R2 - DPR New BHC-VZM 07.04.23
R2 - DPR New BHC-VZM 07.04.23
R2 - DPR New BHC-VZM 07.04.23
CONTENTS
CHAPTER - I ........................................................................................................................ 1
EXECUTIVE SUMMARY ................................................................................................... 1
1.1 Introduction .............................................................................................................................. 1
i|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
1.28 Source of Funding Financial Rate Of Return And Economic Rate Of Return:............... 20
CHAPTER - II ..................................................................................................................... 24
TRAFFIC SURVEY ............................................................................................................ 24
2.1 Justification.............................................................................................................................. 24
3.5 Details Of Soil Investigation And Type Of Strata Along The Alignment :- ..................... 66
CHAPTER – IV ................................................................................................................... 70
REQUIREMENT OF LAND.............................................................................................. 70
4.1 Criteria For Requirement Of Land For Track , Stations, Bridges Etc. :- ..................... 70
ii | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
4.2 Break Up Of Land Requirement State – Wise And District Wise For Private Land,
Government Land And Forest Land :- .............................................................................. 70
CHAPTER – V ..................................................................................................................... 77
PERMANENT WAY........................................................................................................... 77
5.1 Details Of Total Track Length Including Loop Line Etc. :- ........................................... 77
5.2 Design Speed For Main Line And Loop Line :- .......................................................... 77
CHAPTER – VI ................................................................................................................... 79
FORMATION, TUNNELS & BRIDGES.......................................................................... 79
6.1 List of important, major and minor bridges incorporating liner water way in meter,
chainage of bridge, span arrangement, river name, type of bridge etc. in following
format:..................................................................................................................................... 79
6.2 Details and list of road crossing works such as RoBs, RuBs,/LHS and Level Crossings:99
7.3 No. Of Loop Lines And Their Length At Each Station , Turn Out Details At Each
Station. .................................................................................................................................. 114
iii | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
9.2 Details Of Station Wise Running Rooms/Rest House/Rpf Barracks Etc. Proposed And
Its Justification. .................................................................................................................... 176
11.1.5Traction Power supply system (TSS, SP, SSP Location & spacings)...................................... 182
11.1.8Details of feasibility of EHV power supply at nearest GSS for feeding to proposed TSS,
Alignment & expected ROW. ................................................................................................ 183
iv | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
13.4 Detailed Environmental Impact Assessment Due To Project Location, Design And
Construction Including The Impact Of Operation And Maintenance Facilities. :- .... 186
13.6 Environment Monitoring Plan Including For Pre – Construction , Construction Phase,
Operation Phase, Implementation Of Environmental Management Plan And Setting Up
An Environment Managrment System. :- ......................................................................... 186
v|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
14.2 Details Of Clearances Required Such As Asi/Nma, Wild Life, Forest Fca Act, Tree
Cutting Permission Etc. :- ................................................................................................. 187
18.2 Estimation Of Operation And Maintenance Cost, Over Heads :- .................................. 208
19.4 Check List For Economic Cash Flows (As Annexure – Iii Of Railway Project Economic
Apprisal Frame Work . Note For Check List, Circulated Vide Letter No – 2022/ Gati
Shakti/Eu/49 Dated 19/08/2022) :- ..................................................................................... 255
vi | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
19.5 Cash Flow Of Economic Internal Rate Of Return (Eirr) :- .......................................... 255
19.6 Sensitivity Analysis For Critical Factors In The Range Of 5% To 20% Eirr :- ......... 255
19.8 Model Input Data Used Along With Sources ( As Per Annexure – Ii Of Railway Project
Economic Appraisal Frame Work Note For List Of Data Sources, Circulated Vide
Letter No – 2022/ Gati Sakti/Eu/49 Dated 19/8/2022). :- ............................................... 255
vii | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER - I
EXECUTIVE SUMMARY
1.1 Introduction
Ministry of Railway had sanctioned balance 3RD line between BHADRAK-
VIZIANAGARAM (525 Km) in the year 2015-16, vide Pink Book item No.-27, chargeable
to EBR (IF) at a sanctioned cost of Rs 5250.00 Cr and outlay for 2015-16 was Rs120.05 Crs.
3rd line between Bhadrak to Nirgundi (105 Km) and Barang to Khurda Road (35 Km) were
sanctioned earlier as separate work. Therefore the required balance sections for 3rd line are as
follows:
(ii) Khurda Road to Vizianagaram (363 Km) i.e total route length of 385 km, in
Howarh-Chennai main line.
Vision 2024 – Plan of Indian Railway needed for achieving 2024 MT loading in 2024.
Indian Railways and its vast network are the main source of transportation and the back bone
of economic development along with social reform of Independent India. However, now the
growth in other modes especially the road sector, has led to the gradual erosion of Railways
dominant position. Today the Indian Railways carries only 27-28% of the freight traffic and
20% of passenger traffic loosing even intercity travel to emergence of other modes such as
domestic civil aviation. It is with this back drop that increasing Railways modal share in
transportation has become one of the major concerns of national infrastructural planning.
The NITI Aayog has envisaged a modal share of 45% for the Railways by 2030. To achieve a
modal share of 45% of total transportation, the biggest challenge before the Indian railways is
overcoming the capacity constraint. Realising that, this needs to be addressed at the earliest,
the Government of India has substantially increased the annual capital expenditure on
1|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Railway capacity expansion In order to identify the projects and chalk a road map for
investment, the Indian Railways has prepared a National Rail Plan. National Rail Plan
envisages in creating capacity by 2030 that will be able to sustain a 45% modal share for the
Railways right up to 2050.
It has been decided to divide the capacity leap into two leaps – first leap by 2024 and the
second leap by 2030. It is in this context that the “Vision 2024/2024” has been prepared;
identifying the capacity enhancement projects that need to be completed and the volume of
traffic 2024 MT that needs to be targeted by the Year 2024. The Vision 2024 is a sub set of
the National Rail Plan, but since it is also the first leap forward it is most critical as its
success or failure will impact the targets of 2030 and beyond. Many other works which may
start within next few years are indicated as works in the pipeline leading to introduction of
Vision 2025-2030. This is in line with the NRP which is the blueprint for sufficiency of rail
transport till 2050.
This needs timely and even early completion of projects is necessary. Execution of these
identified priority projects need to be planned meticulously .The contract should be on EPC
mode for new sanctioned works. Comprehensive planning for projects including
identification and mitigation of anticipated bottle necks should be done immediately to avoid
time and cost over runs and to reap the benefits of assured funding which comes at substantial
financing cost.
It has been planned to construct 3rd line adjacent to the existing Railway line which will run
almost parallel to UP and DN line of Howrah-Chennai Main line. The proposed alignment
falls in the geographical jurisdiction of coastal parts of Odisha and Andhra Pradesh, The
proposed alignment passes through Cuttack, Khordha and Ganjam districts of Odisha &
Srikakulam & Vizianagaram of Andhra Pradesh. The long coastal lines are rich in minerals
and other natural resources and are on the threshold of an industrial upsurge. The freight
traffic on HWH-Chennai main line is increasing rapidly due to demand of coal and other
minerals, which are being transported to Paradeep, Dhamra, Gopalpur, Vizag and
Gangavaram ports through the HWH- Chennai main line. To facilitate the movement of the
freight trains smoothly, East Coast Railway has the responsibility of conceptualization,
implementation, operation, running and managing of the rail network, under its jurisdiction.
Accordingly, extensive studies have been carried out to rationalize, re-orient the railway
requirements by providing new lines, gauge conversion and doubling, etc., as a part of its
expansion and modernization plan. In view of the above it is highly imperative to connect the
2|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
balance section of 3rd line i.e (i) Nergundi - Barang (22 Km) & Khurda Road-Vizianagaram
(363 Km).
Based on Chapter-V of Indian Railways Engineering Code & Railway Board’s letter
No- 2022/W-I/Gen/DPR Proforma (E-off: 3404238), Dated 02.09.2022 the Detailed Project
Report has been prepared. The chapters consist of the following:
Executive Summary.
A. Traffic & Engineering Survey.
B. Land Requirement.
C. Deatails of Stations, Permanent way, formation, Buldings, Tunnels & Bridges etc.
D. Electrical Engineering (Traction & General).
E. Signal & Telecommunication Engineering.
F. Enviornmenteal and Social Impact Assesment.
G. Cost Estimates.
H. Financial & Economical analysis.
I. Risk analysis
J. Conclusion & Recommendations.
This proposed Railway line is a third line to existing Railway double line between Bhadrak
and Vizianagaram. This has been planned according to the demand to meet the demand for
traffic and to decongest the existing Railway line.
The proposed line is 3rd line of Bhadrak – Vizianagaram balance Railway line. Being
third line of Bhadrak – Vizianagram Railway line, it has been planned to construct the 3rd line
parallel to UP & DN line of Vizinagram – Bhadark Railway line. Acquisition of land will be
very minimum and the existing Infrastructure of the station would be utilised with some
modification to existing infrastructure economically.
Being a proposed third line and it is to be laid at the side of the existing Rail line and to be
utilised the existing infrastructure of Railway, BISAG verification and all other clearances
may not be required. The proposed third line will be the augmentation to the existing and
future traffic demand.
3|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Table - 1
Name of the section Charted capacity No of coaching path % age of
and Goods Trains utilisation
Table – 2
Name of the section Charted No of coaching (including Total % age of
capacity coaching path) and goods trains utilisation
trains including
existing
W/o With No of total Incremental trains. W/o With
MB MB train run in freight trains MB MB
2021-22
including
coaching
(paths)
Nergundi - Cuttack 96 88 107.35 46.34 153.69 160.09 174.65
Cuttack - Barang 91 83 82.60 46.34 128.94 141.69 155.35
Barang - 132 116 96.29 15.26 111.55 84.51 96.16
Mancheswar
Mancheswar - 100 91 96.21 15.26 111.47 111.47 122.94
4|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Bhubaneswar
Bhubaneswar - 116 103 99.21 15.26 117.75 101.51 114.32
Khurda Road
Khurda Road - 62 55 75.90 15.26 91.16 147.03 165.74
Brahmapur
Brahmapur - 62 57 73.24 15.26 88.5 142.74 155.26
Palasa
Palasa - Naupada 68 62 74.39 15.26 89.65 131.84 144.60
Jn.
Naupada - 67 61 73.67 15.26 88.93 132.73 145.79
Vizianagaram Jn.
78.79 (both in ward and out ward) Million Ton of additional traffic has been
expected to move over this line. The details of the traffic with its OD partculars are discussed
in detail in para no 1.26 below and chapter II.
Passenger traffic has not been considered for economic evaluation of the project.
Traffic forecast, anticipated goods traffic , existing sea port, upcoming sea port,
upcoming industrial infrastructure, air port, tourist places, pilgrimage centre etc. etc., have
been considered in traffic report for arriving Internal Rate of Return and Financial Rate of
Return, considering approved DCF technique of Railway.
After examining the details of land available, it is feasible to have 3rd line parallel to
UP main and DN main line with minimum track centre 5.3 m in yard and 7.8 m in block
section according to Guide lines of Railway Board to avoid massive land acquisition.
Switchovers have also been proposed at different locations, which have been brought out in
the following table.
5|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Key Plans:
6|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
7|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
iii) 847 Minor bridges - Attached in Chapter Chapter VI para no 6.1 (iii)
iv) ROB, RUB & LHS - List is attached in Chapter VI para 6.2 (i)
It runs parallel to National Highway 16 and crosses at 22 locations where RUB & at
two locations of ROB has already been constructed over existing line and will require
extension. The switch over from UP side to DN side have been proposed in the approach of
station yard either with the help of existing curves available or by introducing ½ degree
reverse curves.
Table - 3
Name of the Climate Forest area Economy Rainfall per Telegraph &
District w.r.t the total annum Telephone
geographical Facilities
area
8|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
There is no involvement of very deep cutting or high embankment except few patches. As the
Railway alignment traverses along the Coastal belt and having nos. of Minor, Major and
Important bridges, only there is involvement of major protection works to protect the
embankment in high flood and cyclone etc.
SOIL INVESTIGATION: -
Along the coastal belt, mostly alluvial soil is available. Laterite stone is available along the
district of Khurda and Ganjam. At very few patches, black cotton soil is available which is
unsuitable for embankment. Adjacent to proposed alignment, moorum mixed soil is available,
which is suitable for blanketing on top surface of the formation. As a whole, the geological
strata are suitable for construction of Railway formation.
Assessment has been made, considering the soil strata of existing Rail way line. Only for
minor, major and important bridges, the soil investigation will be done prior to construction
of all these structures.
The construction materials such as sand, metals, good quality earth are available locally.
Speed Potential:
9|Page
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
c) Blanketing:
Blanket of adequate depth to be provided depending on the sub-grade
proposed and as per latest guidelines issued by RDSO for earthwork
in formation.
d) Protective Works:
Protective measures, as required, ensuring safety in cutting must be
incorporated.
Comprehensive guidelines and specifications for Railway formation (specification
No RDSO/2020/GE: IRS-0004, Sept 2020 with ACS-1) to be followed.
Track Structure:
a) Rail Section 60 Kg/90 UTS R ails in mainline and 52 Kg rails in loop lines and
sidings or 60kg(S/H) as per availability.
b) Sleeper PSC Wider & Heavier RDSO. Drg. RT-8527/Ordinary 60 Kg PSC
Sleeper
c) Sleeper density 1660 sleepers per km in main line 1540 sleepers per km in
loop line.
d) Ballast Cushion Mainline -350mm. Loop lines-250 mm.
e) Welding of rails As far as possible, CWR/LWR to be provided with ISEJ.
f) Points & Crossings Thick web switches with CMS crossing.
g) All the curves shall be suitably realigned and proper transition lengths shall be
provided. Maximum permissible cant of 185 mm can be provided in the section so
that speed potential on curves is fully exploited.
