SACIC-M-1009-Masonry Units and Plaster Installation Inspection

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 18

EPM Disciplin

S.No RFI No No. e Issue Date Inspection Date

SAC-MYP-QC(P6)-CIVIL-RFI-95021
1 CIVIL 29/Apr/2024 30/Apr/2024
Sepco QC Constu EPM
Inspect Supervi ction EPM
Time Supervi Activity CHECKL SATIP
or sor IST
sor

Muh Plast SAC


erin SACI
ABI am Tanv g IC- TIP-
8:00 AM D mad eer Insp M- M-
ALI Shah ectio 1009 100-
baz 1
n
SATIP Item

SACTIP-M-100-1 3.2
9-
18/
A-B)
at
RFI
Aramc
o
Contra
ctor
Packag Locatio Inspect Drawin Rev No EPM
GRO e
Descrip
n
Inspect
g No PID PID PMT
tion ion ion
UND Level Level
FLO
OR
As AH
per RA- JAZI MA
High Pack C31 6103 B D AL
light age 0-3 W I 18- 0A1 MU HA
ed 6 001 NIR MA
dra D
wing
at
Buil
ding
C31
0-3
at
Pack
age-
6
KIN
G
SAL
MA
N
INTE
RNA
TIO
NAL
CO
MPL
EX
Sub
Remark Contra
s ctor

JPHY
REQUEST FOR INSPECTION
Ref: SAEP 1150 SAC-MYP-QC(P6)-CIVIL-RFI-95021

0004,0005,0006,0 KING SALMAN INTERNATIONAL COMPLEX FOR MARITINE INDUSTRIES


BI 25-00053 JO 007 Phase Package 6 Title AND SERVICES

To: Projects Inspection Unit/ Mr. JAZIB MUNIR Civil Mech. Plumb. Comms. Elect. Other

Inspection/monitoring is required on (date): 29-Apr-24 at (time) : 8:00 AM prior to Coating

Final Inspection of cement Plastering Application of male locker room no# 129,130,132,133,135,236 (GL 9-18/A-B) at GROUND
FLOOR As per Highlighted drawing at Building C310-3 at Package-6 KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME
INDUSTRIES AND SERVICES (MYP).
for the following location /equipment

Work Permit required: Yes No Hold Point Witness Point

SAPMT representative has verified that the work is ready for inspection CONTRACTOR has verified that the work to be inspected is complete
and conforms to the project requirements. and in compliance with the following specifications:
SAPMT Name AHMAD AL HAMAD ITP/Other # SACTIP-M-100-1
Signature Date Contractor/Company Consortium of SEPCO & SINOHYDRO B3
Telephone Fax QA/QC Name ABID ALI

QA/QC Signature : __________________ Date:


Name:
This form received by the undersigned Inspection Department employee:

JAZIB MUNIR Signature: __________________ Date: ________________Time: _________________

NOTE: Inspector's signature is for receiving this request only and not for approval or disapproval of the work or facility inspected.
Distribution: A. Original - Project Management B. 1st Copy - Inspection C. 2nd Copy - Contractor

Copyright©Saudi Aramco 2009. All rights reserved.


( Standards Cut off - MAY,31 2016) Rev 5

SAC TYPICAL INSPECTION PLAN SACTIP No. APPROVED DATE

Concrete Masonry Units and Building Bricks/Blocks SACTIP-M-100-01


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES (MYP) 25-00053,0004, 0005, 0006, CONSORTIUM of BRANCH OF SINO
PACKAGE # 4, 5 & 6 0007/6600042823 (IK) LTD and SEPCO A

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY
NO. ACIVITY CODE PROCEDURE RECORD SAUDI
CONTRACTOR
ARAMCO

1.0 DOCUMENT REVIEW

Concrete Masonry Unit (CMU) Compressive Strength and Aggregate Test


1.1
Reports
SACIC-M-1006 SACIC-M-1006 RH R

Approved IFC
1.2 Approved IFC Drawings/Shop Drawings. Schedule Q Drawings/Shop RH R
Drawings.

