cargo
compressor rooms and on weather decks are in good condition
Additional Requirement for Bulk Carriers / General Cargo ships over 10 years of age
Item Examination
Piping in the cargo Confirmation that all piping and penetrations in cargo holds, including
holds overboard piping, are in good condition.
PERFORMANCE TEST
Item Examination
Weathertight hatch • Hose test (when deemed necessary by the Surveyor)
covers • Random checking of the satisfactory operation of mechanically
operated hatch covers including hydraulic and power components,
wires, chains and link drives
• For mechanically operated hatch covers on bulk carriers, hatch
cover sets within the forward 0.25Lf and at least one additional set,
including hydraulic and power components, wires, chains and link
drives, are to be checked for satisfactory operation so that all sets
on the ship are checked at least once every 5 years between special
surveys
Closing appliances of • Checking whether the appliances work in good order is to be made
watertight door on as deemed necessary by the Surveyor.
watertight bulkheads • Hose tests or equivalent tests are to be carried out. Such tests may
and openings on be dispensed with at the discretion of the Surveyor.
superstructure end
bulkheads, deckhouses
or companions
protecting hatchways
giving access to spaces
below freeboard deck
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 7 of 17
Item Examination
Appliances related to Checking whether the appliances work in good order is to be carried out.
fire protection and
escape
Fire detection system Checking whether the systems work in good order (including proper
and fire alarm system operation of malfunction indicator) is to be made.
including manually
operated call points
Fire pumps (including Performance test of the fire fighting system composed of fire pump,
emergency fire pumps) hydrants, etc. is to be carried out. For ships with fire pumps in periodically
piping, hydrants, hoses, unattended machinery spaces, an operation test of the remote control
nozzles etc. system or automatic operation system of one pump is to be carried out.
Fixed deck foam Checking whether the system works in good order is to be carried out by
system delivering water.
Ventilation system Checking whether the system works in good order is to be carried out.
Stability Computer A performance test is to be carried out on computers for stability
calculation that are installed as a supplement to the stability information
booklet on board ships contracted for construction
Water level detection Checking whether the systems work in order is to be made at random
and alarm systems
Dewatering Checking whether the systems work in order is to be made
arrangements
Bow doors, inner • Checking whether the appliances work in good order is to be
doors, side shell doors carried out.
and stern doors • Hose test (when deemed necessary by the Surveyor)
Shut-off devices for oil Operation tests for the remote shut-off devices for fuel oil tanks and
tanks lubricating oil tanks are to be carried out
Fuel oil pumps, cargo Operation tests for emergency stopping means are to be carried out.
pumps, ventilating fans
and boiler draught fans
Emergency electrical Operation tests for the emergency source of electrical power and its
power source associated equipment are to be carried out in order to ascertain that the
whole system is in good working order. Automatically operated equipment
is to be tested in the automatic mode.
Communication Operation tests for the means of communication between the navigation
systems bridge and the machinery control position and between the navigation
bridge and the steering gear compartment are to be carried out
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 8 of 17
Item Examination
Steering gears Performance tests specified in the following (a) to (e) are to be carried out
for the main and auxiliary steering gears including their associated
equipment and control systems
(a) Operation test for the power units including changeover from one to
another
(b) Operation test for automatic and remote isolation of the power
actuating systems
(c) Test for supply of the alternative source of power
(d) Operation test for the control system including the changeover system
(e) Operation test for the alarm devices, rudder angle indicators and
running indicators of power.
Bilge systems Operation tests for the valves (including ones for emergency use), cocks,
strainers, pumps, reach-rods and level alarms of the bilge systems are to be
carried out.
Safety devices Operation tests for the safety devices, etc. specified in the following (a) to
(d) are to be carried out. However, the tests may be omitted at the
Surveyor s discretion based on the general examination, reports of working
conditions at sea and inspection records taken by the ship s crew.