Tunnel Cross Section: Nil
Bridge loading standard: Design Criteria for Bridges has been designed for 25 Ton
axle load-2008
Interlocking standard & Telecom: All Block Stations are planned for standard-II R with
MACLS.
Electrification: As the existing double line section is electrified, the proposed alignment
has been planned with OHE.
Building Standard: Buildings to be constructed with the extant policy of Railways.
10 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
1. Important: 6 Nos
2. Major: 86 Nos
3. Minor: 847 Nos
4. Tunnel: Nil
5. ROB: 2 Nos
6. RUB: 22 Nos
7. LHS: 21 Nos
8. Level Crossings: 164 Nos
9. ROR: Nil
The details of the bridges and spans etc are attached at Chapter VI, Para-6.1 (i, ii, iii) & Para
6.2 (i, ii)
11 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Minimum number of staff quarters for essential categories of staff is proposed at locations
where small towns and facilities are available. Provisions of watering arrangements have
been made in the estimate.
12 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE NO - 5
13 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
used. Where the existing OFC room infringe to the new line and require dismantling, new
STM-1 & MUX shall be installed. Each station, SP, SSP & TSS are provided with
DTMF type control telephone for section controller and TPC control. DTMF telephones
are also provided Auto telephones are also provided at each station for Hot line
communication. Passenger Amenities like PA system, coach guidance, display boards
are not included in the estimate.
1.22 Statutory Clearances Required :-
This proposed third line is a augmentation to the existing facilities of Railway, no
clearances are required from any other department/organisation.
1.23 Environment and Social Impact Assessment:-
Proposal for construction of third line is a augmentation work to a existing
infrastructure. So environment and Social impact analysis does not required,
14 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
of the yard.
(i) % length on ruling gradient. 20%
10 Nos of PSRs 12
11. Earth work in Embankment. ( lakh 126.86 + Blanketing 4.74 =131.6
Cum)
(i) Maximum bank height. 12.449 m
12. Earth work in cutting (lakh Cum) 38.78
(i) Maximum depth of cutting. 11.160 m
13. Total nos of tunnel. (nos) NIL
(i) Total tunnelling length (km) NIL
(ii) Longest Tunnel (m) NIL
14 Total Adits/Shafts and their length. NIL
15. Total linear water way. 11208 m
(i) Important bridge (Nos) 6 Nos.
(ii) Major Bridges. (Nos) 86 Nos.
(iii) Minor Bridges (Nos) 847 Nos.
16. Loading Standards. 25 Tonne Axle Load.
17. Total stations (Including Originating 57 nos
and Destination Stations, Junction (Odisha: 32, Andhra Pradesh: 25)
Stns, Crossing Stations, halts ) (Nos)
(State wise)
(i) Originating. Nil
(ii) Destination stations. NIL
(iii) Existing stations 57 Nos.
(iv) Junction stations. 5 Nos.
(v) PH. 10 nos
18. Details of Stations (Nos)
a) Station Proposed for integration 16
b) Additional Loop proposed. 22
c) S&T alterations due to LC, etc. 13
d) S&T Works involved 46
19. ROBs (nos) 2 Nos
(i) RUB (Nos) 22 Nos
(ii) LHS (Nos) LHS -21 Nos
(iii) Level crossings. (Nos) 164
20. Rail over Rail Fly over. NIL
21. Track structures
(i) Main line. 60 Kg Rails With Sleeper Density -1660 nos.
(ii) Loop lines. 60 Kg (S/H) with Sleeper density – 1540 Nos
22. Track centre (m) 7.8 m in block section , 5.3 m in yard.
23. Signalling System. Standrd – II (R) Interlocking with MACLS
24. Traction. Electrified Section.
25. Projected Passenger Traffic (Lakhs N.A
passenger/Annum)
(i) Projected Coaching Train in New N.A
line.
26. Projected Freight traffic/ Additional 78.98
freight traffic (MTPA).
(i) Projected Goods train /additional 49
15 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE NO - 8
17 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
18 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CPM-I/RVNL/BBS
Net earnings have been arrived at after deduction of the working expenses from the gross
earnings. The operating ratio in percentage, as an indicator of the viability of the project,
has been calculated by the following formula:
Working Expenses
---------------------- X 100
Gross Earnings
The lower the operating ratio, higher the efficiency in the operation of the project.
The details of calculation of Net Earnings and the Operating Ratio have been shown in
the Table ‘D’ (Calculation Sheet). The Operating Ratio is given below:
TABLE NO - 9
Passenger Traffic
Coaching traffic has not been taken for the financial justification of the present Project.
19 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Freight Traffic
The future additional freight traffic considered for the economic justification of the project
are given below commodity and with OD particulars:
TABLE NO - 10
20 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Total= 32.92 Km
Total= 90.61 Km
21 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Total= 106.83 Km
Total= 153.3 Km
22 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
The proposed 3rd line in balance section between Bhadrak –Vizianagaram which is parallel to
existing double line of HWN – Chennai main route passes through the major stations like
Cuttack, Bhubaneswar, Khurdha Road and Berhampur the commercial hubs as well as
industrial corridor in and around the alignment.
Keeping the future additional traffic projection in view, to reduce the traffic congestions
and saturated capacity utilisation, East Coast Railway has recommended its sanction
since this is a highly remunerative project.
************
23 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER - II
TRAFFIC SURVEY
2.1 Justification
2.1.1. Indian Railways (IR), the 4th largest Railway Network in the world, transported a
record 1418 Million Tonnes (MT) cargo in the financial year 2021-22. IR plays a
stellar role in meeting the logistics needs of the country and is rightly called the
lifeline of the nation. East Coast Railway (ECoR) as a part of IR has contributed a lot
in this respect. As such, East Coast Railway has become the number one zone of IR as
far as the loading is concerned.
As per NITI Ayog’s Vision 2030 document, Railways need to carry 40-45% share of
the freight on economic and environmental considerations. National Rail Plan (NRP)
was released by Ministry of Railways in the year 2020 with the objective of
enhancing the modal share of Rail to 40%-45% of logistics market primarily by
creating adequate capacity ahead of demand. Being a part of IR, ECoR has also
planned to develop its infrastructure. Accordingly, a pipeline of capacity enhancement
works was envisaged for easing the bottlenecks/constraints and augmenting the
network.
3rd line of Bhadrakh- Vizianagaram (BHC-VZM) section is one section where, ECoR
needs its upgradation to enhance the line capacity ad through put. Therefore, Railway
Board sanctioned this line of balance section between BHADRAK-
VIZIANAGARAM (525 Km) in year 2015-16 vide Pink Book item No.-27 under
allocation of Extra Budgetary Resources (Institutional Finance) at a cost of 5250
Cr.The work was awarded to M/s RVNL, Bhubaneswar for execution. M/s
RVNL/BBS submitted the DPR accordingly.
Owing to the upcoming East Coast Dedicated Freight Corridor (ECDFC) project
between Kharagpur – Vijayawada, Railway Board (Director Project Monitoring) has
deferred this project vide letter No. 2015/W-II/ECOR/DL/DPR/13, Dated: 10.05.2021
(Enclosed as Annexure-A). During the visit of Hon’ble Minister of Railway in
January 2022, it has been directed to revive this 3rd line project as the ECDFC is a
separate project. Accordingly, GM/ECoR requested Railway Board for its revival
(The letter enclosed as Annexure-B). The traffic scenario during the DPR submitted
by M/s RVNL/BBS vis-a-vis at present, has a lot of sea change. As per the directives
of Railway Board, the modified traffic report has been prepared. This is an outcome
of this.
The present gross project assessed cost is Rs.4962.87 Cr.
The route length of new project of 3rd line in balanced section between Bhadrak-
Vizianagaram is 385 Km. This section comes under “B” category classification and
situated in the HDN (Highly Utilized Network) route as identified by Railway Board.
24 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
It has been surveyed that the proposed line shall run parallel to UP line of Howrah-
Chennai Main line. The proposed line passes the states of Odisha and Andhra Pradesh
and covers 6 districts (4 in Odisha and 2 in Andhra Pradesh) viz. Bhadrak, Jajpur,
Cuttack, Khurda, Ganjam, Srikakulam and Vizianagaram. Further, 70% of this line is
running almost parallel to the Bay of Bengal and Chilika lake. As such, these regions
with a long coastal line are rich in mineral and other natural resources, and are on the
threshold of an industrial upsurge. Due to the existance of costal area 2 major Ports
and 3 minor ports are existing in the zone of influence. The freight traffic in the
HWH-MAS main line is increasing rapidly due to demand of coal and other minerals.
The freight is being transported to Paradeep, Dhamra, Gopalpur, Gangavaram and
Visakhapatam port through the HWH-MAS main line. To facilitate the smooth
movement of freight trains, East Coast Railway has the responsibility of
conceptualization, implementation, operation, efficiently in running and managing the
rail network under its jurisdiction. Accordingly, it has carried out extensive studies to
rationalize, reorient the railway requirements by providing new lines, gauge
conversion and doubling, etc., as part of its expansion and modernization plan.
Table-1
Sl No Description of the section Length in Km Present status
Therefore the balance section for 3rd line are (i) Nirgundi to Barang (22Km) and(ii)
Khurda Road to Vizianagaram(363 Km) total route length of 385 km is required for 3rd
line work against sanction of 525 km. The jurisdiction of ECoR commences from
RANITAL Jn cabin which is 10 km ex Bhadrakh towards HWH end.
The details of Line Capacity utilisation of this section as per East Coast Railway’s for
the year 2021-22 is given below.
Table-2
Name of the section Charted capacity No of coaching paths and % age of
goods trains utilisation
W/o With MB Chg path. Total W/o With
MB (including MB MB
freight and
departmental
trains)
Ranital Link Cabin - Bhadrak 84 77 53 76.55 91 99
Bhadrak - Jakhapura 66 61 56 86.23 131 143
Jakhapura - Haridaspur 110 99 58 95.05 86 96
Haridaspur - Nergundi 77 68 58 85.85 111 126
Nergundi - Cuttack 96 88 63 107.35 112 122
Cuttack - Barang 91 83 65 82.60 91 99
Barang - Mancheswar 132 116 69 96.29 73 83
Mancheswar - Bhubaneswar 100 91 69 96.21 96 106
Bhubaneswar - Khurda Road 116 103 72 99.21 86 96
Khurda Road - Brahmapur 62 55 46 75.90 122 137
Brahmapur - Palasa 62 57 45 73.24 118 129
Palasa - Naupada Jn. 68 62 45 74.39 109 120
It is seen from the above statement that; the all sectionsare highly saturated. No of trains are
more in Cuttack- Nergundi section. But the capacity utilization is comparatively less as this is
an Automatic Block section, two small block sections. At any industrial organisation capacity
utilisation of more than 70% needs augmentation of infrastructure. Therefore, anticipating the
future traffic projection 3rd line of the balance section of BHC - VZM i.e. NRG-VZM is
highly essential and inevitable for smooth passing of trains.
26 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
The proposed section is having the branch lines at the following junctions.
Table-3
Sl No Name of the Jn. Station The name of the section . Remark
over the proposed section
1 Bhadrakh (BHC) Bhdrakh to Dhamara For Dhamara port traffic
2 Jajpurkeonjhar JJKR- Banspani For movement of Iron Ore from
Road(JJKR) Gandhamardham belt to Dhamara
Port and raw material/finished
product of Tata Steel, JSSL etc.
3 Jakhapura(JKPR) JKPR-Banspani For movement of Iron Ore from
Gandhamardham belt to Paradeep
Port and raw material/finished
product of Tata Steel, JSSL etc.
4 Kapilas Road (KIS) KIS- Talcher For movement of coal of Talcher
area to various destination.
5 Nergundi (NRG) NRG- Talcher For movement of coal of Talcher
area to various destination.
6 Cuttack (CTC) CTC- Paradeep Gateway of Paradeep port.
7 Baranga (BRAG) BRAG- Talcher For movement of coal traffic to
Southern Power houses.
8 Khurda Road (KUR) KUR-Puri For movement of coaching trains
since Puri being a Pilgrimage
station.
9 Chatrapur (CAP) CAP- Gopalpur Port Gateway of Gopalpur station.
10 Naupada (NWP) NWP- Gunupur For movement of coaching trains.
The importance of this line will be
increased once Gunupur is
connected with a rail head at other
end at Theruvali for which the work
is under progress.
11 Vizianagaram (VZM) VZM- Titlagarh VZM is the originating station of
Raipur and Jharsuguda line.
27 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Basing on the concept to meet the increasing traffic potential on HWH-MAS main line in
stretch between Bhadrak-Visakhapatnam, it has been sanctioned by Railway Board to
undertake Preliminary Engineering cum Traffic survey between Khurda Road-Vizianagaram.
Further, the survey for BHC-VZM 3rd line in balance section has been sanctioned vide letter
no.2013/W-I/Gel/survey/dtd. 01.04.2015 at sl.no.9 Bhadrak-Nergundi and Barang-Khurda
Road 3rd line has already been sanctioned by Railway Board.
1. Passenger Traffic:
Sufficient numbers of Mail/Express, Rajdhani, Duronto Exp., Passenger Trains, etc. are
plying in the project section. The No of Coaching trains plying during 2021-22 are shown in
the Lie capacity table shown above. The number of coaching trains shown above in 2021-22
are during the covid pandemic when these trains were not regularised, once coaching trains
are regularised the capacity utilisation will be more. Therefore, running of another coaching
train in this section has been conceived and earnings from the coaching traffic have not been
taken for the financial justification of the present Project.