Approved Masonry
1.3 Approved Masonry and Plastering Works Procedure Schedule Q and Plastering RH R
Works Procedure

RECEIVING
2.0
INSPECTION

2.1 Masonry and Plastering Materials Receiving and Storage Inspection SACIC-M-1007 SACIC-M-1007 I W

2.2 FBE Rebar and Embedments Receiving Inspection SACIC-Q-1007 SACIC-Q-1007 I W

3.0 INSTALLATION

3.1 Concrete and CMU Surface Preparation and Protection Inspection SACIC-M-1008 SACIC-M-1008 I W

3.2 Masonry Units and Plaster Installation Inspection SACIC-M-1009 SACIC-M-1009 I W

4.0 PRE-COMMISSIONING

4.1 N/A

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of Saud
1 Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

3 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not

4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection/Test
APPROVED DATE DISCIPLINE:

CIVIL
CONTRACTOR/SUBCONTRACTOR

CONSORTIUM of BRANCH OF SINOHYDRO CORPORATION COMPANY


LTD and SEPCO ARABIA COMPANY

NSPECTION RESPONSIBILITY
ASSIGNMENTS
REMARKS

Refer to SACTIP-Q-001-02

od, Saudi Aramco Inspection may adjust the levels of Saudi Aramco participation based upon the

scheduled if the QA/QC organization representative is not present.

A/QC organization representative in attendance.

as assigned to Saudi Aramco.

view of Documents
view and Approval of Documents
0% Contractor Inspection/Test
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBE CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

=log!R3 N/A
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

RA-610318-001 0A1 N/A


SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME

4/30/24 12:00 AM
SAUDI ARAMCO USE ONLY
SAC TIP NUMBER SAC ACTIVITY NUMBER WORK PERMIT REQUIRED?

SACTIP-M100-01 3.2
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

W I

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A Concrete Masonry Units (CMUs)/Block Walls and Plaster Installation Inspection

Mortar for use in masonry construction shall conform to article 2.1 and 2.6A of TMS 602/ACI
IBC 2015
A1 530.1/ASCE 6
Sec. 2103.2.1

The mortar shall be Type S or M Mortar Cement Fine and shall conform to the proportions listed
ACI 530.1-
A2 in Table 1 of ASTM C-270.
11,Sec,1.5B(a)

Project Specs.
A3 Mortar shall be type S in accordance with the properties specification of ASTM C 270. RE-609082 Rev
0 Sec. 2.1.5(G)

Admixtures shall not be used including pigments, air-entraining agents, accelerators, retarders, Project Specs.
A4 water-repellent agents, antifreeze compounds, or other admixtures, unless specifically required. RE-609082 Rev
Do not use calcium chloride in mortar or grout. 0 Sec. 2.2.6(A)

Project Specs.
A5 Provide pigmented mortar for exterior work. RE-609082 Rev
0 Sec. 2.2.6(C)

Project Specs.
Unit masonry mortar shall comply with ASTM C 270, Proportion Specification, for types M, S and
A6 RE-609082 Rev
N mortars.
0 Sec. 2.2.6(B)

TABLE 1
Proportion Specification Requirements

PROPORTIONS BY VOLUME
(Cementitious Materials)
Aggregate
Ratio
Portland Masonry cement Mortar cement Measured in
Mortar Type Hydrated Lime or Lime Putty
cement a Damp,
or Loose
blended Conditions
cement M S N M S N

M 1 _ _ _ _ _ _ 1/4
Cement- S 1 _ _ _ _ _ _ Over 1/4 to 1/2
lime N 1 _ _ _ _ _ _ Over ½ to 1¼
O 1 _ _ _ _ _ _ Over 1¼ to 2½ ASTM C-270
A7
Table 1
Not less than
M 1 _ _ _ _ _ 1 _ 2¼ and
M - _ _ _ 1 _ _ _ not more than
Mortar S 1/2 _ _ _ _ _ 1 _ 3
cement S - _ _ _ _ 1 _ _ times the sum
N - _ _ _ _ _ 1 _ of the
O - _ _ _ _ _ 1 _
separate
volumes of
cementitious
M _ _ 1 _ _ _ materials
1 _
M - 1 _ _ _ _ _ _
Masonry S 1/2 _ _ 1 _ _ _ _
cement S - _ 1 _ _ _ _ _
N - _ _ 1 _ _ _ _
O - _ _ 1 _ _ _ _
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBE CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

Standard
Drawing General
The mortar shall be Type S and shall have a minimum compressive strength as per ACI 530-11 Notes
A8
Table 5.4.2 RA-612003
Sheet 002 Rev.
0A1

Table 5.4.2 — Allowable compressive stresses for empirical design of masonry

Allowable compressive stresses1 based on gross cross-


Construction; compressive strength of sectional area, psi (MPa)
masonry unit,
gross area, psi (MPa)
Type M or S Type N
mortar mortar

Solid masonry of brick and other solid units


of clay or shale; sandlime or concrete brick:
8,000 (55.16) or greater
350 (2.41) 300 (2.07)
4,500 (31.03)
225 (1.55) 200 (1.38)
2,500 (17.23)
160 (1.10) 140 (0.97)
1,500 (10.34)
115 (0.79) 100 (0.69)