(a) Main propulsion Operation tests of the following safety/alarm devices on prime movers of
machinery and main propulsion machinery; electric generators; auxiliary machinery
auxiliary machinery essential for propulsion; and auxiliary machinery for manoeuvring and crew
safety are to be carried out. Where deemed necessary by the Surveyor, the
maintenance records of the cooling water and lubricating oil are required to
be presented for review.
(i) Overspeed protective devices
(ii) Automatic shut-off and alarm devices in case of loss or low
pressure of the lubricating oil
(iii) Automatic shut-off devices in case of abnormally low pressure
of the main condenser vacuum for main steam turbines
(b) Boilers, thermal oil Operation tests for the safety devices, alarm devices and pressure
heaters and indicators are to be carried out. Calibration records for the pressure
incinerators indicators are to be ascertained and the relieving gears of the safety valves
are to be examined and tested to verify satisfactory operation. However,
the relief valves provided on the exhaust gas economizers are to be tested
by the Chief Engineer at sea prior to the Annual Survey within the period.
This test is to be recorded in the logbook for review by the attending
surveyor. Where deemed necessary by the Surveyor, the control records of
the boiler water and thermal heater oil are required to be presented for
review.
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 9 of 17
Item Examination
(c) Monitoring devices Operation tests for pressure indicators, thermometers, ammeters,
voltmeters and revolution meters are to be carried out.
(d) Automatic control Operation tests for automatic and remote control devices of auxiliary
devices or remote machinery essential for propulsion, manoeuvring, and crew safety are to be
control devices carried out.
Additional Requirements for Tankers and Ships Carrying Dangerous Chemicals in Bulk
Item Examination
Cargo pumps, bilge Operation tests for the remote control systems and shut-off devices of the
pumps, ballast pumps, pumps installed in cargo pump rooms are to be carried out.
stripping pumps and
ventilators
Bilge systems Operation tests of the bilge systems installed in cargo pump rooms are to
be carried out
Level indicators Operation tests of level indicators used in cargo tanks are to be carried out
Pressure indicators Operation tests of pressure indicators installed in cargo discharge lines are
to be carried out.
Inert gas systems Inert gas systems are subjected to the following tests. Other inert gas
systems are to be examined as deemed appropriate by the Society.
(a) Operation tests of the inert gas blowers and scrubber room ventilation
systems
(b) Function tests of the water seals or general examinations of double-
block and bleed valves and the non-return valves
(c) Operation tests of the remotely operated or automatically controlled
valves
(d) Operation tests of the interlocking system between the soot blowers
and the shut-off valves on gas supply line
(e) Operation tests of the measuring devices, alarm devices and safety
devices
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 10 of 17
Item Examination
Ballast tanks For ships over 5 years of age, an internal examination of the tank(s), of
which an internal examination is required as a consequence of the last
intermediate Survey or special survey, is to be carried out.
Requirements for Tankers, Ships Carrying Dangerous Chemicals in bulk and Ships Carrying Liquefied
Gases in bulk
Engine room and boiler An internal examination is to be carried out
room
Cargo pump rooms, An internal examination is to be carried out after the areas are thoroughly
other pump rooms cleaned out and free of gas. Attention is to be paid to the sealing
adjacent to cargo arrangements of all penetrations of bulkheads, ventilating arrangements,
tanks, cargo foundations and gland seals of pumps and compressors.
compressor rooms and
cargo pipe tunnels
Ballast tanks For oil tankers, ships carrying dangerous chemicals in bulk with integral
tanks and ships carrying liquefied gases in bulk over 5 years of age, an
internal examination of the tank(s), of which an internal examination is
required as a consequence of the last intermediate Survey or special
survey, is to be carried out.
Requirements for Bulk Carriers other than Double Skin Bulk Carriers
Engine room and boiler An internal examination is to be carried out
room
Ballast tanks For bulk carriers over 5 years of age, an internal examination of the tank(s),
of which an internal examination is required as a consequence of the last
Intermediate Survey or Special Survey, is to be carried out
Cargo holds For bulk carriers over 10 years of age, an internal examination of all cargo
holds is to be carried out.