2. Freight Traffic
TATA Bhushan steel Ltd is an integrated steel plant located in Dhenkanal district of Odisha
which is served by Meramandali railway station in East Coast Railway. Present capacity of
plant is 3 MTPA. Raw materials of this plant will be coming from Paradip Port, Gopalpur
Port, Visakhpatnam Port and Gangavaram Port. The plant is going for immediate expansion
of 5.6 MTPA which will require a rail traffic of 18.40 MTPA. A major portion of this traffic
will be from Ports of Andhra Pradesh and Odisha which will essentially require tripling of
Khurda – Vizianagaram section. Traffic expected in this line due to the expansion of the plant
is at least as below. (Source: Expansion DPR of the party)
Table-4
INWARD
Commodity Qty inTonnes PA From To
Coal 2000000 Paradeep Meramandali
Coal 2000000 Gangavaram Port Meramandali
Table-5
28 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
OUTWARD
Commodity QtyinTonnes PA From To
Slag 400000 Meramandali Paradeep
Jindal Stainless Ltd. situated in Jajpur district of Odisha is having rail connectivity from
Sukinda railway station. The present capacity of the plant is 1.6 MTPA. The plant is going
for a huge expansion with additional tipplers and loading facilities. The immediate expansion
is for 3.4 MTPA for which DPR is already approved. As part of this expansion the plant will
be handling 9.63 MTPA traffic will be handled by Railway. Traffic expected by rail in this
line is given below. (Source: Expansion DPR of the party)
Table-6
INWARD
Commodity Qty inTonnes PA From To
Cocking Coal 75000 Paradeep Sukinda
Thermal Coal 30000 Paradeep Sukinda
PCI Coal 21000 Paradeep Sukinda
Lime Stone 100000 Paradeep Sukinda
Table-7
OUTWARD
Commodity QtyinTonnes PA From To
Finished steel 25000 Sukinda Vizag
III) JSPL/Angul
Jindal Steel & Power Ltd. is a big integrated steel plant located in Angul district of Odisha.
The plant has rail connectivity from Kerajanga railway station of East Coast Railway.
Present capacity of the plant is 3 MTPA. The plant is going for huge expansion in various
phases. In first phase of expansion the production will be increased from 3 MTPA to 6
MTPA and in the next phase it will be further increased to 12 MTPA & 5 MTPA new
cement plant. This expansion will require 48 MTPA of rail traffic which will be extremely
difficult to handle without commissioning of this project. Limestone, cocking coal and
non-Cocking coal for this plant is important in Paradip port, Gopalpur port and
Visakhapatnam Port. A huge cement plant is also coming alo0ng with the expansion of
this steel plant. To be on conservative side only rail bound traffic of this cement industry is
taken in projected freight traffic along this line since the steel plant expansion may take
time and a good amount of traffic will go via other routes. (Source: Expansion DPR of the
party)
Table-8
INWARD
Commodity Qty inTonnes PA From To
Gypsum 200000 Paradeep Angul
29 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
This plant is located in Cuttack district of Odisha which is having a capacity of 0.4 MTPA.
The plant is being expanded for a capacity of 4.2 MTPA. The raw material for the plant is
handled at Paradip and Visakhapatnam Port. Rail bound traffic will be 5.7 MTPA after this
expansion. (Source: Expansion DPR of the party)
Table-9
INWARD
Movement Commodity Qty in Tonnes PA From To
Inward Gypsum 120000 Paradeep Byree
V) Arati Steel/Ghantikal:
This is a steel plant located in Cuttack district of Odisha with a capacity of 0.3 MTPA. The
plant is going for expansion of 0.5 MTPA which will be primarily from Paradeep Port. Rail
bound movement of raw materials for this expansion is given below. (Source: Expansion
DPR of the party)
Table-10
Movement Commodity Qty in Tonnes PA From To
Inward Coke 800000 Paradeep Ghantikal
Inward Lime Stone 300000 Paradeep Ghantikal
Inward Dolomite 300000 Paradeep Ghantikal
Outward Finished steel 25000 Ghantikal Paradeep
Hinduja Power is located near Visakhapatnam and is planning to have separate private siding
to handle its inward coal rake. The plant will be handling 6.5 MTPA of coal traffic. The
domestic coal linkage for this plant is mostly from MCL/Talcher. Hence all rakes have to go
via Khurda – Vijaynagaram. Thus this project is important for the domestic coal movement
of this power plant. Expected traffic for this plant is:
Table-11
Movement Commodity Qty in Tonnes PA From To
Inward Coal 6500000 Talcher Vizag
Ultratech Cement is setting up a new plant taking off from Machhapur railway station of East
Coast Railway, located in Cuttack district of Odisha. The plant will have a capacity of 2.2
MTPA. The rail bound traffic will be 2.7 MTPA which will be primarily coming from
Andhra Pradesh. (Source: Expansion DPR of the party)
30 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Table-12
Movement Commodity Qty in Tonnes PA From To
Inward Gypsum 219000 Paradeep Machhapur
Inward Coal 36500 Paradeep Machhapur
Table-13
Movement Commodity Qty in Tonnes PA From To
Inward Slag 250000 Vizag Ghantikal
Table-14
Movement Commodity Qty in Tonnes PA From To
Inward Cocking Coal 875000 Paradeep Dhenkanal
Inward Coal 1589000 Paradeep Dhenkanal
Outward Finished Steel 1837500 Dhenkanal Paradeep
X) NU Vista Ltd/Jakhapura
This is new cement plant coming up near Jakhapura station in East Coast Railway. The Plant
will be handling 2.85 MTPA of rail bound traffic. (Source: Expansion DPR of the party)
Table-15
Movement Commodity Qty in Tonnes PA From To
Inward Gypsum 100000 Paradeep Jakhapura
VISA steel located in Sukinda railway station is coming with a new private siding into the
plant. The plant will require 8.215 MTPA of rail traffic for its function. Some of the traffic
will be coming up from Paradip Port, Gopalpur Port and Visakhapatnam. (Source: Expansion
DPR of the party)
Table-16
Movement Commodity Qty in Tonnes PA From To
Inward Cocking Coal 1080000 Paradeep Sukinda
Inward Coal 1440000 Paradeep Sukinda
31 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
M/s VSPS have granted Rail Transport Clearance to for or expansion capacity of Steel Plant
at Visakhapatnam from 3.5 MPTPA to 6.3 MTPA for the following volume of traffic: -
Table-17
Movement Commodity Qty in Tonnes PA From To
Inward Coal 1000000 Talcher Visakhapamam
Now, this plant has already operated with 7.3 MTPA capacity.
Table-18
Movement Commodity Qty in Tonnes PA From To
Outward Coal 1540000 Naupada Vizianagram/
Western India
32 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Under the Sagaramala project governed by Ministry of Shipping, this Port will have a
signifant impact to boost the national economy. Astaranga Port is an upcoming non-major
port located in Puri district of Odisha. Originally the take arrangement of the port is planned
from Bhubaneswar New / Baranga station of Howarh – Chennai trunk route. Due to
constraint in land acquisition take off arrangement was shifted to Cuttack – Paradip section. It
is a project of Rs 6500 crores Traffic forecast by 2030 is 44.15 MTPA. A huge component of
the port is expected to be moved through the alignment of this proposed tripling. Hence in
order to handle this additional traffic tripling will be essential.
Table-19
Movement Commodity Qty in Tonnes PA From To
Inward Thermal Coal 12000000 Talcher Astaranga Port
Outward Cocking Coal 3000000 Astaranga Port Nergundi/
Eastern India.
XV) ParadipPort: -
Paradip Port is a deep sea major port with a draft to handle huge cape size vessel. Paradip
Port has handled a total of 190 Million tonnes of cargo in the financial year 2021-22. The port
is going for huge expansion for handling both bulk material and white goods. New berth with
25MTPA capacity is being developed at Paradip Port in the Western dock. A consortium of
Jindal Steel and Power Ltd and Jindal Port Private Ltd. has been awarded this contract for
handling Cape size Vessel on BOT basis. The Port is connected with two branch lines i.e.
CTC-PRDP & HDS-PRDP lines. It is excepted that 60% of traffic will be moved via CTC-
PRDP line and rest 40% traffic will moved via HDS-PRDP line as per their expansion
programme. The following are the details of Rail bound traffic will be passed through CTC-
NRG section.
33 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Table-20
Sl Name of the Volume in From To
No. Commodity Tonne/Annum
1. Imported Coal 6000000 PPT Various Steel & Power Plant
2. Iron Ore 6000000 BSPX area PPT
3. Domestic Coal 18000000 MCL Area PPT
4. Imported Coal 1850000 Paradeep Jakhapura
5. Lime 1850000 Paradeep Jakhapura
6. Pet coke 600000 PRDP Various destinations.
Total 34300000
Table-21
Movement Commodity Qty in Tonnes PA From To
Outward Cocking 1140000 Chatrapur Naupada/ Western
Coal/Thermal Coal Odisha,
Chhatisgarh, M.P
Outward Cocking 1140000 Chatrapur Nergundi/Eastern
Coal/Thermal Coal India
Inward Coastal Coal 570000 Naupada/ Chatrapur
Western
Odisha,
Chhatisgarh,
M.P
Inward Coastal Coal 570000 Nergundi/Easter Chatrapur
n India
Outward Fertilizer 285000 Chhatrapur Naupada/ Western
Odisha,
Chhatisgarh, M.P
Outward Fertilizer 285000 Chhatrapur Nergundi/Eastern
India
XVII) COAL:
Talcher Coalfields of MCL is a major mine in Odisha for supplying domestic coal for various
power houses and other industries. Coal Production in Talcher area is going for a huge
expansion. Several new coal bulk has identified and being allotted huge railway network for
fast mile connectivity to these mines are also planned in the form of inner and outer corridor.
A huge portion of this domestic coal will be consumed by various power houses and
34 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
industries in southern region. They will be either using rail-sea-rail mode or all rail routes for
transporting this coal. If Paradip port is used for coastal movement of this coal, then it will
pass through Nergundi – Cuttack section. If all rail route movement is shown for this traffic.
It is go through Khurda – Vizianagaram section. Hence in both the cases this project is
essential for feeding domestic coal to important power houses in the southern region of the
country. This includes NTPC/Simhadri, Hinduja Power and other power house in Andhra
Pradesh, Karnataka and Tamilnadu. The new coal blocks and coal resources identified in
Talcher area and its capacity is shared below:
Table-22
New Coal Mines of MCL/Talcher- Traffic to be moved via Rail cum Sea Route.
35 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
36 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
38 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Western India
14. Edible Oil 204000 Naupada Nergundi/ Eastern
India
15. Coal 2000000 Talcher APGENCO,
Vijayawada
16. Coal 5000000 Talcher Tamilnadu/Karnata
ka
17. Cocking Coal/Thermal 1140000 Chatrapur Naupada/Western
Coal Odisha,
Chhatisgarh, M.P
18. Cocking Coal/Thermal 1140000 Chatrapur Nergundi/Eastern
Coal India
19. Coastal Coal 570000 Naupada/Western Chatrapur
Odisha,
Chhatisgarh, M.P
20. Coastal Coal 570000 Nergundi/Eastern Chatrapur
India
21. Fertilizer 285000 Chhatrapur Naupada/Western
Odisha,
Chhatisgarh, M.P
22. Fertilizer 285000 Chhatrapur Nergundi/Eastern
India
TOTAL 26095000
Since KUR-VZM Auto Signaling has been proposed for commissioning, 25% of KUR-VZM
traffic has been kept aside for movement in the proposed Auto Signaling section of KUR-
VZM. So the final traffic for KUR-VZM will be:
Table-26
Table-28
SI Name of theCommodity Volume inTonne From TO
No Annum
1 Coal 1155000 Naupada Vizianagram
2 Coal 495000 Naupada Khurda Road
3 Coal 427500 Naupada Chatrapur
4 Coal 427500 Khurda Road Chatrapur
5 Coal 12375000 Khurda Road Vizianagram
6 Cocking Coal 714000 Naupada Vizianagram
7 Cocking Coal 306000 Naupada Khurda Road
40 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Summary of the Originating/ Terminating and through passing traffic is furnished in the
following table:
Table-29
SINo Name of theCommodity Volume inTonne Annum From TO
28 Coal 1155000 Naupada Vizianagram
29 Coal 495000 Naupada Khurda Road
30 Coal 427500 Naupada Chatrapur
31 Coal 427500 Khurda Road Chatrapur
32 Coal 12375000 Khurda Road Vizianagram
33 Coal 41526500 Nergundi Cuttack
34 Cocking Coal 714000 Naupada Vizianagram
35 Cocking Coal 306000 Naupada Khurrda Road
36 Cocking Coal 855000 Chatrapur Naupada
37 Cocking Coal 855000 Chatrapur Khurda Road
38 Cocking Coal/ Coke 6430000 Cuttack Nergundi
39 Finished Steel 18750 Khurda Road Vizianagram
40 Finished Steel 1862500 Nergundi Cuttack
41 Lime Stone 267750 Naupada Vizianagram
42 Lime Stone 114750 Naupada Nergundi
43 Lime/ Lime Stone 2250000 Cuttack Nergundi
44 Slag 187500 Vizianagram Khurda Road
45 Slag 400000 Nergundi Cuttack
46 Iron Ore 6000000 Nergundi Cuttack
47 Dolomite 300000 Cuttack Nergundi
48 Gypsum 639000 Cuttack Nergundi
49 Fertilizer 304500 Naupada Vizianagram
50 Fertilizer 130500 Naupada Khurda Road
51 Fertilizer 213750 Chhatrapur Khurda Road
41 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
42 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
It is seen from the above table that, if the 3rd line project is not executed, then movement of
trains shall be hampered badly which will result heavy detention to both Rolling stocks and
Loco motives even after 3rd line with Auto signaling.
