Schedule Template

Uploaded by

jose cajas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Timeframe

Project Name

Work breakdown structure Duration Predecessor


1 Component
1.1 Product
1.1.1 Deliverable
1.1.1.1 Work package
1.1.1.1.1Activity Duration Predecessor
1.1.1.1.2Activity Duration Predecessor
1.1.1.1.3Activity Duration Predecessor
1.2 Product
1.2.1 Deliverable
1.2.1.1 Work package
1.2.1.1.1Activity Duration Predecessor
1.2.1.1.2Activity Duration Predecessor
1.2.1.1.3Activity Duration Predecessor
2 Component
2.1 Product
2.1.1 Deliverable
2.1.1.1 Work package
2.1.1.1.1Activity Duration Predecessor
2.1.1.1.2Activity Duration Predecessor
2.1.1.1.3Activity Duration Predecessor
2.2 Product
2.2.1 Deliverable
2.2.1.1 Work package
2.2.1.1.1Activity Duration Predecessor
2.2.1.1.2Activity Duration Predecessor
2.2.1.1.3Activity Duration Predecessor
3 Component
3.1 Product
3.1.1 Deliverable
3.1.1.1 Work package
3.1.1.1.1Activity Duration Predecessor
3.1.1.1.2Activity Duration Predecessor
3.1.1.1.3Activity Duration Predecessor

Recommendation:
Before filling out the template, complete the
network diagram with the post-it technique
involving the project's key interested parties.
meframe

Estimated cost

Estimated cost
Estimated cost
Estimated cost

Estimated cost
Estimated cost
Estimated cost

Estimated cost
Estimated cost
Estimated cost

Estimated cost
Estimated cost
Estimated cost

Estimated cost
Estimated cost
Estimated cost
Project Schedule

Educational Support

Work breakdown structure Duration Predecessor


1 Quality infrastructure
1.1 30 schools built
1.1.1 Construction companies contracted
1.1.1.1 Work package
1.1.1.1.1Activity Duration Predecessor
1.1.1.1.2Activity Duration Predecessor
1.1.1.1.3Activity Duration Predecessor
1.1.2 30 sites prepared
1.1.2.1 30 sites awarded
1.1.2.1.1Searching for sites 20 days -
1.1.2.1.2Selecting sites 5 days 1.1.2.1.1
1.1.2.1.3Awarding sites 10 days 1.1.2.1.2
1.1.2.2 Site preparation contracted
1.1.2.2.1Preparing TdRs 2 days -
1.1.2.2.2Bidding for works 15 days 1.1.2.2.1
1.1.2.2.3Selecting company 1 day 1.1.2.2.2
1.1.2.3 Site preparation program
1.1.2.3.1Agreeing on the sequence of the works 1 day 1.1.2.2.3
1.1.2.3.2Preparing works program 3 days 1.1.2.3.1
1.1.3 30 works concluded
1.1.3.1 Work package
1.1.3.1.1Activity Duration Predecessor
1.1.3.1.2Activity Duration Predecessor
1.1.3.1.3Activity Duration Predecessor
1.2 30 schools fitted out
1.2.1 Deliverable
1.2.1.1 Work package
1.2.1.1.1Activity Duration Predecessor
1.2.1.1.2Activity Duration Predecessor
1.2.1.1.3Activity Duration Predecessor
1.3 30 schools with maintenance
1.2.1 Deliverable
1.2.1.1 Work package
1.2.1.1.1Activity Duration Predecessor
1.2.1.1.2Activity Duration Predecessor
1.2.1.1.3Activity Duration Predecessor
2 Improving the quality of education
2.1 Product
2.1.1 Deliverable
2.1.1.1 Work package
2.1.1.1.1Activity Duration Predecessor
2.1.1.1.2Activity Duration Predecessor
2.1.1.1.3Activity Duration Predecessor
3 Support for and acceptance of the project
3.1 Product
3.1.1 Deliverable
3.1.1.1 Work package
3.1.1.1.1Activity Duration Predecessor
3.1.1.1.2Activity Duration Predecessor
3.1.1.1.3Activity Duration Predecessor
4 Support for and acceptance of the project
4.1 Product
4.1.1 Deliverable
4.1.1.1 Work package
4.1.1.1.1Activity Duration Predecessor
4.1.1.1.2Activity Duration Predecessor
4.1.1.1.3Activity Duration Predecessor
oject Schedule

Estimated cost

Estimated cost
Estimated cost
Estimated cost

$2,000
$500
$1,000

$200
$300
$100

$100
$300

Estimated cost
Estimated cost
Estimated cost

Estimated cost
Estimated cost
Estimated cost

Estimated cost
Estimated cost
Estimated cost

Estimated cost
Estimated cost
Estimated cost

Estimated cost
Estimated cost
Estimated cost

Estimated cost
Estimated cost
Estimated cost

You might also like