Requirements for Double Skin Bulk Carriers
Engine room and boiler An internal examination is to be carried out.
room
Ballast tanks For bulk carriers over 5 years of age, an internal examination of the tank(s),
of which an internal examination is required as a consequence of the last
Intermediate Survey or Special Survey, is to be carried out.
Cargo holds • For bulk carriers over 10 years and up to 15 years of age, an
internal examination of two selected cargo holds is to be carried
out.
• For bulk carriers over 15 years of age, an internal examination of all
cargo holds is to be carried out.
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 11 of 17
DOCKING SURVEY
In-water Surveys may be accepted in lieu of Surveys in the dry dock or on the slipway subject to prior
approval by the Society. In any case, Surveys in the dry dock or on the slipway to be carried out at the
times specified in (1) or (2) are not to be replaced with In-water Surveys. Except where expressly
approved by the Administration, consecutive In-water Surveys should not be accepted in lieu of Surveys
in dry dock or on slipway carried out. Enhanced Survey Programme (abbreviated to ESP) (2) Docking
Surveys carried out for ships with the class notation Enhanced Survey Programme (abbreviated to ESP),
all of which are 15 years of age and over.
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 12 of 17
Item Examination
Sealing devices for In the case of oil or freshwater lubricated stern tube bearings, the efficiency
stern tube and shaft of the oil or freshwater gland is to be checked.
bracket bearing
Propeller Propellers are to be examined. Where a controllable pitch propeller is
fitted, the pitch control device is to be examined without dismantling
Anchor, anchor chain, At the Docking Surveys anchor and anchor chains are to be ranged and all
ropes, hawse pipe, chains and chain related equipment are to be verified and externally
chain locker and cable examined. In cases where In-water Surveys in lieu of Docking Surveys
clenches anchors and anchor chains may not be required to be ranged and examined
at the discretion of the Society provided they were examined (including
visual inspection by diver) and found to be in good order. In such cases,
anchors and anchor chains should be ranged and all chains and chain
related equipment should be verified and externally examined at the next
Docking Surveys conducted in dry dock or on slipway. At Special Survey
No.2 and subsequent Special Surveys, the diameter of the anchor chain is to
be measured. If the mean diameter of a link, at its most worn part, is
reduced by 12% or more from its required nominal diameter, it is to be
renewed.
Tanks and spaces The internal examination, close-up surveys and thickness measurements
are to be carried out as stipulated below.
(i) At Docking Surveys in the dry dock or on the slipway carried out
in conjunction with Special Surveys at least the portions below
the light ballast water line of the cargo holds/tanks and water
ballast tanks
(ii) At Docking Surveys
BOILER SURVEY
REQUIREMENTS OF BOILER SURVEY
Item Examination
Pressure parts of To be internally examined with the manholes, cleaning holes and inspection
boilers holes dismantled. Where considered to be necessary for external
examination by the Surveyor, the parts are to be examined to the Surveyor
satisfaction with the insulation around the parts removed
Super heaters, To be examined internally and externally. For exhaust gas economizers of
economizers and the shell type, all accessible welded joints are to be subject to a visual
exhaust gas examination for cracking and non-destructive testing may be requested
economizers where deemed necessary by the Surveyor
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 13 of 17
Item Examination
Combustion parts of The furnaces, combustion chambers, combustion gas chambers, etc. are
boilers and thermal oil internally examined with their doors opened
heaters
Valves and cocks The principal mountings and their fastening bolts or studs are to be opened
up and examined
Thickness of plates and To be measured where deemed necessary by the Surveyor
tubes and size of stays
Safety valves and The safety valves are to be adjusted under steam to a pressure not more
relevant parts of than 103 % the approved working pressure after the open-up examination.
boilers, superheaters The pressure gauge used for this adjustment is to be calibrated properly.
and thermal oil heaters The relieving gears of the valves are to be examined and tested to verify
satisfactory operation. However, for exhaust gas economizers, if steam
cannot be raised at port, the relief valves may be set by the chief engineer
at sea, and the results recorded in the logbook for review by the Surveyor.