43 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Revenues used for computation of ROR of the present project has not been used for
justifying viability of any other project. Rolling stocks have been computed as per the
ratio of the length of the project to the average lead of traffic.
Working Expenses:
The working expenses for the project for its operation will be Rs. 846.64 Crores for 1st year
(shown in Table No. ‘D’ as as per the convention adopted by the Railways.
Cost of documentation.
Cost of provision and maintenance of carrying units.
Terminal services.
Cost of line hauls services.
Cost of other transportation services including train passing staff.
Cost of track & signaling.
Cost of General and overhead charges.
Cost of Central charges (towards Zonal Headquarter, Railway Board and other
central services).
The unit cost for each of the above elements of working capital has been
calculated as per the unit cost norms pertaining to East Coast Railway as per the
latest unit cost rates published by the Cost Analysis Cell of the Railway Board.
So the escalation factor for the year 2022-2023 has been taken as 6.55% over the
cost of 2020-21.
Net Earnings and Operating Ratio:
Net earnings have been arrived at after deduction of the working expenses from the
gross earnings. The operating ratio in percentage, as an indicator of the viability of
the project, has been calculated by the following formula:
Working Expenses
---------------------- X 100
Gross Earnings
The lower the operating ratio, higher the efficiency in the operation of the project.
The details of calculation of Net Earnings and the Operating Ratio have been shown
in the Table ‘D’ (Calculation Sheet). The Operating Ratio is given below:
Details of Net Earnings & Operating Ratio for 1st Year (2027-28)
TABLE NO - 32
The number of Electric Locomotives has been worked out by the following formulae.
Electric Engine Km. = No. trains (Loaded+Empty) x Route Km. coveredby
Electric loco.
Bare requirement of Electric Locos
= Electric Engine Km. (Annually)
Electric Engine Km. per day in use x 365
44 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Electric Engine km. per day per engine in use has been taken as 329 km. as per the
Annual Statistical Statement of East Coast Railway of 2019-20.
The rolling stock requirement is dependent on the type of wagons, wagon turn round
and repairing allowance. The type of wagons required for carrying the commodities
have been mentioned in the calculation sheet of GTKM (Table -B).
The wagon turn round of different streams of traffic has been calculated by the
following formula.
The average turn round of wagons in E.Co.Railway and average lead in E.Co.Railway
has been taken as 2.45 days and 306 km. respectively as per Annual Statistics of
E.Co.Railway for the year 2019-20.
Calculation of Wagons:
The number of the wagons required has been worked out by the following formulae.
Bare requirement of wagons = Total No. of wagons to be loaded
annually x turn round of wagon) x365.
Repair Allowance = Bare Requirement of Wagons x 8%
Total requirement of wagons = Bare requirement + Repair Allowance
Like this, the requirement of different types of wagons of operation of the project has
been shown in Table-E (Calculation sheet) of the survey report.
Summary of the requirement of wagons in the first year of the project for movement of
goods traffic is as follows: -
TABLE NO - 33
BOXN 2222
BCN 78
TOTAL 2300
The financial viability of the project has been examined by means of DCF
technique. The works of Civil Engineering, S&T Engineering, and Electrical
Engineering Departments will be completed by 31.03.2027 in order to enable the line
to be opened for traffic. Hence, 2026-27 has been taken as the Base year for the
purpose of calculation of cash inflow and outflow. The ROR works out to 23.15%
(shown in Table ‘I’, of the respective calculation.)
SENSITIVITY ANALYSIS UP TO + 20% VARIATIONS IN ESTIMATED COST AND PROJECTED EARNINGS: -
TABLE NO - 34
46 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
ANNEXURE-A
47 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
ANNEXURE-B
48 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
49 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – III
ENGINEERING SURVEY
3.1 Methodology Of Topographical Survey :-
(SURVEY OF INDIA MAPS, DGPS SURVEY, PERMANENT AND TEMPORARY BENCH
MARKS, ARIAL PHOTOGRAMMETRY BY DRONES, LIDAR SURVEY TOTAL STATIONS
ETC.)
Field survey may be taken up according to approved alignment. During the field survey, the
guide lines of Engineering code vide Chapter – II (Modes of investigation of Railway
Project.) and Para no – 420 to 456 are to be referred.
The latest equipment i.e Drone, LiDAR, GPS, DGPS may be used for finalisation of
alignment for Horizontal as well as vertical position.
The km post, curve post, any other obligatory point may be marked permanently for
the reference during the period of construction. The different stages of activities are as under.
50 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Alternative routes selection does not require and validation from BISAG does not
require.
(ii) The proposed line has to be designed to accommodate within the available land of
Railway. In unavoidable situations only minimum land may be planned to acquire just
to lay the proposed line .
(iii). Existing loop of station yard has to be connected to proposed third line; in lieu one
loop may be proposed according to the requirement of traffic flow along the block
section.
51 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
The following List of Document have been developed and annexed to the DPR for better
appreciation.
(ii) L – section.
CURV
E CURVE CIRCULAR
SL NO RADIUS DEGREE TRANSITION TPTC1 TPTC2
DIREC LENGTH CURVE
TION
1 L 875 2 905.53 785.531 120 401113.52 402019.05
2 R 583.33 3 426.36 256.365 170 402687.74 403114.1
3 L 1166.67 1.5 310.57 230.569 80 404453.16 404763.73
4 L 1050 1.67 244.14 184.137 60 407996.19 408240.33
5 R 1166.67 1.5 651.2 571.196 80 410090.59 410741.79
6 L 1750 1 778.53 698.531 80 412519.17 413297.7
7 R 583.3 3 765.66 595.661 170 415170.59 415936.25
8 L 500 3.5 636.75 486.747 150 418530.37 419167.12
9 L 586.6 2.99 382.34 322.339 60 419357.76 419740.1
10 R 1750 1 910 770 140 458575 459485
11 L 1750 1 700 650 180 460691 461391
12 L 1750 1 680 480 200 470321 471001
13 R 1750 1 795 530 60 479027 479822
14 L 1750 1 265 150 120 489415 489680
63 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CURV
E CURVE CIRCULAR
SL NO RADIUS DEGREE TRANSITION TPTC1 TPTC2
DIREC LENGTH CURVE
TION
15 R 1750 1 480 360 120 495515 495995
16 R 1750 1 264 144 120 498992 499256
17 R 1750 1 595 475 120 513756 514351
18 L 1750 1 520 360 160 516026 516546
19 L 1750 1 787 627 160 516594 517381
20 L 1750 1 747 587 160 523740 524487
21 R 1750 1 400 240 160 530128 530528
22 L 1750 1 805 645 160 533302 534107
23 L 1750 1 260 100 160 537062 537322
24 L 875 2 410 230 180 543686 544096
25 L 875 2 1032 852 180 544978 546010
26 L 1750 2 380 220 160 546599 546979
27 R 583.33 3 1460 1140 320 547075 548535
28 L 583.33 3 680 360 320 550212 550892
29 R 875 2 830 650 180 551038 551868
30 R 875 2 774 594 180 554857 555631
31 R 1750 1 771 611 160 557031 557802
32 L 1750 1 1021 861 160 560037 561058
33 R 1750 1 340 180 160 561571 561911
34 L 1750 1 295 135 160 564787 565082
35 L 1750 1 339 179 160 566130 566469
36 L 875 2 543 363 180 570940 571483
37 L 1166.67 1.5 250 110 140 581001 581251
38 R 875 2 510 330 180 582255 582765
39 L 875 2 740 560 180 583047 583787
40 R 875 2 320 140 180 584037 584357
41 R 1166.67 1.5 230 90 140 585567 585797
42 L 875 2 610 430 180 586278 586888
43 L 875 2 450 270 180 587479 587929
44 R 1750 1 310 150 160 589304 589614
45 L 1750 1 330 190 140 591124 591454
46 L 875 2 330 150 180 593159 593489
47 R 1750 1 1610 1450 160 594305 595915
48 L 1750 1 390 230 160 596306 596696
49 L 1750 1 270 110 160 599021 599291
50 L 875 2 510 330 180 599352 599862
51 L 700 2.5 680 460 220 600528 601208
52 L 875 2 300 120 180 604470 604770
53 R 875 2 500 320 180 605245 605745
54 L 875 2 310 130 180 606465 606775
55 L 875 2 350 170 180 607221 607571
56 R 1750 1 360 200 160 608589 608949
64 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CURV
E CURVE CIRCULAR
SL NO RADIUS DEGREE TRANSITION TPTC1 TPTC2
DIREC LENGTH CURVE
TION
57 L 875 2 520 340 180 611204 611724
58 R 875 2 580 410 200 612501 613081
59 R 875 2 610 430 180 621629 622239
60 L 875 2 690 510 180 615274 615964
61 R 1166.67 1.5 330 190 140 621702 622032
62 L 3500 0.5 130 50 80 624905 625035
63 L 875 2 420 240 180 627452 627872
64 L 875 2 520 340 180 628401 628921
65 R 875 2 380 200 180 629325 629705
66 R 1750 1 460 300 160 633952 634412
67 R 1750 1 480 320 160 635351 635831
68 L 875 2 270 90 180 634705 634975
69 R 1750 1 400 240 160 635309 635709
70 L 875 2 392.744 252.744 140 645371.45 645764.19
71 R 1750 1 165.69 75.689 90 649130.25 649295.94
72 L 1750 1 1120.9 1030.904 90 654938.64 656059.54
73 L 1750 1 307.25 217.248 90 658350.54 658657.79
74 L 1750 1 107.49 17.487 90 666188.39 666295.88
75 L 875 2 298.942 158.942 140 668767.42 669066.36
76 R 875 2 358.81 218.811 140 671245.09 671603.9
77 L 583.33 3 604.021 472.021 132 672200.46 672804.48
78 L 283.33 3 277.62 145.62 132 674499.66 674777.28
79 R 875 2 557.538 417.538 140 676764.6 677322.14
80 L 875 2 597.749 457.749 140 681738.92 682336.67
81 L 1750 1 216.3 126.297 90 682724.36 682940.66
82 R 700 2.5 285.91 145.909 140 687008.14 687294.05
83 R 700 2.5 218.57 78.568 140 693365.09 693583.66
84 L 1750 1 320.64 230.645 90 706142.76 706463.4
85 R 875 2 51.1 -88.899 140 707184.35 707235.45
86 L 875 2 244.72 104.719 140 707940.6 708185.32
87 L 1000 1.75 669.42 579.416 90 709833.14 710502.56
88 R 1750 1 768.46 678.46 90 714057.22 714825.68
89 L 875 2 540.242 400.242 140 715569.63 716109.87
90 L 1750 1 321.09 231.086 90 722373.97 722695.06
91 R 875 2 493.08 353.083 140 726755.67 727248.75
92 L 875 2 238.44 98.441 140 728285.19 728523.63
93 L 3500 0.5 412.45 370.453 42 733854.38 734266.83
94 R 1000 1.75 424.96 334.963 90 737702.3 738127.26
95 R 875 2 542.81 402.813 140 739860.96 740403.77
96 L 1000 1.75 300.71 210.711 90 742698.67 742999.38
97 L 875 2 610.41 470.411 140 745047.23 745657.64
98 R 875 2 182.08 42.085 140 750709.99 750892.07
65 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CURV
E CURVE CIRCULAR
SL NO RADIUS DEGREE TRANSITION TPTC1 TPTC2
DIREC LENGTH CURVE
TION
99 R 1750 1 285.94 195.944 90 754374.22 754660.16
100 L 875 2 643 502.995 140 756934.89 757577.89
101 L 1750 1 235.83 145.828 90 759414.97 759650.8
102 R 3500 0.5 287.84 245.836 42 762580.86 762868.7
103 L 2333.33 0.75 98.44 56.44 42 771276.97 771375.41
104 L 1750 1 1141.96 1051.962 90 777780.49 778922.45
105 R 1000 1.75 113.05 23 90 780013.33 780126.38
106 L 875 2 185.58 45.58 140 780938.01 781123.59
107 R 875 2 272.83 132.832 140 782838.26 783111.09
108 L 3500 0.5 797.77 755.773 42 786610.54 787408.31
109 L 875 2 668.82 528.821 140 788662.03 789330.85
110 R 875 2 264.81 124.806 140 790160.27 790425.08
111 L 875 2 434.45 294.448 140 791952.33 792386.78
112 R 875 2 440.72 300.722 140 759345.09 759785.81
113 L 1750 1 720.71 630.711 90 806306.72 807027.43
114 R 875 2 488.16 348.158 140 808407.85 808896.01
115 R 583.33 3 626.04 494.037 132 811032.1 811658.14
116 L 875 2 222.79 82.788 140 812202.38 812425.17
117 R 875 2 396.71 256.71 140 815916.24 8116313
118 L 875 2 577.43 437.433 140 816417.77 816995.2
119 R 875 2 524.81 384.814 140 817852.98 818377.79
3.5 Details Of Soil Investigation And Type Of Strata Along The Alignment :-
3.5.1. Geotechnical Investigation
The geotechnical investigation at the proposed site was carried out as per
methodology mentioned in the Bureau of Indian Standards (BIS). The geotechnical
investigation is divided into two parts.
