Scala
Scala
Tel 04 473 7935 Freephone 0800 500 460 Fax 04 473 8621
PO Box 27-204 Wellington 6141, New Zealand. Email [email protected] Web www.triginstruments.co.nz
Scope
This test is used to measure the in situ penetration resistance of soils by means of a dynamic cone
penetrometer. It is limited to fine grained materials. The results may be used to estimate the field CBR
of cohesive soils.
Procedures: There are two main ways to think about the test: blows per distance, or distance per
blow.
For Foundations.
For testing the site of building foundations to NZ Standard 3604 the approach is to count how many
blows per 100mm up to 300mm of penetration. This can be done by watching the graduations on the
rods (i.e. not using a tape measure or rule).
For Layers
The penetrometer readings will also identify the upper and lower positions of layers of different
strengths.
Safety: Is there any gas, water, electricity or telephone service where you are testing?
NZ Standard: Working to NZS 3604 you may set the penetrometer cone in a probe hole augured for
the purpose, but in this case you do not count any hammer blows until the cone tip is 300mm below
the top of the hole.
If you are working to NZS 3604 and using a tape measure or metre rule you should measure from a
board placed on the ground.
In any case when you are measuring from the ground up, once the cone is bedded in this measure is
your depth at zero blows.
Measure from the ground or board to a reference point on the penetrometer such as the bottom of the
anvil.
(d) Raise the hammer to its upper stop at the handle and let it drop to the anvil.
If you keep hammering with so little penetration you are likely to break something, there may be an
obstruction. If you think there is likely to be an obstruction, move the test area a little and start again.
There might be a very hard top layer with softer ground underneath. More investigation may be
required. You can still do the penetrometer test on the softer layer, if one is found.
(e) Continue drops until a series of eight consecutive blows achieves less than 20mm depth.
Sometimes when a hard layer lies above a soft layer an extra blow will cause lot of penetration as the
cone breaks through to the soft layer. In this case the distance penetrated with this final blow should
not be considered with the reading for the hard layer: you should record the approximate depth of the
hard layer.
Take depth readings to the nearest 1mm for each blow or series of blows recording the depth and
number of blows.
The amount of depth achieved with a series of blows should not be more than 50mm. I.e. if you are
doing three blows and advancing 150mm between readings, that is too much distance between
recordings.
NZ Standard.
If you are working on a site for foundations to NZS 3604 the main consideration is how many blows
per 100mm.
The Standard says that the soil for the foundations is assumed to have a safe bearing pressure of
100kPa when:
(i) Three [blows per 100mm] down to a depth equal to the width of
the widest footing below the underside of the proposed footing.
Do not neglect the other common sense points in the standard, e.g. at the location of your tests there
should not be soft peat, organic soil or soft clay with gravel below the level of the proposed footings.
The following tables are for estimating CBR from penetrometer readings.
By convention reporting is as follows:
For CBR values of 5 or less – to the nearest 0.5 units
For CBR values of 5 to 20 – to the nearest whole number
For CBR values greater than 20 – to the nearest 5 units
Table 1: Field CBR Estimated from Scala Penetrometer
(Table From Country Roads Board)
Penetration In Millimetres Estimated Field CBR