The general conditions of relief pipes for thermal oil heaters are to be
examined. The popping pressure of safety valves fitted on thermal oil
heaters is to be ascertained
Safety devices, alarm These devices examined to ascertain that they are in good working
devices and automatic conditions after the above examinations
combustion control
devices
Review of the records Review of the following records since last boiler survey is to be carried out.
of the logbook • Operation
• Maintenance
• Repair history
• Quality control of the feed water or thermal oil
CRANES: Visually inspected the crane structure for deformation, excessive wear, corrosion, and
damage or fractures. Crane boom was lowered for examination. Crane hooks were visually
examined for deformation, excessive wear or fractures. Crane hooks were subjected to NDT (for
personnel lifting cranes and offshore cranes only). A visual exam and operational test was
carried out of the crane machinery including prime movers, clutches, brakes, hoisting, slewing
and luffing machinery. The wire rope including end attachment was visually examined for
excessive wear, corrosion, flattening, kinks, strand separation, core failure or other defects. The
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 14 of 17
slewing ring assembly was examined for slack bolts, damaged bearings and deformation or
fractured weldments. Rocking test results were reviewed, which are to be taken in accordance
with bearing manufacturer’s instructions. Function tests were conducted for the main and
auxiliary load hoisting and lowering, crane boom raising and lowering, slewing (swinging), safety
protective (fail-safe) and limiting devices, and load and crane boom angle or radius indicators.
CONVENTIONAL BOOMS: All structural parts, including winches, booms, stayed masts, pins and
connections, wire ropes, chains, rings, hooks, links, swivels, and blocks were visually examined.
Replacement wire rope was supplied with manufacturer's certificate conforming to the
construction type, size, and minimum breaking strength specified in the load diagram design
data.
2. Post test examination of all gear carried out as follows and found satisfactory.
CRANES: Examined each crane, together with all critical accessories, including foundation,
sheaves and rope guides, wire ropes including end connections, hoist machinery, brakes and
clutches, hooks, slewing ring assembly and bolting arrangements for slack bolts, damaged
bearings, and deformed or fractured weldments. Rocking test and grease samples taken, and if
bearing wear is indicated, the bearing to be internally examined. Based on the age of the crane,
a representative sample of the slewing ring assembly bolts is to be removed and examined by a
suitable nondestructive testing method. Upon completion of proof tests: (1) pedestal critical
butt welds and pedestal/slew ring transition pieces subjected to volumetric NDT, and (2) critical
fillet welds in the pedestal and transition pieces subjected to NDT (for offshore cranes only).
CONVENTIONAL BOOMS: Examined all cargo gear, with the whole of the gear accessory thereto,
including all chains, rings, hooks, links, shackles, swivels, pulley blocks or other loose gear for
damage or permanent deformation.
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 15 of 17
REMOTE SURVEYS
View the uncertainties due to the Covid 19 pandemic and restricted attendance by Class
Surveyors, some of the surveys may be done by remote means.
Remote surveys may be used as an alternative to physical inspection on board. It involves
direct interaction between the nominated Class Surveyor and the ship staff by employing
remote inspection techniques. Such a survey can be carried out wherever the ship is
located.
Classification societies have clear guidelines/procedures regarding the conduct of remote
surveys.
One of the requirements is that the Company has a procedure in place in their SMS for
the conduct of a remote survey.
APPLICABILITY
Eligibility of the remote survey is to be decided based on type and scope of the requested
survey, in accordance with the below list. It is subject to Flag permission in case of
statutory items and when the Society is carrying out the statutory survey on behalf of the
flag State Administration.
A remote survey is deemed eligible when it provides the same level of assurance, as if it
was conducted with attendance on board by the Surveyor.
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 16 of 17
SURVEY PROCESS
1. The Company will apply for the remote survey as per the requirements of the Class
society. The nominated Surveyor will review the survey request and decide the
means of hardware/software to conduct the surveys in direct co-ordination with the
ship. The means include live streaming of audio-visual data through video
conferencing, trend analysis etc. Depending on the scope of survey, the means of
inspection may also include the use of divers, unmanned robot arm, remote
operated vehicles (ROV), climbers, drones, thickness measurement/ultrasonic
testing machines, vibration meters and other means acceptable to the Class society.