66 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Rotary drilling method of boring was adopted for the present geotechnical investigation. The
drilling methodology is as per IS: 1892 - 2021. By using rotary drilling rigs, the boreholes
were progressed up to the desired depth. Bentonite slurry was used as drilling mud to
stabilize the side of the borehole to give the least disturbance to soils for collection of truly
undisturbed samples. Where caving of boreholes occurred, casings were used to keep the
boreholes stable. The diameter of boring was 150mm whereas this was reduced to NX
(76mm) when hard strata was encounter in the field. For the hard strata, bits were attached to
the Core barrels of double tube type in rotary core drilling. For diamond core drilling IS:
6926-1982 (Reaffirmed 2020) was followed.
Standard Penetration Tests were conducted at 1.5 m interval as per the procedure in IS: 2131
–1981 (Reaffirmed 2021). Donut hammer with rope & pulley arrangement was used for
conducting SPT. The weight & free fall of hammer is 63.5 kg &75 cm respectively. The split
spoon sampler used is with room for liner during testing. Standard test procedure was
adopted as per IS: 2131 and SPT blow counts are recorded in the field data sheet.
Drilling in Rock
The rotary core drilling equipment and procedure for drilling conforms to IS:6926-
1996(Reaffirmed 2020). The drilling was carried out using a hydraulic feed as well as
mechanical drilling rig. The drilling was done by using impregnated NX size diamond drill
bit and double tube core barrel, which produces a nominal core and hole diameter of 54.7 mm
and 76 mm respectively. The equipment was provided with necessary facilities to regulate the
spindle speed, bit pressure and water pressure during core drilling to get a good core
recovery. For drilling through soils suitable cutter was used. Casing and mud circulation was
done to stabilize the boreholes. Full observations in respect of the colour and nature of the
return drill water, water loss, speed of drilling, core loss and other relevant details have been
made as described in IS: 1892-2021. After taking out coring tool from boreholes, the rock
sample was placed properly in a standard labeled core box and the core recovery (CR) and
RQD were recorded before taking photographs of the core sample.
67 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
From the core strata core recovery {CR% = (Length of Core /Length of run) x 100} & stone
quality designation (RQD) = (total length of core pieces of more than 100mm /length of run)
x 100} were computed for every drilling run.
Sampling
For the present investigation both disturbed (DS) and undisturbed (UDS) samples for soil and
core samples for rock were collected from site.
Undisturbed samples were collected using 100mm dia. and 450mm long MS tube samplers
specified in IS 11594:1985 (Reaffirmed 2020).
For refusal strata (N>100) rock core samples were collected as per IS:1892-2021 using
diamond bits and double tube core barrel. Core samples recovered were stored properly in
accordance with IS 4078:1980 (Reaffirmed 2019).
The depth at which groundwater is struck during boring was carefully noted and the depth of
water level were ascertained subsequently in the completed boreholes. The water level in the
boreholes were determined as per IS 6935-1973 clause 3.1.1 i.e a Tape with a weight. A steel
tape having least count of 5 mm was used. When the tape was inserted into the borehole due
to the weight of tape the water level should not be increased above 10mm. From ground level
of the bore hole to the top wet portion of the tape was measured which directly indicates the
water level.
For further examination and testing, all collected samples were transported to NABL
accredited laboratory to determine the properties of the samples. Following tests were
conducted at the laboratory on the collected samples.
Moisture Content
Dry density
Natural Density
Grain Size Distribution (Dry Sieving )
Hydrometer Analysis
Atterberg’s Limits (LL & PL)
Specific Gravity
Free Swell Index
Shear Strength (Triaxial shear strength/ Direct Shear)
Water Content of Rock
Density of Rock
Hardness of Rock
Un Confined Compressive strength of Rock
Point Load Test of Rock
68 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Type of Sub-strata
The sub soil at the proposed locations were found to be sandy clay at shallow depth up to
approximately 4.5 m depth below the existing G.L. Below which a clayey sand stratum
present. Then a highly weathered rock strata is present which is followed by week to
moderately week and moderately strong rock strata are present up to the maximum depth of
exploration.
69 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – IV
REQUIREMENT OF LAND
4.1 Criteria For Requirement Of Land For Track , Stations, Bridges Etc. :-
Principles have been adopted to lay the proposed line within the available Railway land
except few patches, where land has to be acquired in unavoidable situations.
4.2 Break Up Of Land Requirement State – Wise And District Wise For
Private Land, Government Land And Forest Land :-
Total Required land, as assessed in course of Final location survey.–
70 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
between
near
Manguli-
1 402.0 402.0 Km 15.25 4546.86 1.1236 Manguli
Kendrapada
Km
stn
TABLE NO - 5
72 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE NO - 6
73 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
74 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
75 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
76 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – V
PERMANENT WAY
i) Maximum speed 130 KMPH (Passenger) & Minimum speed 65 Kmph (Goods)
ii) Cant actual: for A & B Routes - Max.185mm, for Other Routes - max. 165mm
iii) Cant deficiency: - Max. 100 mm
iv) Cant Excess: not more than 75mm
77 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
5.5 Curves
a) Degree of Curvature
i) Maximum speed 130 KMPH (Passenger) & Minimum speed 65 Kmph (Goods)
ii) Cant actual: for A & B Routes - Max.185mm, for Other Routes - max. 165mm
iii) Cant deficiency: - Max. 100 mm
iv) Cant Excess: not more than 75mm
(i) Glued joint will be provided in track circuited area i.e in and around of points and
crossings, on main line in yard.
(ii) Switch expansion Joint (Improved SEJ) will be provided at the end of LWR/SWR and
on both side of bridges.
78 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – VI
TABLE NO - 1
TABLE NO - 2
79 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
80 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE NO - 3
81 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
82 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
83 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
84 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
85 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
86 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
87 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
88 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
89 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
90 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
91 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
92 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
93 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
94 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
95 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
96 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
97 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
98 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
6.2 Details and list of road crossing works such as RoBs, RuBs/LHS and Level
Crossings:
(i). Nos of ROB/RUB = 45 Nos
TABLE NO - 4
99 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE NO - 5
100 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
101 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
102 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
103 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
6.4 Tunnel details and type of strata. Typical Cross Section of Tunnel. List of
Tunnels in the following format:
There is no tunnel have been proposed in this route
104 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – VII
105 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
106 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
10. TAPANG:- Tapang is the existing station on HWH- CHENNAI main line at
KM.473.100(F/HWH). It is a 5 line station which includes one engineering siding.
Apart from above one ballast siding of 200 m long is available behind the station
building. One new loop has been provided. Adequate crossovers have been proposed
from 3rd line to loop line.
11. NIRAKARPUR:- Nirakarpur is the existing station on HWH- CHENNAI main line
at Km. 481.100 (F/HWH). It is a 4 line station. One new loop has been provided.
Adequate crossovers have been proposed from 3rd line to loop line.
Provision for Construction of 4 Nos of Ty-II staff quarters have been made.
12. BHUSANDPUR:- Bhusandapur is the existing station on HWH-CHANNAI main line
at Km. 488.700 (F/HWH). It is a 4 line station. One new loop has been provided.
Adequate crossovers have been proposed from 3rd line to loop line.
Provisions for construction of 4 Nos of Ty-II staff quarters have been made.
13. MUKTESWAR PH:- Mukteswar PH is the existing PH one HWH- CHENNAI main
line at Km.494.240 (F/HWH). The PH is proposed to be converted to block halt. One
new ticket counter cum waiting hall has been proposed.
14. KALUPARA GHAT:- Kaluparaghat is the existing station HWH-CHENNAI main
line at Km.198.600 (F/HWH). It is a 4 line station. One new loop has been provided.
Adequate crossovers have been proposed from 3rd line to loop line for operational
point of view.
Provision for Construction of 4 Nos of Ty-II and 1 no of Type-III staff quarters have
been made.
15. KUHURI PH :- Kuhuri PH is the existing PH one HWH-CHANNAI main line at
Km.505.298(F/HWH). The PH is proposed to be converted to block halt. One new
ticket counter cum waiting hall has been proposed.
16. GANGADHARPUR :- Gangadharpur is the existing station on HWH-CHANNAI
main line at Km.513.200(F/HWH). It is a 4-line station. No. new loop has been
provided. Adequate crossovers have proposed for working of 3rd line. From this
station the 3rd line make switch over from left to right i.e from parallel to UP main to
parallel to DN main.
Provision for Construction of 4 Nos of Ty-II staff quarters have been made.
17. SOLARI PH :- Solari PH is the existing PH on HWH-CHANNAI main line at
Km.518.397 (F/HWH). The PH is proposed to be converted to block halt. One new
ticket counter cum waiting hall has been proposed.
107 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
108 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
existing goods siding at east side of station is proposed to be converted to loop line.
From this station the 3rd line make switch over from right to left i.e from parallel to
DN main to parallel to UP main. Adequate crossovers have been proposed for 3rd line
working. One new station building has been proposed.
Provision for Construction of 4 Nos of Ty-II and 2 no of Ty-III staff quarters have
been made.
25. JAGANNATHPUR:- Jagannathpur is the existing station on HWH-CHANNAI main
line at Km. 593.300 (F/HWH). It is a 5 line station excluding one engineering siding
of 212m. One new loop has been provided. Adequate crossovers have been proposed
for 3rd line working.
Provisions for construction of 4 Nos of Ty-II staff quarters have been made.
26. BRAHMAPUR:- Brahmapur is the existing station on HWH-CHANNAI main line at
Km.602.000 (F/HWH). It is a 5 line station. No new loop has been provided.
Adequate crossovers have been proposed for 3rd line working.
Provision for Construction of 8 Nos of Ty-II, 2 nos of Type-III and 1 No of Type-IV
staff quarters have been made.
27. GOLANTHARA:- Galanthara is the existing station on HWH-CHANNAI main line
at Km.612.700 (F/HWH). It is a 4 line station. One new loop has been provided.
Adequate crossovers have been proposed for 3rd line working. From this station the 3rd
line make switch over from left to right i.e from parallel to UP main to parallel to DN
main.
Provision for Construction of 4 Nos of Ty-II staff quarters have been made.
28. SURLA ROAD:- Surla Road is the existing station on HWH-CHANNAI main line at
Km.617.100 (F/HWH). It is a 4 line station excluding two loading line of 600 m each
and one ballast siding of 580 m. Ballast siding is to be converted to 3rd line Two more
new loops have been provided. Adequate crossovers have been proposed for 3rd line
working.
Provision for Construction of 4 Nos of Ty-II staff quarters have been made.
29. ICCHAPURAM:- Ichhapuram is the existing station on HWH-CHANNAI main line
at Km.624.400 (F/HWH). It is 4 line station. One new loop has been provided.
Adequate crossovers have been proposed for 3rd line working.
Provision for Construction of 4 Nos of Ty-II staff quarters has been made.
109 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
110 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
36. PUNDI:- Pundi is the existing station of HWH-CHANNAI main line at Km.688.338
(F/HWH). It is a 4 line station. One new loop has been provided. Adequate cross-
overs have been proposed from 3rd line to loop line.
Provision for Construction of 4 Nos of Ty-II staff quarters has been made.
37. NUAPADA Jn:- Nuapada Jn. Is the existing station of HWH-CHANNAI main line at
KM.701.581(F/HWH). It is a 5 line station. The Gunupur-Nuapada (B.G) line has
been connected on the VSKP end of Nuapada yard. One new loop has been provided.
Adequate cross-overs have been proposed for working of 3rd line.
Provision for Construction of 4 Nos of Ty-II and 1 No.Ty-III staff quarters has been
made.
38. KOTABOMMALI :- Kotabommali is the existing station on HWH-CHANNAI main
line at Km 715.503 (F/HWH). It is a line station. One new loop has been provided.
Adequate cross-overs have been proposed from 3rd line to loop line.
Provision for Construction of 4 Nos of Ty-II staff quarters has been made.
39. TILARU:- Tilaru is the existing station on HWH-CHANNAI main line at
km.729.228(F/HWH). It is a 4 line station with one hot axle siding. One new loop has
been provided. Adequate cross-overs have been proposed from 3rd line to loop line.
The 3rd line makes switch over form left to right i.e. from parallel to UP main to
parallel to DN main at Km. 727.800 with the help of existing curve.
Provision for Construction of 4 Nos of Ty-II staff quarters has been made.
40. URLAM :- Urlam is the existing station on HWH-CHANNAI main line at Km.
738.853(F/HWH). It is a 4 line station. No new loop has been provided. 3rd line will
pass the station with no connectivity to existing lay-out of yard.
Provision for Construction of 4 Nos of Ty-II staff quarters has been made.
41. SRIKAKULAM ROAD :- Srikakulam Road is the existing station on HWH-
CHANNAI main line at KM. 748.880 (F/HWH). It is a 5 line station. No new loop has
been provided. The existing R-4 will be converted to 3rd line.
Provision for Construction of 4 Nos of Ty-II staff quarters has been made.
42. DUSI :- Dusi is the existing station on HWH-CHANNAI main line at Km.755-
350(F/HWH). IT is a 4 line station. One new loop has been provided. Adequate cross-
overs have been proposed from 3rd line to loop line.
Provision for Construction of 4 Nos of Ty-II staff quarters have been made.
111 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
112 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Existing stations are to be utilised for accommodation of third line. No new stations have
been proposed for this project. Hence, all these details may not be required.
The existing station building, concourse, Platform circulating area and Shelters will be the
common structure for 1st/2nd/3rd line. The proposed third line is being planned to ease out the
excess traffic flow on existing line and also for future traffic. Only to accommodate the future
traffic , in some stations the existing structures are to be remodelled or to be extended, which
is very minor, in comparison to the 385 Km third line. i.e
(i) The dilapidated station building will be dismantled and new building will be
constructed.
(ii) In some station buildings extension have been proposed to accommodate the new
signalling facilities.