Grouted masonry of clay or shale; sand-lime


or concrete:
4,500 (31.03) or greater 225 (1.55) 200 (1.38)
2,500 (17.23) 160 (1.10) 140 (0.97)
1,500 (10.34) 115 (0.79) 100 (0.69)

Solid masonry of solid concrete masonry


units:
3,000 (20.69) or greater 225 (1.55) 200 (1.38) ACI 530.1-11
A9 2,000 (13.79) 160 (1.10) 140 (0.97) Table 5.4.2
1,200 (8.27) 115 (0.79) 100 (0.69)

Masonry of hollow load-bearing units of clay


or shale2:
2,000 (13.79) or greater 140 (0.97) 120 (0.83)
1,500 (10.34) 115 (0.79) 100 (0.69)
1,000 (6.90) 75 (0.52) 70 (0.48)
700 (4.83) 60 (0.41) 55 (0.38)

Masonry of hollow load-bearing concrete


masonry units, up to and including 8 in. (203
mm) nominal thickness:
2,000 (13.79) or greater 140 (0.97) 120 (0.83)
1,500 (10.34) 115 (0.79) 100 (0.69)
1,000 (6.90) 75 (0.52) 70 (0.48)
700 (4.83) 60 (0.41) 55 (0.38)

Masonry of hollow load-bearing concrete


masonry units, greater than 8 and up to 12
in. (203 to 305 mm) nominal thickness:
2,000 (13.79) or greater 125 (0.86) 110 (0.76)
1,500 (10.34) 105 (0.72) 90 (0.62)
1,000 (6.90) 65 (0.49) 60 (0.41)
700 (4.83) 55 (0.38 50 (0.35)

Fine grout mix proportions shall be: 1 part Portland cement; 0 - 0.1 part Hydrated lime; and the
SBC 305
volume of fine aggregate shall be 2.25 - 3.0 times the sum of the volumes of cementitiuos
A10 Sec 3.10.0 Table
materials.
3.10.1

Coarse grout mix proportions shall be: 1 part Portland cement; 0 - 0.1 part Hydrated lime; fine
aggregate shall be 2.25 - 3 times the sum of the volumes of Cementitiuos materials; coarse SBC 305
A11 aggregate is 1-2 times the volumes of the cementitious materials. Sec 3.10.0 Table
3.10.1
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

ACI 530 sec.


Before the start of installation ensure all trades and interface shall be cleared. Conduits, Pipes
A12 1.15, IFC
and Sleeves of any material to be embedded in masonry shall be compatible with masonry.
Drawings

Before the start of CMU block works installation and prior to rendering ensure all trades and
A13 IFC Drawings
interface are cleared.

ACI-530.1-11
A14 Place clean units while the mortar is soft and plastic. Remove and re-lay in fresh mortar any Sec. 3.3 B.7.a
unit disturbed to the extent that initial bond is broken after initial positioning.

Prior to placing masonry and blocks, remove laitance, loose aggregate, and anything else that ACI-530.1-11
A15
would prevent mortar from bonding to the foundation. Sec. 3.2 B

Construct 3/8-in. (9.5-mm) thick bed and head joints, except at foundation or with glass unit
ACI-530.1-11
A16 masonry. Construct bed joint of the starting course of foundation with a thickness not less than
Sec. 3.3 B.1
1/4 in. (6.4 mm) and not more than 3/4 in. (19.1 mm).

The minimum vertical reinforcement shall be 12mm diameter bars at 1.2 meters spacing.
Horizontal joint reinforcement shall consist of at least two longitudinal WD 4 wires spaced not
SBC 305
A17 more than 400 mm for walls greater than 100 mm in width and at least one longitudinal WD 4
Sec 6.1.4.2.3 a,b
wire spaced not more 400 mm for walls not exceeding 100 mm in width; or at least one (Dia
12) bar spaced not more than 1200 mm.

The maximum size of reinforcement used in masonry shall be (Dia 36). The diameter of SBC 305
A18 reinforcement shall not exceed one-half the least clear dimensionof the cell, bond beam, or Sec 4.8.2.1,
collar joint in which it is placed. 4.8.2.2

Vertical bars are placed 2 in. (50.8 mm) of the required location along the length of the wall ACI 530.1-11,
A19
when the wall segment length exceeds 24 in. (610 mm). Sec. 3.4B.11b

The maximum spacing of cross-wires in ladder-type joint reinforcement and of point of SBC 305
A20
connection of cross wires to longitudinal wires of truss-type reinforcement shall be 400 mm Sec. 3.11.2

Place reinforcing bars in walls and flexural elements within a tolerance of ± 1/2 in. (12.7 mm)
when the distance from the centerline of reinforcing bars to the opposite face of masonry, d, is
ACI 530.1-11,
A21 equal to 8 in. (203 mm) or less, ± 1 in. (25.4 mm) for d equal to 24 in. (610 mm) or less but
Sec. 3.4B.11a
greater than 8 in. (203 mm), and ± 11/4 in. (31.8 mm) for d greater than 24 in. (610 mm).

