Final Report-1

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 31

GOVERNMENT ENGINEERING COLLEGE, DAMAN

INTERNSHIP REPORT

A REPORT PRESENTED FOR DEGREE OF

BACHELOR OF ENGINEERING

Singh Nikhil Pradeepkumar


DEPARTMENT OF CIVIL ENGINEERING

2024-2025
A REPORT ON

INDUSTRIAL INTERNSHIP
FORTUNE DREAMS-CON PVT.LTD

Submitted by

SINGH NIKHIL PRADEEPKUMAR

211420106001
To

GOVERNMENT ENGINEERING COLLEGE, DAMAN

In partial fulfilment of the requirements for the Award of Degree of

BACHELOR OF ENGINEERING
In
CIVIL ENGINEERING

Department of Civil Engineering


Gujarat Technological University, Ahmedabad
JULY 2024
CERTIFICATE

This is to certify that the project report submitted along with the

project entitled Summer Internship has been carried out by Singh

Nikhil Pradeepkumar under my guidance in partial fulfilment for the

degree of Bachelor of Engineering in Civil Engineering, 7th Semester of

Gujarat Technological University, Ahmedabad during the academic year

2024 – 2025.

Mayank I. Patel Dr. Avinash R. Chaudhari


Assistant Professor Principal
Department of Civil Engineering Government Engineering College,
Daman
COMPLITION CERTIFICATE
GOVERNMENT ENGINEERING COLLEGE, DAMAN
Varkund, Mota Falia
Nani Daman

DECLARATION

I hereby declare that the Internship report submitted along with the

Internship entitled Summer Internship submitted in partial fulfilment for

the degree of Bachelor of Engineering in Civil Engineering to Gujarat

Technological University, Ahmedabad, is a Bonafide record of original

project work carried out by me / us at Fortune Dreams-CON PVT.LTD

under the supervision of Dr. Avinash R. Chaudhari and that no part of this

report has been directly copied from any student’s reports or taken from any

other source, without providing due reference.

Name of Students Sign of Students

SINGH NIKHIL PRADEEPKUMAR


ACKNOWLEDGEMENT

I take this opportunity to express my deep and sincere gratitude to my guide Dr.
Avinash R. Chaudhari for his supervision, advice and guidance from the very early
stage of this Internship as well as for giving me extraordinary experiences
throughout the work. Apart from the subject of my Internship, I learned a lot from
him, which I am sure, will be useful in different stages of my life.
I would like to extend our gratitude to Mr. Mayank I. Patel Head of the Civil
Engineering Department at Government Engineering College, Daman for his
continuous encouragement and motivation.
I would like to thank our principal, Dr. Avinash R. Chaudhari, for providing me with
such a wonderful working atmosphere.
I would also like to thank the people at FORTUNE DREAM-CON PVT.LTD
for taking me as an intern and guiding me and for expanding my knowledge and I
would like to give a special thanks to the engineer Mr. Pankesh Jethwa for
helping me out and guiding me with their vision and expertise in the field.
I am heartily thankful to my parents who has always inspired and encouraged me
throughout my life against all odds and blessed me to achieve all my goals.
We wish to express our heartiest gratitude and gentle thanks to all the staff
members of the Department of Civil Engineering for their affection and support.

Thank to all
Singh Nikhil Pradeepkumar

i
ABSTRACT

This abstract summarizes a twoweek internship experience at a


construction site. The primary focus of the Internship was to gain
practical insights into the diverse operations and activities within a
construction environment. The objectives included observing safety
protocols, understanding project management, and learning about the
roles and coordination among various construction teams.
This project focuses on the construction of a residential building,
highlighting key structural activities such as staircase casting and
column extension. The project involves the application of fundamental
civil engineering principles in the planning, design, and execution
phases. The staircase casting process ensures the creation of safe and
durable access between floors, while the column extension is crucial
for transferring loads from the upper floors to the foundation,
maintaining the buildings structural integrity. Throughout the project,
stringent quality control measures are implemented to meet safety
standards and design specifications. The successful completion of
these activities marks significant progress in the overall construction,
contributing to the realization of a well-structured and functional
residential building.
During this training period, I acquired practical skills and knowledge
in my field. I started communication with the site engineers and also
with the site workers. I learned about how to execute work in the
field. I was able to find some queries carried out in the field by using
the different layout plans and drawing.
During this Internship period, my skills increased and I gained more
experience in the construction period which will be very helpful for
me in the future.