(iii) For accommodation of third line some infrastructures have to be dismantled. In lieu of
the same new provision have been kept.
(iv) However in some stations passenger amenities have been proposed i.e.
Provision for extension of High level platforms have been made at Chhatrapur,
Ichhapuram, Sompeta, Baruva, Nuapada, Jn., Tilaru and Dusi stations. Medium level
platform has been proposed at Nirakarpur, Gangadharpur, Rambha, Gajam, Chhatrapur,
Jagannathpur, Urlam station. Approach road wherever necessary have been proposed. Apart
from above medium level platforms has been proposed atArgul PH, Dhaulimuhan PH,
Mukteswar PH, Kuhuri PH and Solari PH.
113 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
7.3 No. Of Loop Lines And Their Length At Each Station , Turn Out Details At
Each Station.
According to terms of reference vide P – Way manual and Engineering code, the proposed
third line has to be connected to dead end of existing loop and in lieu another loop line has to
be provided with isolated or common loop , according to the need of facilities
demanded/required.
Based on this principle, each and every station , one loop has been proposed with two
cross over to make loop operational. In all the loop , the clear available length has been kept
as 750 meter , to accommodate the 26 Coaches.
Station wise details have been prepared and cited below.
TABLE NO - 1
STATION LIST
Sl. NAME OF STATIONS KM DISTANCE INTIGR ADDITION ALTERATION S & T
No. IN ATION AL LOOP DUE TO L.C WORKS
BETWEEN INVOLVED
(KM)
NIRGUNDI - BARANG
1 NIRGUNDI 398.058 Yes Yes
2 MANGULI 400.692 2.634
3 KENDRAPARA ROAD 404.589 3.897 Yes Yes Yes
4 CUTTACK 408.749 4.160 Yes Yes
5 KATHAJORI PH 410.294 1.545
6 GOPALPUR BALIKUDA 413.000 2.706 Yes Yes
7 BARANG 420.160 7.160 Yes Yes
KHURAD ROAD - VIZIANAGARAM
8 KHURDA ROAD 455.300 0.000 Yes Yes
9 ARUGUL PH 460.573 5.273
10 KAIPADARA ROAD 464.500 3.927 Yes Yes
11 DHAULIMUNHA PH 469.083 4.583
12 TAPANG 473.100 4.017 Yes Yes
13 GOLABAI PH 477.741 4.641
14 NIRAKARPUR 481.100 3.359 Yes Yes
15 BHUSANDPUR 488.700 7.600 Yes Yes
16 MUKTESWAR PH 494.240 5.540
17 KALUPARA GHAT 498.600 4.360 Yes Yes
18 KUHURI PH 505.298 6.698 Yes Yes
19 GANGADHARPUR 513.200 7.902 Yes Yes
20 SOLARI PH 518.397 5.197 Yes Yes
21 BALUGAON 526.200 7.803 Yes Yes
22 CHILIKA 533.400 7.200 Yes Yes
23 KHALIKOT 543.300 9.900 Yes Yes
114 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
STATION LIST
Sl. NAME OF STATIONS KM DISTANCE INTIGR ADDITION ALTERATION S & T
No. IN ATION AL LOOP DUE TO L.C WORKS
BETWEEN INVOLVED
(KM)
24 RAMBHA 554.500 11.200 Yes Yes
25 BIRUDI BH 560.000 5.500 Yes Yes
26 HUMMA 565.500 5.500 Yes Yes
27 GANJAM 571.800 6.300 Yes Yes
28 CHHATRAPUR COURT 579.700 7.900
PH
29 CHHATRAPUR 580.700 1.000 Yes Yes
30 NARSHIMAPUR PH 586.600 5.900
31 JAGANNATHPUR 593.300 6.700 Yes Yes
32 BERHAMPUR 602.000 8.700 Yes Yes
33 GOLANTHARA 612.700 10.700 Yes Yes
34 SURLA ROAD 617.100 4.400 Yes Yes
35 ICHHAPURAM 624.400 7.300 Yes Yes Yes
36 JHADAPUDI 638.200 13.800 Yes Yes
37 SOMPETA 644.368 6.168 Yes Yes
38 BARUVA 653.374 9.006 Yes Yes
39 MANDASA ROAD 663.280 9.906 Yes Yes
40 SUMADEVI 669.410 6.130 Yes Yes
41 PALASA 676.047 6.637 Yes Yes Yes
42 PUNDI 688.338 12.291 Yes Yes
43 ROUTHPURAM PH 694.594 6.256
44 NAUPADA JN. 701.581 6.987 Yes Yes Yes
45 DINDU GOPALAPURAM 707.524 5.943
PH
46 KOTABOMMALI 715.503 7.979 Yes Yes
47 HARISCHANDRAPURAM 723.786 8.283
PH
48 TILARU 729.228 5.442 Yes Yes
49 URLAM 738.853 9.625 Yes Yes
50 SRIKAKULAM ROAD 748.880 10.027 Yes Yes
51 DUSI 755.350 6.470 Yes Yes
52 PONDURU 764.193 8.843 Yes Yes
53 SIGADAM 774.260 10.067 Yes Yes
54 CHIPURUPALLI 787.534 13.274 Yes Yes Yes
55 GARIVIDI 793.997 6.463 Yes Yes
56 NELLIMARLA 806.440 12.443 Yes Yes
57 VIZIANAGARAM 818.300 11.860 Yes Yes
115 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
116 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
117 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
118 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
119 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
120 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
121 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
122 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
123 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
124 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
125 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
126 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
127 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
128 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
129 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
130 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
131 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
132 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
133 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
134 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
135 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
136 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
137 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
138 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
139 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
140 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
141 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
142 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
143 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
144 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
145 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
146 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
147 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
148 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
149 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
150 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
151 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
152 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
153 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
154 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
155 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
156 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
157 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
158 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
159 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
160 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
161 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
162 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
163 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
164 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
165 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
166 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
167 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
168 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
169 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
170 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
171 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
172 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
173 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – VIII
8.1 List Of Service Building Station – Wise Along With Plinth Area And
Justification :-
All these details have been elaborated in chapter Railway stations and yards. Hence, it is not
been mentioned under this chapter, to avoid repetition.
The quality of construction will be adhered to all the embodied guideline of IS codes
and specifications of Indian Railways.
174 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – IX
9.1 Details Of Type Wise And Station Wise Residential Quarters With Basis Of
Proposal :-
For the maintenance purpose of upcoming third line. Need based qrs have been included for
Emergency staff and maintenance staff.
In chapter Railway Stations and yards all these details have been mentioned. However . the
details are mentioned here.
175 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
28 Urlam 4 - - -
29 Srikakulam Road 4 - - -
30 Dusi 4 - - -
31 Ponduru 4 - - -
32 Sigdam 4 - - -
33 Chipurpalli 4 1 - -
34 Garvidi 4 - - -
35 Nillimarla 4 - - -
36 Vizianagram 12 4 2 -
180 20 7 0
No rest house, barrack have been proposed as the existing infrastructure is sufficient to
accommodate the future demand.
9.2 Details Of Station Wise Running Rooms/Rest House/Rpf Barracks Etc. Proposed
And Its Justification.
- NIL -
Being third line no running room, Rest house, and RPF barrack etc. has not been proposed.
9.3 Standard Of Construction.
In reference to the Railway Board guide lines and Zonal statutory guide lines issued by the
different PHOD have been taken into cognizance to chalk out the requirement in course of
construction of third line. The expenditure to be incurred has been accounted in detailed
estimate.
The quality of construction will be adhered to all the embodied guideline of IS codes
and specifications of Indian Railways.
176 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – X
SHIFTING OF UTILITIES.
As per the preliminary survey, the provision for 2 Nos. EHT Crossing modification (132 KV)
has been kept in the estimate. The details of Transmission line modification along with
payment to SEBs are given as under:
TABLE NO - 1
The proposed third line has been planned to lay at side of the existing line and within the
Railway Boundary, it may not be required for shifting of utilities. For accommodation of third
line, only dismantling and modification of Railway structure is required , which have been
taken care of in detailed estimate, Minor Head/Sub Head/ Detailed Head wise.
177 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – XI
178 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
carried by OHE will be reduced to half of the current to that of OHE under existing 25kV
system. Therefore, the voltage drop is much less as compared to conventional system.
Additional power requirement for running of trains at 160Kmph, can be catered by adopting
2x25 kV power supply system. The scope of work of this project involves switching over
from the existing 1x25kV AC to 2x25kV system of railway Electrification system.
OHE standards required for running of trains at 160 kmph are governed primarily by Railway
Board’s letter number 2001/Elect(G)/170/1 dated 22.12.2016 taking into account 2x25 kV
Auto Transformer system of traction distribution.
On this entire route, Scott connected 60MVA transformers shall be used in traction
substations for feeding power supply to the overhead equipment’s (OHE) considering
advantage of least voltage imbalance. The average spacing between traction substations has
been kept 50-60 Km for triple line for supplying power at 2x25kV AC to the OHE.
Scope of work for 160 KMPH
In order to work out the scope of work, existing infrastructure was thoroughly surveyed in
light of RDSO/Board’s guidelines for 160 kmph speed. Gaps were identified between existing
infrastructure and required infrastructure to estimate the cost and magnitude of work.
Infrastructural requirements for running of 160 kmph can further be sub-divided into two
major groups viz. Inputs pertaining to Overhead equipment items (OHE items) and inputs
pertaining to power supply items (PSI items).
OHE ITEMS:
1. Existing 1x25kV traction system is required to be converted to 2x25kV system in order to
match with the increased load requirement.
2. Reducing the maximum permissible span in view of section wind zone and increased
tension in OHE based on latest mast employment schedule wind pressure in section.
TABLE NO - 1
179 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
a. 25kV Feeder wire arrangement with All Aluminium spider conductor of size 234 sq. mm or
150sq.mm copper on separate mast for up and down tracks separately should be provided as
per Drawing No. TI/DRG/OHE/FEEDER/RDSO/00001/19/0.
b. Implantation of Feeder masts should be chosen as per para no 20.1 and 20.2 of Appendix-I
of ACTM Vol.-II Part II with latest ACS.
c. The new Feeder line spans should be chosen from respective wind zone Employment
Schedule. In case new foundation is infringing with the old OHE mast foundation, the new
feeder line span can be reduced to nearest lower value of the permissible span. The two
consecutive spans shall not normally differ by more than 18m as per Para 5.5 of ACTM
Vol. II Part-II.
d. The horizontal spacing/distance (X) between Feeder mast foundations and existing OHE
mast foundations should be greater than the width of feeder mast foundation(Y) i.e., X>Y.
4. With 1200 kgf tension of contact wire, condemning diameter of contact wire will increase
from existing 8.25mm to 8.42mm to achieve minimum factor of safety of 2.3.
5. Dropper schedule for 1200/1200 kgf tension with 0.8mm/m pre-sag in OHE issued vide
this office letter no. TI/OHE/GA/2018 dated 20.09.2018. For 72m span pre-sag will be
58mm (0.8X72). Dropper Assembly should be provided as per Drg. No. ETI/OHE/P/1190
Rev. B.
6. Reduction of Contact wire Gradient to be done from 3mm/m to 2mm/m & Relative
gradient from 1.5mm/m to 1mm/m.
7. Adjustment at turnouts:
a. At obligatory mast vertical gap between main line and turn out contact wire is to be
maintained between 50 to 60mm.
b. At 5m distance from obligatory mast, gap is to be maintained at 50 mm.
c. At 10m distance from obligatory mast, gap is to be maintained between 40mm to 50mm.
d. Track separation is to be kept between 290mm to 550mm. Mast should be changed if track
separation is less than 290mm.
e. Span length of turnout location reduced during increasing track separation.
f. From main line to loop line “take off” may be maintained in between 720 to 750mm.
8. Regulating equipment (Three Pulley Type higher tension) should be provided as per RDSO
specification no. TI/SPC/OHE/3PHTATD/0150 with ACS 1) with counter weight eye rod
as per drawing no. ETI/OHE/SK/588 Rev. B.
9. Current carrying ‘A’ dropper as per Specification No. TI/SPC/OHE/CCFD/ 0160(02/2020)
or one C jumper (in span jumper) in every span should be provided.
180 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
10. Rigid droppers shall not be provided, only loop type droppers should be provided.
11. Double pole Isolator type II should be provided at Insulated Overlap of 1250 Amp rating
as per Specification No. ETI/PSI/133.
12. G Jumpers: 105 mm2 G Jumper may be replaced by 160 mm2 G Jumper as per
specification no. ETI/OHE/3(2/94) with the approval of CEE.
13. Structure Number Plate: Retro reflective structure number plate shall be provided as per
Railway Board letter No. 2001/Elect (G)/170/1 Pt dated 07.05.2012. Retro Reflective
number plate may be provided at additional masts if required, by Zonal Railway, as per
Rly Board’s letter No. 2001/Elect (G)/170/1 Pt dated 18.10.2012.
14. Earthing & Bonding:
a. AEC (Arial Earth Conductor) shall be provided to contain the touch & step potential of
the track. AEC of 12.24 mm dia. ACSR Raccoon conductor should be erected on the back
side of the OHE masts/Portals.
b. BEC (Buried Earth Conductor) of 20 mm dia. (cross section 238.64 mm2), galvanized
steel conductor should be laid underground along the UP and DN track separately, 300mm
below ground surface and approximately one meter away (or as per site conditions) from
the OHE foundation towards opposite direction of track. The BEC will be connected to
each OHE mast/Portal and Feeder mast by same conductor having Tee Connector & Lug
Connector as per Drawing No. TI/DRG/ OHE/TC/RDSO/00001/20/0 & TI/DRG/OHE/SC
/RDSO/00001/20/0.
c. The cross bonding of the UP BEC – UP Mast/Portal-UP Traction Rail and DN Traction
Rail-DN mast/Portal – DN BEC should be done by 50X6 mm MS/GS flat at every 450
mtr.