Alignments of masonry walls shall be within ±1/2 in (12.7mm) for bearing walls and columns; ACI 530.1-11
A22
and ±3/4 in. (19.1mm) for non-bearing walls. Sec. 3.3.F.2.d

For conspicuous vertical lines, such as external corners, door jambs, reveals, and expansion Project Specs.
A23 and control joints, the plumbness shall not vary by more than 6 mm in 6 m, nor 12 mm RE-609082 Rev
maximum. 0 Sec. 2.3.2.K (1)

Project Specs.
For vertical alignment of exposed head joints, the plumbness shall not vary by more than 6
A24 RE-609082 Rev
mm in 3 m, nor 12 mm maximum.
0 Sec. 2.3.2.K (2)

Project Specs.
For conspicuous horizontal lines, such as exposed lintels, sills, parapets, and reveals, the
A25 RE-609082 Rev
level shall not vary by more than 6 mm in 6 m, nor 12 mm maximum.
0 Sec. 2.3.2.K (3)

For exposed bed joints, the thickness indicated shall not vary by more than plus or minus 3 Project Specs.
A26 mm, with a maximum thickness limited to 12 mm. Do not vary from bed-joint thickness of RE-609082 Rev
adjacent courses by more than 3 mm 0 Sec. 2.3.2.K (4)

Project Specs.
For exposed head joints, the thickness required shall not vary by more than ± 3 mm. Do not
A27 RE-609082 Rev
vary from adjacent bed-joint and head-joint thicknesses by more than 3 mm.
0 Sec. 2.3.2.K (5)

Project Specs.
For Bond Pattern for Exposed Masonry, lay exposed masonry in the following bond pattern; do
A28 RE-609082 Rev
not use units with less than nominal 100-mm horizontal face dimensions at corners or jambs.
0 Sec. 2.3.2.K (8)
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Lay concealed masonry with all units in a wythe in running bond or bonded by lapping not less
Project Specs.
than 50 mm. Bond and interlock each course of each wythe at corners. Do not use units with
A29 RE-609082 Rev
less
0 Sec. 2.3.2.K (9)
than nominal 100-mm horizontal face dimensions at corners or jambs.

Project Specs.
Using less-than-half-size units, particularly at corners, jambs, and, where possible, at other
A30 RE-609082 Rev
locations shall be avoided
0 Sec. 2.3.2.K (7)

Project Specs.
Fill space between hollow-metal frames and masonry solidly with mortar, unless otherwise RE-609082 Rev
A31
required. 0 Sec. 2.3.2.K
(12)

Fill cores in hollow concrete masonry units with grout 600 mm under bearing plates, beams, Project Specs.
lintels, posts, and similar items, unless otherwise required. I. Build non-load-bearing interior RE-609082 Rev
A32
partitions full 0 Sec. 2.3.2.K
height of story to underside of solid floor or roof structure above, unless otherwise required (14)

Levelness of both bedding joints and tops of walls shall be within ±1/4 in. (6.4mm) in 10 ft.
ACI 530.1-11,
A33 (3.05m) or ±1/2 in (12.7mm) maximum.
Sec. 3.3.F.2.a

Plumbness of masonry walls shall be ± 0.25"/10' (6.4mm in 3.05m) to ± 0.375/20' (9.5mm in ACI 530.1-11,
A34
6.10m) or to a maximum of ± 0.5" (13 mm). Sec. 3.3.F.2.b

ACI 530.1-11,
A35 Solid masonry units or hollow units filled with mortar or grout shall be used. .
Sec. 1.12.2a

ACI 530.1-11,
A36 Solid masonry units shall have head and bed joints filled with mortar
Sec. 3.3B.4
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Face shells of bed joints are fully mortared. Head joints are mortared, a minimum distance ACI 530.1-11,
A37
from each face equal to the face shell thickness of the unit. Sec. 3.3B.3 a&c

Hollow units are placed so that the vertical cells to be grouted are aligned and unobstructed ACI 530.1-11,
A38
openings for grout placement. Sec. 3.3B.3d

Do not embed aluminum conduits, pipes, and accessories in masonry, grout, or mortar, unless
ACI 530.1-11,
A39 effectively coated or covered to prevent chemical reaction between aluminum and cement or
Sec. 3.3E(6)
electrolytic action between aluminum and steel.

