PMP
PMP
Below are the detailed notes for each topic, including an in-depth
explanation and recommended resources for preparing for the PMP exam.
---
**Building a Team**
- **Stages of Team Development**:
- **Forming**: Team members get to know each other.
- **Storming**: Conflicts arise as team members assert their roles.
- **Norming**: Team starts to work together cohesively.
- **Performing**: Team reaches optimal performance.
- **Adjourning**: Project ends and team disbands.
- *Resource*: "Team Development" by Bruce Tuckman, PMBOK Guide, 7th Edition,
Chapter 3.
**Managing Conflict**
- **Conflict Resolution Techniques**:
- **Avoiding**: Withdrawing from the conflict.
- **Accommodating**: Yielding to others' viewpoints.
- **Compromising**: Finding a middle ground.
- **Collaborating**: Working together to find a win-win solution.
- **Competing**: Assertive, standing one's ground.
- **Sources of Conflict**: Schedules, Priorities, Resources, Technical opinions.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 9.
**Leading a Team**
- **Leadership Styles**:
- **Directive**: Telling team members what to do.
- **Supportive**: Providing support and encouragement.
- **Participative**: Involving team members in decision-making.
- **Achievement-Oriented**: Setting challenging goals.
- **Situational Leadership**: Adapting leadership style to team maturity and task
complexity.
- *Resource*: "Leadership in Organizations" by Gary Yukl.
**Supporting Team Performance**
- **Performance Assessments**: Individual and team performance evaluations.
- **Feedback Mechanisms**: Constructive feedback to improve performance.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 9.
---
**Collect Requirements**
- **Techniques**: Interviews, Focus groups, Surveys, Brainstorming, Prototyping.
- **Requirements Documentation**: Functional and non-functional requirements.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 5.
**Define Scope**
- **Project Scope Statement**: Detailed description of project scope, deliverables,
and exclusions.
- **Product Scope**: Features and functions of the product.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 5.
**Create WBS**
- **Work Breakdown Structure (WBS)**: Decomposition of project scope into
manageable tasks.
- **WBS Dictionary**: Detailed description of each WBS element.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 5.
**Validate Scope**
- **Scope Validation**: Formal acceptance of completed deliverables by
stakeholders.
- **Inspection**: Review and acceptance process.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 5.
**Control Scope**
- **Scope Creep**: Uncontrolled changes to the project scope.
- **Variance Analysis**: Comparing planned vs. actual scope performance.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 5.
**Define Activities**
- **Activity List**: Detailed list of all project activities.
- **Milestone List**: Significant points or events in the project.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 6.
**Sequence Activities**
- **Network Diagram**: Visual representation of activity sequences.
- **Dependencies**: Mandatory, Discretionary, External, Internal.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 6.
**Develop Schedule**
- **Schedule Network Analysis**: Identifying the critical path, Slack, and float.
- **Critical Path Method (CPM)**: Longest path through the project.
- **Resource Leveling**: Adjusting the schedule to account for resource
constraints.
- **Schedule Compression**: Techniques like crashing and fast tracking to shorten
the schedule.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 6.
**Control Schedule**
- **Performance Reviews**: Measuring project performance against the schedule
baseline.
- **Variance Analysis**: Identifying deviations from the schedule.
- **Earned Value Management (EVM)**: Integrating scope, schedule, and cost data.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 6.
**Estimate Costs**
- **Estimation Techniques**:
- **Analogous Estimating**: Using historical data from similar projects.
- **Parametric Estimating**: Using statistical relationships between historical
data and other variables.
- **Bottom-Up Estimating**: Aggregating estimates of lower-level components.
- **Three-Point Estimating**: Considering optimistic, pessimistic, and most
likely scenarios.
- **Reserve Analysis**: Determining the contingency and management reserves.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 7.
**Determine Budget**
- **Cost Baseline**: Time-phased budget used to measure, monitor, and control cost
performance.
- **Funding Requirements**: Identifying the periodic funding needs based on the
cost baseline.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 7.
**Control Costs**
- **Earned Value Management (EVM)**: Integrating scope, schedule, and cost data to
assess project performance.