15. Re-spanning of OHE mast as per employment schedule of respective wind zone/ wind
pressure if required.
16. Use of Bent Steady Arm Assembly of Modified Design.
17. Stagger on Tangent track contact wire shall normally be 150mm (at Support) on either
side of track and maximum 250mm on curved track.
Note: The proposed 3rd Line is being made suitable for 2 x 25 KV system. The proposed
estimate for 3rd Line only covers the work related to 3rd Line.
11.1.4 Pegging Plan
In order to work out the scope of work for 2 x 25 KV system, existing infrastructure was
preliminary surveyed in light of RDSO/Board’s guidelines for 160 kmph speed. Gaps were
181 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
identified between existing infrastructure and required infrastructure to estimate the cost
and magnitude of work.
11.1.5 Traction Power supply system (TSS, SP, SSP Location & spacings)
2x25 kV system of power supply to be used and TSS, SP, SSP to be constructed
accordingly. For this three-phase double circuit transmission lines at High voltage
(220/132kV) are to be drawn from GSS (STU/CTU) and 2x25kV AC traction sub stations
(TSS) are to be constructed equipped with 2 Nos 60/84/100 MVA by using transformer
cooling method (ONAN/ONAF/OFAF) Scott connected transformers with 2 Nos Auto
transformers for each Scott connected transformer
Existing switching stations (SP/SSP) are to be replaced by new switching stations with
auto transformers.
Along the track, feeder of 234 sq.mm (aluminium) /150 Sq.mm (copper) size is to be run
on independent masts.
Power Supply Structure: The required TSS, SP & SSPs on this route for supplying 2x25
kV AC voltage to the OHE as below. Transformer rating to be kept as 60 MVA for each
TSS instead of existing 12.5 MVA or 21.6MVA or 30MVA. The spacing of TSS shall be
considered at the existing TSS to save cost towards new transmission lines and ensured
feed zone 50-60 for triple line of 2X25 kV supply system.
TABLE NO - 2
182 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
11.1.8 Details of feasibility of EHV power supply at nearest GSS for feeding
to proposed TSS, Alignment & expected ROW.
2x25 kV system of power supply to be used and TSS, SP, SSP to be constructed
accordingly. For this three-phase double circuit transmission lines at High voltage
(220/132kV) are to be drawn from GSS (STU/CTU). The spacing of TSS shall be
considered at the existing TSS to save cost towards new transmission lines.
11.1.9 Provision of fire supersession system in Transformer.
Provision of fire supersession system has included in the transformer.
183 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – XII
12.2 Details Of Survey Regarding Type Of Soil For Cable Laying , Cable Route,
Track Crossings, Approach/Locations Of S&T Installations, Infringements, Rssi Etc
Survey for cable route, cable laying and track crossing shall be done before execution of
work. Horizontal boring shall be done for running lines. :-
Kendrapara Road-02nos. Cuttack-04 nos. Gopalpur Balikuda-02 nos. Barang Jn.-02 nos.
Khurda Road-01 no. Tapang-02 nos. Nirakarpur-01 no. Kaluparaghat-01 no. Gangadharpur-
02 nos. Balugaon-02 nos. Chilika-03 nos. Khalikota-02 nos. Rambha-02 nos. Humma-02
nos. Ganjam-02 nos. Chhatrapur-03 nos. Jagannathpur-01 no. Berhampur-02 nos.
Golanthara-02 nos. Icchapuram-02 nos. Jhadupudi-02 nos. Somepeta-02 nos. Baruva-01 no.
Mandasa-01 no. Sumadevi-02 nos. Palasa-02 nos. Pundi-01 no. Nuapada Jn.-01 no.
Kotabomali-02 nos. Urlam-02 nos. Srikakulam Road-02 nos. Dusi-02 nos. Sigdam-01 no
Chipurupali-02 nos. Garividi-02 nos. Nellimarla-02 nos. Vizianagaram-01 no.
50 KVA AT 02 Nos. each are required at Chatrapur, Berhampur and Surla Road stations.
25 KVA AT 02 Nos. each are required at Kendrapara Road. Gopalpur Balikuda, Barang Jn.
Tapang, Khalikota, Golanthara, Icchapuram, Baruva, Pundi, Nuapada, Chipurupalli stations.
184 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
10 KVA AT required at Kuhudi, Solari & Biridi stations and 34 nos. mid section Interlocked
LC Gates.
12.7 Provision of EI, ABS, A TP, CTC, LTE etc as per extant guidelines
- Only EI
12.9 Standard Checklist and Performa for Signaling & Telecomm items.
All the safety signaling equipments are as per RDSO specifications. The equipments are
tested as per RDSO guide line and OEM checklist.
185 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – XIII
N.B = Being the third line to existing infrastructure for augmentation, the environmental
assessment and social impact assessment may not be required. So these assessment have not
been carried out/ conducted.
186 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – XIV
STATUTORY CLEARANCES
14.1 List Of Forest/Wild Life Sanctuaries Through Which Proposed Project Is
Passing. :-
This is the augmentation work. So no need of any specific sanction and approval is required.
14.2 Details Of Clearances Required Such As Asi/Nma, Wild Life, Forest Fca Act,
Tree Cutting Permission Etc. :-
Land Acquisition =
It is being planned to lay the proposed third line by utilising the exiting Railway land. In
some patches, Railway land is required to meet out the statutory provision for
construction/accommodation of Railway line and related infrastructure. The existing Railway
land was acquired during early 1960’s or beyond. At present it may not be possible to assess
the category of land adjacent to Railway boundary. The adjacent land to Railway Boundary
may belong to PRIVATE / GOVERNMENT / REVENUE FOREST / ORDINARY
FOREST/RESERVED FOREST category, unless until the concerned revenue examined it.
All these activities shall be taken up after the project sanctioned by Ministry of Railway. So,
necessary permission/ compensation will be applicable in later stage. So provision of
statutory expenditures has been accounted for.
Tree Cutting =
After sanction of project and prior to commencement of work, tree cutting permission has to
be taken up from Forest department, according to guide lines.
187 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – XV
COST ESTIMATES.
(ii) Cost of P – Way materials have been considered according to the Circular of Railway
Board.
(iii) Latest market rate for cement and steel have been considered.
Land
188 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – XVI
The length of Bhadrakh to Vizianagaram secton is 525 KM, out of which 3rd line at the
following sections are either commissioned or sanctioned.
TABLE NO - 1
189 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Keeping the upsurge of both freight and coaching trains in the ensuing years, Railway Board
has planned the ECDFC. In the existing route there is a diversion route is available from
Kapilas Road to Baranga (both are existing stations over the proposed line) by passing
Cuttack to avoid congestion. This bypass line is provided with Auto Signalling from
Nergundi to Rajathgarh and 3rd & 4th line work is also in progress from Salegaon to
Rajatjgarh.
The proposed section is having the branch lines at the following junctions.
TABLE NO - 2
190 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Basing on the concept to meet the increasing traffic potential on HWH-MAS main line in
stretch between Bhadrak-Visakhapatnam, it has been sanctioned by Railway Board to
undertake Preliminary Engineering cum Traffic survey between Khurda Road-Vizianagaram.
Further, the survey for BHC-VZM 3rd line in balance section has been sanctioned vide letter
no.2013/W-I/Gel/survey/dtd. 01.04.2015 at sl.no.9 Bhadrak-Nergundi and Barang-Khurda
Road 3rd line has already been sanctioned by Railway Board.
Sufficient numbers of Mail/Express, Rajdhani, Duronto Exp., Passenger Trains, etc. are
plying in the project section. The No of Coaching trains plying during 2021-22 are shown in
the Lie capacity table shown above. The number of coaching trains shown above in 2021-22
are during the covid pandemic when these trains were not regularised, Once coaching trains
are regularised the capacity utilisation will be more. Therefore running of another coaching
train in this section has been conceived and earnings from the coaching traffic have not been
taken for the financial justification of the present Project.
Projection for Freight Traffic:
A large number of industries have shown interest to set up their steel plants/sponge iron
plants/power plants in East Coast Railway jurisdiction in view of Iron Ore/Bauxite/Coal
mines Details of the industries that have applied for and have been granted Rail Transport
Clearances
16.2 Earnings: -
Gross Earnings:
As per convention, the gross earnings from the new commodities generated by a project line
is taken on the basis of actual distances traveled by the commodity over the East Coast
Railway. This applies to new traffic only which is expected to move over the project line.
The gross earnings from the traffic mentioned in the traffic projections chapter has been
calculated in Table ‘A’ (Calculation sheet) by the following formula.
Volume of Traffic in tonnes x Rate per tonne as per distance and classification of
Commodity).
Revenues used for computation of ROR of the present project has not been used for justifying
viability of any other project.Rolling stocks have been computed as per the ratio of the length
of the project to the average lead of traffic.
191 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Working Expenses:
The working expenses for the project for its operation will be Rs. 846.64 Crores for 1st year
is as per the convention adopted by the Railways.
Cost of documentation.
Cost of provision and maintenance of carrying units.
Terminal services.
Cost of line hauls services.
Cost of other transportation services including train passing staff.
Cost of track & signaling.
Cost of General and overhead charges.
Cost of Central charges (towards Zonal Headquarter, Railway Board and other
central services).
The unit cost for each of the above elements of working capital has been calculated as per
the unit cost norms pertaining to East Coast Railway as per the latest unit cost rates
published by the Cost Analysis Cell of the Railway Board. So the escalation factor for the
year 2022-2023 has been taken as 6.55% over the cost of 2020-21.
Net Earnings and Operating Ratio:
Net earnings have been arrived at after deduction of the working expenses from the gross
earnings. The operating ratio in percentage, as an indicator of the viability of the project, has
been calculated by the following formula:
Working Expenses
---------------------- X 100
Gross Earnings
The lower the operating ratio, higher the efficiency in the operation of the project.
The details of calculation of Net Earnings and the Operating Ratio have been shown in the
Calculation Sheet. The Operating Ratio is given below:
Details of Net Earnings & Operating Ratio for 1st Year (2027-28)
TABLE NO - 3
192 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Loco Requirement:
The number of Electric Locomotives has been worked out by the following formulae.
Electric Engine Km. = No. trains (Loaded+Empty) x Route Km. covered by Electric
loco.
Bare requirement of Electric Locos = Electric Engine Km. (Annually)
Electric Engine Km. per day in use x 365
Electric Engine km. per day per engine in use has been taken as 329 km. as per the Annual
Statistical Statement of East Coast Railway of 2019-20.
The rolling stock requirement is dependent on the type of wagons, wagon turn round and
repairing allowance. The type of wagons required for carrying the commodities have been
mentioned in the calculation sheet of GTKM .
The wagon turn round of different streams of traffic has been calculated by the following
formula.
Calculation of Wagons:
The number of the wagons required has been worked out by the following formulae.
Summary of the requirement of wagons in the first year of the project for movement of goods
traffic is as follows: -
193 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE NO - 4
BOXN 3262
BCN 3
BTPN 1
TOTAL 3266
The calculation of requirement of Brake van has been shown as per the following formulae.
The financial viability of the project has been examined by means of DCF technique. The
works of Civil Engineering, S&T Engineering, and Electrical Engineering Departments will
be completed by 31.03.2027 in order to enable the line to be opened for traffic. Hence, 2026-
27 has been taken as the Base year for the purpose of calculation of cash inflow and outflow.
The ROR works out to 23.15% of the respective calculation.
194 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Table-A
STATEMENT SHOWING THE COMMODITY WISE CLASSIFICATION, RATE PER TONNE, DISTANCE AND
GROSS EARNINGS FROM GOODS TRAFFIC LIKELY TO MOVE OVER THE PROJECT SECTION IN THE
FIRST YEAR (2027-28) OF THE PROJECT. THE FREIGHT RATE W.E.F.01.11.2018 AND CLASSIFICATION
ARE FROM IRCA GOODS TARIFF NO.49 PT II (VOL.II) W.E.F.01.11.2018 CIRCULATED BY MINISTRY OF
RAILWAY VIDE LETTER NO: TCR/1078/2018/15 dated 31.10.2018 (RC-19/2018) & 2015/TC (CR)/505/1 dated
04.01.2019.
Rate Gross
Name of Project Volume
Sl. Type of Classifi- per Earnings
the From To section of traffic
No movement cation tonne in 000' of
Commodity Distance in Tonne
in Rs Rs.
14 Lime Stone Naupada Vizianagram Train 145 117 223.60 267750 59869
Load
15 Lime Stone Naupada Nergundi Train 145 247 411.00 114750 47162
195 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Load
26 Edible Oil Naupada Vizianagram Train 140A 117 198.50 357000 70865
Load
27 Edible Oil Naupada Khurda Train 140A 247 365.00 153000 55845
Road Load
196 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE-B
197 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE-C
198 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE-D
Statement showing the working expenses of goods traffic in the ist year (2027 - 28) of the project
Unit Cost
Sl. Description of Services Rate in Rs. No.of Units Cost in ‘000' of Rs.
No. (2020-21)
1 TERMINAL SERVICES
b) Cost of other terminal services (per wagon full loaded) 2410.56 1235869 2979136
2 MAINTENANCE SERVICES 0
a) Cost of provision and maintenance of carrying units per 1325.56 777483 1030600
wagon day.