Project Specs.
A40 Do not apply loads until work has set and cured and is ready to accept loading. RE-609082 Rev
0 Sec. 2.1.7 (F )

Project Specs.
Protect unit masonry Work when temperature and humidity conditions produce excessive
A41 RE-609082 Rev
evaporation of water from mortar and grout. Follow manufacturer's recommendations.
0 Sec. 2.1.7 (F )

Project Specs.
Build cavity and composite walls and other masonry construction to full thickness shown. Build
A42 RE-609082 Rev
singlewythe walls to actual widths of masonry units, using units of widths required.
0 Sec. 2.3.2 (A)

Project Specs.
A43 Install control and expansion joints in unit masonry where required. RE-609082 Rev
0 Sec. 2.3.2 (E)

Project Specs.
Form control joints using preformed control-joint gaskets designed to fit standard sash block in
A44 RE-609082 Rev
concrete masonry
0 Sec. 2.3.2 (F)

Project Specs.
Provide masonry lintels where shown and where openings of more than 64 mm for block size
A45 RE-609082 Rev
units are shown without structural steel or other supporting lintels.
0 Sec. 2.3.2 (G)

For seismic design mansonry walls, a bond beam reinforcement shall be provided at least
ACI 530 sec.
0.2in2 (129mm2) in cross-sectional area spaced not more than 10ft. (3.05 meter) in cross
A46 1.13.2 / SBC 305
sectional. Horizontal reinforcement shall be provided at the bottom of top of wall openings and
Sec. 6.1.1.2.1
shall extend not more than 610mm or less than 40 bar diameter

IFC Drawings/
All movement joints shall be provided with lateral restrain material spaced as per project
A47 Project
requirements.
Specification

Project Specs.
Install embedded flashing and weep holes in masonry at shelf angles, lintels, ledges, other
A48 RE-609082 Rev
obstructions to the downward flow of water in the wall, and where required.
0 Sec. 2.3.2 (I)

Project Specs.
A49 Provide minimum bearing of 200 mm at each jamb, unless otherwise required RE-609082 Rev
0 Sec. 2.3.2 (H)

Project Specs.
At fire-rated partitions, install fire stopping in joint between top of partition and underside of
A50 RE-609082 Rev
structure above to comply with Section MN-07841, “Through Penetration Fire Stop Systems."
0 Sec. 2.3.2 (L)

Project Specs.
A51 Unit masonry grout shall comply with ASTM C 476. RE-609082 Rev
0 Sec. 2.2.6 (D)

Standard
Drawing General
Notes
A52 CMU blocks shall be fully grouted where vertical rebars are to be provided
RA-612003
Sheet 002 Rev.
0A1

Construct grout spaces free of mortar dropping, debris, loose aggregates, and any material ACI 530.1-11,
A53
deleterious to masonry grout. Sec. 3.2D

ACI 530.1-11,
A54 Do not exceed the maximum grout pour height given in Table 7 (Grout Space Requirements)
Sec. 3.5C

Table 7 — Grout space requirements

Minimum clear
Maximum grout Minimum clear grout space dimensions for
width
Grout Type ¹ pour height, grouting cells of hollow units,(3,4,5)
of grout space,²,³
ft (m) in. x in. (mm x mm)
in. (mm)

ACI 530.1-11,
A55
Sec. 3.5C
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Fine 1 (0.30) 3/4 (19.1) 11/2 x 2 (38.1 x 50.8)


Fine 5.33 (1.63) 2 (50.8) 2 x 3 (50.8 x 76.2)
Fine 12.67 (3.86) 21/2 (63.5) 21/2 x 3 (63.5 x 76.2)
Fine 24 (7.32) 3 (76.2) 3 x 3 (76.2 x 76.2)

ACI 530.1-11,
A55
Coarse 1 (0.30) 11/2 (38.1) 11/2 x 3 (38.1 x 76.2) Sec. 3.5C
Coarse 5.33 (1.63) 2 (50.8) 21/2 x 3 (63.5 x 76.2)
Coarse 12.67 (3.86) 21/2 (63.5) 3 x 3 (76.2 x 76.2)
Coarse 24 (7.32) 3 (76.2) 3 x 4 (76.2 x 102)

1 Fine and coarse grouts are defined in ASTM C476.


2 For grouting between masonry wythes.
3 Minimum clear width of grout space and minimum clear grout space dimension are the net dimension of the space
determined by subtracting masonry protrusions and the diameters of horizontal bars from the as-built cross-section of the
grout space. Select the grout type and maximum grout pour height based on the minimum clear space.
4 Area of vertical reinforcement shall not exceed 6 percent of the area of the grout space.
5 Minimum grout space dimension for AAC masonry units shall be 3 in. (76.2 mm) x 3 in. (76.2 mm) or a 3 in. (76.2 mm)
diameter cell