2. The Company will provide the required devices to the ship staff to be used as per
the Surveyor’s requirement and instructions. Specialized devices which require a
qualified operator will be decided on a case-by-case basis.
3. The use of the above devices will be subject to safety considerations of the vessel
and the local port regulations.
Rev No. : 1
Annex 02 Date : 15-May-22
CLASS SURVEY REPORT Page : 17 of 17
4. The Surveyor will be in direct contact with the ship staff to obtain the necessary
information or documents by email, telephone/video calls.
5. An opening meeting will be held between the Surveyor and the ship by video
conferencing to decide the scope of survey, the extent of inspection and the data
required by the Surveyor. All exchange of data is to be done in an environment
which does not pose a cybersecurity risk to the ship.
6. The nominated person onboard will collect and provide all the data as directed by
the Surveyor. In case specialized devices are used, the qualified operator will do this
task. Based on his analysis of the data provided, the Surveyor will determine the
result and convey it in the closing meeting.
7. All electronic data transmitted must have an accurate time stamp.
8. The live videos must have sufficient resolution with quality of images to the
Surveyor’s satisfaction.
9. If the Surveyor determines that the data provided by the devices is of poor quality
or is insufficient to make a judgement, the remote survey may be cancelled.
10. In such case, the Company will arrange for a re-inspection by onboard attendance
at a feasible port.
"Safety Critical" - an individual piece of equipment, a control system or an individual protection device which in the event of
a single point of failure (SPOF) may:
- Result in a hazardous situation which could lead to an accident.
- Directly cause an accident that results in harm to people, the ship itself and/or the environment. (loss of containment)
The "Safety Critical" mandatory spares list is to be drawn vessel specific by the Ch/Engr & Tech Supt, and approved by the office.
The approved "Safety Critical" spares list is not a static document and needs to be reviewed for additions frequently.
EQUIPMENT
SPARES UNIT MIN QTY REQD
Main Engine Crank case - Oil Mist Detector Photocell / Detector Head Pcs 1
(OMD) Filters / Sintered Bronze Filter Set 1
Main Engine Safety Shutdowns LO Low pressure trip relay Pcs 1
Shut Down Solenoid Pcs 1
Overspeed Trip relay Pcs 1
Shut Down Solenoid Pcs 1
Main Engine - Main Components Piston Assembly Complete Set 1
Piston Ring Set 2
Gaskets & packings for unit overhaul Set 2
Cylinder Liner Pcs 1
Starting Air valve Pcs 1
Exhaust Valve Set 2
Cylinder Cover Set 1
Indicator Cock Pcs 1
Fuel Valve Pcs 6
Fuel Oil High Pressure Pipes Pcs 1
Exhaust Valve High Pressure Pipes Pcs 1
Fuel pump Plunger & Barrel Set 1
Fuel pump valves & springs Set 1
Connecting Rod Bearing Set 1
Crosshead Bearing Set 1
Bottom End Bearing / Crank pin Bearing Set 1
Thrust Bearing Segment Set 1
Chain drive Set 1
Cylinder Lubricator Set 1
Stern Tube Bearing Temperature Temperature Sensor Probe Pcs 1
ME- Engines: Engine Control System CCU Multi-Purpose Controller (MPC) Pcs 1
Multi-way valve (ELFI) Pcs 1
FIVA valve Pcs 1
HPS pressure transducer Pcs 1
Proportional Valve for Hyd pump Pcs 1
Hydraulic hoses (vessel specific) Set 1
RT-FLEX- Engines: Engine Control System ALM Module Set 1
Power supply unit for E95 Pcs 1
PCV for IFA Set 1
Hydraulic hose for Fuel rail Pcs 1 each