ii
CONTENTS
Acknowledgement………………………………………………………i
Abstract…………………………………………………………………ii
List Of Figures………………………………………………………….iv
Chapter: 1 Introduction………………………………………………..1
Chapter: 2 Project Overview…………………………………………..2
Chapter: 3 Design Of Reinforcement of Staircase……………………5
Chapter: 4 Beam work…………………………………………………8
Chapter: 5 Horizontal Cuplock Ledger………………………………13
Chapter: 6 Column Extension………………………………………..16
Chapter: 7 Material Used On Site……………………………………19
Chapter: 8 Learning Outcomes………………………………………21
Conclusion……………………………………………………………..22

iii
LIST OF FIGURES

Fig. 2.2 Site Location………………………………………………………2


Fig. 2.4 Site Plan…………………………………………………………..4
Fig. 3.1 Reinforcement Work of Stairs…………………………………...5
Fig. 3.2 Shuttering Work of Stairs………………………………………..5
Fig. 3.3 Casting of Staircase………………………………………………6
Fig. 3.4 Making of Mix Design Concrete………………………………...7
Fig. 4.1 Beam Frame Work ………………………………………………8
Fig. 4.2 After Curing of Beam Work……………………………………..8
Fig. 4.3 Beam Frame Work Installation…………………………………9
Fig. 4.4 Beam Reinforcement……………………………………………10
Fig. 4.5 Beam Placing……………………………………………………11
Fig. 4.6 Beam Frame Work View……………………………………….12
Fig. 5.1 Supporting Beam Frame with Cup lock Ledger………………13
Fig. 5.2 Cup lock Ledger…………………………………………………14
Fig. 5.3 Supporting Elevator Frame Work……………………………...15
Fig. 6.1 Formwork Assembly for Column Extension…………………..16
Fig. 6.2 Placement of Reinforcement in Column……………………….17
Fig. 6.3 Form Casting for Column Extension…………………………..18
Fig. 7.1 Cover Block………………………………………………………19
Fig. 7.2 Applying Shuttering Oil on Plywood…………………………..20

iv
612098 Introduction

CHAPTER: 1 INTRODUCTION

1.1 Purpose of Internship:


 The purpose of my internship was to gain hands-on experience in the field of
industrial construction, particularly in understanding Staircase casting, Column
extension and site management.
 As a student pursuing civil engineering, I aimed to enhance my practical
knowledge of construction techniques, observe project workflows, and improve
my ability to interpret technical drawings and manage on-site tasks.
 It helped me learn how to plan work effectively, coordinating with different teams
to ensure tasks are implemented efficiently and the project is completed on time.
 This experience was intended to help me develop the professional skills needed
for a future career in the construction industry.

1.2 Organization Overview:


 During my internship, I was involved in the construction of an Amaira
Appartment, where I gained firsthand experience in foundational work,
reinforcement activities, and column construction.
 The company’s well-organized site management and focus on quality made it a
great place to learn.
 During my 2-week internship, I observed the essential tasks required to keep a
complex construction project running smoothly. However, the project faced
challenges due to rainfall.

1
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Project Overview

CHAPTER: 2 PROJECT OVERVIEW

2.1 Project Name:


 Amaira Appartment, Daman

2.2 Site Location:

 The construction site is located at College Ground Road, Daman. This area was
selected for its strategic location, providing easy access to major transportation
routes and utilities.

Fig. 2.2 Site Location

2
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Project Overview

2.3 Project Scope:


 Staircase casting: A building either residential, commercial, or multi-story
building, the stair is definite or precise arrangements that give or provide us access
from one floor to another floor or to each floor of a building.
 Structural Work: Erection of steel columns, reinforcement of concrete elements,
and casting Staircase.
 Site Development: Preparation of the site, including grading, installation of
drainage systems, and construction of access roads to facilitate transportation and
site logistics.
 Quality and Safety Management: Implementation of rigorous quality control
measures and safety protocols to ensure that construction standards and regulatory
requirements were met.

3
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Project Overview

2.4 Site Plan:

Figure 2.4: Site Plan

4
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Beam Work

CHAPTER:3 Design 0f Reinforcement of Staircase

Fig. 3.1: Reinforcement Work of Stairs


 The image shows the initial phase of Staircase, where RCC frame work has been
applied
 It is dogleg type staircase.

Fig. 3.2: Shuttering Work of Stairs


 Shuttering, also known as formwork, is a process of providing support to wet
concrete until it sets and attains adequate strength to carry its self-weight.
 Essentially, the process involves creating temporary moulds of wood or steel in
which the concrete will be poured. Once the concrete sets and hardens, the
formwork may be removed.

5
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Beam Work

Fig. 3.3: Casting of staircase


• Standard mix used for stairs are 3 parts cement, 2 parts sand, 4 parts
gravel and water. It is recommended to use a concrete vibrator while
pouring the concrete to completely fill the gaps of the stairs and to avoid
the honeycomb formation

6
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098

Fig. 3.4: Making Mix Design on Site


 To mix concrete on site, follow these steps
 Prepare your work area: Choose a level, solid ground for
stability during the cement mixing process.
 Measure your ingredients: Accurate measurements are
essential for sturdy concrete.
 Combine your ingredients: For pre-mixed bags, follow
the instructions on the bag.
 Check your mix: Ensure the consistency is right.
 Get started: Mix thoroughly.