ACI 530.1-11,
A56 Place grout within 1½ hr. from introducing water in the mixture and prior to initial set.
Sec. 3.5 A

ACI 530.1-11,
A57 Place grout in lifts not exceeding 5 ft.(1.52m)
Sec. 3.5

For ready-mixed grout: ACI 530.1-11,


A58
Addition of water is permitted at the time of discharge to adjust slump Sec.3.5 A (2)

Standard
Drawing General
Horizontal masonry beams or lintels shall be provided to distribute concentrated loads at the Notes
A59
roof and above and below openings in general. RA-612003
Sheet 002 Rev.
00
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Expanded Metal Lath shall be installed as shown on the IFC Drawings for Portland Cement
A60 IFC Drawings
Plaster or Stucco.

Project Specs.
Prevent grout, mortar, and soil from staining the face of masonry to be left exposed or painted,
A61 Re-609082 Rev 0
and immediately remove when it is in contact.
Sec. 2.1.7 (D)

Project Specs.
Final Cleaning shall commence after mortar is thoroughly set and cured, and then clean
A62 RE-609082 Rev
exposed masonry.
0 Sec. 2.3.4 (D)

Project Specs.
Provide final protection and maintain conditions that ensure unit masonry is without damage
A63 RE-609082 Rev
and deterioration at time of Substantial Completion.
0 Sec. 2.3.4 (E)

Masonry mortar joints are properly cured, sufficiently hydrated, and capable of supporting the ACI 524R-04
A64
masonry members' designed dead load before plaster application. Sec. 8.3

B Plastering

ACI 530.1-08
Chapter 6,
B1 Concrete masonry plaster bases are clean and free from bond inhibitors. Reference 6.21
ACI 524R-04
Sec. 8.3

Comply with requirements of referenced plaster application standards and recommendations Project Specs.
B2 of plaster manufacturer for environmental conditions before, during, and after plaster RE-609082 Rev
application. 0 Sec. 20.1.6 (A)

Control joints shall be formed at junctions where parts of the structure are movement
separated from other parts. The joints shall consist of galvanized stop beads internally and Project Specs.
B3 stainless steel RE-609082 Rev
stop beads externally to receive render and fixed to leave gap for filling with sealant. Control 0 Sec. 20.3.1(D)
joints shall also be provided at each wall to column junction or as directed by the EMPLOYER.

Control Joints shall be installed at required locations or, if not mentioned, at locations
complying with the following criteria and approved by EMPLOYER:
a. Where an expansion or contraction joint occurs in surface of construction directly behind
plaster membrane. Project Specs.
b. Distance between Control Joints: Not to exceed 5.4 m in either direction or a length-to-width RE-609082 Rev
B4
ratio of 2-1/2 to 1. 0 Sec.
c. Wall Areas is not more than 13 sq. m. 20.3.3(A.3)
d. Horizontal Surfaces is not more than 9 sq. m in area.
e. Where plaster panel sizes or dimensions change, extend joints full width or height of plaster
membrane.

Project Specs.
RE-609082 Rev
B5 Install casing beads at termination of plaster, unless otherwise mentioned or required.
0 Sec.
20.3.3(A.2)

Project Specs.
B6 Do not use materials that are frozen, caked, lumpy, dirty, or contaminated by foreign materials RE-609082 Rev
0 Sec. 20.3.4 (B)

Project Specs.
B7 Do not use excessive water in mixing and applying plaster materials. RE-609082 Rev
0 Sec. 20.3.4 (C)

Grout hollow-metal frames, bases, and similar work occurring in plastered areas, with base- Project Specs.
B8 coat plaster material, and before lathing where necessary. Except where full grouting is RE-609082 Rev
mentioned or required for fireresistance rating, grout at least 152 mm at each jamb anchor 0 Sec. 20.3.4 (E)

Project Specs.
Sequence plaster application with installation and protection of other work so that neither will
B9 RE-609082 Rev
be damaged by installation of other.
0 Sec. 20.3.4 (F)

Project Specs.
Corners: Make internal corners and angles square; finish external corners flush with
B10 RE-609082 Rev
cornerbeads on interior work, square and true with plaster faces on exterior work.
0 Sec. 20.3.4 (H)