3 LINE HAUL SERVICES (PER 1000 GTKM)
a) Cost of traction
TOTAL 6417973
TOTAL 7936465
TOTAL 7945989
6 Escalation factor to enhance the cost upto 202-23 level 6.55% 520462
from 2020-21.
7 Total working Expenses 8466451
Unit Cost Rates are obtained from the Summary of End Results Freight Services Unit Costs 2020-
21 issued by Railway Board in March - 2022.
199 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE-E
STATEMENT SHOWING THE REQUIREMENT OF WAGONS IN THE FIRST YEAR (2027- 28)
OF THE PROJECT FOR MOVEMENT OF GOODS TRAFFIC.
No of wagons to Repair
Type of Wagon turn Bare Total
Sl. No be loaded Allowance
Wagon round Requirement Requirement
annually @8%
1 BOXN 18047 0.94 46.48 3.72 50.20
2 BOXN 7734 1.98 41.95 3.36 45.31
3 BOXN 6680 0.77 14.09 1.13 15.22
4 BOXN 6680 1.01 18.48 1.48 19.96
5 BOXN 193359 2.91 1541.57 123.33 1664.90
6 BOXN 648852 0.09 159.99 12.80 172.79
7 BOXN 11156 0.94 28.73 2.30 31.03
8 BOXN 4781 1.98 25.94 2.08 28.02
9 BOXN 13359 0.77 28.18 2.25 30.43
10 BOXN 13359 1.01 36.97 2.96 39.93
11 BOXN 100469 0.09 24.77 1.98 26.75
12 BOXN 293 2.91 2.34 0.19 2.53
13 BOXN 29102 0.09 7.18 0.57 7.75
14 BOXN 4184 0.94 10.78 0.86 11.64
15 BOXN 1793 1.98 9.73 0.78 10.51
16 BOXN 35156 0.09 8.67 0.69 9.36
17 BOXN 2930 2.91 23.36 1.87 25.23
18 BOXN 6250 0.09 1.54 0.12 1.66
19 BOXN 93750 0.09 23.12 1.85 24.97
20 BOXN 4688 0.09 1.16 0.09 1.25
21 BOXN 9984 0.09 2.46 0.20 2.66
22 BCN 5161 0.94 13.29 1.06 14.35
23 BCN 2212 1.98 12.00 0.96 12.96
24 BCN 3623 1.01 10.03 0.80 10.83
25 BCN 3623 0.77 7.64 0.61 8.25
26 BCN 6051 0.94 15.58 1.25 16.83
27 BCN 2593 1.98 14.07 1.13 15.20
TOTAL 1235869 2300.52
SUMMARY
Stock Requirement Rounded off to
Whole no
BOXN 2222.10 2222
BCN 78.42 78
Total 2300
200 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE-F
Statement Showing The Requirement Of Brake Van In The First Year (2027- 28) Of The Project.
Repair
Sl. Total No. of Bare Total
Turn Round Allowance
No. Loaded Trains Requirement Requirement
@8%
1 305.88 0.94 0.79 0.06 0.85
2 131.08 1.98 0.71 0.06 0.77
3 113.22 0.77 0.24 0.02 0.26
4 113.22 1.01 0.31 0.02 0.33
5 3277.27 2.91 26.13 2.09 28.22
6 10997.49 0.09 2.71 0.22 2.93
7 189.08 0.94 0.49 0.04 0.53
8 81.03 1.98 0.44 0.04 0.48
9 226.42 0.77 0.48 0.04 0.52
10 226.42 1.01 0.63 0.05 0.68
11 1702.86 0.09 0.42 0.03 0.45
12 4.97 2.91 0.04 0.00 0.04
13 493.25 0.09 0.12 0.01 0.13
14 70.92 0.94 0.18 0.01 0.19
15 30.39 1.98 0.16 0.01 0.17
16 595.86 0.09 0.15 0.01 0.16
17 49.66 2.91 0.40 0.03 0.43
18 105.93 0.09 0.03 0.00 0.03
19 1588.98 0.09 0.39 0.03 0.42
20 79.46 0.09 0.02 0.00 0.02
21 169.22 0.09 0.04 0.00 0.04
22 122.88 0.94 0.32 0.03 0.35
23 52.67 1.98 0.29 0.02 0.31
24 86.26 1.01 0.24 0.02 0.26
25 86.26 0.77 0.18 0.01 0.19
26 144.07 0.94 0.37 0.03 0.40
27 61.74 1.98 0.33 0.03 0.36
TOTAL 39.52
SUMMARY
Rounded off to
Stock Requirement Whole no
Brakevan 39.52 40
201 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
TABLE-G
Total No. of
No. of
Trains Repair
Sl. Route Engine Bare No. of locos Total No.
Loaded+ Allowance
No. in Km. Km. Requirement Locos per of Locos
Empty @20%
train
1 550.58 117 64418 0.54 0.11 0.65 2 1.30
2 235.94 247 58277 0.49 0.10 0.59 2 1.18
3 203.80 96 19565 0.16 0.03 0.19 2 0.38
4 203.80 126 25679 0.21 0.04 0.25 2 0.50
5 5899.09 363 2141370 17.83 3.57 21.40 2 42.80
6 19795.48 11 217750 1.81 0.36 2.17 2 4.34
7 340.34 117 39820 0.33 0.07 0.40 2 0.80
8 145.85 247 36025 0.30 0.06 0.36 2 0.72
9 407.56 96 39126 0.33 0.07 0.40 2 0.80
10 407.56 126 51353 0.43 0.09 0.52 2 1.04
11 3065.15 11 33717 0.28 0.06 0.34 2 0.68
12 8.95 363 3249 0.03 0.01 0.04 2 0.08
13 887.85 11 9766 0.08 0.02 0.10 2 0.20
14 127.66 117 14936 0.12 0.02 0.14 2 0.28
15 54.70 247 13511 0.11 0.02 0.13 2 0.26
16 1072.55 11 11798 0.10 0.02 0.12 2 0.24
17 89.39 363 32449 0.27 0.05 0.32 2 0.64
18 190.67 11 2097 0.02 0.00 0.02 2 0.04
19 2860.16 11 31462 0.26 0.05 0.31 2 0.62
20 143.03 11 1573 0.01 0.00 0.01 2 0.02
21 304.60 11 3351 0.03 0.01 0.04 2 0.08
22 221.18 117 25878 0.22 0.04 0.26 2 0.52
23 94.81 247 23418 0.20 0.04 0.24 2 0.48
24 155.27 126 19564 0.16 0.03 0.19 2 0.38
25 155.27 96 14906 0.12 0.02 0.14 2 0.28
26 259.33 117 30342 0.25 0.05 0.30 2 0.60
27 111.13 247 27449 0.23 0.05 0.28 2 0.56
T o t a l: 59.82
NB: Electric Engine Km. per day per engine in use is 329 Km. as per Statistics published in the Financial
Results & Important Statistical Highlights 2019-20 for E.Co.Railway by FA&CAO/BBS.
SUMMARY
Rounded off to
Stock Requirement
Whole no
Locomotive 59.82 60
202 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Table-H
D. Residual Value
1 Land Cost 902409
2 Rail Cost 4717067
3 CRRM Value of Rail Rail Cost 4717067 x50% 2358534
10% on Engg. Assets (After deducting land cost and 44009182 x10% 4400918
4
Rail cost from civil engg estimate)
10% on Rolling Stock (Initial
5
Investment) 11792340 x10% 1179234
7938686
TOTAL
203 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
204 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Table-I
PROJECT EVALUATION STATEMENT WITH DCF TECHNIQUE (Figures in '000' Rs.) & Rate of
Return.
4 2025-
(-) 1st Year 12407165 1.2000 14888598 1.3000 16129315
2026
5 2026-
0 Year 26133538 1.0000 26133538 1.0000 26133538
2027
205 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
40978244
20 + 3.15 = 23.15 %
30 - 6.85 = 23.15 %
206 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
17.1 Various Existing & Anticipated Source Of Nfr , Details Of Projected Non – Fare
Revenue :-
207 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
208 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Net earnings have been arrived at after deduction of the working expenses from the gross
earnings. The operating ratio in percentage, as an indicator of the viability of the project, has
been calculated by the following formula:
Working Expenses
---------------------- X 100
Gross Earnings
The lower the operating ratio, higher the efficiency in the operation of the project.
The details of calculation of Net Earnings and the Operating Ratio have been shown in the
Calculation Sheet. The Operating Ratio is given below:
Details of Net Earnings & Operating Ratio for 1st Year (2027-28)
TABLE NO - 2
Unit Cost
Sl.
Description of Services Rate in Rs.
No.
(2020-21)
1 TERMINAL SERVICES
2 MAINTENANCE SERVICES
a) Cost of provision and maintenance of carrying units per wagon day. 1325.56
a) Cost of traction
i) 354.97
Diesel (Through)
ii) 122.05
Electric (Through)
b) Cost of other transportation services including train passing staff 49.64
6 Escalation factor to enhance the cost upto 2022-23 level from 2020-21. 6.55%
209 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
210 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
Residual 3175
0.0042 0.0004
Value 7938686 33342
100% land 902409 902409 902409 902409
cost not
discounted
TOTAL 91789248 61701605
Note: the ammount shown under the column head of power pack for the year 2052-53 is midlife
rehabilation cost towards WAG7 Electric engine (No of Loco x Repairing cost per loco i.e.Rs.70lakhs)
40978244
20 + 3.15 = 23.15 %
30 - 6.85 = 23.15 %
211 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
18.6 Sensitivity Analysis With Respect To Expected Traffic (Range of +/- 20%),
Cost Escalation (+/- 20% And Time Over Run (+/- 20%).
212 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
213 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – XIX
ECONOMIC ANALYSIS
19.4 Check List For Economic Cash Flows (As Annexure – III) Of Railway Project
Economic Apprisal Frame Work . Note For Check List, Circulated Vide Letter No –
2022/ Gati Shakti/Eu/49 Dated 19/08/2022) :-
19.6 Sensitivity Analysis For Critical Factors In The Range Of 5% To 20% Eirr :-
255 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CHAPTER – XX
RISK ANALYSIS
20.1 Cost Risk:-
Risk analysis and its management is a key project management practice to ensure that the
least number of untoward incidents occurs, while the project is under way. The construction
of Railway line is a linear project. Particularly the construction of 2nd/3rd Railway line,
adjacent to existing Railway line is very risk prone and vulnerable to the construction man
and machineries as well as to passengers in running train and machineries. Prediction of
involvement of risk is a hypothetical assessment. But probability of occurrence may not be
ruled out.
(ii) All the persons involved in construction activities have to undergo training for
construction activities as well as safety at work site.
(iii) Conduct of safety seminar, periodical refresher course may be conducted in regular
interval for alertness during construction.
(iv) Explicitly allocate responsibility for risk management to relevant parties to address
adequately and appropriately in the planning and management of a project.
(v) To prepare the risk register to identify the risks and to detail clearly and concisely how
the risk are to be identified and to be mitigated.
(vi) Risk management to be reviewed very frequently for identification and mitigation also.
256 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
ANNEXURE – I
257 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
258 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
ANNEXURE-II
259 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
260 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
261 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
CPM-I/RVNL/BBS
262 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
ANNEXURE – III A
A. Construction Cost.
1. Whether cost of land acquisition has been incorporated- Yes
2. Whether State’s share of project cost has been excluded- NA
3. Whether construction cost of each department has been incorporated- Yes
4. Whether the cost of construction has been projected year-wise as per schedule of
Construction-Yes
5. Whether CRRM is incorporated as per Para -223 of IRFC Vol I-Yes
B. Working Expenses:
6. Whether maintenance cost of each department has been incorporated as per extant
Maintenance Schedule- NA
7. Whether the repair cost of each department has been considered-NA
8. Whether the cost of replacement of assets as per latest available policy instruction has been
factored in- NA
9. Whether it is verified that depreciation and interest has not been considered as per Para
215 of IRFC Vol – I- NA
10. Whether operational expenses is considered based n the latest traffic costing/ Statistical
Data- NA
Cash Inflows:
A. Traffic earnings
11. Whether both outward and inwards traffic data is considered- Yes
12. Whether savings in engine days or wagon days or both is worked out as per Para 202 of
IRFC Vol. I- Yes
13. Whether reduction in Revenue of other lines/Railways due to diversion has been
Considered- Yes
14. Whether any non – fare revenue is considered- No
15. Whether the latest available Statistical data has been used- Yes
B. Residual Value.
16. Whether Residual value of assets at the end of project period is considered as per Para
233 of IRFC VOL I- NA
17. Whether Land has been factored in as per Blue Book Value- NA
18. Whether Second hand Value of assets has been calculated as per Para 241, IRFC Vol-I- Yes
263 | P a g e
DETAILED PROJECT REPORT OF BHADRAK -VIZIANAGRAM 3rd
LINE SECTION IN EAST COAST RAILWAY
ANNNEXURE III B
(Checklist for Detailed Financial Cash Flow in DPR for Estimating FIRR)
Name of Project: 3rd line between Nergundi and Vizianagaram Railway: ECoR
SN Item Description
1 Total capital cost (states's share to be excluded,if any) -
270 Acres
2 Total land to be acquired and cost
Rs 90.24 Crores.
Total capital cost of the project, with department
3 wise(Civil,Mechanical,electrical and S&T) phasing of costs for each
year of construction Enclosed
Cost of rolling stock in year zero, and additional rolling stock cost in
4
subsequent years, if applicable Enclosed
5 Renewal & replacement cost Cosidered
Gross coaching working expenses for 1st/6th/11th year of the
6
project(Cr.) Not Considered
9 Gross goods working expenses for 1st/6th/11th year of the project (Cr.)
Enclosed
CTPM/ECoR/BBS
264 | P a g e