Hydraulic hose for servo rail Pcs 1 each
Pulse lubricating pump Unit Pcs 1
Steering gear & Hydraulic telemotor system Alarm relays Pcs 1
(Isolation System & alarms), Emergency Steering Filters (Suction) Pcs 1
Filters (Return Line) Pcs 1
Actuator repair kit Set 1
Solenoid Valve Pcs 1
Pump - Motor Coupling /Chain Coupling /Spider
Set 1
Coupling
Gaskets & O-Rings or V-Packing for Cyl Ram Set 1
Emergency Diesel Generator & Switchboard Cartridge Oil filter Set 1
1 of 3
Original : Vessel File Rev No: 0
Copy : Synergy Date : 15-May-22
Annex 3
List of Minimum Mandatory Safety Critical Spares
3 of 3
Original : Vessel File Rev No: 0
Copy : Synergy Date : 15-May-22
ANNEX 4
GENERIC LIST OF COMPLIANCE
CRITICAL SPARES
"Compliance Critical"- an individual piece of equipment, a control system, an individual protection device or a spare part which in the
event of a failure may:
- Result in Environmental damage. (violations & non-compliance)
- Result in non-compliance with the requirements of various IMO Conventions such as SOLAS, MARPOL, Load Line, BWMC, MLC etc
- Result in intervention by PSC/Flag State and affect the outcome of external inspections/audits
The "Compliance Critical" spares list is to be drawn vessel specific by Ch/Engr & Tech Supt, and approved by the office.
1 of 3
Original : Vessel File Rev No: 0
Copy : Synergy Date : 15-May-22
ANNEX 4
GENERIC LIST OF COMPLIANCE
CRITICAL SPARES
2 of 3
Original : Vessel File Rev No: 0
Copy : Synergy Date : 15-May-22
ANNEX 4
GENERIC LIST OF COMPLIANCE
CRITICAL SPARES
3 of 3
Original : Vessel File Rev No: 0
Copy : Synergy Date : 15-May-22
ANNEX 5
GENERIC LIST OF
BUSINESS SENSITIVE SPARES
"Business Sensitive"- an individual piece of equipment, a control system, an individual protection device or a spare part which in the
event of a failure may:
- Result in restricting /degrading the smooth operations of the vessel
- Result in major commercial impact
The "Business Sensitive" spares list is to be drawn vessel specific by Ch/Engr & Tech Supt, and approved by the office.
*Note: There are mandated items in this list, which please see below the table
1 of 5
Original : Vessel File Rev No: 0
Copy : Synergy Date : 15-May-22
ANNEX 5
Windlass
GENERIC LIST OF
BUSINESS SENSITIVE SPARES
5 of 5
Original : Vessel File Rev No: 0
Copy : Synergy Date : 15-May-22
TECHNICAL MANUAL
Rev No. : 2
Date : 15-Dec-22
APPENDIX 01 – CE’S STANDING ORDER BOOK Page : 1 of 7
Rev No. : 2
Date : 15-Dec-22
APPENDIX 01 – CE’S STANDING ORDER BOOK Page : 2 of 7
Rev No. : 2
Date : 15-Dec-22
APPENDIX 01 – CE’S STANDING ORDER BOOK Page : 3 of 7
Evening and Morning walk rounds of the machinery spaces are to be carried out during
unmanned periods.
Where fitted, the Deadman system must be switched ON when entering the ER during
UMS operation (set at 15 minutes). The duty engineer must also inform the OOW
whenever entering the Engine Room or exiting after a UMS alarm call out.
LOOK, LISTEN, TOUCH, SMELL are all important qualities of a good Watch keeper. If in
any doubt, and before a situation gets out of control, do not hesitate to call for
assistance from the Chief or Second Engineer.
The Duty Engineer must be within audible or visual range of the UMS alarm system or a
UMS alarm extension at all times.
All alarms that occur while in UMS mode must be entered in the Log Book showing
clearly the alarm channel, description and time.
STAND-BY REQUIREMENTS:
During stand-by operations the engine room must be manned.