Number of Coats: Apply plaster of composition required, to comply with the following
requirements:
Project Specs.
1. Two Coats: Over the following plaster bases:
B11 RE-609082 Rev
a. Concrete unit masonry.
0 Sec. 20.3.4 (I)
b. Concrete, cast-in-place or precast when surface condition complies with ASTM C 926 for
plaster bonded to solid base
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Project Specs.
Float Finish: Apply finish coat to a minimum thickness of 3 mm to completely cover base coat, RE-609082 Rev
B12
uniformly floated to a true even plane with fine-textured finish matching EMPLOYER's sample. 0 Sec. 20.3.4
(J.1)

Project Specs.
Trowel-Textured Finish: Apply finish coat with hand-troweled-textured finish matching RE-609082 Rev
B13
EMPLOYER's sample. 0 Sec. 20.3.4
(J.2)

Project Specs.
Dash Finish: Machine-apply finish-coat plaster in 2 coats evenly and uniformly to produce RE-609082 Rev
B14
textured finish matching EMPLOYER's sample. 0 Sec. 20.3.4
(J.3)

Project Specs.
Prepared Finish: Apply stucco finish coats, acrylic-based finish coats, and other factory- RE-609082 Rev
B15
prepared finish coats according to manufacturer's written instructions. 0 Sec. 20.3.4
(J.4)

Project Specs.
Moist-cure plaster base and finish coats to comply with ASTM C 926, including written
B16 RE-609082 Rev
instructions for time between coats and curing in "Annex A2 Design Considerations."
0 Sec. 20.3.4 (K)

Cut, patch, replace, repair, and point up plaster as necessary to accommodate other work.
Repair cracks and indented surfaces. Point-up finish plaster surfaces around items that are Project Specs.
B17 built into or penetrate plaster surfaces. Repair or replace work to eliminate blisters, buckles, RE-609082 Rev
check cracking, dry outs, efflorescence, excessive pinholes, and similar defects. Repair or 0 Sec. 20.3.5 (A)
replace work as necessary to comply with required visual effects.

Provide final protection and maintain conditions, in a manner acceptable to manufacturer and Project Specs.
B18 Installer that ensure plasterwork is without damage or deterioration at the time of Substantial RE-609082 Rev
Completion. 0 Sec. 20.3.6 (B)

The finish coat should be applied in one continuous application. Terminations in the
ACI 524R-04
B19 application of the finish coat should occur at control joints, beads, section or panel stops, or
Sec. 10.3.4
natural breaks in the surface plane

Curing shall be accomplished by supplementing moisture to the plaster through sprinkling,


ACI 524R-04
B20 spraying, soaking, immersing, or
Chapter 12
otherwise maintaining moisture within the plaster

The inside corner accessory is designed to provide stress ACI 524R-04


B21
relief at internal angles. Therefore, its shape is similar to a control joint accessory. Sec. 6.3

ACI 524R-04
B22 Casing beads should be installed wherever plaster terminates or abuts dissimilar material
Sec. 6.4

Project Specs.
Metal lathing shall be used for all corner reinforcement and be expanded mesh sheet steel Re-609082 Rev
B23
with a mesh size of 6 mm and weighing min. 1.63 kg/m2. B Sec.
20.2.3.A(1)

Each flat junction of concrete and CMU blockwork shall use 150 mm wide strip of Glass Project Specs.
Woven Yarn Fabric for plaster reinforcement, mesh size 11x8 mm, weight 110 gms/m2, Re-609082 Rev
B24
tensile strength in B Sec.
warp and weft 120 kg/50 mm, fabric coated to give it alkali resistance. 20.2.3.A(2)

Where fire-resistance-rated Portland cement plaster assemblies are


Project Specs.
required, provide materials and construction identical to those of assemblies tested for fire
B25 RE-609082 Rev
resistance per ASTM E 119 by an independent testing and inspecting agency acceptable to
0 Sec. 20.1.5 (D)
authorities having jurisdiction.

Protect plaster against uneven and excessive evaporation and from


Project Specs.
strong flows of dry air, both natural and artificial. Apply and cure plaster as required by climatic
B26 RE-609082 Rev
and job conditions to prevent dry out during cure period. Provide suitable coverings, moist
0 Sec. 20.1.6 (D)
curing, barriers to deflect sunlight and wind, or combinations of these, as required.

Flat Surface Tolerances: Do not deviate more than plus or minus 3 mm in 3 m from a true Project Specs.
B27 plane in finished plaster surfaces, as measured by a 3-m straightedge placed at any location RE-609082 Rev
on surface. 0 Sec. 20.3.4 (D)
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

C Gypsum Plaster

SBC 201 Sec.