- **Planned Value (PV)**: Authorized budget assigned to scheduled work.
- **Earned Value (EV)**: Measure of work performed expressed in terms of budget
authorized for that work.
- **Actual Cost (AC)**: Realized cost incurred for work performed.
- **Cost Variance (CV)**: EV - AC.
- **Schedule Variance (SV)**: EV - PV.
- **Cost Performance Index (CPI)**: EV / AC.
- **Schedule Performance Index (SPI)**: EV / PV.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 7.
**Manage Quality**
- **Quality Assurance**: Ensuring quality processes are followed.
- **Continuous Improvement**: Techniques like Plan-Do-Check-Act (PDCA) cycle, Six
Sigma, and Lean.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 8.
**Control Quality**
- **Quality Control Techniques**:
- **Inspection**: Examining work products to determine if they meet standards.
- **Statistical Sampling**: Selecting a subset of items for testing.
- **Control Charts**: Visualizing process stability over time.
- **Cause-and-Effect Diagrams**: Identifying root causes of defects.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 8.
**Acquire Resources**
- **Resource Acquisition**: Obtaining team members, facilities, equipment,
materials, and other resources.
- **Negotiation and Pre-Assignment**: Assigning resources in advance when they are
critical.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 9.
**Develop Team**
- **Team Building**: Activities to enhance team performance.
- **Training and Development**: Providing team members with skills needed for the
project.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 9.
**Manage Team**
- **Performance Assessments**: Evaluating team performance and addressing issues.
- **Conflict Management**: Handling disagreements within the team.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 9.
**Control Resources**
- **Resource Monitoring**: Ensuring resources are used as planned.
- **Resource Optimization**: Adjusting resource allocation to meet project needs.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 9.
**Manage Communications**
- **Information Distribution**: Ensuring information is delivered in the right
format and at the right time.
- **Communication Methods**:
- **Interactive**: Two-way communication (e.g., meetings).
- **Push**: Sending information to recipients (e.g., emails).
- **Pull**: Recipients accessing information (e.g., intranet).
- *Resource*: PMBOK Guide, 7th Edition, Chapter 10.
**Monitor Communications**
- **Performance Reviews**: Assessing the effectiveness of communication.
- **Stakeholder Feedback**: Gathering input from stakeholders to improve
communication.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 10.
**Identify Risks**
- **Risk Identification Techniques**:
- **Brainstorming**: Generating risk ideas.
- **Checklists**: Using predefined lists of risks.
- **SWOT Analysis**: Identifying strengths, weaknesses, opportunities, and
threats.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 11.
**Monitor Risks**
- **Risk Audits**: Reviewing the effectiveness of risk management.
- **Risk Reassessment**: Periodically reviewing and updating risks.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 11.
**Conduct Procurements**
- **Bidder Conferences**: Meetings with potential vendors to clarify requirements.
- **Proposal Evaluation**: Assessing and selecting vendors.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 12.
**Control Procurements**
- **Contract Administration**: Managing the contract and relationship with the
vendor.
- **Performance Reviews**: Evaluating vendor performance.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 12.
**Identify Stakeholders**
- **Stakeholder Register**: Document listing stakeholders and their interests,
influence, and impact.
- **Stakeholder Analysis**: Assessing stakeholder needs and expectations.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 13.
---
**Benefits Realization**
- **Benefits Management Plan**: Document outlining how and when the benefits will
be delivered.
- **KPIs (Key Performance Indicators)**: Metrics used to measure the project's
success in delivering its benefits.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 2.
### Compliance
**Regulatory Compliance**
- **Regulatory Requirements**: Understanding and adhering to laws, regulations,
standards, and guidelines that affect the project.
- **Compliance Audits**: Reviewing the project to ensure it meets regulatory
requirements.
- *Resource*: PMBOK Guide, 7th Edition, Chapter 2.
---
---
## **Study Plan**
---
By following these detailed notes and utilizing the recommended resources, you will
be well-prepared for the PMP exam in 2024. Good luck with your studies and exam
preparation!