Call the Chief Engineer for every stand-by operation. Ensure the gear is tested in ample
time prior to stand by and arrival and departure checklists are completed accurately,
and the Engine Logbook is endorsed.
No maintenance work is to be carried out whilst on stand-by without prior permission of
the Chief Engineer. In congested waters use the dump controller to keep the boiler in
use at minimum fire, the consequences of failure by far outweigh any fuel savings.
Ensure all counters required are entered in the logbook for EOP and RFA. When using
the Movement Book, record steering motors on, generators in use, and whether the
steering gear, clocks and telegraph have been tested. The Main Engine may be in ECR
control or on bridge control and this fact is to be logged in the movement book. In the
event of any altercation with other vessels/obstructions the time of the event is to be
logged and all further movements are to be recorded manually, if necessary, call extra
personnel.
PUMPING OF BILGES:
To comply with regulations in MARPOL Annex 1, bilges are to be pumped out as follows:
• IN PORT-Pump wells to the bilge tank, sound the tank after each use. Bilge
overboard valves are to be locked shut and separator is not to be used.
Rev No. : 2
Date : 15-Dec-22
APPENDIX 01 – CE’S STANDING ORDER BOOK Page : 4 of 7
• RFA-Under normal circumstances when 12 miles or over off nearest land, pump
the bilges through the bilge separator. Always check with O.O.W. and enter
details in the Logbook & Oil Record Book.
The OIL RECORD BOOK IS TO BE KEPT UP TO DATE (Guidelines on how to record each
entry can be found in the oil record book and EMS manual).
NOTE: Prior to each OWS operation the alarm and overboard solenoid valve operation is
to be proved working.
BOILER OPERATION:
The remote water level gauges in the control room are for indication only and are not to
be relied upon when raising steam, blowing down etc. Any alarm or change in water
level is to be confirmed using direct mounted gauges.
Any oil in the gauge glasses is to be reported immediately to the Chief Engineer. When
flashing a boiler or after a flame failure it is essential to ensure the furnace is properly
purged prior to any attempt to ignite. The boiler management system should correctly
purge the furnace but must not be relied upon. Purging is to be monitored at all times,
after flame failures and when flashing from cold.
INCINERATOR OPERATION :
Ch 3.1.5 of the Environment & Energy Management System (EEMS) Manual is to be
referred for guidance on incinerator operation. In any case, incinerator operation must
always be under attendance and it is not to be operated during UMS periods.
STERN TUBE:
Remember that the temperature probe is located below the bearing surface and any
temperature indicated will be lower than the actual surface temperature. The slightest
deviation from normal taking into consideration the sea water temperature and main
engine operation must be considered serious and call me immediately.
INERT GAS SYSTEM (If fitted):
This system is to be monitored during cargo operations. Attention is to be paid to the
oxygen content of the inert gas and should be no greater than 5%.
BAD WEATHER EXCESSIVE MAIN ENGINE LOAD:
During inclement weather the power meter is to be monitored and the average must be
maintained at NCR, if not the engine speed is to be reduced until within range.
Ensure this is monitored and brought back to normal once the weather has eased.
Rev No. : 2
Date : 15-Dec-22
APPENDIX 01 – CE’S STANDING ORDER BOOK Page : 5 of 7
CARGO OPS:
Before start of cargo operation, each cargo related equipment is to be tested and
checked. In tanker vessels, cargo pump to be tested on CCR (Cargo Control Room)
remote trip prior to use before each cargo operation. Test to be recorded in the log
book.
Running hours of each cargo related equipment needs to be recorded. A close check on
the stuffing box and bearing temperatures is to be maintained.
BUNKER OPS:
Before start of Bunker operation, all bunker tanks are to be tested and checked.
Technical manual chapter 5 section 5.1 related to Bunkering operation to be followed,
relevant readings recorded in the logbook.
FUEL CHANGEOVER :
Fuel changeover is to be carried out as per approved ship specific procedure. Reference
is made to Ch 7 of the Fuel Management Plan for guidance.