C1 Gypsum plaster shall not be used on exterior surfaces.
10.8.2

Project Specs
C2 Site mix plaster shall be as per BS 8481 RE-609085 Rev
0 Sec. 17.3.3

Project Specs
C3 For plaster thickness type A: The Final coat shall be 2-3mm applied in coat RE-609085 Rev
0 Sec. 17.3.4 (B)

Project Specs
C4 For plaster thickness type B: The Final coat shall be as per Manufacturer's recommendation RE-609085 Rev
0 Sec. 17.3.5 (B)

Project Specs
RE-609085 Rev
C5 For Finish to Plaster Type A: The standard of finish shall be as per BS EN 13914-2, Level 4
0 Sec. 17.3.6
(B.3)

Project Specs
Steel float finish: An even overall texture. Finish with a dry steel float as soon as wet sheen RE-609085 Rev
C6
has disappeared. 0 Sec. 17.3.6
(B.4)

Project Specs
RE-609085 Rev
C7 For Finish to Plaster Type B: The standard of finish shall be as per BS EN 13914-2, Level 1
0 Sec. 17.3.7
(B.3)

Project Specs
Wood float finish: An even overall texture. Finish with a dry wood float as soon as wet sheen RE-609085 Rev
C8
has disappeared 0 Sec. 17.3.7
(B.4)

Project Specs
RE-609085 Rev
Textured and patterned finishes: Consistent and even. Carry out work on each surface as one
C9 0 Sec. 17.3.6
continuous operation
(B.5) / 17.3.7
(B.5)

Installation of lathing and plaster materials shall conform with Table 2511.1 & Table 2507.2 of IBC 2015 Sec.
C10
IBC 2015. 2511.1.1

D Sampling and Testing Inspection

Prepare one mortar sample for compressive strength tests once per 1,000 square feet or Project Specs.
D1 fraction thereof of wall laid up per day. Prepare four standard 2 inch-diameter by 4 inch RE-609082 Rev
cylinders 0 Sec. 2.1.6 (D)

Perform compression strength tests for samples at 7 days using one cylinder and at 28 days Project Specs.
D2 using two cylinders. Test the fourth cylinder at 56 days if the 28-day tests are below the RE-609082 Rev
specified strength. 0 Sec. 2.1.6 (E )
( Standards Cut off - MAY,31, 2016) Rev 5

SAC INSPECTION CHECKLIST SACIC NUMBER DATE APPROVED QR NUMBER

SAC-MYP-QC(P6)-CIVIL-
Masonry Units and Plaster Installation Inspection SACIC-M-1009 RFI-95021
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES 25-00053-0004, 0005,
CONSORTIUM of BRANCH OF SINOHYDRO
CORPORATION COMPANY LTD and
(MYP) PACKAGE # 4, 5 & 6 0006,0007/6600042823 (IK)
SEPCO ARABIA COMPANY

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Prepare one sample of grout for compressive strength tests per 50 cubic yards or fraction Project Specs.
D3 thereof of grout placed per day. Prepare four 3 inch by 3 inch by 6 inch grout prisms, or other RE-609082 Rev
configuration as dictated by the testing agency, per ASTM C1019 per sample. 0 Sec. 2.1.6 (F )

Perform compression strength tests for samples at 7 days using one prism and at 28 days Project Specs.
D4 using two prisms. Test the fourth prism at 56 days if the 28-day tests are below the specified RE-609082 Rev
strength. 0 Sec. 2.1.6 (G)

Project Specs.
D5 Make grout slump tests in accordance with ASTM C143/C143M. RE-609082 Rev
0 Sec. 2.1.6 (H)

E Final Inspection

IFC Drawings,
Finished walls are plumb and in alignment as shown on IFC Drawings. Tolerances,
E1 ACI 530.1-05
dimensions, elements and location of elements shall conform with ACI 530 sec. 3.3G
sec. 3.3 G

REMARKS:

REFERENCE DOCUMENTS:
1-Specification for Masonry Structures (TMS 602-11/ACI 530.1/ASCE 6-11)
2- Saudi Building Code Structural Requirements for Masonry Construction (SBC 305)
3- IBC 2015 ---- International Building Code
4-RE-609082 Rev 0 ---- Roof and Wall Cladding Specification
5-RE-609085 Rev 0 - Specification for Interior Architectural Elements
6-ACI 524R-04 ---- Guide to Portland Cement Based Plaster
7- RA-612003 - Standard Drawing General Notes
8-SBC 201 ---- Saudi Building Code

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
Tanveer AHMAD AL HAMAD
QC Inspector PID Representative
Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
ABID ALI JAZIB MUNIR
QC Supervisor Proponent and Others
Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Muhammad Shahbaz Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

You might also like