7
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Beam Work

CHAPTER:4 Beam Work

Fig. 4.1: beam frame work placing


 When it comes to constructing beams, one crucial aspect that demands attention
is the installation of Beam Formwork. The process of installing beam formwork
requires careful planning and execution to ensure the structural integrity and
stability of the beams.

Fig4.2 After Curing of Beam Work

8
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098

Fig. 4.3: Beam Frame Work Installation

9
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Beam Reinforcement

Fig. 4.4: Beam Reinforcement

 Reinforcement are essential part of a concrete beam. It resists tension forces,


increase the compression capacity, enhance ductility and reduce long-term
deflections in the concrete. Additionally, reinforcement prevent cracking of
concrete due to shear stresses, shrinkage and temperature stresses.

10
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098

Fig. 4.5: Beam placing

 The size of Reinforcement bar is 150X620 (MM X MM)


 The size of Bottom Bar is 2-16mm (Straight)
 The size of Bottom Bar is 2-12mm (Curtail)
 The size of Top Bar is 2-10mm
 The size of Top Bar is 2-16mm (Extra at top)
 The size of Stirrups is 8mm@150mm c/c
 The size of Stirrups between Curtail & Support is 8mm@125mm c/c
 Remark provided 2-12mm side bar

11
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098

Fig. 4.6: Beam Frame Work Casting

12
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Horizontal Cuplock Ledger

CHAPTER: 5 Horizontal Cuplock Ledger

Fig. 5.1: Supporting Frame Work of Beam With Cuplock Ledger.

 It is a horizontal member of the scaffold that connects the vertical standards


and provides support for the scaffold platform. The Cuplock ledger has a
unique design that allows it to be easily connected to the vertical standards
using a cup-shaped socket, which gives the system its name.

13
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Horizontal Cuplock Ledger

Fig. 5.2: Cuplock Ledger

14
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098

Fig. 5.3: Supporting Elevator formwork

15
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Column Extension

CHAPTER: 6 COLUMN EXTENSION

Fig. 6.1: Formwork Assembly for Column Extensions


 The image shows the formwork being assembled around the existing columns for
extension work. The columns will be extended to such height.

16
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098

Fig. 6.2: Placement of Reinforcement in Columns

 Reinforcement bars are placed inside the formwork to ensure the extended
columns can bear additional loads. Bars of size 20 mm are used, spaced at 100
mm intervals.
 Reinforcement placement in columns is critical for ensuring the structural
integrity and load-carrying capacity of buildings. Columns are vertical
structural elements that transfer loads from beams and slabs to the
foundation.

 Proper reinforcement placement ensures structural safety and prevents


column failure, structural collapse, and damage from seismic activity.

17
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Column Extension

Fig. 6.3: Form casting of column extension

18
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Material used on site

CHAPTER: 7 MATERIALS USED ON SITE

7.1 RCC Cover Block

Fig. 7.1: Cover Block

 A cover block is basically a spacer that is used to lift the rebar matrix off the
ground so that concrete may flow underneath the rebar. In order to
prevent corrosion of the rebar, it requires to be fully embedded in concrete.

 It usually requires about 2 to 3 inches of coverage on all sides. Hence the


cover block lifts the rebar up by about 2 to 3 inches and becomes a permanent
and integral part of the poured concrete, assure that no part of the rebar sags
and minimizes that required concrete coverage during the pour.

19
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Material Used on Side

Fig 7.2: Applying Shuttering Oil on Plywood

20
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098

CHAPTER-8 LEARNING OUTCOMES

7.1Technical Skills
 Site Management: I learned how to oversee various construction activities,
coordinate between teams, and manage workflow to ensure timely project
execution.
 Foundation and Structural Work: Gained hands-on experience in key processes
such as foundation excavation, formwork assembly, reinforcement placement, and
concrete pouring.
 Reinforcement Work: Observed and participated in reinforcement cutting,
bending, and placing, gaining insight into how structural stability is ensured
through proper rebar configuration.
 Column and Beam Construction: Learned how columns and beams are extended
and reinforced to support additional floors or structures, along with the importance
of curing concrete to achieve desired strength.

7.2Project Planning and Coordination


 Time Management: Learned how to manage timelines for different construction
phases and how delays in one stage can affect the overall schedule.

 Team Collaboration: Experienced the significance of effective communication


and teamwork between site engineers, labourers, and contractors to ensure smooth
project flow.

21
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN
612098 Conclusion

CONCLUSION

 During my two-week internship at the construction site of Amaira Apartment., I


gained valuable hands-on experience in various aspects of commercial building. I
observed and participated in critical activities such as Staircase casting,
reinforcement cutting and bending, and column extensions. These tasks allowed
me to understand the importance of accuracy, coordination, and efficiency in
large-scale construction projects.
 This internship provided me with a deeper understanding of the complexities
involved in managing a construction site. I learned how engineers and site
managers must collaborate with different teams, from labourers to suppliers, to
ensure the smooth progression of the project.

22
GUJARAT TECHNOLOGICAL UNIVERSITY GOVERNMENT ENGINEERING COLLEGE, DAMAN

You might also like