De Jesus Bom Temporary Water Tank
De Jesus Bom Temporary Water Tank
De Jesus Bom Temporary Water Tank
Materials Labor
Item Description Qty Unit Total Amount
Unit Cost Total Cost Unit Cost Total Cost
I. GENERAL REQUIREMENTS
1.01 Supervision & Support Services 1.00 lot 4,000.00 4,000.00 4,000.00
1.03 Water Tank (1000 Liters) including delivery fee 1.00 lot 7,500.00 7,500.00 7,500.00
SUB- TOTAL 7,500.00 4,000.00 11,500.00
II. SITE WORKS
2.01 Excavation Works -
a. Column Footing 7.50 cu.m 275.00 2,062.50 2,062.50
SUB- TOTAL 0.00 2,062.50 2,062.50
III. CONCRETING WORKS
3.01 Column Footings -
a. F1 0.50 cu.m 1,113.75 675.00 337.50 1,451.25
3.02 Columns -
a. C - 1 0.50 cu.m 1,113.75 675.00 337.50 1,451.25
SUB- TOTAL 2,227.50 675.00 2,902.50
IV. REINFORCING BARS -
4.01 Column Footings 0.00
a. F1 20.00 kgs 1,526.25 18.50 370.00 1,896.25
4.02 Columns 0.00 - -
b. C - 1 20.00 kgs 1,500.00 18.50 370.00 1,870.00
4.03 Tank Framing 0.00
c. F1 65.00 kgs 3,968.25 18.50 1,202.50 5,170.75
SUB- TOTAL 6,994.50 - 1,942.50 8,937.00
V. FORMWORKS -
5.01 Column Footings 0.00
a. F1 1.50 sq.m 1,237.50 250.00 375.00 1,612.50
5.02 Columns - -
a. C - 1 1.50 sq.m 1,237.50 250.00 375.00 1,612.50
SUB- TOTAL 2,475.00 750.00 3,225.00
VI. Water Tank framing -
6.01 framing
a. Angle Bar 2 x 2 x 6mm thk 2.00 pcs. 1,800.00 3,600.00 3,600.00
b. Angle Bar 1 x 1 x 6mm thk 2.00 pcs. 1,200.00 2,400.00 2,400.00
c. steel plate 4.00 pcs. 500.00 2,000.00 2,000.00
d. Bolts and Nuts 16Ø mm 16.00 pcs. 75.00 1,200.00 1,200.00
6.02 Accessories - -
a. Welding Rod 1.00 lot 500.00 500.00 500.00
b. Grinding Disk 1.00 lot 500.00 500.00 500.00
SUB- TOTAL 10,200.00 10,200.00
29,397.00 9,430.00 38,827.00
DIRECT COST PHP 38,827.00