FIRE DETECTION:
Zones are only to be isolated when absolutely necessary. They are to be reinstated as
soon as work is completed. Bridge must be informed.
Minimum isolation only – restricted to only those areas where there is a realistic chance
of a fire detector being activated.
All personnel to be aware of State of readiness of on-board fire-fighting equipment and
procedure to follow if alarm is raised.
GAS DETECTION: (APPLICABLE FOR ENGINE CONSUMING LNG AS FUEL):
The gas monitoring system is fitted on board and operated continuously while the ship
is in service which is composed of fixed gas detectors and fixed gas sampling points.
In the event of gas detection, alarms are activated simultaneously at the ICMS stations
on the wheelhouse, cargo control room and engine control room, and on the repeater
units in the wheelhouse and engine control room.
ATMOSPHERIC EMISSIONS:
The IMO annex VI requirements or subsequent amendment shall apply to all smoke
emissions from vessels, unless more stringent local regulations are applicable.
Rev No. : 2
Date : 15-Dec-22
APPENDIX 01 – CE’S STANDING ORDER BOOK Page : 6 of 7
Funnel smoke indicators, if installed must be kept fully operational. Great care must
always be taken to control the emission of any smoke.
DEFECT REPORTING:
All defects must be reported to the Second Engineer and entered into the Ship Palm
system in a timely manner.
The following items are required by class to be kept up to date:
a. The planned maintenance period routines
b. The planned maintenance monthly routines
c. The planned maintenance weekly routines
d. The condition monitoring system (Latest update of vibration report)
e. Unscheduled maintenance work must be entered into the system together
with correct function number. A wok under order should be created and
issued prior to the maintenance,
f. Monthly alarm prints out sheets to be kept for one year (The check list must
be updated daily by the duty Engineer).
All of the following must be recorded in the ER logbook as well as in Ship Palm:
Generator trips, quick closing valves, boiler trips, emergency stops, steering gear 3
monthly test, M.E on local control test, M.E alarms & trips tests.
NOTE: The date in Ship Palm must match log book date.
GENERAL:
No alteration to alarm set points, instrumentation settings, proportional band / reset
etc. without the permission of the Chief Engineer with all changes recorded.
Second Engineer along with other Engine room stay should finalise the list of repair
work to be carried out during stay in port. All planned/unplanned job should be entered
in Daily work planner. Indicator lamp checks are to be carried out daily and EO to ensure
adequate stock levels.
The designated location for hot work is the engine room w/shop. All hot work and cold
work to be done in the engine room is subject to the Permit to Work system as
described in Ch 02 of the Health and Safety Manual (HSM).
You are expected within reason, to clean up your own working area on completion of
maintenance.
Rev No. : 2
Date : 15-Dec-22
APPENDIX 01 – CE’S STANDING ORDER BOOK Page : 7 of 7
The welding workshop is a designated hot work area and as such should be kept clear of
combustible materials at all times. Any other hot work you require the appropriate
permit. All welding and gas equipment is to be shut off when hot work is finished or
stopped.
No Notices are to be put up without the permission of the Chief Engineer.
Oil gauge glass clamps are only to be used on storage tanks when topping up oil sumps
and filling. At any other time, they are to be kept by the Second Engineer in a locked
cupboard. Under no circumstances is any form of clamping arrangement to be in use at
any other time.
Makers’ manuals are to be checked prior to any maintenance being carried out. There
are 2 copies onboard (1 working and 1 master), inform the Chief Engineer if any are
missing and a copy will be requested.
It is the responsibility of each engine room staff to check and ensure company’s work
and rest hours policy is followed without any compromise. Same to be recorded in ISF
Watchkeeper software.
In case of black-out, all engine room staff should maintain calm and restore back ship as
per checklist.
Personal individual computer files are not considered good practice to keep for
unplanned work or maintenance histories. Apart from your handover notes ALL
maintenance details are to be kept in Ship Palm. Likewise, any common files should be
kept on shared drives only and not on your personal desktop. On your desktop create a
shortcut to the specific file in the shared drive.